African Gold Group, Inc. (TSX-V: AGG) (“
AGG” or
the “
Company”) is pleased to provide an update on
the development of its flagship Kobada Project. During the past
months, the Company has been working diligently at advancing the
project, focusing mainly on increasing the reserve base and
optimizing the free-milling sulphide metallurgical testing as noted
in previous press releases on March 16, 2021 and March 30, 2021.
Following the highly encouraging results from
the exploration drilling campaign and sulphide metallurgical
testwork, the Company has received board approval to initiate an
update to the July 2020 Definitive Feasibility Study
(“DFS”) with the goal of increasing the production
profile and overall project economics beyond the robust results of
the previous DFS.
Highlights of July 2020
DFS:
- Average annual production
of 100,000 ounces of gold per annum for the first 5 years of
operation.
- Total gold production of
728,654 ounces over 9.4 years life of mine, based on current
reserves.
- Average total operating
cash costs US$704/oz for the Life of Mine (“LOM”).
- LOM All-In Sustaining Cost
(“AISC”) of US$782/oz.
- Pre-tax
NPV5% of US$283.9 million
with an IRR of 45.5% and a post-tax
NPV5% of $226 million with
an IRR of 41.1% at US$1,530/oz gold.
- Kobada Gold Project capital
expenditure of US$125 million (plus a contingency of US$11
million).
The feasibility study is being updated to
reflect the improved optimisation work on the processing plant,
increase in reserve base and gold price environment and results
from the sulphide metallurgical testwork. The Company believes an
update on the feasibility study will further enhance the economics
of the project.
Danny Callow, Chief Executive Officer of AGG
comments;
“We are continuing our progress towards
improving the scale and economics of the Kobada project through an
update to the July 2020 Definitive Feasibility Study. Our target is
to deliver more reserve ounces, which should show improved life of
mine and economics. The updated study requires significant work as
we will need to review resources and reserves, an updated mine
optimisation and schedule, additional refinements to the processing
plant and a larger tailings dam. In addition, we will work through
the updates to the ESIA.”
Throughout the past 19 months we have undertaken
a systematic process to review and clean up historical data, drill
close to 20,000 exploration metres, optimise oxide and sulphide
test work and deliver a Definitive Feasibility Study that produces
a world class project, with substantial economic returns to
shareholders. The update of the DFS is the next step in our
programme to continue to increase the value and free cash flow in
this project.”
Appointment of SENET
SENET (Pty) Ltd. (“SENET”), a
DRA Global Group Company, has been awarded the contract to deliver
an update on a definitive feasibility study.
SENET is one of the leading project management
and engineering firms in the field of mineral processing. For
almost three decades SENET has provided project management,
multidisciplinary engineering, procurement and logistics
management, and construction services to the mining and mineral
processing industry. SENET has a proven track record in taking
projects from feasibility study through to production.
To date, SENET has completed in excess of 200
projects and facilities, as well as over 300 studies, and in which
the scope of work has included a variety of mineral/metallurgical
process plants, crushing and screening plants and bulk materials
handling facilities for mining and industrial applications.
Hugo Swart, Projects Director of SENET
comments;
“We are very pleased to continue our
collaboration with AGG on the Kobada Project. We have been involved
in the Kobada project throughout the past 19 months and have seen
the study evolve from a 50,000oz project in 2019 to the 100,000oz
project delivered in the DFS in 2020. We will continue to optimise
all aspects of the study and look forward to incorporating the
additional sulphides testwork and additional drilling information
into the next update.”
About African Gold Group
African Gold Group is a TSX Venture Exchange
(TSX-V: AGG) listed exploration and development company with a
focus on building Africa’s next mid-tier gold producer. The Company
has a highly experienced board and management team with a proven
track record in the African mining sector operating mines from
development through to production. AGG’s principal asset is the
Kobada Project in southern Mali, which is in an advanced stage of
development having completed the 2020 definitive feasibility study
and is targeting gold production of 100,000 oz per annum. As well
as the initial Kobada Gold Project, other exploration locations
have been identified on the Kobada, Farada and Kobada Est
concessions, offering potential for an increase in resource. For
more information regarding African Gold Group visit our website at
www.africangoldgroup.com.
For more information:
Danny Callow President and Chief Executive Officer+(27) 76 411
3803 Danny.Callow@africangoldgroup.com
Scott EldridgeNon-Executive Chairman of the Board(604)
722-5381Scott.Eldridge@africangoldgroup.com
Daniyal Baizak VP Corporate Development (647)
835-9617Daniyal.Baizak@africangoldgroup.com
Camarco (Financial PR)Gordon Poole Nick Hennis +44 (0) 20 3757
4997 AfricanGoldGroup@camarco.co.uk
Cautionary statements
This press release contains “forward-looking
information” within the meaning of applicable Canadian securities
legislation. Forward-looking information includes, but is not
limited to, statements regarding, processing of sulphide materials,
appointment of officers and the grant of incentive stock options.
Generally, forward-looking information can be identified by the use
of forward-looking terminology such as “plans”, “expects” or “does
not expect”, “is expected”, “budget”, “scheduled”, “estimates”,
“forecasts”, “intends”, “anticipates” or “does not anticipate”, or
“believes”, or variations of such words and phrases or statements
that certain actions, events or results “may”, “could”, “would”,
“might” or “will be taken”, “occur” or “be achieved”.
Forward-looking information is subject to known and unknown risks,
uncertainties and other factors that may cause the actual results,
level of activity, performance or achievements of AGG to be
materially different from those expressed or implied by such
forward-looking information, including but not limited to: receipt
of necessary approvals; general business, economic, competitive,
political and social uncertainties; future prices of mineral
prices; accidents, labour disputes and shortages and other risks of
the mining industry. Although AGG has attempted to identify
important factors that could cause actual results to differ
materially from those contained in forward-looking information,
there may be other factors that cause results not to be as
anticipated, estimated or intended. There can be no assurance that
such information will prove to be accurate, as actual results and
future events could differ materially from those anticipated in
such statements. Accordingly, readers should not place undue
reliance on forward-looking information. AGG does not undertake to
update any forward-looking information, except in accordance with
applicable securities laws.
NEITHER TSX VENTURE EXCHANGE NOR ITS
REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE
POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR
THE ADEQUACY OR ACCURACY OF THIS RELEASE.
African Gold (TSXV:AGG)
Historical Stock Chart
From Oct 2024 to Nov 2024
African Gold (TSXV:AGG)
Historical Stock Chart
From Nov 2023 to Nov 2024