Orezone Gold Corporation (TSX.V: ORE, OTCQX: ORZCF) (the “Company”
or “Orezone”) is pleased to provide an update on construction
progress at its Bomboré Gold Project in Burkina Faso.
Patrick Downey, President and CEO stated,
“Significant progress has been achieved during the first half of
2021 and I am very pleased to report that the project capital cost
remains consistent with the estimate in the 2019 Feasibility Study
(“2019 FS”) and the project is on schedule and fully funded to pour
first gold in Q3-2022. Over the past several months, raw material
costs such as steel, copper, and plastics have trended higher along
with logistics and transportation costs. The ability to maintain
our capital budget during this period of increasing global
inflationary pressures is a testament to the work and preparedness
of the Orezone team and our consulting engineers. It is also a
reflection of the high quality of the 2019 FS as our bulk material
quantities such as earthworks, steel, piping, and platework are all
trending favourably to those estimated in the 2019 FS. We will be
posting monthly video updates of progress to keep our shareholders
and stakeholders fully informed of all ongoing construction
activities over the next year.”
Highlights
-
Bulk quantities tracking 2019 feasibility study:
Engineering is now over 60% complete and progressing on schedule.
All bulk quantities for the project remain at or within the
estimates in the 2019 FS.
-
Major orders made prior to global materials cost
inflation: The Company, together with its engineering
consultants, completed detailed reviews and optimization studies
during 2020 to ensure a smooth start to detailed engineering and
procurement at the award of the EPCM contract. This facilitated
rapid tendering and procurement of the major process plant
equipment. Firm orders have now been placed for most mechanical and
electrical equipment including the ball mill, CIL agitators, CIL
inter-tank screens, mineral sizer, apron feeder, vibrating screens,
slurry pumps, all gold recovery circuit equipment, and high voltage
switchgear and transformers. Orders for major bulk items such as
HDPE membranes and geotextiles, HDPE piping, concrete rebar, tank
platework, and all major structural steel have also been
placed.
-
Major construction contracts awarded: Contracts
have been awarded for the Plant Concrete, CIL Tank Erection, and
Overland and Tailing Pipeline Installation. Tenders for the plant
Structural/Mechanical/Piping (“SMP”) are under evaluation and will
be awarded in the coming weeks. This leaves only the Electrical
& Instrumentation installation contract which will be the final
major site installation package and will follow the award of the
SMP but is generally the lowest cost of these 4 major contracts. To
date, all contracts are trending on budget.
-
Site earthworks and site infrastructure: Early
civil works to provide year-round access to all construction areas
including additional camp upgrades to meet peak occupancy, the
construction of the Nobsin River haul road bridge, clearing and
grubbing of the tailings storage facility (“TSF”), the process
plant footprint, and the mine access roads are now complete.
Construction of the TSF will commence in August.
-
Plant Power: The power purchase agreement (“PPA”)
signed providing life of mine LNG and solar generated power for the
Phase I oxide plant (see news release dated June 2, 2021).
-
Mining of the Off-Channel Reservoir (“OCR”): This
contract was awarded to a local mining contractor and mobilization
commenced in February 2021 with the first bench mined in March
2021. The OCR is the first ore pit to be mined and will also
function as the main water storage for the project during
operations and be available to the surrounding communities after
mine closure. The OCR is expected to be completed before the onset
of the 2022 rainy season in June. Mining is progressing very well
with costs and material movement tracking to plan.
Mining and Resource
Reconciliation
Prior to commencing mining of the OCR, a
detailed 20,000 metre grade control drilling program was
undertaken. Results have been incorporated into the block model and
reconciliation on both tonnes and grade compared to the 2019 FS for
the OCR has been positive. Overall, the reserve tonnes and ounces
are approximately 30% above those estimated in the 2019 FS. Grade
control drilling will now focus on the Maga and Maga Hill pit areas
which will be the source of the planned higher-grade ore feed to
the process plant in the first 1 to 2 years of gold production.
Development Update Pictures and
Video:
Orezone’s first monthly Bomboré construction
video for May 2021 can be viewed at
https://bit.ly/May21Construction.
Figure 1: Off Channel Reservoir Mining
https://www.globenewswire.com/NewsRoom/AttachmentNg/d2ac02d5-ad9f-4cc3-81a3-0665349c3b36
Figure 2: New Nobsin River Bridge Crossing
https://www.globenewswire.com/NewsRoom/AttachmentNg/95b8a77f-e3da-4149-b2e5-e87c52274f06
Figure 3: Fuel Storage Area under
construction
https://www.globenewswire.com/NewsRoom/AttachmentNg/941009b4-7485-4e4c-80ea-ab8cdf72fbaa
Figure 4: Surface Water Management Pond under
construction
https://www.globenewswire.com/NewsRoom/AttachmentNg/8d743341-9003-4103-86c0-d3d991aaad80
Figure 5: Orezone hosts the Burkina Faso
Minister of Energy and Mines, and Coris Bank at Bomboré, June
2021
https://www.globenewswire.com/NewsRoom/AttachmentNg/ec508c94-2916-467a-8625-5e45178897a5
About Orezone Gold
Corporation
Orezone Gold Corporation (TSX.V: ORE OTCQX:
ORZCF) is a Canadian development company which owns a 90% interest
in Bomboré, one of the largest undeveloped gold deposits in Burkina
Faso.
The 2019 feasibility study highlights Bomboré as
an attractive shovel-ready gold project with forecasted annual gold
production of 118,000 ounces over a 13+ year mine life at an All-In
Sustaining Cost of US$730/ounce with an after-tax payback period of
2.5 years at an assumed gold price of US$1,300/ounce. Bomboré is
underpinned by a mineral resource base in excess of 5 million gold
ounces and possesses significant expansion potential. Orezone is
fully funded to bring Bomboré into production with the first gold
pour scheduled for Q3-2022.
Patrick DowneyPresident and Chief Executive
Officer
Vanessa PickeringManager, Investor Relations
Tel: 1 778 945 8977 / Toll Free: 1 888 673
0663info@orezone.com / www.orezone.com
Qualified Person
Ian Chang, P. Eng., VP Projects, is the
Qualified Person who has approved the technical information in this
news release.
For further information please contact
Orezone at +1 (778) 945-8977 or visit the Company’s
website at www.orezone.com.
Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
Cautionary Note Regarding
Forward-Looking Statements
This press release contains certain information
that may constitute “forward-looking information” within the
meaning of applicable Canadian Securities laws and “forward-looking
statements” within the meaning of applicable U.S. securities laws
(together, “forward-looking statements”). Forward-looking
statements are frequently characterized by words such as "plan",
"expect", "project", "intend", "believe", "anticipate", "estimate",
"potential", "possible" and other similar words, or statements that
certain events or conditions "may", "will", "could", or "should"
occur. Forward-looking statements in this press release include,
but are not limited to, statements with respect to the Bomboré
project being fully funded to production and projected first gold
by Q3-2022.
All such forward-looking statements are based on
certain assumptions and analyses made by management in light of
their experience and perception of historical trends, current
conditions and expected future developments, as well as other
factors management and the qualified persons believe are
appropriate in the circumstances.
All forward-looking statements are subject to a
variety of risks and uncertainties and other factors that could
cause actual events or results to differ materially from those
projected in the forward-looking statements including, but not
limited to, delays caused by the COVID-19 pandemic, terrorist or
other violent attacks, the failure of parties to contracts to
honour contractual commitments, unexpected changes in laws, rules
or regulations, or their enforcement by applicable authorities; the
failure of parties to contracts to perform as agreed; social or
labour unrest; changes in commodity prices; unexpected failure or
inadequacy of infrastructure, the possibility of project cost
overruns or unanticipated costs and expenses, accidents and
equipment breakdowns, political risk, unanticipated changes in key
management personnel and general economic, market or business
conditions, the failure of exploration programs, including drilling
programs, to deliver anticipated results and the failure of ongoing
and uncertainties relating to the availability and costs of
financing needed in the future, and other factors described in the
Company's most recent annual information form and management
discussion and analysis filed on SEDAR on www.sedar.com. Readers
are cautioned not to place undue reliance on forward-looking
statements.
Although the forward-looking statements
contained in this press release are based upon what management of
the Company believes are reasonable assumptions, the Company cannot
assure investors that actual results will be consistent with these
forward-looking statements. These forward-looking statements are
made as of the date of this press release and are expressly
qualified in their entirety by this cautionary statement. Subject
to applicable securities laws, the Company does not assume any
obligation to update or revise the forward-looking statements
contained herein to reflect events or circumstances occurring after
the date of this press release.
Orezone Gold (TSXV:ORE)
Historical Stock Chart
From Dec 2024 to Jan 2025
Orezone Gold (TSXV:ORE)
Historical Stock Chart
From Jan 2024 to Jan 2025