Anglesey Mining Plc Parys Mountain Progress Report
June 19 2023 - 1:00AM
UK Regulatory
TIDMAYM
[image]
Trading Symbol
AIM: AYM
19th June 2023
Anglesey Mining plc
("Anglesey" or "the Company")
Parys Mountain Progress Report
Anglesey Mining plc (AIM:AYM), the UK minerals development company, is pleased
to provide an update on progress at the Company's Parys Mountain Cu-Zn-Pb-Ag-Au
project located on the Isle of Anglesey.
Highlights
· The Company has commenced the design, planning and logistics for the first
round of infill drilling into the Northern Copper Zone ("NCZ") since 1974. The
proposal is based on 6 drillholes (3,700m) to infill portions of the current
resource and to provide verification of the historical drilling. The drilling
will also be testing for extensions of the nearby, high-grade Garth Daniel and
Central Zones.
· The NCZ has a 2012 resource estimate of 9.4Mt at 1.27% Cu, plus minor Au,
Ag, Zn and Pb credits (1.6% CuEq) - although very few holes were assayed for all
the metals. The internal resource estimate from the early 1970's was >30Mt at
0.81% Cu, which excluded any by-products.
· The 6 proposed holes could potentially provide up to 14 pierce points across
the NCZ, the Garth Daniel Zone and the Central Zone, based on current
interpretations. The Company expects the rig to be mobilised to site sometime in
August with the programme potentially taking up to 25 weeks.
· The Company has also been informed by our retained mineral processing
consultancy firm, Grinding Solutions Limited ("GSL"), that the metallurgical
testwork will commence in late June and will take approximately 10 weeks to
complete. This testwork has been designed to determine which pre-concentration
method is the most optimal process to go into the plant design (Dense Media
Separation or XRT ore-sorting).
· The Company dispatched a 340kg sample to GSL comprising a blend of White
Rock and Engine Zone with a combined head-grade of 0.42% Cu, 3.60% Zn, 3.08% Pb,
49g/t Ag and 0.7g/t Au (3.4% CuEq). The blend as delivered is 3.3 (White Rock)
to 1.0 (Engine Zone), similar to the contribution that is expected to be
delivered from the mine in the early years, prior to the Northern Copper Zone
commencing.
· Subsequent to the previously announced Pre-Application Consultation in April
2023, the Company has now received the responses from the statutory consultees.
These responses will be reviewed and included in the Environmental Impact &
Social Assessment ("EISA") Scoping Document, which will form the basis for the
EISA that is required to be submitted as part of the planning consent process.
· Other environmental work recently undertaken includes additional day and
night wildlife surveys and preparations for the commencement of the groundwater
survey, which will feed into both the infrastructure foundation designs and the
dry-stack tailings engineering studies.
Jo Battershill, Chief Executive of Anglesey Mining, commented: "We are very
pleased to provide this update on the Company's Parys Mountain base and precious
metals project. The proposed drilling of the Northern Copper Zone is very
exciting and could potentially lead to a significant portion of the deposit
being upgraded into the Indicated category, while also delivering some broad
widths of copper mineralisation into a copper hungry market. Historical drilling
hits included 146.3m at 1.0% Cu, 0.2% Pb, 0.3% Zn and 7g/t Ag, and 86.4m at 0.9%
Cu."
"The programme has been designed to also test for extensions to the Garth Daniel
and Central Zones where previous drilling has identified very high-grade zones
that are just a short distance from the Northern Copper Zone. Very few of the
historical intersections were incorporated into the current mineral resource
estimate, so any success on these zones could have very positive implications on
future resource updates. Historical drilling intersections include 5.2m at 3.3%
Cu, 6.2% Pb, 11.7% Zn, 434g/t Ag and 0.23g/t Au in the Garth Daniel zone and
3.8m at 8.3% Cu and 32g/t Ag in the Central Zone."
"We are cognisant that the market for junior resources remains very difficult.
However, with an advanced base metals project located in the UK, the Board
believes Anglesey Mining can differentiate itself from the pack."
Parys Mountain
The Parys Mountain Project is located on the Isle of Anglesey in North Wales.
The deposit is a volcanogenic massive sulphide ("VMS") containing elevated
levels of Cu, Zn, Pb, Ag and Au. The current resource estimate is 16.1 Mt @ 1.0%
Cu, 1.3% Zn, 0.7% Pb, 15g/t Ag & 0.2g/t Au and contains almost 500,000t of
combined Cu, Zn and Pb along 8.0Moz of silver and over 100,000oz of gold. The
resources are contained within five key zones - White Rock, Engine Zone, Deep
Engine Zone, Garth Daniel and the Northern Copper Zone (Figure 1).
[image]
Figure 1 - Schematic long section of the Parys Mountain deposit showing the
different mineralised zones, the extent of existing drilling and the two
sections to be drilled
The deposit is interpreted to be hosted within an overturned synclinal structure
with some subsequent thrust faulting. Mineralisation is associated with
rhyolites that have been intruded into a sedimentary sequence - the modern-day
analogy for VMS deposits are `black smokers' found on the seabed.
Drilling has been designed to infill two sections of the Northern Copper Zone -
4600mE and 4800mE as shown on Figure 1. Due to the orientation of the deposits,
extending the Northern Copper Zone infill holes will also allow for additional
testing of the high-grade Garth Daniel zone (Inferred resource of 0.34Mt @ 5.8%
Zn, 2.8% Pb, 1.9% Cu, 66g/t Ag and 0.1g/t Au). Two of the holes will also drill
through the interpreted position of the `Central Zone', which has previously
been identified by limited drilling but does not have a resource estimate -
previous holes within the Central Zone include intersections of 6.7m @ 2.4%
CuEq, 3.8m @ 8.6% CuEq, 1.3m @ 2.8% CuEq and broader hits of 28m @ 0.82% CuEq
and 35m @ 0.75% CuEq.
The holes proposed for this programme are detailed in the table below and in
figures 2 and 3, and may be subject to change.
[image]
Table 1 - Parys Mountain drill hole proposal
[image]
Figure 2 - Schematic cross section through 4600mE showing geology
interpretation, existing drill holes and proposed drilling
[image]
Figure 3 - Schematic cross section through 4800mE showing geology
interpretation, existing drill holes and proposed drilling
About Anglesey Mining plc
Anglesey Mining is traded on the AIM market of the London Stock Exchange and
currently has 379,809,689 ordinary shares on issue.
Anglesey is developing its 100% owned Parys Mountain Cu-Zn-Pb-Ag-Au deposit in
North Wales, UK with a reported resource of 5.3 million tonnes at over 4.0%
combined base metals in the Measured and Indicated categories and 10.8 million
tonnes at over 2.5% combined base metals in the Inferred category.
Anglesey also holds an almost 50% interest in the Grängesberg Iron project in
Sweden, together with management rights and a right of first refusal to increase
its interest to 100%. Anglesey also holds 12% of Labrador Iron Mines Holdings
Limited, which through its 52% owned subsidiaries, is engaged in the exploration
and development of direct shipping iron ore deposits in Labrador and Quebec.
For further information, please contact:
Anglesey Mining plc
Jo Battershill, Chief Executive - Tel: +44 (0)7540 366000
John Kearney, Chairman - Tel: +1 416 362 6686
Davy
Nominated Adviser & Joint Corporate Broker
Brian Garrahy / Daragh O'Reilly - Tel: +353 1 679 6363
WH Ireland
Joint Corporate Broker
Katy Mitchell / Harry Ansell - Tel: +44 (0) 207 220 1666
LEI: 213800X8BO8EK2B4HQ71
This information was brought to you by Cision http://news.cision.com
https://news.cision.com/anglesey-mining-plc/r/parys-mountain-progress-report,c3771361
The following files are available for download:
https://mb.cision.com/Public/22377/3771361/a3bff3cdd5a59ea8.pdf RNS Parys Mountain update
END
(END) Dow Jones Newswires
June 19, 2023 02:00 ET (06:00 GMT)