First Majestic Silver Corp. (AG: NYSE; FR: TSX; FMV:
Frankfurt) ("First Majestic" or the "Company") announces total
production in the second quarter of 2020 reached 3.5 million silver
equivalent ounces consisting of 1.8 million ounces of silver and
15,764 ounces of gold. Quarterly production was impacted following
Mexico’s Ministry of Health’s Federal Decree requiring all
non-essential businesses, including mining, to temporarily suspend
activities throughout most of April and May in response to the
global pandemic. Despite having limited operations in the quarter,
total production was better than expected due to a slower ramp down
at San Dimas compared to the other mining units. In the first half
of 2020, the Company has produced a total of 9.7 million silver
equivalent ounces consisting of 5.0 million ounces of silver and
47,967 ounces of gold.
SECOND QUARTER HIGHLIGHTS
- Total production reached 3.5 million
silver equivalent ounces, consisting of 1.8 million ounces of
silver and 15,764 ounces of gold.
- As of June 30, 2020, the Company
held 970,000 ounces of silver in inventory in anticipation of
realizing higher selling prices in the second half of 2020.
- By quarter end, all operations have returned to near full
production rates following the Mexican Government’s decision to
allow the Company to restart mining activities on May 23,
2020.
- San Dimas received delivery of a new 3,000 tpd High Intensity
Grinding (“HIG”) mill with additional mill modernization components
during the quarter.
- Development activities resumed at Santa Elena’s Ermitaño
project in June and successfully intersected the Ermitaño
vein.
- Civil construction activities resumed in June on the Liquid
Natural Gas (“LNG”) plant at Santa Elena. The LNG generators
and storage tanks are estimated to be delivered to site in the
third quarter.
- At the end of the second quarter, 14 exploration drill rigs
were active across the Company’s projects consisting of 11 rigs at
San Dimas, two rigs at Santa Elena and one rig at La Encantada. The
Company anticipates adding seven additional rigs in the third
quarter with a primary focus on the regional potential around Santa
Elena.
- Preventative controls such as the practice of social
distancing, the cancellation of any non-essential visits to the
mines, comprehensive sanitation measures for the workplace and
company transportation, as well as pre-screening for virus symptoms
remain in effect.
“Despite the temporary shutdown of operations
during the quarter, our production results were better than
anticipated as a result of implementing an extended and safe ramp
down of the San Dimas operation throughout the month of April,”
said Keith Neumeyer, President and CEO. “San Dimas produced a
total of 2.4 million silver equivalent ounces, or 35% lower than
the previous quarter. Total production at the Santa Elena and La
Encantada operations were 63% and 45% lower, respectively, compared
to the prior quarter as a result of suspending operations in early
April.”
Mr. Neumeyer continues, “We began implementing
restart procedures in mid-May following the Ministry of Health’s
announcement that mining activities were now deemed an essential
business throughout Mexico. As of today, our operations are
back to pre-pandemic production rates and our focus for the second
half of 2020 is to try and fully recover the lost ounces due to the
shutdown.”
PRODUCTION TABLE
|
Q2 |
Q2 |
Y/Y |
Q1 |
Q/Q |
2020 |
2019 |
Change |
2020 |
Change |
Ore
processed/tonnes milled |
333,559 |
736,896 |
-55 |
% |
599,142 |
-44 |
% |
Total production -
ounces of silver eqv. |
3,505,376 |
6,410,483 |
-45 |
% |
6,195,057 |
-43 |
% |
Silver ounces
produced |
1,834,575 |
3,193,566 |
-43 |
% |
3,151,980 |
-42 |
% |
Gold ounces produced |
15,764 |
33,576 |
-53 |
% |
32,202 |
-51 |
% |
QUARTERLY REVIEWTotal ore
processed during the quarter at the Company's mines amounted to
333,559 tonnes, representing a 44% decrease compared to the
previous quarter. The decrease in tonnes processed compared to the
prior quarter was due to Mexico’s Ministry of Health’s Decree
requiring non-essential businesses to temporarily suspend
activities in response to the global pandemic.
Consolidated silver grades in the quarter
averaged 193 g/t compared to 185 g/t in the previous quarter. This
4% increase was primarily the result of higher grades at San Dimas.
Consolidated gold grades averaged 1.52 g/t compared to 1.74 g/t in
the prior quarter representing a 12% decrease primarily due to
lower gold grades at Santa Elena.
Consolidated silver and gold recoveries were
consistent averaging 89% and 96%, respectively, during the
quarter.
MINE BY MINE PRODUCTION
TABLE
|
|
|
|
|
|
|
|
|
|
Mine |
Ore Processed |
Tonnesper Day |
Ag Grade(g/t) |
Au Grade(g/t) |
AgRecovery |
AuRecovery |
Ag OzProduced |
Au OzProduced |
EquivalentAg Ounces |
San Dimas |
114,390 |
1,257 |
318 |
3.38 |
94 |
% |
97 |
% |
1,102,931 |
12,042 |
2,395,633 |
Santa Elena |
89,590 |
985 |
83 |
1.34 |
92 |
% |
95 |
% |
222,100 |
3,677 |
595,651 |
La Encantada |
129,579 |
1,424 |
158 |
0.01 |
78 |
% |
90 |
% |
509,544 |
45 |
514,092 |
Total |
333,559 |
3,665 |
193 |
1.52 |
89 |
% |
96 |
% |
1,834,575 |
15,764 |
3,505,376 |
|
|
|
|
|
|
|
|
|
|
*Certain amounts shown may not add exactly to the total amount
due to rounding differences.*The following prices were used in the
calculation of silver equivalent ounces: Silver: $16.37 per ounce,
Gold: $1,711 per ounce.
At the San Dimas Silver/Gold
Mine:
- During the quarter, San Dimas produced 1,102,931 ounces of
silver and 12,042 ounces of gold for a total production of
2,395,633 silver equivalent ounces, reflecting a 35% decrease
compared to the prior quarter due to the COVID-19 related
shutdown.
- The mill processed a total of 114,390 tonnes with average
silver and gold grades of 318 g/t and 3.38 g/t, respectively.
- Silver and gold recoveries were slightly higher during the
quarter averaging 94% and 97%, respectively.
- Initial production from the Tayoltita mine began in June and is
expected to ramp-up to 300 tpd by the end of 2020.
- Mill modernization and optimization programs have resumed at
San Dimas, including the mid-May delivery of the 3,000 tpd HIG mill
and several components. As a result of the temporary suspension
during the quarter, assembly and installation of the new HIG mill
is now expected to be completed in the second quarter of
2021.
- In mid-June, production was temporarily suspended due to a
union work stoppage. Following a two-week standstill period, the
Company and union came to a mutually negotiated bonus agreement at
the end of June, and at which time production returned to normal
operating levels.
- A total of 11 drill rigs, consisting of one surface rig and 10
underground rigs, were active at the end of the quarter. Drilling
is currently being focused in the Central, Sinaloa and Tayoltita
blocks.
At the Santa Elena Silver/Gold
Mine:
- During the quarter, Santa Elena produced 222,100 ounces of
silver and 3,677 ounces of gold for a total production of 595,651
silver equivalent ounces, or approximately 63% below the previous
quarter.
- The mill processed a total of 89,590 tonnes, consisting of
58,223 tonnes of underground ore and 31,366 tonnes from the above
ground heap leach pad.
- Silver and gold grades from underground ore averaged 109 g/t
and 1.70 g/t, respectively, while silver and gold grades from the
above ground heap leach pad averaged 32 g/t and 0.62 g/t,
respectively.
- Silver and gold recoveries averaged 92% and 95%, respectively,
during the quarter.
- To help minimize health risks and accommodate Santa Elena
workers that travel from outside communities, the Company
established a temporary camp at Santa Elena. In addition, a second
temporary camp was constructed near Ermitaño to assist with housing
of the development contractors and construction workers.
- Development and construction activities resumed at the Ermitaño
project in June and successfully intersected the Ermitaño vein. At
the end of the quarter, a total of 468 metres of underground
development have been completed and approximately 480 metres of
main ramp and 80 metres of lateral development remain to be
developed in order to access the high-grade portion of the Ermitaño
ore body.
- The LNG power generation plant resumed civil construction
activities in June. Delivery of the LNG generators and storage
tanks are expected to be onsite in the third quarter of 2020. As a
result of the temporary suspension, the LNG plant is now estimated
to be completed and commissioned in the first quarter of 2021.
- Due to the temporary suspension of activities in the quarter,
the Ermitaño pre-feasibility study is now expected to be completed
in the first half of 2021. In addition, initial production from
Ermitaño has been extended to mid-2021.
At the La Encantada Silver
Mine:
- During the quarter, La Encantada
processed 129,579 tonnes of ore and produced 509,544 ounces of
silver, or approximately 45% below the previous quarter.
- Silver grades and recoveries during
the quarter averaged 158 g/t and 78%, respectively.
- Silver recoveries continue to
exceed historical rates primarily due to optimal blending of
stockpiles and maintaining an efficient pumping level on the
precipitate tanks.
OUTLOOK
The Company is revising its second half and full
year 2020 guidance to reflect changes due to the temporary
suspension of production and sales as well as adjustments to metal
price assumptions, foreign exchange rates, and the fixed exchange
ratio on the San Dimas streaming agreement. Details of the changes
and their expected impacts are presented below:
- Deferred a total of approximately 340,000 tonnes of ore
production, consisting of 1.6 million ounces of silver and 15,000
ounces of gold, due to the temporary shutdown in the second quarter
of 2020
- As of June 30, 2020, the Company held 970,000 ounces of silver
in inventory in anticipation of realizing higher selling prices in
the second half of 2020
- Increased the gold price assumption to $1,700 per ounce (up
from $1,450), reflecting a 100:1 silver to gold ratio
- Increased the MXN:USD ratio assumption to 21:1 (up from
19:1)
- Effective April 1, 2020, the silver to gold fixed exchange
ratio related to the San Dimas streaming agreement with Wheaton
Precious Metals was adjusted to 90:1 (from 70:1) due to the silver
to gold ratio averaging above 90:1 for the previous six months.
This ratio adjustment is expected to have a positive effect on
revenues by approximately $3.0 million for the remainder of 2020,
subject to achieving the mid-point of the new production guidance
and realizing silver and gold prices per ounce of $17.00 and
$1,700, respectively.
As a result of these adjustments, our 2020 total
production remains relatively unchanged at 21.4 to 22.9 million
silver equivalent ounces compared to the prior guidance of 21.5 to
24.0 million silver equivalent ounces. The Company is also
anticipating a reduction in annualized cash costs of approximately
30% due to the higher gold by-product revenues and the weaker
Mexican Peso.
The Company is also providing guidance below on
a mine-by-mine basis for the second half of 2020. Cash cost
and AISC guidance is shown per payable silver ounce. Assumptions
used for calculating silver equivalent ounces are: silver:
$17.00/oz and gold: $1,700/oz.
GUIDANCE FOR SECOND HALF OF
2020
Mine |
Silver Oz (M) |
Gold Oz (k) |
Silver Eqv Oz (M) |
Cash Costs ($) |
AISC ($) |
San Dimas |
3.3 – 3.6 |
42 – 47 |
7.5 – 8.3 |
(0.95) – 0.23 |
4.72 – 6.55 |
Santa Elena |
1.1 – 1.2 |
16 – 18 |
2.7 – 3.0 |
2.53 – 3.72 |
6.75 – 8.43 |
La Encantada |
1.7 – 1.8 |
– |
1.7 – 1.8 |
10.86 – 11.56 |
12.82 – 13.75 |
Totals: |
6.1 – 6.6 |
58 – 65 |
11.9 – 13.1 |
$2.93 – $3.99 |
$10.57 – $12.49 |
*Certain amounts shown may not add exactly to
the total amount due to rounding differences.*Consolidated AISC
includes general and administrative cost estimates and non-cash
costs of $2.35 to $2.62 per payable silver ounce.
In the second half of 2020, the Company expects
silver production to range between 6.1 to 6.6 million ounces,
representing an increase of approximately 27% when compared to the
first half of 2020. Additionally, total production is now expected
to range between 11.9 to 13.1 million silver equivalent ounces in
the second half of 2020, representing an increase of approximately
29% when compared to the first half of 2020. The increase in
production is primarily due to the operations returning to regular
production rates in the second half of 2020, as well as a higher
contribution of gold credits due to an increase in the gold to
silver ratio.
Cash costs in the second half of 2020 are
expected to be significantly lower to within the range of $2.93 to
$3.99 per ounce, primarily due to higher gold by-product credits at
San Dimas and Santa Elena and the weaker Mexican Peso. In addition,
AISC are expected to be within a range of $10.57 to $12.49 per
ounce in the second half of 2020.
A mine-by-mine breakdown of the revised full
year 2020 production guidance is included in the table below and
assumes the same metal prices and foreign currency assumptions as
stated previously.
GUIDANCE FOR FULL YEAR 2020
Mine |
Silver Oz (M) |
Gold Oz (k) |
Silver Eqv Oz (M) |
Cash Costs ($) |
AISC ($) |
San Dimas |
6.0 – 6.4 |
75 – 80 |
13.5 – 14.4 |
0.75 – 1.49 |
7.09 – 8.22 |
Santa Elena |
1.9 – 2.0 |
31 – 33 |
4.8 – 5.2 |
3.60 – 4.38 |
8.33 – 9.43 |
La Encantada |
3.1 – 3.3 |
– |
3.1 – 3.3 |
10.42 – 10.77 |
12.59 – 13.07 |
Totals: |
11.0 – 11.7 |
106 – 113 |
21.4 – 22.9 |
$3.95 – $4.59 |
$12.29 – $13.45 |
*Certain amounts shown may not add exactly to
the total amount due to rounding differences.*Consolidated AISC
includes general and administrative cost estimates and non-cash
costs of $2.81 to $2.99 per payable silver ounce.
For the full year of 2020, the Company now
estimates silver production will range between 11.0 to 11.7 million
ounces compared to the prior guidance of 11.8 to 13.2 million
ounces. Additionally, total production in 2020 is estimated to
range between 21.4 to 22.9 million silver equivalent ounces
compared to the prior guidance of 21.5 to 24.0 million silver
equivalent ounces.
Annual cash costs are now expected to be within
the range of $3.95 to $4.59 per ounce, or approximately 30% below
the previous guidance of $5.76 to $6.97 per ounce, primarily due to
higher gold by-product credits at San Dimas and Santa Elena and the
weaker Mexican Peso. In addition, annual AISC are expected to be
within a range of $12.29 to $13.45 per ounce, or approximately 10%
below the previous guidance of $13.37 to $15.46 per ounce.
REVISED CAPITAL BUDGET
In an effort to maintain its strong balance
sheet, the Company has updated its annual 2020 capital budget to
include the reallocation of development and exploration
expenditures across its operations and investments in innovative
projects. As a result, the Company now plans to invest a total of
$131.8 million, representing a 23% decrease compared with previous
guidance of $171.5 million, on capital expenditures in 2020
consisting of $45.7 million of sustaining investments and $86.1
million of expansionary investments.
The revised 2020 annual budget includes total
capital investments of $54.0 million on underground development,
$27.4 million towards property, plant and equipment, $21.4 million
on exploration and $29.0 million towards automation and efficiency
projects.
In the first half of 2020, the Company completed
15,555 metres of underground development and 50,709 metres of
exploration drilling. Under the revised 2020 budget, the Company is
planning to complete a total of approximately 35,100 metres of
underground development, representing a 9% decrease compared to the
original guidance. In addition, the Company is now planning to
complete a total of approximately 139,000 metres of exploration
drilling in 2020, representing a 28% decrease compared to the
original guidance.
CONFERENCE CALL
The Company will be holding a conference call
and webcast today, July 15, 2020 at 8 am PDT (11 am EDT) to
discuss the quarterly results.
To participate in the conference call, please
dial the following:
Toll Free Canada & USA: |
|
1-800-319-4610 |
Outside of Canada & USA: |
|
1-604-638-5340 |
Toll Free Germany: |
|
0800 180 1954 |
Toll Free UK: |
|
0808 101 2791 |
Participants should dial in 10 minutes prior to
the conference.
Click on WEBCAST on the First Majestic homepage
as a simultaneous audio webcast of the conference call will be
posted at www.firstmajestic.com.
The conference call will be recorded, and you
can listen to an archive of the conference by calling:
Canada & USA Toll Free: |
|
1-800-319-6413 |
Outside Canada & USA: |
|
1-604-638-9010 |
Access Code: |
|
4820 followed by the # sign |
The replay will be available approximately one
hour after the conference and will available for seven days
following the conference. The replay will also be available
on the Company’s website for one month.
Q2 EARNINGS ANNOUNCEMENT
The Company is planning to release its second
quarter 2020 unaudited financial results on Thursday, August 6,
2020.
ABOUT THE COMPANY
First Majestic is a publicly traded mining
company focused on silver production in Mexico and is aggressively
pursuing the development of its existing mineral property assets.
The Company presently owns and operates the San Dimas Silver/Gold
Mine, the Santa Elena Silver/Gold Mine and the La Encantada Silver
Mine. Production from these mines are projected to be between
11.0 to 11.7 million silver ounces or 21.4 to 22.9 million silver
equivalent ounces in 2020.
FOR FURTHER INFORMATION contact
info@firstmajestic.com, visit our website at www.firstmajestic.com
or call our toll-free number 1.866.529.2807.
FIRST MAJESTIC SILVER CORP.
"signed"
Keith Neumeyer, President & CEO
Cautionary Note Regarding Forward Looking
Statements
This press release contains “forward‐looking
information” and "forward-looking statements” under applicable
Canadian and U.S. securities laws (collectively, “forward‐looking
statements”). These statements relate to future events or the
Company's future performance, business prospects or opportunities
that are based on forecasts of future results, estimates of amounts
not yet determinable and assumptions of management made in light of
management's experience and perception of historical trends,
current conditions and expected future developments.
Forward-looking statements include, but are not limited to,
statements with respect to: the Company’s business strategy; future
planning processes; commercial mining operations; cash flow;
budgets; the timing and amount of estimated future production;
recovery rates; mine plans and mine life; the future price of
silver and other metals; costs of production; costs and timing of
the development of new deposits; capital projects and exploration
activities and the possible results thereof. Assumptions may
prove to be incorrect and actual results may differ materially from
those anticipated. Consequently, guidance cannot be guaranteed. As
such, investors are cautioned not to place undue reliance upon
guidance and forward-looking statements as there can be no
assurance that the plans, assumptions or expectations upon which
they are placed will occur. All statements other than statements of
historical fact may be forward‐looking statements. Statements
concerning proven and probable mineral reserves and mineral
resource estimates may also be deemed to constitute forward‐looking
statements to the extent that they involve estimates of the
mineralization that will be encountered as and if the property is
developed, and in the case of measured and indicated mineral
resources or proven and probable mineral reserves, such statements
reflect the conclusion based on certain assumptions that the
mineral deposit can be economically exploited. Any statements that
express or involve discussions with respect to predictions,
expectations, beliefs, plans, projections, objectives or future
events or performance (often, but not always, using words or
phrases such as “seek”, “anticipate”, “plan”, “continue”,
“estimate”, “expect”, “may”, “will”, “project”, “predict”,
“forecast”, “potential”, “target”, “intend”, “could”, “might”,
“should”, “believe” and similar expressions) are not statements of
historical fact and may be “forward‐looking statements”.
Actual results may vary from forward-looking
statements. Forward-looking statements are subject to known and
unknown risks, uncertainties and other factors that may cause
actual results to materially differ from those expressed or implied
by such forward-looking statements, including but not limited to:
the duration and effects of the coronavirus and COVID-19, and any
other pandemics on our operations and workforce, and the effects on
global economies and society, risks related to the integration of
acquisitions; actual results of exploration activities; conclusions
of economic evaluations; changes in project parameters as plans
continue to be refined; commodity prices; variations in ore
reserves, grade or recovery rates; actual performance of plant,
equipment or processes relative to specifications and expectations;
accidents; labour relations; relations with local communities;
changes in national or local governments; changes in applicable
legislation or application thereof; delays in obtaining approvals
or financing or in the completion of development or construction
activities; exchange rate fluctuations; requirements for additional
capital; government regulation; environmental risks; reclamation
expenses; outcomes of pending litigation; limitations on insurance
coverage as well as those factors discussed in the section entitled
"Description of the Business - Risk Factors" in the Company's most
recent Annual Information Form, available on www.sedar.com, and
Form 40-F on file with the United States Securities and Exchange
Commission in Washington, D.C. Although First Majestic
has attempted to identify important factors that could cause actual
results to differ materially from those contained in
forward-looking statements, there may be other factors that cause
results not to be as anticipated, estimated or intended.
The Company believes that the expectations
reflected in these forward‐looking statements are reasonable, but
no assurance can be given that these expectations will prove to be
correct and such forward‐looking statements included herein should
not be unduly relied upon. These statements speak only as of the
date hereof. The Company does not intend, and does not assume any
obligation, to update these forward-looking statements, except as
required by applicable laws.
First Majestic Silver (TSX:FR)
Historical Stock Chart
From Jan 2025 to Feb 2025
First Majestic Silver (TSX:FR)
Historical Stock Chart
From Feb 2024 to Feb 2025