TIDMKMR 
 
 
   Kenmare Resources plc ("Kenmare" or "the Company") 
 
   15 October 2020 
 
   Q3 2020 Production Report 
 
   Kenmare Resources plc (LSE:KMR, ISE:KMR), one of the leading global 
producers of titanium minerals and zircon, which operates the Moma 
Titanium Minerals Mine (the "Mine" or "Moma") in northern Mozambique, is 
pleased to provide a trading update for the quarter ending 30 September 
2020 ("Q3 2020"). 
 
   Statement from Michael Carvill, Managing Director: 
 
   "Following the safe relocation of Wet Concentrator Plant B to the 
Pilivili ore zone in late September, project execution continues to 
progress well. We now expect to begin production at Pilivili in the 
coming days, ahead of our target of the middle of the quarter. Downtime 
for the move is estimated at less than eight weeks, which is a 
significant achievement by our team. Consequently, Q4 2020 is 
anticipated to be our strongest quarter of the year for production, with 
WCP B mining high grade ore and taking us an important step closer to 
our goal of producing 1.2 million tonnes per annum of ilmenite on a 
sustainable basis. 
 
   It is encouraging to see pigment markets improving more quickly than 
expected from COVID-19-related restrictions and consequently we believe 
the outlook for the ilmenite market is robust in Q4 and continuing into 
2021." 
 
   Q3 2020 overview 
 
 
   -- Relocation of Wet Concentrator Plant ("WCP") B completed safely in 
      September 2020 -- mining is expected to commence in the Pilivili ore zone 
      in the coming days 
 
   -- As previously announced, sadly there was a fatality at the Moma Mine on 
      31 August 2020 
 
   -- Lost time injury frequency rate ("LTIFR") of 0.29 per 200,000 hours 
      worked to 30 September 2020 (30 September 2019: 0.20), excluding the 
      fatality 
 
   -- Heavy Mineral Concentrate ("HMC") production of 258,000 tonnes in Q3 
      2020, a 15% decrease compared to Q3 2019 (304,100 tonnes), in line with 
      expectations and due primarily to WCP B temporarily ceasing production 
      from late August onwards, partially offset by WCP C 
 
   -- Ilmenite production of 167,900 tonnes in Q3 2020, a 27% decrease compared 
      to Q3 2019 (230,800 tonnes), primarily as a result of reduced HMC 
      consumption and a short-term reduction in ilmenite content in the HMC 
 
   -- Primary zircon production of 10,900 tonnes, representing a 16% decrease 
      compared to Q3 2019 (12,900 tonnes) due to reduced HMC consumption 
 
   -- Total shipments of finished products of 118,000 tonnes, a 39% decrease 
      compared to Q3 2019 (192,000 tonnes) due to improvement works on a 
      transhipment vessel and continuing poor sea conditions -- Q4 is expected 
      to be the strongest quarter of the year for shipments and has begun well 
 
   -- Kenmare has the majority of its ilmenite sales contracted for the 
      remainder of 2020 and the outlook for 2021 is robust, supported by strong 
      Chinese demand and a recovering pigment market 
 
   -- Oversupply in the zircon market continued in Q3 2020, however supply 
      discipline from the major producers is slowing price declines and the 
      medium-term fundamentals for all of Kenmare's products remain strong 
 
   -- Further strengthening of Kenmare's COVID-19 response, with the opening of 
      a testing facility on site 
 
 
   Operations update 
 
   Operational results for the Moma Mine in Q3 2020 were as follows: 
 
 
 
 
                     Q3 2020      Q3 2019                Q2 2020 
-----------------  ------------  ---------  ----------  ----------  ---------- 
                      tonnes      tonnes    % variance    tonnes    % variance 
-----------------  ------------  ---------  ----------  ----------  ---------- 
Excavated ore(1)      8,333,000  9,219,500        -10%  10,317,000        -19% 
-----------------  ------------  ---------  ----------  ----------  ---------- 
Grade(1)                  3.58%      3.63%         -1%       3.29%          9% 
-----------------  ------------  ---------  ----------  ----------  ---------- 
Production 
-----------------  ------------  ---------  ----------  ----------  ---------- 
HMC production          258,000    304,100        -15%     310,300        -17% 
-----------------  ------------  ---------  ----------  ----------  ---------- 
HMC consumption         260,400    318,800        -18%     311,900        -17% 
-----------------  ------------  ---------  ----------  ----------  ---------- 
Ilmenite                167,900    230,800        -27%     209,900        -20% 
-----------------  ------------  ---------  ----------  ----------  ---------- 
Primary zircon           10,900     12,900        -16%      11,600         -6% 
-----------------  ------------  ---------  ----------  ----------  ---------- 
Rutile                    1,600      2,100        -24%       1,500          7% 
-----------------  ------------  ---------  ----------  ----------  ---------- 
Concentrates(2)           9,000     10,700        -16%       9,000          0% 
-----------------  ------------  ---------  ----------  ----------  ---------- 
Shipments               118,000    192,900        -39%     219,100        -46% 
-----------------  ------------  ---------  ----------  ----------  ---------- 
 
 
   1. Excavated ore and grade prior to any floor losses. 
 
   2. Concentrates include secondary zircon and mineral sands concentrate. 
 
 
   Regrettably, and as previously announced, there was a fatality at the 
Moma Mine on 31 August 2020. The employee, a front-end loader operator, 
suffered a fatal crush injury during the night shift at WCP A's dry 
mining operations. Kenmare's rolling 12 month LTIFR for the 12 months to 
30 September 2020 was 0.29 per 200,000 man-hours worked (30 September 
2019: 0.20), with two lost time injuries recorded during the period. 
These figures exclude the fatality as the primary cause of the incident 
has been found to be not work-related. 
 
   HMC production was 258,000 tonnes in Q3 2020, a 15% decrease compared to 
Q3 2019 (304,100 tonnes) due primarily to a reduction in excavated ore 
volumes to 8.3 million tonnes (Q3 2019: 9.2 million tonnes). This was in 
line with expectations, as a result of no production from WCP B in 
September as it relocated to Pilivili, partially offset by production 
from WCP C. WCP B represents approximately 40% of mining capacity and 
WCP C represents 8%. 
 
   Ore grades in Q3 2020 were 3.58%, broadly in line with Q3 2019 (3.63%). 
They increased by 9% compared to Q2 2020 as WCP A began mining higher 
grades whilst WCP B ceased mining lower grades at the end of its mine 
path. WCP C mined grades averaging 5.99% during the quarter, making a 
robust contribution to production. With the start of production from WCP 
B in the high grade Pilivili ore zone in Q4, average ore grades are 
expected to continue to strengthen. 
 
   As expected, production of all finished products decreased in Q3 2020 
compared to Q3 2019. This was due to an 18% reduction in HMC consumption 
offset by HMC being produced at a lower heavy mineral grade resulting in 
higher mine recoveries during a period of lower HMC production. Ilmenite 
production was 167,900 tonnes, representing a 27% decrease compared to 
Q3 2019 (230,800 tonnes). Ilmenite production was further impacted by 
lower Mineral Separation Plant recoveries due to limited HMC 
availability, and the reduced ilmenite content in HMC, as WCP B 
completed mining in Namalope. It is expected that ilmenite content in 
HMC will increase upon WCP B commencing mining in Pilivili. 
 
   Primary zircon production was 10,900 tonnes, representing a 16% decrease 
compared to Q3 2019 (12,900 tonnes), in line with reduced HMC 
consumption. Rutile production was 1,600 tonnes, a 24% decrease (Q3 
2019: 2,100 tonnes), due to similar reasons as for primary zircon. 
Concentrates production was 9,000 tonnes, a 16% decrease compared to Q3 
2019 (10,700 tonnes) and also in line with reduced HMC availability. 
 
   Kenmare shipped 118,000 tonnes of finished products during the quarter, 
which represents a 39% decrease compared to Q3 2019 (192,900 tonnes). 
This comprised 112,800 tonnes of ilmenite and 5,200 tonnes of 
concentrates. No primary zircon or rutile was shipped during the 
quarter. Q3 2020 shipments were impacted by reduced availability of the 
Peg transhipment vessel, which was undergoing planned five-yearly 
maintenance procedures and improvement works in dry dock during 
September, and continuing adverse weather conditions. 
 
   Kenmare expects Q4 to be the strongest quarter of the year for shipments 
and it has begun well. 
 
   Closing stock of HMC at the end of Q3 2020 was 4,400 tonnes, compared 
with 6,800 tonnes at the end of Q2 2020. Closing stock of finished 
products at the end of Q3 2020 was 227,300 tonnes, compared to 157,000 
tonnes at the end of Q2 2020. 
 
   COVID-19 update 
 
   On 7 September 2020, Mozambique transitioned from a State of Emergency 
to a State of National Public Calamity. This change in status was as a 
result of new legislation being passed and restrictions have largely 
been maintained, such as limitations on public gatherings. However some 
travel restrictions have been eased, allowing for members of the 
management team to travel to site and for employees to leave site and 
return, while still undertaking a mandatory quarantine period. 
 
   As previously announced, a limited number of positive test results have 
been received for employees and contractors. All individuals with 
confirmed positive tests are required to self-isolate in the Moma camp 
and are given appropriate care. 
 
   Management continues to be focused on minimising the potential for 
COVID-19 to spread to the operations, with stringent mitigation measures 
having been in place since March 2020. These include heightened health 
protocols, social distancing measures and testing procedures. During Q3 
2020 Kenmare established an on-site testing facility, which began 
operation in early October 2020. 
 
   Capital projects update 
 
   Kenmare has been progressing three development projects that together 
have the objective of increasing ilmenite production to 1.2 million 
tonnes (plus co-products) per annum on a sustainable basis. 
 
   The third of these projects is the relocation of WCP B and its dredge. 
WCP B and its dredge were relocated 23 kilometres from their former 
mining area at Namalope to a new high grade ore zone called Pilivili. 
Following the move, WCP B and its dredge were positioned onto plinths. 
Establishment of associated infrastructure is underway and the plant is 
being prepared to float in to the starter pond. Following this, the 
dredge and plant will be connected to walkways and feedlines, and 
commissioning of critical equipment at the infrastructure terrace will 
commence. Kenmare expects to produce first HMC from Pilivili and to 
begin commissioning of WCP B in the coming days. 
 
   As previously announced, installation of the positive displacement pumps 
and the overhead powerline experienced delays due to COVID-19-related 
fabrication and transport restrictions. As a result, initially Kenmare 
will truck HMC from Pilivili to the Mineral Separation Plant and power 
will be provided at the Pilivili site by temporary diesel generators. 
Although this will increase operating costs on a temporary basis, it 
ensures that mining can begin at Pilivili as soon as possible, allowing 
Kenmare to access higher grade ore. The Company expects to commission 
the overhead powerline before year-end and the ramp-up of the positive 
displacement pumps is anticipated to begin during Q1 2021. 
 
   While the original project scope remains on budget (US$106 million), the 
additional initiatives required to mitigate the impacts of 
COVID-19-related delays are anticipated to increase overall project 
costs. Capital costs are expected to increase by approximately 17%, 
which are expected to be fully funded by Kenmare's existing financial 
resources. This has increased from previous estimates of a 10% increase 
due to an extension of the project schedule, primarily caused by the 
delayed delivery of the HMC pipeline. Additional operating costs are 
also expected to be incurred for the costs of hauling HMC by road until 
the pipeline is completed and the provision of power by temporary diesel 
generators, but are included in Kenmare's 2020 operating cost guidance. 
 
   Market update 
 
   Ilmenite prices were marginally softer in Q3 2020, as limited supply was 
offset by lower demand from certain geographic regions as a result of 
the pandemic. Kenmare has the majority of its ilmenite sales contracted 
for the remainder of 2020 and is seeing strong demand for remaining spot 
sales in Q4. 
 
   Global pigment demand was negatively impacted by COVID-19-related 
restrictions in Q2 2020, which continued into Q3. Pigment production was 
reduced in response to this lower demand, which resulted in lower demand 
for ilmenite in Q3. However, downstream markets are recovering more 
quickly than expected, as the return of construction activity adds to 
the improving demand for architectural coatings and plastics experienced 
in Q3. 
 
   In China, pigment production remained very strong in Q3 as both the 
domestic and export markets improved throughout the quarter. This higher 
production supported strong demand for ilmenite. Domestic ilmenite 
production remains at lower levels compared to 2019, stimulating 
increased demand for imported ilmenite. Increased imports of low-quality 
ilmenite products and ilmenite concentrates are somewhat bridging this 
gap. Kenmare is seeing strong demand from China for its remaining spot 
sales in Q4 as a result of low inventories of high-quality ilmenite. As 
a result, Kenmare has a more robust outlook for the ilmenite market in 
Q4 and continuing into 2021. 
 
   The oversupply in the zircon market continued in Q3 2020. Demand for 
zircon was subdued prior to COVID-19 and it has been exacerbated further 
by global lockdowns. Prices for Kenmare's zircon were also impacted by a 
reduction in zircon product quality during Q3 due to the operational 
impacts of lower HMC availability and COVID-19-related staff shortages, 
both affecting product recoveries. Travel restrictions have now begun to 
ease, allowing employees to travel to and from site, and product quality 
is expected to return to normal levels during Q4 once WCP B re-commences 
production and HMC availability improves. 
 
   Additionally, the return of construction and real estate activity 
globally is increasing demand. Inventories in the supply chain sit 
mostly with the major zircon producers and supply discipline from these 
producers is slowing price declines. 
 
   Kenmare expects the zircon market to remain challenging in the short 
term, but to strengthen in the medium term as the major zircon mines 
deplete, leading to constrained supply. 
 
   For further information, please contact: 
 
   Kenmare Resources plc 
 
   Jeremy Dibb / Katharine Sutton 
 
   Investor Relations 
 
   https://www.globenewswire.com/Tracker?data=nnr3IxPpJfr3bLYNE88qYaAnxExkmxLT8nXCIP0bHDOhrokafB9XP5plq9zrRhMYv6m6XinaX7SG5p3lZFXIJPhVT0FCpwUBbYInk7rjfI4= 
ir@kenmareresources.com 
 
   Tel: +353 1 671 0411 
 
   Mob: + 353 87 943 0367 / + 353 87 663 0875 
 
   Murray (PR advisor) 
 
   Joe Heron 
 
   Tel: +353 1 498 0300 
 
   Mob: +353 87 690 9735 
 
   About Kenmare Resources 
 
   Kenmare Resources plc is one of the world's largest producers of mineral 
sands products. Listed on the London Stock Exchange and the Euronext 
Dublin, Kenmare operates the Moma Titanium Minerals Mine in Mozambique. 
Moma's production accounts for approximately 7% of global titanium 
feedstocks and the Company supplies to customers operating in more than 
15 countries. Kenmare produces raw materials that are ultimately 
consumed in everyday "quality-of life" items such as paints, plastics 
and ceramic tiles. 
 
   Forward Looking Statements 
 
   This announcement contains some forward-looking statements that 
represent Kenmare's expectations for its business, based on current 
expectations about future events, which by their nature involve risks 
and uncertainties. Kenmare believes that its expectations and 
assumptions with respect to these forward-looking statements are 
reasonable. However, because they involve risk and uncertainty, which 
are in some cases beyond Kenmare's control, actual results or 
performance may differ materially from those expressed or implied by 
such forward-looking information. 
 
 
 
 
 
 

(END) Dow Jones Newswires

October 15, 2020 02:00 ET (06:00 GMT)

Copyright (c) 2020 Dow Jones & Company, Inc.
Kenmare Resources (LSE:KMR)
Historical Stock Chart
From Mar 2024 to Apr 2024 Click Here for more Kenmare Resources Charts.
Kenmare Resources (LSE:KMR)
Historical Stock Chart
From Apr 2023 to Apr 2024 Click Here for more Kenmare Resources Charts.