AIM and Media Release
19 October 2021
BASE RESOURCES
LIMITED
Quarterly Activities Report – September
2021
Key Points
- Ongoing strong demand for all products supported further price
increases in the quarter.
- Kwale Operations mine life extended to December 2023 following finalisation of mining
lease extension.
- Bumamani PFS released concluding that higher grade subsets of
the Bumamani and Kwale North Dune deposits can be economically
mined, which would extend Kwale mine life to mid-2024.
- Three Tanzanian prospecting licences granted, with a fourth
pending, and preparatory work for an exploration program
commenced.
- Ranobe Mineral Resources and Ore Reserves estimates updated to
incorporate drilling program results.
- Toliara Project scale and economics enhanced with release of
DFS2.
- FY21 full-year dividend of AUD4.0 cents per share paid,
totalling US$34.8 million.
African mineral sands producer, Base Resources Limited
(ASX & AIM: BSE) (Base Resources or the Company)
is pleased to provide a quarterly operational, development and
corporate update.
COVID-19 UPDATE
Base Resources continues to closely monitor the COVID-19
pandemic and its impacts on the Company’s business, people and
wider stakeholders. The Company’s Kwale Operations in
Kenya operates under a suite of
controls and mitigations aimed at protecting the health and safety
of our employees and neighbouring communities, including modified
workplace practices and a focus on hygiene and social distancing.
On site rapid antigen COVID-19 testing is utilised and
employees have been encouraged to access the Government of
Kenya vaccination program.
The Company continues to assist governments and communities
with initiatives focused on the construction of hygiene facilities,
and the donation and distribution of food and medical supplies and
equipment.
KWALE OPERATIONS
Production &
Sales |
Sept
2020 Quarter |
Dec
2020 Quarter |
Mar
2021 Quarter |
June
2021 Quarter |
Sept
2021 Quarter |
Production
(tonnes) |
Ilmenite |
65,863 |
78,500 |
84,178 |
88,735 |
72,866 |
Rutile |
15,513 |
18,171 |
19,448 |
20,116 |
17,762 |
Zircon |
6,000 |
6,677 |
7,388 |
7,057 |
6,069 |
Zircon low
grade* |
426 |
516 |
482 |
454 |
506 |
Sales
(tonnes) |
Ilmenite |
75,502 |
53,798 |
97,179 |
93,959 |
34,107 |
Rutile |
11,651 |
12,017 |
26,074 |
24,597 |
13,791 |
Zircon |
7,336 |
6,399 |
6,612 |
7,690 |
5,622 |
Zircon low
grade* |
505 |
- |
502 |
698 |
617 |
*Reported as tonnes of zircon concentrate which
contains low grades of zircon and rutile credits.
Mining operations continued to plan on the South Dune orebody
with mined tonnage decreasing due to two mining block moves during
the quarter. As expected, heavy mineral (HM) grade for
the quarter was lower at 3.26% (last quarter: 3.65%) due to mining
commencing on the lower grade fringes of the new mining blocks.
Mining
& WCP Performance |
Sept
2020 Quarter |
Dec
2020 Quarter |
Mar
2021 Quarter |
June
2021 Quarter |
Sept
2021 Quarter |
Ore mined
(tonnes) |
3,938,494 |
4,600,172 |
4,695,052 |
4,748,860 |
4,409,883 |
HM % |
3.12 |
3.43 |
3.58 |
3.65 |
3.26 |
VHM % |
2.36 |
2.62 |
2.80 |
2.78 |
2.50 |
HMC produced
(tonnes) |
103,730 |
142,309 |
149,618 |
162,428 |
133,874 |
Wet concentrator plant (WCP) production of heavy mineral
concentrate (HMC) was lower as a consequence of the lower
mined tonnes and ore grade. HMC stocks were slightly lower at
16.5kt (last quarter: 20kt). Sand tails continued to be
deposited into the mined-out Central Dune area and capped with a
2m thick co-disposed slimes/sand
layer to aid water retention and subsequent rehabilitation or
alternate land use. Agricultural trials on the co-disposed
water retention layer are proving successful. Rehabilitation
of the mined-out sections of the South Dune proceeded according to
plan.
MSP
Performance |
Sept
2020 Quarter |
Dec
2020 Quarter |
Mar
2021 Quarter |
June
2021 Quarter |
Sept
2021 Quarter |
MSP Feed
(tonnes of HMC) |
114,873 |
134,019 |
145,110 |
160,691 |
137,182 |
MSP feed rate
(tph) |
61 |
64 |
69 |
76 |
64 |
MSP
recovery % |
Ilmenite |
100 |
102 |
102 |
101 |
100 |
Rutile |
102 |
102 |
100 |
100 |
104 |
Zircon |
86 |
87 |
85 |
86 |
84 |
Mineral separation plant (MSP) feed tonnage of 137kt was
lower than the prior quarter (last quarter: 161kt), being limited
by HMC feed availability. Underlying MSP product recoveries
were steady, with the increase in reported rutile recoveries due to
a one-off stock adjustment. Production of final products was
in line with plan. Production of HMC, MSP feed and final
product output are expected to increase in the coming quarter as
higher-grade mining areas are accessed.
Bulk loading operations at the Company’s Likoni export facility
continued to run smoothly, dispatching a combined 54kt of bulk
ilmenite and rutile during the quarter (last quarter: 104kt).
Containerised shipments of rutile and zircon through the Mombasa
Port proceeded to plan.
Summary of unit costs
& Revenue per tonne (US$) |
Sept
2020 Quarter |
Dec 2020
Quarter |
Mar 2021
Quarter |
June
2021 Quarter |
Sept
2021 Quarter |
Unit operating costs
per tonne produced |
$189 |
$161 |
$142 |
$148 |
$174 |
Unit cost of goods
sold per tonne sold |
$192 |
$207 |
$169 |
$202 |
$264 |
Unit revenue per tonne
of product sold |
$413 |
$464 |
$478 |
$497 |
$668 |
Revenue: Cost of goods
sold ratio |
2.1 |
2.2 |
2.8 |
2.5 |
2.5 |
Total cash operating costs of US$16.9
million were steady compared to the prior quarter (last
quarter at US$17.2 million), however
lower production results in higher unit operating costs of
US$174 per tonne produced (rutile,
ilmenite, zircon and low-grade zircon) (last quarter: US$148 per tonne).
Unit cost of goods sold is influenced by both the underlying
operating costs and product sales mix. Operating costs are
allocated to each product based on revenue contribution, which sees
the higher value rutile and zircon products attracting a higher
cost per tonne than the lower value ilmenite. Therefore, the
greater the sales volume of rutile and zircon relative to ilmenite
in a quarter, the higher both unit revenue per tonne and unit cost
of goods sold will be.
Ilmenite, and most rutile, is sold in bulk, with typical
shipment sizes of 50kt for ilmenite and 10kt for rutile, which
means any given quarter will usually contain either one or two bulk
ilmenite and rutile sales. Zircon is sold in smaller parcels
and sales generally align with production volume. Product
sales mix will therefore vary depending on the number of bulk
shipments of ilmenite and rutile in each quarter.
Cost of goods sold of US$264 per
tonne sold (operating costs, adjusted for stockpile movements, and
royalties) increased due to the sales mix (last quarter:
US$202 per tonne). Average unit
revenue increased to US$668 per tonne
(prior quarter: US$497 per tonne) due
to sales mix and increased prices for all products. Due to
the above factors and the timing of sales, the revenue to cost of
goods sold ratio for the quarter remained steady at 2.5 (last
quarter: 2.5).
FY22 PRODUCTION GUIDANCE
Kwale Operations production guidance for the 2022 financial year
remains at:
- Rutile - 73,000 to 83,000 tonnes.
- Ilmenite - 310,000 to 340,000 tonnes.
- Zircon - 24,000 to 28,000 tonnes.
This guidance is based on the following assumptions:
- Mining of 17.4Mt at an average HM grade of 3.53%.
- Average MSP feed rate of 68tph.
- Average MSP product recoveries of 101% for rutile, 101.5% for
ilmenite and 84.5% for zircon.
The possibility of a halt to, or curtailment of, operations at
some point in the future remains if a severe COVID-19 outbreak
occurs on site or if government health directives change.
MARKETING
Despite the usual seasonal dip in the Chinese pigment market at
the start of the northern hemisphere summer, which has since
recovered, overall global pigment demand remained very strong
through the quarter leading to ongoing robust demand for titanium
feedstocks. As a result, pigment prices maintained upward
momentum with further price increases expected in coming
months.
Demand for ilmenite as a feedstock for Chinese pigment producers
was again very strong in the quarter, enabling further ilmenite
price gains. Increased ilmenite supply from some African
sources, Vietnamese exports and Chinese domestic production through
2021 is not yet sufficient to meet demand and ilmenite prices are
expected to continue their upward trend through the December
quarter. However, escalating bulk freight costs to
China are partially eroding these
price gains.
Demand for high grade feedstocks (which includes rutile)
increased significantly through the quarter as western pigment
producers sought to maximise output rates and the welding
consumable and titanium metal sectors continued to
strengthen. The tight market for high grade feedstocks is
being exacerbated by supply constraints and uncertainties at major
high grade feedstock producers. Rutile prices increased
through the quarter and are expected to accelerate further through
the coming quarters.
Zircon demand continues to be very strong due to recoveries in
all end use sectors and regions, which, when combined with limited
supply and minimal inventories, has resulted in a tightening zircon
market and significant upward price pressure. Zircon prices
for the Company’s September quarter contracts increased by
approximately US$150/t from the June
quarter and prices agreed for the Company’s December quarter
contracts have increased by an additional US$600/t.
SAFETY
There were no lost time injuries during the quarter, or in the
past year, at Kwale Operations or the Toliara Project, resulting in
a lost time injury frequency rate (LTIFR) for the Company of
zero. Compared to the Western Australian All Mines 2019/2020
LTIFR of 2.1, this is an exceptional performance reflective of the
ongoing focus and importance placed on safety by management.
Base Resources group employees and contractors have now worked 25.9
million hours lost time injury (LTI) free, with the last LTI
recorded in early 2014.
Two medical treatment finger injuries were recorded during the
quarter. As a result, Base Resources’ total recordable injury
frequency rate is 0.50 per million hours worked.
COMMUNITY AND ENVIRONMENT
Kwale Operations
Base Resources has continued to assist the Kwale community
through the COVID-19 pandemic, including collaborating with county
and national health authorities to provide public education through
community health workers.
Agricultural livelihood programs in Kwale continued through the
PAVI farmer’s cooperative although, with rains being significantly
below average throughout most of the year, alternative drought
resistant crop variants have been planted. Poultry and
beekeeping continue to expand and provide farmers and community
groups with substantial incomes.
Implementation of the Community Development Agreements
(CDAs) with the Msambweni, Lunga and Likoni communities
progressed well. Representing their respective communities,
each committee undertook further training and capacity building to
ensure more efficient delivery of community development projects
set out in each CDA.
Rehabilitation activities on the mined-out sections of the South
Dune continued in the quarter with community groups supplying
indigenous legumes, grass seed and manure.
The heads of several government ministries and lead agencies
visited Kwale Operations in the quarter to see the success of
ongoing rehabilitation activities and the agricultural potential of
rehabilitated land on the South Dune. This information
sharing is key to creating awareness and understanding among
stakeholders of the various options being considered for
post-mining land use. Crops harvested from trial plots on the
South Dune continue to be distributed to local schools and
children’s homes.
Toliara Project
All community training programs, and social infrastructure
construction, remained on hold with the Government of Madagascar’s
suspension of the Toliara Project’s on-the-ground activities.
The 24 Malagasy apprentices, who recently completed their two-year
training programs in Kenya at
Kwale Operations, returned to Madagascar following their certification
through the Kenyan training authority and completion of further
work experience at Kwale Operations.
Base Resources partnered with local governments and community
health groups in the Toliara region to provide additional support
to vulnerable communities affected by COVID-19, including programs
to address food insecurity and hygiene.
BUSINESS DEVELOPMENT
Toliara Project development -
Madagascar
In November 2019, the Government
of Madagascar required the Company
to suspend on-the-ground activity on the Toliara Project while
discussions on fiscal terms applying to the project were
progressed. Activity remains suspended as Base Resources
continues to engage with the Government in relation to the
country’s Large Mining Investment Law regime, fiscal terms
applicable to the Toliara Project and the lifting of the
on-the-ground suspension.
In September, updated Ranobe Mineral Resources and Ore Reserves
estimates were released, incorporating available assay results from
the 2018/19 drill program. This resulted in the Ranobe
Mineral Resources almost doubling to 2,580Mt (597Mt Measured, 793Mt
Indicated, 1,190Mt Inferred) at an average HM grade of 4.3% and Ore
Reserves contained heavy mineral tonnes increasing by 45% to 55Mt
(30Mt Proved, 25Mt Probable) at 6.1% HM grade.1
The substantially increased Ranobe Ore Reserves estimate,
combined with the attractive long-term supply-demand outlook for
mineral sands, provided the opportunity for Base Resources to
complete an enhanced Definitive Feasibility Study (DFS2) for
the Toliara Project incorporating an increase in scale, the
outcomes of which were released in September 2021. DFS2,
compared to the 2019 DFS, has delivered a substantial improvement
in the forecast financial returns for the Toliara Project,
including a post-tax/pre-debt (real) NPV10 of
US$1.0 billion and an average revenue
to cost of sales ratio of 3.5, over an initial 38-year mine
life.2
The DFS2 schedule assumes construction will commence at the
start of 2023, at a capital cost of US$520
million, which would see production starting in early
2025. However, timing of the Final Investment Decision
(FID) to proceed with the construction of the Toliara
Project remains subject to lifting of the suspension of
on-the-ground activities and agreeing acceptable fiscal terms with
the Government of Madagascar. Once these two key milestones
are achieved, there will be approximately 11 months’ work to
complete prior to reaching FID, including finalising funding,
completing the land acquisition process, concluding major
construction contracts and entering into offtake agreements with
customers. Resumption of reasonable international travel will
also be required to complete a significant portion of this pre-FID
work and the Company maintains readiness to accelerate progress
when conditions support.
Total expenditure on the Toliara Project for the quarter was
US$2.1 million (last quarter:
US$3.1 million).
[Notes:
(1) For further information, refer to Base
Resources’ announcement on 27 September
2021 “Updated Ranobe Mineral Resources and Ore Reserves
estimates”. Base Resources confirms that it is not aware of
any new information or data that materially affects the information
in this announcement and that all material assumptions and
technical parameters underpinning the estimates in that
announcement continue to apply and have not materially
changed.
(2) For further information, refer to
Base Resources’ announcement on 27 September
2021 “DFS2 enhances scale and economics of the Toliara
Project”. Base Resources confirms that all the material
assumptions underpinning the production information and forecast
financial information in this announcement continue to apply and
have not materially changed.]
Kwale mine life extension
Significant progress was made in the quarter to extend mine life
at Kwale Operations.
In anticipation of completing tenure arrangements to extend the
boundary of Kwale’s Special Mining Lease 23 (SML 23), the
Kwale South Dune Ore Reserves estimate was updated to incorporate
previously defined Mineral Resources falling outside of SML 23,
resulting in Ore Reserves of 40Mt (30Mt Proved, 11Mt Probable) at
an average grade of 3.3% for 1.3Mt of contained HM as at
30 June 2021.3 The
Company subsequently finalised a Deed of Variation with the
Government of Kenya to extend the
boundary of SML 23 to incorporate these additional South Dune Ore
Reserves, taking mine life to December
2023.
In addition, Base Resources completed the Bumamani
pre-feasibility study (PFS) which concluded that it was
economically viable to mine higher-grade subsets of the Bumamani
and Kwale North Dune (P199) deposits, which would extend
mine life at Kwale Operations by a further 7.5 months to
July 2024.4 A DFS is
now underway to improve the accuracy of project estimates and is
expected to be completed in the first half of 2022.
Refer to the full PDF version of this announcement, available
from Base Resources’ website
(https://baseresources.com.au/investors/announcements/), for a map
showing the extended boundary of SML 23 and the location of the
P199 higher grade subsets.
[Notes:
(3): For further information, refer to
Base Resources’ announcement on 20 August
2021 “Updated Kwale South Dune Mineral Resources and Ore
Reserves estimates”. Base Resources confirms that it is not aware
of any new information or data that materially affects the
information in this announcement and that all material assumptions
and technical parameters underpinning the estimates in that
announcement continue to apply and have not materially
changed.
(4): For further information, refer to
Base Resources’ announcements on 3 September
2021 “Bumamani PFS supports extension of Kwale mine life”
and “Further supporting information for Bumamani PFS”. Base
Resources confirms that all the material assumptions underpinning
the production information and forecast financial information in
these announcements continue to apply and have not materially
changed.]
Extensional exploration – Kenya & Tanzania
No further work was conducted on Vanga Prospecting License
(PL/2015/0042) in the quarter and completion of the remaining
drilling program (4,200 metres) in the North-East Sector (Kwale
East) of PL 2018/0119 remains on hold pending community access
being secured.
Prospecting licence applications lodged for an area in the
Kuranze region of Kwale county, about 70 km west of Kwale
Operations (applications 2019 0260, 2510 and 2512), together with
an area south of Lamu (applications 2019 0263, 0265, 0266), remain
in progress towards granting. An additional prospecting
licence application has been lodged for the area surrounded by the
Kuranze applications in Kenya,
however application numbers and boundaries have not yet been
issued. A Government of Kenya moratorium on the issuance of
prospecting licences in November 2019
has affected the progress of all licence applications. The
Company continues to work with the Government, and other mining
sector stakeholders, to see the moratorium lifted and
recommencement of the issuance of mineral rights.
During the quarter, the Company received three prospecting
licences in Tanzania for areas
adjacent to the Kuranze region in Kenya with a fourth licence pending.
Training of a Tanzanian exploration field team is underway
ahead of an auger drilling program planned to commence in the
December quarter.
Refer to the full PDF version of this announcement, available
from Base Resources’ website
(https://baseresources.com.au/investors/announcements/), for a map
showing the location of the Company’s Tanzanian prospecting
licences and remaining prospecting licence application, and Kuranze
prospecting licence applications.
Expenditure on exploration activities in Kenya during the quarter was US$0.3 million (last quarter: US$0.1 million) and in Tanzania was US$0.1
million (last quarter: zero).
CORPORATE
FY21 full-year dividend payment
Following release of the Company’s FY21 annual financial
results, the disciplined application of the Company’s capital
management policy saw a full-year dividend of AUD 4.0 cents per share (unfranked) paid to
shareholders on 29 September 2021,
representing a cash payment of US$34.8
million (in aggregate). This takes total dividends in
respect of FY21 to US$61.4 million,
representing AUD 7.0 cents per share
(unfranked).
Kenyan VAT receivable and Kwale
royalty rate
During the period Base Titanium Limited, Base Resources’ wholly
owned Kenyan Subsidiary, and the Government of Kenya signed Deeds of Variation for the Kwale
SML 23 that amended the mining lease boundary and increased the
rate of royalties payable5 to the Government of
Kenya, such that:
- For the period from the date of first export of minerals to
30 June 2018, the royalty is increased to 3%.
- For the period from 1 July 2018 to the end of SML 23,
the royalty is increased to 5%.
[Note (5): For further
information, refer to Base Resources’ announcement on 30 September 2021 “Kwale mining lease extension
secured and royalty discussions finalised”.]
Prior to being varied, the applicable royalty rate under
SML 23 was 2.5% and it is on this basis that royalties have
been paid. However, from first export of minerals, royalty
costs have been provided for, and expensed, by the Company at an
assumed royalty rate of 5%, based on an expected outcome from the
long running discussions with the Government of Kenya. In
consideration for entry into the Deeds of Variation, in particular
agreement to a royalty for the period to 30
June 2018 at a rate lower than had been accrued, Base
Titanium withdrew its claim for refund of VAT receivables related
to the construction of Kwale Operations.
On the basis of values at 30 June
2021, the net effect of the above is:
- Payment by Base Titanium of US$18.6
million for the agreed increases in royalty rates,
consisting of the 0.5% increase for the period to 30 June 2018 and the 2.5% increase for the period
from 1 July 2018.The related accruals will be extinguished.
- A net US$3.2 million expense will
be recorded in the Company’s financial statements, consisting of
the write back of the excess 2% royalty accrual for the period to
30 June 2018, totalling US$12.8 million, and the write-off of the
construction period VAT receivable of US$16.0 million.
The above additional royalty payments are due in the December
quarter.
Base Resources continues to have refund claims for VAT paid in
Kenya relating to the period since
operations commenced, which totalled approximately US$4.5 million at 30 September 2021. No VAT
refunds were received during the quarter (last quarter:
nil).
In summary, as at 30 September 2021:
- Net cash of US$36.7 million
consisting of:
- Cash and cash equivalents of US$36.7
million.
- No debt.
As at 18 October 2021:
- 1,178,011,850 fully paid ordinary shares on issue.
- 62,435,197 performance rights on issue pursuant to the terms of
the Base Resources Long Term Incentive Plan, comprising:
- 13,835,392 vested performance rights, which remain subject to
exercise6.
- 48,599,805 unvested performance rights subject to performance
testing in accordance with their terms of issue.
[Note (6): Vested
performance rights have a nil cash exercise price. Unless
exercised beforehand, these rights expire five years after
vesting.]
FORWARD LOOKING STATEMENTS
Certain statements in or in connection with this announcement
contain or comprise forward looking statements. Such
statements may include, but are not limited to, statements with
regard to future production and grades, capital cost, capacity,
sales projections and financial performance and may be (but are not
necessarily) identified by the use of phrases such as “will”,
“expect”, “anticipate”, “believe” and “envisage”. By their
nature, forward looking statements involve risk and uncertainty
because they relate to events and depend on circumstances that will
occur in the future and may be outside Base Resources’ control.
Accordingly, results could differ materially from those set
out in the forward-looking statements as a result of, among other
factors, changes in economic and market conditions, success of
business and operating initiatives, changes in the regulatory
environment and other government actions, fluctuations in product
prices and exchange rates and business and operational risk
management. Subject to any continuing obligations under
applicable law or relevant stock exchange listing rules, Base
Resources undertakes no obligation to update publicly or release
any revisions to these forward-looking statements to reflect events
or circumstances after today's date or to reflect the occurrence of
unanticipated events.
ENDS.
For further information contact:
James Fuller, Manager Communications
and Investor Relations |
UK Media Relations |
Base Resources |
Tavistock Communications |
Tel: +61 (8) 9413 7426 |
Jos Simson and Gareth Tredway |
Mobile: +61 (0) 488 093 763 |
Tel: +44 (0) 207 920 3150 |
Email:
jfuller@baseresources.com.au |
|
About Base Resources
Base Resources is an Australian based, African focused, mineral
sands producer and developer with a track record of project
delivery and operational performance. The Company operates
the established Kwale Operations in Kenya and is developing the Toliara Project in
Madagascar. Base Resources is an ASX and AIM listed
company. Further details about Base Resources are available
at www.baseresources.com.au
PRINCIPAL & REGISTERED
OFFICE
Level 3, 46 Colin Street
West Perth, Western Australia, 6005
Email: info@baseresources.com.au
Phone: +61 (0)8 9413 7400
Fax: +61 (0)8 9322 8912
NOMINATED ADVISOR
RFC Ambrian Limited
Stephen Allen
Phone: +61 (0)8 9480 2500
JOINT BROKER
Berenberg
Matthew Armitt / Detlir Elezi
Phone: +44 20 3207 7800
JOINT BROKER
Canaccord Genuity
Raj Khatri / James Asensio /
Patrick Dolaghan
Phone: +44 20 7523 8000