Carmen Gold-Silver Deposit Project Site Construction Update, Sonora
Mexico
PR Newswire
HERMOSILLO, Mexico, May 8, 2013
HERMOSILLO, Mexico, May 8,
2013 /PRNewswire/ -- Silver Scott
Mines, Inc. (OTC: SILS) is pleased
to announce the near
completion of construction at the
Carmen mine and processing site. Crushing machinery
with associated rolling stock equipment is now arriving and
planned to be operational in approximately two weeks.
Leach pad and ponds with contractor installed
HDPE plastic liners have been completed. Detailed
laser topography data has also been acquired
over the old mine and newly prepared plant
sites by a local contractor service provider. This
provider will also monitor in successive scans, to accurately
determine the volumes of rock produced.
Plans for the project site for the remainder of
the year include processing of up to 100,000 tonnes
of mineralized rock using contractor mining services.
This will be accomplished through the utilization of
the portable crusher plant due to arrive within the next few
days. As soon as sufficient mineralized rock has been crushed
and placed on the leach pad, the precious metal leaching
solution will be applied. Decisions regarding additional
production beyond 100,000 tonnes will be assessed by the
end of July, 2013.
Mel Herdrick, company QP and Registered
Geologist of the company commented, "Advancement of
the Carmen project into initial scale levels of
producing precious metals is now progressing rapidly. Our
overall corporate goal is to explore, define,
and produce gold and silver by heap
leach mine methods
and continue expansion of the projects
potential."