SKIL Ports & Logistics Limited Project Update (6156R)
March 10 2016 - 1:00AM
UK Regulatory
TIDMSPL
RNS Number : 6156R
SKIL Ports & Logistics Limited
10 March 2016
10 March 2016
SKIL Ports & Logistics Limited
("SPL" or the "Company")
Project Update
SKIL Ports & Logistics (SPL) is pleased to provide the
following update in regard to the development of its port and
logistics project in Navi Mumbai, India.
The Company is pleased to report that good progress continues to
be made at the site. Reclamation has continued to progress since
the last update, with four temporary piles and three permanent
piles having been completed. The piling gantry is now erected and
there has been further dredging in the berth pocket. The Company's
website has been updated with photographs taken on 9 March. Further
drone footage will be uploaded on the website in the near
future.
The Company continues to receive regular updates and reports
from the project contractors. Now that work has continued
uninterrupted for a number of months, the Company and its engineers
have more empirical data from which to gauge progress and schedule
the overall milestones to completion. SPL remains satisfied with
progress. However, it has become apparent that certain work streams
will take longer than previously scheduled. In particular, a change
to the design of the piling gantry had to be made whilst on site
and there has been a knock on effect of this on other work streams.
In addition, a new configuration had to be made for the batching
plant and, overall, a more conservative view is being taken of the
timetable.
Taken together, the Company now estimates that the facility will
become operational during December this year. The revised
construction schedule includes the following key milestones;
-- Completion of 30 hectares of reclamation by June 2016
-- Completion of dredging in the approach channel by July
2016
-- Equipment order by July 2016
-- Completion of 400 meters of jetty by the end of 2016
-- Completion of dredging in the harbour basin by end of
2016
-- Installation of infrastructure utilities by November 2016
SPL recognises that construction projects of this magnitude
inherently come with execution risks and the precise timing of
specific milestones may change. The Company will update
shareholders against these milestones as appropriate.
Enquiries:
SPL Nikhil Gandhi/Pavan Bakhshi/Jay Mehta
C/O Redleaf Communications
+44 (0)20 7382 4730
Cenkos Securities plc Stephen Keys/Camilla Hume
(Nomad and Broker) +44 (0)20 7397 8926
Redleaf Communications Charlie Geller/Harriet Lynch
(Financial PR) +44 (0)20 7382 4769
SKIL@redleafpr.com
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCLLFVTVSIAIIR
(END) Dow Jones Newswires
March 10, 2016 02:00 ET (07:00 GMT)
Skil Ports & Lg (LSE:SPL)
Historical Stock Chart
From Jan 2025 to Feb 2025
Skil Ports & Lg (LSE:SPL)
Historical Stock Chart
From Feb 2024 to Feb 2025