Sherwood Copper Corporation (TSX VENTURE:SWC)(TSX VENTURE:SWC.DB) today
announced results of an independent preliminary economic assessment ("PEA") for
its high grade Kutcho copper project in NW British Columbia. This study
significantly simplifies development approach to the project, but only evaluates
the development of part of one of the three identified mineral deposits at
Kutcho. However, the PEA lays out several opportunities for enhanced project
economics, a number of which Sherwood is already evaluating as part of its
on-going work program.


"The completion of the preliminary economic assessment for the high grade Kutcho
copper project is just the first step in Sherwood's on-going reassessment of the
project's potential," said Stephen Quin, President & CEO. "This study evaluates
the potential for the development of a smaller, less capital intensive open pit
mining operation on a portion of the Main deposit that can be developed
relatively quickly. We are now pursuing two parallel tracks to enhance this base
case option by evaluating: (a) a number of opportunities identified within the
study that could significantly enhance the economics of the project as defined,
and (b) the potential of increasing the production and mine life by
incorporating some of the more than 50% of the project mineral resources not
considered in this study," he said. "The most significant upside opportunities
currently being evaluated are increasing the tonnes and grade of material to be
processed and improving metallurgical recoveries beyond those assumed in the
study. To this end, we have a major drill program underway at Kutcho to not only
better define the highest grade, closest to surface portion of the Main deposit,
but to provide sample material for extensive metallurgical testing designed to
evaluate opportunities for enhanced metal recoveries."


Using the PEA as a platform, Sherwood intends to re-engage the regulatory
agencies and advance the Kutcho copper project through the permitting process.
With extensive baseline data, Sherwood has commenced drafting an Environmental
Assessment for submission in the third quarter of 2008. In parallel with the
regulatory process, Sherwood aims to continue to actively engage the Tahltan and
Kaska First Nations in a consultation process in order to gain their support for
the advancement of this project.


"Given the decline of active mining in NW British Columbia and the uncertainty
surrounding the potential development of a number of other projects in the
region, the high grade Kutcho copper project stands out as a mine that could be
advanced to production relatively quickly, assuming appropriate support and
approvals for the project," said Mr. Quin. "Our approach to the development of
the project should significantly reduce the environmental footprint of the
project versus previous proposals and should simplify the long-term abandonment
and restoration of the site post-closure," he said. "In addition, the smaller
scale of the proposed development may result in an extended mine life, once the
remainder of the mineral resources not considered in this study are evaluated
and, if warranted, incorporated into an expanded project."


Sherwood intends to issue an updated PEA in the fall of 2008 that would
incorporate the results of the 2008 infill drilling, results from initial
metallurgical testing currently in process and incorporation of other mineral
resources not considered in the PEA. "Our approach to Kutcho will be similar to
that used with our Minto Mine, where we relentlessly pursue every opportunity
for increasing the value of the asset we own," said Mr. Quin. "We aim to
evaluate each opportunity and drive it to ground in parallel with our
feasibility and permitting process, so that there are regular, incremental
increases in the value of the asset."


Highlights

The PEA lays out the basis for the development of an open pit mining operation
based on mining of the Main deposit only. Highlights of the PEA, as compared to
previously announced plans by prior owners, include the following (note that "M"
at the end of a number means "millions" and "K" means "thousands"):


- Open pit mining of approximately 63% of the Main deposit only, comprising
10.5M tonnes of indicated mineral resource at an average grade of 1.73% copper,
2.35% zinc, 0.27g/t gold and 26.3g/t silver, containing over 400M lbs of copper
and 540M lbs of zinc, 90,000oz of gold and 8.9M oz of silver plus some minor
amounts of inferred mineral resource; deeper portions of the Main deposit and
all of the Sumac and Esso deposits which, combined, total more than 50% of the
total resources at Kutcho remain to be evaluated in subsequent studies;


- Open pit redesigned to optimize grade and strip ratios over the mine life,
with an overall strip ratio of 5.1:1 waste:material processed versus 6.7:1 in
prior studies;


- Processing 4,000 tonnes per day ("tpd") vs. prior plans for 6,000tpd, with
recoveries of 84% for copper, 74% for zinc and 50% and 52% for gold and silver,
respectively;


- Average annual payable production of 45M lbs of copper, 48M lbs of zinc,
5,600oz of gold and 584,000oz of silver over a 7.3 year mine life;


- Life of mine payable production of 331M lbs of copper, 348M lbs of zinc,
41,000oz of gold and 4.2M oz of silver over an a 7.3 year mine life, with
potential for additional life from underground mining of the remaining 6M tonnes
in the Main deposit, as well the Esso and, possibly, portions of the Sumac
deposits in later years;


- Production of separate copper and zinc concentrates, averaging 30.3% copper
and 55% zinc, respectively, with payable the precious metals reporting to the
copper concentrates;


- Average unit operating costs of $52.49 per tonne yielding cash costs of $1.70
to $1.72 per pound of copper before by-product credits and $0.82 to $0.93 per
pound of copper after by-product credits;


- Pre-production capital of $183.3M, versus $299M in the pre-feasibility study
prepared by prior owners;


- Pre-tax NPV of $300M to $52M and pre-tax IRR's of 54% to 19% based on metal
prices ranging from the recent forward curve (gold and silver prices kept flat)
to a 30% discount to the forward curve, giving payback in 1.5 to 3.0 years;


- Approximately 50% reduction in the aerial extent of disturbance;

- Switch to compacted and encapsulated dry-stack tailings and buffered waste
dumps for any potentially acid generating waste rock. The dry-stack approach to
tailings disposal would eliminate the need for a conventional tailings dam
across Andrea Creek and would significantly reduce the environmental impact of
the project.


The PEA represents an interim update on the Kutcho Project with mineral resource
estimates as of the end of 2007 and costs as of May 2008 and only addresses
mining of a portion of the Main deposit. However, the PEA identifies a number of
significant value enhancement opportunities that suggest that additional value
could be extracted from the Kutcho Project. Sherwood will continue to pursue the
crystallization of these enhancements, including possible extraction of some or
all of the remaining mineral resources in the Main deposit, Esso deposit and
Sumac deposit, possibly by underground methods. These and other opportunities
will be addressed in subsequent studies.


Basis of Preliminary Economic Assessment

In May 2008, Sherwood completed the acquisition of Western Keltic Mines Ltd. and
its Kutcho Project, so that the Kutcho Project is 100% owned by Kutcho Copper
Corp. ("KCC"), a wholly owned subsidiary of Sherwood. On the basis of the then
impending acquisition, Sherwood commissioned the independent PEA completed under
the supervision of SRK Consulting (Canada) Inc. ("SRK"). While compiled by SRK,
the PEA relies extensively on the contributions of the following companies; JDS
Energy and Mining Inc., Rescan Environmental Services Ltd., Techpro, Sacre-Davey
Engineering and Kirkham Geosystems Ltd.


The PEA only evaluated open pit mining of a portion of one of the three known
deposits comprising the Kutcho Project, known as the "Main" deposit. The Main
deposit is a tabular body of high grade copper-zinc mineralization that outcrops
on surface. West of the Main deposit lies the poorly drilled Sumac deposit and,
beyond that, the Esso deposit, the highest grade of the three know deposits.


It is envisioned that, based on the results of this study, KCC will seek permits
and support to develop the Kutcho Project as set out in the PEA while, in
parallel, advancing the project through completion of a feasibility study and
evaluating options to increase the total quantity of material to be mined and
processed by considering the potential for mining the remaining portions of the
Main deposits, as well as the Esso and Sumac deposits.


Mineral Resources

The mineral resource estimate for the Main deposit at Kutcho was completed by
Garth Kirkham, P.Geo., of Kirkham Geosystems Ltd., using industry standard
methods that conform with National Instrument 43-101 and utilizing MineSight(TM)
Software. The resource estimate for the Main deposit was based upon historical
data from 221 Main deposit drill holes supplied by KCC.




Kutcho PEA - Mineral Resource Estimate (@ 0.75 %CuEq cut-off) - Main
Deposit Only

--------------------------------------------------------------------------
                          In situ Grade              Contained Metal
                       ---------------------------------------------------
                          %    %  g/t  g/t      Cu     Zn    Ag         Au
Class          Tonnes    Cu   Zn   Ag   Au    (Mlb)  (Mlb) (Moz) (000's oz)
--------------------------------------------------------------------------
Indicated  17,285,000  1.56 2.12 26.1 0.29   594.5  807.9  14.5      161.2
--------------------------------------------------------------------------
Inferred      367,000  1.62 1.77 23.6 0.13    13.1   14.3   0.3        1.5
--------------------------------------------------------------------------



Mine Plan

The Main deposit is proposed to be developed as an open pit that would produce a
total of 10.7 million tonnes (Mt) of mill feed and 54.3 Mt of waste over an
initial 7.3-year mine operating life. Additional mineral resources remain within
the Main deposit, as well as those in the Sumac and Esso deposits, that could
potentially support an extended life. The life-of-mine ("LOM") plan for the Main
deposit open pit focuses on achieving the required mill feed production rate,
while balancing grade and strip ratios. Due to the susceptibility of the Kutcho
mineralization to oxidation, minimal stockpile and blending capacity is assumed
in the PEA.


Mine design for the Main deposit open pit was initiated with the development of
a Net Smelter Return ("NSR") model. The model included estimates of metal
prices, exchange rate, mining dilution, mill recovery, concentrate grade
smelting and refining payables and costs, freight and marketing costs and
royalties. The NSR model was based on a 5m x 5m x 5m block size. The model was
then used with the Gemcom Whittle - Strategic Mine Planning(TM) ("Whittle")
software to determine the optimal mining shell. Mine planning and scheduling was
then conducted on the optimal pit shell with the use of MineSight(TM) software
and mineral resources were estimated (see table below). A $31/t NSR cut-off was
used within the planned pit.




Kutcho PEA - Open Pit Life-of-Mine Mineral Resource (@ $31/t NSR cut-off)
 - Main Deposit Only

--------------------------------------------------------------------------
                           In situ Grade            Contained Metal
                       ---------------------------------------------------
                          %    %  g/t   g/t    Cu    Zn      Au         Ag
Class          Tonnes    Cu   Zn   Au    Ag  (Mlb) (Mlb)    (oz)       (oz)
--------------------------------------------------------------------------
Indicated   10,513,000 1.73 2.35 0.27  26.3 400.7 543.7  90,400  8,900,000
--------------------------------------------------------------------------
Inferred       163,000 1.67 1.93 0.11 22.16   6.0   6.9     600    116,100
--------------------------------------------------------------------------



The mining sequence was divided into eight phases designed to maximize grade,
reduce pre-stripping requirements, while providing the required mill feed
production per period. The Main pit is most economical when phases are mined
concurrently. The LOM mine production schedule is summarized in the table below.




Kutcho PEA -Life of Mine Production Schedule - Main Deposit Only

---------------------------------------------------------------------------
                                              Production Year
                        Pre-  ---------------------------------------------
Parameter       Units  prod      1    2    3    4    5    6    7    8 Total
---------------------------------------------------------------------------
Mineralized        Mt     -   1.46 1.46 1.46 1.46 1.46 1.46 1.46  0.5  10.7
 rock mined(i)
---------------------------------------------------------------------------
Waste mined        Mt   0.6    5.0  8.6  8.5 12.4   10  6.0  2.8  0.3  54.3
---------------------------------------------------------------------------
Strip ratio     Wt:Ot     -    3.4  5.9  5.8  8.5  6.8  4.1  1.9  0.8   5.1
---------------------------------------------------------------------------
Cu grade         % Cu     -   1.83 1.74 1.93 1.72 1.65 1.53 1.75 1.65  1.73
---------------------------------------------------------------------------
Zn grade         % Zn     -   2.83 2.38 2.65 2.22 2.07 1.96 2.39 2.06  2.34
---------------------------------------------------------------------------
Au grade       Au g/t     -   0.29 0.34 0.32 0.26 0.21  0.2 0.24 0.26  0.27
---------------------------------------------------------------------------
Ag grade       Ag g/t     -   26.6 28.7 29.8 26.1 23.8 23.4 24.9 28.6  26.3
---------------------------------------------------------------------------
(i) Since this is a PEA and incorporates inferred mineral resources (1.5%
    of the total), this material cannot be quantified as a reserve under
    NI 43-101.



Waste Management

Tailings from the mill will be sent to the proposed dry-stack location to the
east of the mill facility. The approach for dry-stacking will be similar to that
used by Sherwood at its Minto Mine in the Yukon, with the addition of berms to
retain and encapsulate the tailings for permanent abandonment. Non-potentially
acid generating ("non-PAG") waste rock from the Main pit will be deposited in a
number of dumps adjacent to the pit, as well as in buffered containments for the
dry-stack tailings. A separate waste dump has been designed for the potential
acid generating ("PAG") rock that will be extracted from the Main pit.
Backfilling into previously mined out areas would offer an improvement in the
waste haulage cycle for the trucking of waste out of the main pit and will be
considered in future studies.


Processing

The mineralogy of the Kutcho deposit is fine grained and requires a relatively
fine primary grind followed by a very fine regrind to produce copper and zinc
concentrates at reasonable recoveries. The mineralized zone rock has been
determined to be soft and obtaining a fine grind is not considered to be an
issue. The flotation circuit is expected to be a standard copper-zinc circuit
with copper being recovered followed by zinc flotation. Both copper and zinc
rougher concentrates will be reground to approximately 10 microns followed by
three stages of cleaning. Copper concentrate produced will contain sufficient
zinc to likely incur a smelter penalty. The penalty has been assumed to be
$4.00/dmt of concentrate. The copper concentrate is expected to be 30.3% copper.
The sphalerite is low in iron and the grade of the concentrate will be high at
55% zinc. Recoveries are expected to be 82-84% for copper and 72-74% for zinc.
The recovery assumptions used in this report are shown in the table below.


Metallurgical test work is ongoing to refine the fineness of primary grind and
the reagent scheme. Variability testing will refine the metallurgical response
with depth and will refine annual production of metals. The current drill
program is an opportunity to refine the characteristics of the mineralization
with respect to bornite/chalcopyrite ratios, degree of dissemination and pyrite
content and relate these characteristics to metallurgical response.




Kutcho PEA - Assumed Metallurgical Parameters Used in Cash Flow - Main
Deposit Only

--------------------------------------------------------------
           Assumed            Assumed Cu            Assumed Zn
Metal     recovery     concentrate grade     concentrate grade
--------------------------------------------------------------
Copper         84%                30.30%
--------------------------------------------------------------
Zinc           74%                                         55%
--------------------------------------------------------------
Gold           50%                4 g/t
--------------------------------------------------------------
Silver         52%              330 g/t
--------------------------------------------------------------



Operating & Capital Costs

Operating and capital expenses were derived from a number of sources. Many costs
were factored from Sherwood's Minto Mine in the Yukon. The Minto Mine is also a
small high-grade deposit with many similarities to the Kutcho design and,
therefore, served as a valuable reference of a small, northern open pit base
metal mine and mill. Capital and operating expense estimates are summarized in
the tables below.




Kutcho PEA - Operating Cost Assumptions & Estimates - Main Deposit Only

----------------------------------------------------
Parameter                 Unit Cost             Unit
----------------------------------------------------
Mining cost                    1.64        C$/t rock
----------------------------------------------------
Mining cost                    9.87      C$/t milled
----------------------------------------------------
Site Services & G&A cost
----------------------------------------------------
Labour                         4.48      C$/t milled
----------------------------------------------------
Equipment                      0.68      C$/t milled
----------------------------------------------------
Materials                     14.02      C$/t milled
----------------------------------------------------
Expenses                       0.94      C$/t milled
----------------------------------------------------
Contingency                    2.01      C$/t milled
----------------------------------------------------
Total Services and G&A        22.13      C$/t milled
----------------------------------------------------
Milling cost
----------------------------------------------------
Labour                         4.04      C$/t milled
----------------------------------------------------
Equipment                      0.62      C$/t milled
----------------------------------------------------
Materials                      7.48      C$/t milled
----------------------------------------------------
Expenses                       0.37      C$/t milled
----------------------------------------------------
Contingency                    1.25      C$/t milled
----------------------------------------------------
Total Milling                 13.76      C$/t milled
----------------------------------------------------
Capital leases (total)          5.0      C$/t milled
----------------------------------------------------
Royalties                        2%              NSR
----------------------------------------------------


Kutcho PEA - Capital Cost Estimates - Main Deposit Only

--------------------------------------------
                             Initial Capital
Item                               (Millions)
--------------------------------------------
Site Infrastructure                    $8.80
--------------------------------------------
Mining                                 $7.10
--------------------------------------------
Process Plant                         $72.50
--------------------------------------------
Services                               $2.30
--------------------------------------------
Ancillary Buildings                    $5.90
--------------------------------------------
Construction Camp Costs                $6.10
--------------------------------------------
Off site Infrastructure               $18.00
--------------------------------------------
Total Direct Capital Costs           $120.70
--------------------------------------------
Indirect Capital Costs                $38.70
--------------------------------------------
Total Project                        $159.40
--------------------------------------------
Contingency @ 15%                     $23.90
--------------------------------------------
G R A N D  T O T A L                 $183.30
--------------------------------------------



In addition to the capital in the table above, there is another $43.1M in
capital equipment that will be leased over a seven-year period. Approximately
50% of the leased capital is mobile equipment for the open pit mine.


Production

The following sets out the copper, zinc, gold and silver in concentrates and
estimated payable metal detailed in the PEA.




Kutcho PEA - Life-of-Mine Metal Production Forecast - Main Deposit Only

                                ------------------------------
                                             Year
--------------------------------------------------------------
Item                     Unit        1       2       3       4
--------------------------------------------------------------
Copper in cons       lb ('000)  49,400  47,100  52,300  46,400
--------------------------------------------------------------
Zinc in cons         lb ('000)  67,500  56,700  63,400  52,800
--------------------------------------------------------------
Gold in cons         oz ('000)     6.8     8.0     7.4     6.0
--------------------------------------------------------------
Silver in cons       oz ('000)     653     705     734     643
--------------------------------------------------------------
Conc. grade              % Cu     30.3    30.3    30.3    30.3
--------------------------------------------------------------
Payable copper(i)    lb ('000)  47,700  45,400  50,500  44,800
--------------------------------------------------------------
Payable zinc(i)      lb ('000)  57,400  48,200  53,900  44,900
--------------------------------------------------------------
Payable gold      oz Au ('000)     6.1     7.2     6.7     5.4
--------------------------------------------------------------
Payable silver    oz Ag ('000)     588     634     661     578
--------------------------------------------------------------


                                ------------------------------
                                             Year
-----------------------------------------------------------------------
Item                     Unit        5       6       7       8    Total
-----------------------------------------------------------------------
Copper in cons       lb ('000)  44,600  41,500  47,500  14,700  343,000
-----------------------------------------------------------------------
Zinc in cons         lb ('000)  49,200  46,700  57,100  16,100  409,000
-----------------------------------------------------------------------
Gold in cons         oz ('000)     4.9     4.7     5.7     2.0     45.5
-----------------------------------------------------------------------
Silver in cons       oz ('000)     585     574     613     232    4,739
-----------------------------------------------------------------------
Conc. grade              % Cu     30.3    30.3    30.3    30.3     30.3
-----------------------------------------------------------------------
Payable copper(i)    lb ('000)  43,100  40,000  45,800  14,100  331,000
-----------------------------------------------------------------------
Payable zinc(i)      lb ('000)  41,800  39,700  48,500  13,700  348,000
-----------------------------------------------------------------------
Payable gold      oz Au ('000)     4.4     4.2     5.1     1.8       41
-----------------------------------------------------------------------
Payable silver    oz Ag ('000)     527     517     552     208    4,265
-----------------------------------------------------------------------
(i) Copper, gold and silver are payable only within the Cu concentrate.
    Zn is payable only within the Zn concentrate.



As noted above, additional smoothing of production is planned post-PEA as part
of an on-going process of open pit optimization, as well as evaluating options
for extending the mine life by incorporating additional mineral resources
defined on the Kutcho Project but not considered in the PEA, including the
balance of the Main deposit and those in the Esso and Sumac deposits.


Economic Analysis

The economic assessment in the PEA is preliminary in nature and uses inferred
mineral resources that are considered too speculative geologically to have the
economic considerations applied to them that would enable them to be categorized
as mineral reserves, and there is no certainty that this PEA will be realized.
The inferred mineral resource used in the mine plan is 1.5% of the total LOM
resource.


Three cash flow cases were studied. All cash flow cases used the same mineral
resource estimate and production factors as shown in the table below.




Kutcho PEA - Summary of Production Cases - Main Deposit Only

--------------------------------------------------------------------------
                                                                 All Cases
Item                                               Unit    Totals/Averages
--------------------------------------------------------------------------
Waste mined                                    M tonnes               54.4
--------------------------------------------------------------------------
Mineralized rock mined                         M tonnes               10.7
--------------------------------------------------------------------------
Strip ratio                       Waste rock:Plant feed                5.1
--------------------------------------------------------------------------
Mill Feed                                      M tonnes               10.7
--------------------------------------------------------------------------
Copper millhead grade (average)                    % Cu               1.73%
--------------------------------------------------------------------------
Zinc millhead grade (average)                      % Zn               2.34%
--------------------------------------------------------------------------
Gold millhead grade (average)                    g/t Au               0.26
--------------------------------------------------------------------------
Silver millhead grade (average)                  g/t Ag               26.5
--------------------------------------------------------------------------
Copper in Cu cons                                  M lb                343
--------------------------------------------------------------------------
Zinc in Zn cons                                    M lb                409
--------------------------------------------------------------------------
Gold in Cu cons                                    K oz                 46
--------------------------------------------------------------------------
Silver in Cu cons                                  K oz              4,739
--------------------------------------------------------------------------
Cu Concentrate Grade                               % Cu               30.3%
--------------------------------------------------------------------------
Zn Concentrate Grade                               % Zn                 55%
--------------------------------------------------------------------------



The cash flow cases were differentiated by average metal prices and the results
for each case are shown in the table below. Case 3 pricing was based on the
forward curve for copper as of April, 2008, and spot prices for gold and silver
with no escalation or de-escalation going forward. Case 2 represents an
approximately 15% discount to Case 3 copper gold and silver prices, and Case 1 a
30% discount of copper, gold and silver prices compared to Case 3. Zinc prices
were set at current spot prices for Case 3 with a US$0.01/lb and US$0.02/lb
reduction for Cases 2 and 1 respectively. All cases used a gradual zinc price
decrease to US$0.92/lb by the 4th year of production. Exchange rates are based
on historic correlations of C$ exchange rates and copper prices for Case 3, but
were not changed for case 2 and 1, whereas historic relationships suggest that
the C$ would be weaker than indicated at these metal prices.




Kutcho PEA - Summary of Results by Case - Main Deposit Only

--------------------------------------------------------------------------
Item                                       Unit   Case 1   Case 2   Case 3
--------------------------------------------------------------------------
Average Copper Price                     US$/lb    $2.24    $2.73    $3.20
--------------------------------------------------------------------------
Average Zinc Price                       US$/lb    $0.94    $0.95    $0.96
--------------------------------------------------------------------------
Average Gold price                       US$/oz     $600     $725     $850
--------------------------------------------------------------------------
Average Silver price                     US$/oz   $10.00   $13.00   $16.00
--------------------------------------------------------------------------
Exchange rate                            C$:US$    $1.11    $1.11    $1.11
--------------------------------------------------------------------------
NSR                                 C$/t milled      $88     $106     $125
--------------------------------------------------------------------------
Unit Mining costs (ex equip. lease)   $/t mined    $1.64    $1.64    $1.64
--------------------------------------------------------------------------
Unit Mining costs (ex equip. lease)  $/t milled    $9.87    $9.87    $9.87
--------------------------------------------------------------------------
Unit Milling costs                   $/t milled   $13.76   $13.76   $13.76
--------------------------------------------------------------------------
Unit G&A and Site services (ex       $/t milled   $22.13   $22.13   $22.13
 equip. lease)
--------------------------------------------------------------------------
Unit Lease costs                     $/t milled    $5.00    $5.00    $5.00
--------------------------------------------------------------------------
Unit Total OPEX (inc royalties)      $/t milled   $52.49   $52.86   $53.24
--------------------------------------------------------------------------
Unit OPEX                              C$/lb Cu    $1.70    $1.71    $1.72
--------------------------------------------------------------------------
Unit OPEX (with Zn, Au, Ag credits)    C$/lb Cu    $0.93    $0.87    $0.82
--------------------------------------------------------------------------
Pre-Production Capital (excluding           $ M  $183.30  $183.30  $183.30
 sustaining capital, capital
 leases and closure)
--------------------------------------------------------------------------
NPV @ 10% discount rate pre-tax             $ M      $52     $176     $300
--------------------------------------------------------------------------
NPV @ 10% discount rate after tax           $ M      $31     $116     $199
--------------------------------------------------------------------------
IRR pre-tax                                   %       19%      38%      54%
--------------------------------------------------------------------------
IRR after tax                                 %       16%      33%      46%
--------------------------------------------------------------------------
Payback period (tax in)                   Years        3        2      1.5
--------------------------------------------------------------------------



Sensitivity Analysis

Sensitivity analysis was done using metal prices, mill head grade, capital costs
and operating costs as variables. As with many projects, the Net Present Value
("NPV") was most sensitive, in order of magnitude, to metal price, grade and
recovery, operating expenses ("OPEX") and capital expenses ("CAPEX"). Each
variable was changed independently while all other variables were held at the
constant base case level.


In Case 1, a 20% increase in metal prices leads to an increase in the post-tax
NPV using a 10% discount rate ("NPV10%") from $31M to $148M. The mill head grade
and recovery also have a similar large impact with a $79M NPV10% gain for a 20%
increase in grade or recovery. Conversely, decreases in metal prices, mill head
grades or recoveries have a correspondingly large negative effect on the NPV10%.
The Case 1 results show the project is uneconomic if metal prices or mill head
grade/recovery drop by more than 5-7%. Cases 2 assumes higher metal prices than
Case 1 and is therefore more immune to negative metal price changes. Case 2
shows the same large variances in NPV10% as Case 1 but an 18% drop in metal
prices is required before it will lead to a negative NPV10%. Case 3 assumes
metal prices approximately in line with the forward curve for copper and zinc,
but with no escalation of precious metal prices, and is the most robust
scenario.


Environmental

The Kutcho Project is subject to the British Columbia Environmental Assessment
Act and the Canadian Environmental Assessment Act. The former requires that the
project undergo an environmental assessment and obtain an Environmental
Assessment ("EA") Certificate. The Project was initiated into the BC EA process
through the issuance of a Section 10 order by the BC Environmental Assessment
Office ("EAO") on July 29, 2005. The provincial and federal processes will be
integrated in a harmonized review, with the EAO taking the lead. On December 24,
2007, the Canadian Environmental Assessment Agency announced that the Kutcho
Project would be subject to a Comprehensive Study.


In 2005, a program of environmental and socio-economic baseline studies was
begun to provide the information necessary to prepare the EA Application and to
develop management and monitoring plans. It covered all facets of the
biophysical and human environment, including meteorology, air quality,
hydrology, hydrogeology, metal leaching and acid rock drainage, aquatic ecology,
fish and fish habitat, soils, vegetation, ecosystem mapping, wildlife, wetlands,
archaeology, socio-economics, land use, country foods and human health, and
traditional use and traditional ecological knowledge. The program was completed
in 2007. Monitoring of meteorology, air quality, hydrology and water quality
will continue throughout the construction, operation, closure and post-closure
phases. The most significant environmental issue for the Project will be
maintaining water quality in the receiving environment. Treatment of mine
effluent to BC water quality criteria will be required during all mine phases.


The Kutcho Project is in the traditional territories of the Tahltan and Kaska
Dena First Nations. Consultation with these First Nations and other stakeholders
has been ongoing since activity at the Kutcho Project re-started approximately
four years ago.


Project Risks

The major risk areas identified in the PEA are:

1. Environmental and permitting requirements could delay or preclude the
development of the Kutcho Project;


2. Adverse changes in exchange rates, metal prices and external financial
influences could negatively impact the development of the project;


3. Process recoveries could be less than assumed in the PEA, negatively
affecting project returns;


4. Potential for increases in capital costs over those estimated in the PEA;

5. Poor grade control could result in over-dilution of the high grade
mineralization, negatively affecting recoveries.


Project Opportunities

The most important opportunities to improve the project are:

1. Increased grade of the in situ mineral resource as a result of in-fill
drilling currently in process (In-fill drilling in 2006 on a limited portion of
the Main deposit suggested potential to increase overall mineral resource grades
versus that previously modelled - with a comprehensive in-fill drill program
underway, Sherwood will be better able to evaluate this opportunity by the fall
of 2008);


2. Optimization of mine plan following in-fill drilling to maximize grade and
reducing stripping in the early years of the mine plan (an increase of 1M tonnes
of mill feed at the average grade used in the PEA would increase the pre-tax
NPV10% $12M;


3. Increased life of mine production as a result of mining additional mineral
resources from the Main pit (only 63% of the Main deposit mineral resource is
extracted in the proposed open pit, leaving 6.3Mt that could be exploitable,
depending on metal prices and costs, and extending the mine life);


4. Exploitation of mineral resources from the other deposits already known (Esso
and Sumac) which, together with the unmined portion of the Main deposit,
comprise more than 50% of the total project resources;


5. Reduced stripping by steepening pit walls, if supported by planned
geotechnical drilling (a 0.1 reduction in the strip ratio increases the pre-tax
NPV10% by $1M);


6. Improved metallurgical recoveries in the process plant as a result of
metallurgical test work currently in process (a 1% increase in recoveries
increases the pre-tax NPV by $7M and IRR by 1%) and improved concentrate grades
(a 1% increase in concentrate grade increases pre-tax NPV10% by $4M);


7. Reduced energy usage as equipment is specified and sized;

8. Reduced capital costs through expanded utilization of used and refurbished
equipment;


9. Reduced overall transportation costs of concentrate from mine to smelter (a
10% reduction increases pre-tax NPV10% by $3M); and


10. Potential for lower than assumed TC/RC's, especially copper, where current
rates are well below those assumed in the PEA (a10% reduction in TC/RC's
increases pre-tax NPV10% by $3M).


It should be noted that the upside potential indicated above could also become
negative if the factors are worse than expected. In this regard, the list can be
used to identify which parameters might have the largest positive or negative
effect on the project and risk mitigation plans could be developed.


Moving Forward

As a result of the recommendations in the PEA, Sherwood has an extensive work
program underway to investigate the project opportunities identified and to
mitigate the project risks. This work program includes:


1. In-fill drilling the Main deposit in order to better define the high grade
mineralization, optimize the mine planning and enhance the quality of the assay
database;


2. Geotechnical investigations to steepen up the pit walls and reduce the
overall stripping;


3. Evaluating the potential of an expanded open pit or underground extraction of
the unplanned portions of the Main deposit immediately adjacent to the current
proposed open pit;


4. Evaluating the potential of the Esso and Sumac resources as potential sources
of supplemental feed, possibly by ramp access out of the proposed open pit,
extending the mine life;


5. Extensive metallurgical testing in order to determine the potential for
improved metallurgical recoveries and improved concentrate grades;


6. Possible recovery of free gold in a gravity circuit;

7. Conducting more ABA testing to better define the extent of potentially acid
generating rock;


8. Geotechnical and hydrogeological evaluations to optimize open pit planning;

9. Re-engage the regulatory agencies to advance the Kutcho copper project
through the permitting process.


10. Re-engage the Tahltan and Kaska First Nations to attain meaningful and
equitable IBA agreements.


An updated PEA is planned for the fall of 2008, incorporating some or all of the
results from items #1, #3, #4 and #5 above, and a feasibility study in the first
half of 2009 (depending on timeliness of work programs required to support a
feasibility study).


Resource Estimation Methodology

Kirkham Geosystems Ltd. prepared the mineral resource estimate for the Kutcho
deposit. Mr. Kirkham has reviewed pertinent geological information in sufficient
detail to support the data incorporated in the resource estimate. Garth Kirkham,
P.Geo. of Kirkham Geosystems Ltd. is the Independent Qualified Person under
National Instrument 43-101 responsible for the resource estimate.


The estimates for copper, zinc, silver and gold were completed for the PEA
Report dated June of 2008 using the MineSight(TM) 3-dimensional mine planning
software system. The estimate was based upon a database comprised of 346 drill
holes supplied by Kutcho Copper. The estimation process was constrained by a
solid model based on lithological boundaries combined with grade contours.
Assays were then composited into 2.5m intervals for statistical and
geostatistical analysis to be performed within the constraining domains. A 5m by
5m by 5m orthogonal block model was created and Ordinary Kriging was used as the
method to interpolate grades into each block within the solid domain. Bulk
density measurements were supplied within the drill hole database and also
interpolated into each block using Inverse Distance to the 3rd power as the
interpolator. Individual blocks were then classified into indicated and inferred
categories based on number of drillholes, number of composites, average distance
to composite, distance to nearest composite and relative error. The grades and
tonnages reported in the resource estimate represent the material contained
within the mineralized portion (as a percentage) of the classified block below
topography.


Mineral resources that are not mineral reserves do not have demonstrated
economic viability. Mineral resource estimates do not account for mineability,
selectivity, mining loss and dilution. These mineral resource estimates include
inferred mineral resources that are normally considered too speculative
geologically to have economic considerations applied to them that would enable
them to be categorized as mineral reserves. There is also no certainty that
these inferred mineral resources will be converted to measured and indicated
mineral resource categories through further drilling, or into mineral reserves
once economic considerations are applied.


Technical Report

A National Instrument 43-101 compliant technical report will be filed within the
next week on SEDAR and, once filed, can be accessed under Sherwood's profile at
www.sedar.com.


Diagrams

Kutcho PEA - Claim area showing schematic of proposed mine site -
http://media3.marketwire.com/docs/swc612a.pdf


Kutcho PEA - Proposed project layout - http://media3.marketwire.com/docs/swc612b.pdf

Kutcho PEA - Computer Generated Image of the Three Known Massive Sulphide
Deposits, Drill Holes, and Surface Topography (Wardrop 2007) -
http://media3.marketwire.com/docs/swc612c.pdf


Kutcho PEA - Proposed phasing of open pit on Main deposit (looking south) -
http://media3.marketwire.com/docs/swc612d.pdf


About Sherwood Copper

Sherwood's objective is the profitable production of base and precious metals
from high grade, open pit mines in Canada. Sherwood's first operating mine, the
high grade Minto copper-gold mine in Yukon, Canada, was built on budget and
ahead of schedule. The Minto Mine is one of the highest-grade open pit
copper-gold mines in the world, and is forecast to be a low cost producer.
Aggressive exploration on the Minto property has yielded significant success,
providing Sherwood the opportunity to 'grow from within' by expanding the
mineral resource and mineral reserve base, potentially leading to further
production increases. To further accelerate its production growth, Sherwood
intends to pursue merger & acquisition opportunities that fit its business model
and, in May 2008, Sherwood acquired 100% ownership in Western Keltic Mines Ltd.,
owner of the high-grade Kutcho copper-zinc-gold-silver deposit in northwestern
British Columbia. Sherwood expects to lever off its successful development of
the Minto Mine and rapidly advance the Kutcho Project to a production decision.


Quality Assurance

The technical information in this news release has been prepared in accordance
with Canadian regulatory requirements set out in National Instrument 43-101 and
reviewed by Stephen P. Quin, P.Geo., President & CEO of Sherwood. The following
SRK employees are QPs for this project; Gordon Doerksen, P.E. (WY) - Project
Overview; Dino Pilotto, P.Eng. - Mining;. Garth Kirkham, P.Geo. of Kirkham
Geosystems - Mineral Resource Estimates, Jeff Stibbard P.Eng. - Capital, G&A and
Operating Costs, Dave Hendriks, P.Eng. - Metallurgy and Mineral Processing, Brad
Mercer P.Geo. - Geology.


The report relies on the work and opinions of non-QP experts without
verification by SRK, including: Roger Nonis and Robert Johnston, P.Eng., of
Sacre-Davey Engineering (mineral processing and project infrastructure), Mike
McGurk of Rescan Environmental (environmental and permitting), Carl Hovey of
All-North Consultants (access road and site earthworks), Wentworth Taylor of WH
Taylor Inc. (taxation).


Additional Information

Additional information on Sherwood and its Minto & Kutcho projects can be
obtained on Sherwood's website at http://www.sherwoodcopper.com.


On behalf of the board of directors

SHERWOOD COPPER CORPORATION

Stephen P. Quin, President & CEO

Forward-Looking Statements

This document may contain "forward-looking statements" within the meaning of
Canadian securities legislation and the United States Private Securities
Litigation Reform Act of 1995. These forward-looking statements are made as of
the date of this document and the Company does not intend, and does not assume
any obligation, to update these forward-looking statements.


Forward-looking statements relate to future events or future performance and
reflect management's expectations or beliefs regarding future events and
include, but are not limited to, statements with respect to the estimation of
mineral reserves and resources, the realization of mineral reserve estimates,
the timing and amount of estimated future production, costs of production,
capital expenditures, success of mining operations, environmental risks,
unanticipated reclamation expenses, title disputes or claims and limitations on
insurance coverage. In certain cases, forward-looking statements can be
identified by the use of words such as "plans", "expects" or "does not expect",
"is expected", "budget", "scheduled", "estimates", "forecasts", "intends",
"anticipates" or "does not anticipate", or "believes", or variations of such
words and phrases or statements that certain actions, events or results "may",
"could", "would", "might" or "will be taken", "occur" or "be achieved" or the
negative of these terms or comparable terminology. By their very nature
forward-looking statements involve known and unknown risks, uncertainties and
other factors which may cause the actual results, performance or achievements of
the Company to be materially different from any future results, performance or
achievements expressed or implied by the forward-looking statements. Such
factors include, among others, risks related to actual results of current
exploration activities; changes in project parameters as plans continue to be
refined; future prices of resources; possible variations in ore reserves, grade
or recovery rates; accidents, labour disputes and other risks of the mining
industry; delays in obtaining governmental approvals or financing or in the
completion of development or construction activities; as well as those factors
detailed form time to time in the Company's interim and annual financial
statements and management's discussion and analysis of those statements, all of
which are filed and available for review on SEDAR at www.sedar.com. Although the
Company has attempted to identify important factors that could cause actual
actions, events or results to differ materially from those described in
forward-looking statements, there may be other factors that cause actions,
events or results not to be as anticipated, estimated or intended. There can be
no assurance that forward-looking statements will prove to be accurate, as
actual results and future events could differ materially from those anticipated
in such statements.


Accordingly, readers should not place undue reliance on forward-looking statements.

Kincora Copper (TSXV:KCC)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Kincora Copper Charts.
Kincora Copper (TSXV:KCC)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Kincora Copper Charts.