VANCOUVER, BC, March 13, 2024 /CNW/ - (TSX: LUC) (BSE: LUC)
(Nasdaq Stockholm: LUC)
Lucara Diamond Corp. ("Lucara" or the "Company") is pleased
to announce the filing of a technical report (the "Report") for the
updated Feasibility Study ("FS" or "Study"), prepared in accordance
with National Instrument 43-101 – Standards of Disclosure for
Mineral Projects ("NI 43-101") on its Underground Expansion
Project ("UGP" or "Project") at the Karowe Diamond Mine ("Karowe")
located in Botswana. The Report is
titled "Karowe Mine – Botswana
2023 Feasibility Study Technical Report", with an effective date of
June 30, 2023, and was prepared for
Lucara by JDS Energy & Mining Inc. The Report is available
under the Company's profile on SEDAR+ at www.sedarplus.ca or from
the Company's website at www.lucaradiamond.com. View PDF
Karowe is located in north-central Botswana, one of the world's most prolific
diamond producing areas, and is a producer of large, high value
type IIa diamonds and the only diamond mine to have produced four
diamonds in excess of 1,000 carats in size. The underground
expansion at Karowe is expected to double the mine life, and to
generate significant revenue and cashflow out to 2040, extending
benefits to the Company, its employees, shareholders, communities
surrounding the mine, and Botswana. The Report provides an update to the
2019 underground feasibility study ("2019 FS") and 2021 financed
base case to reflect changes to project duration, capital
expenditure, and technical updates to the Project. All amounts are
in U.S. dollars unless otherwise noted.
COMBINED OPEN PIT/ UNDERGROUND HIGHLIGHTS
- Extending mine life by 15 years;
- Total life of mine ("LOM") diamond recoveries of 6.8 million
carats;
- Operational highlights include ~42.4 million tonnes of ore
mined and ~52.2 million tonnes of ore processed;
- Highest value EM/PK(S) unit of the South Lobe is the dominant
rock type mined over the LOM of the underground; a significant
source of many large high value diamonds, including the 1,109 carat
Lesedi La Rona, the 549 carat
Sethunya, and more recently the 1,080 carat Type IIa white stone
recovered in August 2023;
- Pre-production capital costs for the UGP totalling $683 million, to be expended over an eight-year
pre-production construction and commissioning period until H2/2027,
of which three and a half years have already been successfully
completed;
- The UGP is projected to generate $1.1
billion in cash flow;
- Fully financed project as announced on January 9, 2024 (link to Press Release), when the
Company amended its debt package that was originally entered into
in 2021; and
- The amended facilities consist of a project finance facility
("Project Loan") of $190.0 million
(previously $170.0 million) to fund
underground development, and a $30.0
million (previously $50.0
million) senior secured working capital facility (the "WCF")
which is used to support ongoing operations along with operating
cash flow from the Karowe open pit.
William Lamb, President and CEO
of Lucara Diamond Corp., commented: "Lucara is excited to share the
updated Feasibility Study for the Karowe Underground Expansion
Project, which reinforces our strategic decision to extend mine
life and continue to generate benefits for our stakeholders. Karowe
is a world-class mine, and we look forward to continuing to recover
large, exceptional diamonds from the South Lobe at Karowe."
This report is updated from the original 2019 UGP FS (link to
Press Release) and 2021 financed base case (link to Press Release)
and encompasses the following significant modifications:
- Project construction progress (surface infrastructure and
underground development) to June 30,
2023;
- Revised economic modelling with updated diamond prices and
exchange rates, exclusion of sunk costs and inclusion of financing
costs;
- Re-baselining the UGP schedule and as a result, the open pit
mine and processing facility production plans;
- Re-estimation of the current operations budgets and project
capital and operating cost projections;
- Modifications to the mine design;
- Fine tailings storage and management;
- Advancement of detailed engineering designs;
- Re-modeling of the hydrogeological conditions;
- Underground dewatering and grouting methodology; and
- Groundwater management on surface.
PROJECT DESCRIPTION
- The UGP is focused on the South Lobe of the AK06
kimberlite;
- The UGP is designed to support operation of a 2.7 million
tonnes per annum underground mine and processing plant;
- 8.5 metre finished internal diameter Production Shaft
approximately 767 metres deep equipped to hoist a nominal 7,400
tonnes per day of ore and additional development waste;
- 6 metre finished internal diameter unequipped Ventilation Shaft
with a planned final depth of 729 metres;
- Extraction of approximately 400 vertical metres of the South
Lobe of the AK06 kimberlite from 310 metres above sea level
("masl") (700 metres below surface) to the bottom of the depleted
open pit (approximately 710 masl or 300 metres below surface).
KEY OPERATIONAL PARAMETERS
Table 1: Key Operational
Parameters
Tonnage and
Grade
|
Karowe Base
Case
|
Waste Tonnes mined
(millions)
|
3.5
|
Ore Tonnes mined
(millions)
|
42.4
|
Processed Tonnes
(millions)
|
52.2
|
Diamond grade (carats
per hundred tonne or "cpht")
based on a 1.25mm
bottom cut-off size
and inclusive of
estimated mining dilution
|
13.10
|
Recovered carats
(millions)
|
6.8
|
Diamond revenue ($
millions)
|
5,073
|
Mine Life
(years)
|
~15 years
|
FEASIBILITY STUDY APPROACH
The FS has been prepared following Canadian Institute of Mining
Guidelines for the development of an underground mine. Production
from the underground is planned after open pit operations have been
completed and the Company will rely on the processing of stockpiled
material during the latter part of the underground development and
ramp-up to full production in Q1, 2028.
The results of the FS represent forward-looking information that
are subject to a number of risks, uncertainties and other factors
that may cause results to differ materially from those presented
here. (See "Cautionary Note Regarding Forward Looking
Statements" below.)
OPERATING AND CAPITAL COST ESTIMATES
The mine operating cost estimate for the Karowe Project is based
on a combination of experience, reference projects, first principle
calculations, budgetary quotes, and factors as appropriate for a
FS.
Table 2: Summary of Operating Cost Estimate
Operating
Costs
|
Average
Annual(1)
|
Life of
Mine
|
Tonnes
Processed(2)
|
Unit Cost per tonne
Processed
|
Weighting
|
M$
|
M$
|
Mt
|
$/t
|
%
|
Open Pit Mining
Costs
|
24.2
|
72.6
|
5.5
|
13.2
|
4
|
Underground Mining
Costs
|
29.5
|
413.2
|
37.0
|
11.2
|
24
|
Rehandle
Costs
|
3.4
|
23.6
|
9.7
|
2.4
|
1
|
Process
Costs
|
24.7
|
493.7
|
52.2
|
9.5
|
29
|
Other Power
Costs
|
5.3
|
105.2
|
52.2
|
2.0
|
6
|
G&A
|
18.3
|
365.8
|
52.2
|
7.0
|
21
|
Cost of
Sales
|
4.4
|
87.9
|
52.2
|
1.7
|
5
|
Corporate Charges
(Botswana)
|
8.0
|
159.2
|
52.2
|
3.1
|
9
|
Total
|
86.1
|
1,721.1
|
52.2
|
33.0
|
100
|
Notes:
|
(1)
|
Average cost per year
in which costs occur.
|
(2)
|
Tonnes processed in
relation to operating cost.
|
|
|
Source: 2023
FS
|
The capital cost estimate was prepared using a combination of
first principles, applying project experience and using vendor/
contractor provided budgetary quotes while avoiding the use of
general industry factors. The estimate is derived from engineers,
contractors, and suppliers who have provided similar services to
existing operations and have demonstrated success in executing the
plans set forth in the study.
Table 3: Capital Cost Summary
Capital
Costs
|
Pre-Production
|
Sustaining
(M$)
|
LOM
Total
(M$)
|
Weight
(%)
|
Sunk
(M$)
|
Estimated
(M$)
|
Subtotal
(M$)
|
Mining
|
140.4
|
253.1
|
393.5
|
124.8
|
518.2
|
63 %
|
Site
Development
|
12.7
|
13.4
|
26.1
|
6.6
|
32.7
|
4 %
|
Process
Plant
|
-
|
0.1
|
0.1
|
-
|
0.1
|
0 %
|
Tailings and Mine
Waste
|
-
|
-
|
-
|
42.8
|
42.8
|
5 %
|
On-site
Infrastructure
|
13.0
|
5.1
|
18.1
|
-
|
18.1
|
2 %
|
Buildings and
Facilities
|
2.1
|
3.1
|
5.2
|
-
|
5.2
|
1 %
|
Off-site
Infrastructure
|
23.3
|
0.4
|
23.7
|
-
|
23.7
|
3 %
|
Project
Indirects
|
9.4
|
21.7
|
31.1
|
1.4
|
32.5
|
4 %
|
Owner Costs
|
63.6
|
89.9
|
153.5
|
-
|
153.5
|
19 %
|
Subtotal
|
264.5
|
386.8
|
651.3
|
175.6
|
826.9
|
100 %
|
Contingency
|
-
|
31.9
|
31.9
|
13.3
|
45.2
|
|
Closure
|
-
|
-
|
-
|
34.0
|
34.0
|
|
Total Capital
Costs
|
264.5
|
418.7
|
683.3
|
222.9
|
906.1
|
|
ECONOMICS
The main assumptions with respect to the economic model are
listed in Table 4. Table 5 shows the baseline diamond prices by
zone.
Table 4: Economic Assumptions
Item
|
Unit
|
Value
|
BWP:US$ FX
|
BWP:US$
|
12.5
|
ZAR:US$ FX
|
ZAR:US$
|
17
|
Table 5: Baseline Diamond Prices
Unit
|
Unit
|
2023
FS
|
North
|
$/ct
|
273
|
Centre
|
$/ct
|
392
|
EM/PK(S)
|
$/ct
|
828
|
M/PK(S)
|
$/ct
|
707
|
Stockpiles
|
$/ct
|
574
|
SENSITIVITIES
A univariate sensitivity analysis was performed to examine which
factors most affect the Project economics when acting independently
of all other cost and revenue factors. Each variable evaluated was
tested using the same percentage range of variation, from -20% to
+20%, although some variables may actually experience significantly
larger or smaller percentage fluctuations over the LOM. The Project
is most sensitive to diamond prices and grade and the least
sensitive to capital costs.
Table 6: Sensitivity Results (Post-Tax NPV @ 8%)
Variable
|
Post-tax
NPV8% (M$)
|
-20%
Variance
|
-10%
Variance
|
Base
|
+10%
Variance
|
+20%
Variance
|
Diamond
Price
|
252.3
|
400.1
|
531.8
|
672.0
|
811.3
|
Mining Cost
|
556.8
|
544.3
|
519.2
|
506.7
|
Processing
Cost
|
561.6
|
546.4
|
517.1
|
502.4
|
All Operating
Costs
|
607.1
|
568.1
|
495.6
|
459.6
|
Upfront
CAPEX
|
584.6
|
556.6
|
509.3
|
487.0
|
Sustaining
CAPEX
|
548.1
|
539.9
|
523.6
|
515.5
|
All capital
costs
|
602.3
|
565.4
|
501.2
|
473.1
|
MINERAL RESOURCES
The 2023 mineral resource estimate for Karowe incorporates
drilling and sampling data obtained prior to 2018, and additional
drilling and sampling information obtained in 2018/ 2019 which
targeted delineation of the deep extension of South Lobe (deeper
than approximately 600m from
surface). In 2019, the geological data were used to develop an
updated internal geology model for the South Lobe and to update the
external contacts for the South, Centre and North Lobes. The 2023
update also includes geological information and production data
derived from open pit mining to the end of June 30, 2023.
The 2023 mineral resources for Karowe, as summarized in Table 7,
have been classified as either Indicated or Inferred Mineral
Resources, according to CIM Definition Standards for Mineral
Resources and Mineral Reserves (CIM, 2014). Mineral Resources
reported are inclusive of those portions of the Mineral Resource
that have been converted to Mineral Reserves and have an effective
date of June 30, 2023.
Table 7: Karowe 2023 Mineral Resource Statement (effective
date of June 30, 2023)
Classification
|
Domain
|
Volume
(Mm3)
|
Tonnes
(Mt)
|
Density
(t/m3)
|
Carats
(Mcts)
|
Grade
(cpht)
|
Average
($/ct)
|
Indicated
|
South_M/PK(S)
|
7.02
|
20.92
|
2.96
|
2.27
|
10.8
|
707
|
South_EM/PK(S)
|
6.77
|
19.77
|
2.90
|
4.16
|
21.0
|
828
|
Centre
|
0.30
|
0.81
|
2.57
|
0.12
|
15.5
|
392
|
North
|
0.18
|
0.42
|
2.45
|
0.05
|
11.6
|
273
|
Total
Indicated
|
14.27
|
41.92
|
2.90
|
6.60
|
15.8
|
793
|
Inferred
|
South_M/PK(S)
|
0.10
|
0.31
|
3.05
|
0.03
|
10.5
|
707
|
South_EM/PK(S)
|
1.40
|
4.18
|
2.97
|
0.87
|
20.9
|
828
|
South_KIMB3
|
0.32
|
0.94
|
2.94
|
0.10
|
10.9
|
707
|
Total
Inferred
|
1.82
|
5.42
|
2.97
|
1.01
|
18.6
|
804
|
Notes:
|
1.
|
Mineral Resources are
not Mineral Reserves and do not have demonstrated economic
viability. All numbers have been rounded to reflect accuracy of the
estimate;
|
2.
|
Mineral Resources are
in-situ Mineral Resources and are inclusive of in-situ Mineral
Reserves;
|
3.
|
The base of the South
Lobe Indicated Mineral Resource is 250masl and 60masl for the
inferred resource;
|
4.
|
Mineral Resources are
exclusive of all mine stockpile material;
|
5.
|
Mineral Resources are
quoted above a +1.25 mm bottom cut-off and have been factored to
account for diamond losses within the smaller sieve classes
expected within the current configuration of the Karowe process
plant;
|
6.
|
Inferred Mineral
Resources are estimated on the basis of limited geological evidence
and sampling, sufficient to imply but not verify geological grade
and continuity. They have a lower level of confidence than that
applied to an Indicated Mineral Resource and cannot be directly
converted into a Mineral Reserve;
|
7.
|
Average diamond value
estimates are based on 2023 diamond sales data provided by Lucara
Diamond Corp.; and
|
8.
|
Mineral Resources have
been estimated with no allowance for mining dilution and mining
recovery.
|
Source: 2023
FS
|
MINERAL RESERVES
The effective date for the Mineral Reserve Estimate contained in
the updated FS report is June 30,
2023 and was prepared by Qualified Person (QP) Brandon Chambers, P.Eng. All Mineral Reserves in
Table 8 are classified as Probable Mineral Reserves. The Mineral
Reserves, except stockpiles, are not in addition to the Mineral
Resources, but are a subset thereof.
The QP has not identified any legal, political, or environmental
risks that would materially affect potential Mineral Reserves
development.
Table 8: Karowe Mineral Reserve Estimate (effective date of
June 30, 2023)
Lobe
|
Reserve
Category
|
Ore
Tonnage
|
Carats
|
Grade
|
LOM Diamond
Price
|
(Mt)
|
('000s
ct)
|
(cpht)
|
($/ct)
|
Open
Pit
|
Centre
|
Probable
|
0.6
|
96
|
16.3
|
392
|
South -
EM/PK(s)
|
Probable
|
1.3
|
323
|
25.4
|
828
|
South -
M/PK(s)
|
Probable
|
3.6
|
384
|
10.7
|
707
|
Open
Pit
|
Total
|
5.5
|
803
|
14.7
|
718
|
Underground
|
South -
EM/PK(s)
|
Probable
|
18.6
|
3,361
|
18.1
|
828
|
South -
M/PK(s)
|
Probable
|
18.4
|
1,871
|
10.2
|
707
|
Underground
|
Total
|
37.0
|
5,232
|
14.2
|
785
|
Stockpile
|
Mixed
Stockpile
|
Probable
|
4.0
|
502
|
12.7
|
433
|
Life of Mine
|
Probable
|
5.8
|
296
|
5.1
|
574
|
Stockpile
|
Total
|
9.7
|
798
|
8.2
|
485
|
Combined
|
All
|
Total
|
52.2
|
6,834
|
13.1
|
742
|
Notes:
|
1.
|
Prepared by Brandon
Chambers, P.Eng. JDS Energy & Mining Inc.;
|
2.
|
CIM definitions were
followed for Mineral Reserves;
|
3.
|
Process recovery of the
diamonds was assumed to be 100% as the recoveries were included in
the mineral resource block model assumptions and therefore have
taken recoveries into account;
|
4.
|
The bottom elevation of
the Probable Reserve is 310 masl;
|
5.
|
Mineral Reserves are
quoted above a +1.25 mm bottom cut-off and have been factored to
account for diamond loses within the smaller sieve classes expected
within the current configuration of the Karowe Process
Plant;
|
6.
|
Diamond price estimates
are provided by Lucara; prices are derived from historical sales
and adjusted for current market conditions;
|
7.
|
Tonnages are rounded to
the nearest 100,000 t, diamond grades are rounded to one decimal
place to properly reflect the Reserve estimate accuracy;
|
8.
|
Tonnage and grade
measurements are in metric units; contained diamonds are reported
as thousands of carats;
|
9.
|
Open pit Mineral
Reserves are estimated at a cut-off value of $37/t based on an open
pit mining cost of $13/t, a processing cost of $12/t and a G&A
cost of $12/t;
|
10.
|
Underground Mineral
Reserves are estimated at a cut-off value of $35/t based on an
underground mining cost of $11/t, a processing cost of $12/t and a
G&A cost of $12/t;
|
11.
|
Mine Call Factor is a
modifying factor used by Lucara which tracks the reconciliation
between the block model and actual recovered carats. Mine Call
Factor is assumed to be 100%, historically this factor has
reconciled either near or above 100%, however in the 12-month
period prior to the Reserve Statement the Mine Call Factor has
deviated away from historical average performance and is currently
at 95%;
|
12.
|
Underground dilution
assumptions in the 2019 FS were revised in 2023. Underground
dilution included in the Reserve was estimated from the following
three sources:
|
|
•
|
1.0 m of zero-grade
overbreak from stoping adjacent to the granite host
rock;
|
|
•
|
2.7 Mt of zero-grade
overbreak from stoping adjacent to sedimentary rocks (based on
geomechanical modelling); and
|
|
•
|
Inclusion of inferred
KIMB3 kimberlite within the overall pipe shape as zero-grade
waste.
|
13.
|
Stockpile Mineral
Reserves are estimated at a cut-off value of $19/t based on a
rehandle cost of $2/t, a processing cost of $12/t and a G&A
cost of $5/t, when processed at the end of mine life;
|
14.
|
Stockpile Reserves are
not included in the Karowe Mineral Resource Estimate, which covered
only in-situ mineralized material;
|
15.
|
Stockpile Reserves are
based on surveyed volumes and block model grades; and
|
16.
|
Stockpile LOM diamond
price is determined from the weighted average of the North, Centre,
South - M/PK(s), and South - EM/PK(s) lobe ratios.
|
Source: 2023
FS
|
GEOTECHNICAL
A geotechnical investigation program was carried out to support
underground mine design, building on the open pit and underground
preliminary economic assessment ("PEA") geotechnical modelling
carried out in 2017. The geotechnical drilling, sampling and
testing program was designed to comply with the data confidence
requirements of a FS, in support of a feasibility-level mine
design, and leading into optimization of the design implementation.
The investigation focused on defining the geotechnical
characteristics of the surrounding country rock as well as the
South Lobe kimberlite and involved the drilling, geotechnical
logging and sampling of 37 diamond drillholes, totaling more than
23,500m, with field and laboratory
testing of the core samples. Almost 11,000 tests were conducted on
samples across the various lithologies.
HYDROGEOLOGY
Water control and hydrogeological context of the deposit and
host rocks are key elements in the mine plan. The AK6 deposit sits
within layered, sedimentary, regional aquifers that have been
documented since the 1980's.
Since the release of the 2019 feasibility study report, five key
updates were made:
- The groundwater flow model was updated;
- A planned drainage gallery at the 680 Level (680 L) was not
implemented;
- The groundwater flow model in the 2019 FS assumed that grouting
in the granites will take place in all underground development and
will be 75% successful. The predicted inflow rate in the updated
model (2023) only assumed 66% successful grouting during shaft
sinking and station development up to January 1, 2026; the model also assumes that no
grouting activities are undertaken once underground pumping
capacity is available unless particularly high inflows are
encountered that hinder development;
- The underground drainage systems were updated; and
- The depressurization target for the open pit slope was
updated.
MINERAL PROCESSING
The Karowe processing plant has been treating unweathered South
Lobe ore since 2015 and mineral processing characteristics are very
well understood.
A comminution test program was conducted to test the milling
characteristics of the South Lobe material below the open pit to
determine if the mill is suitable for deeper EM/PK(S) ore.
The second test involved testing of Tomra's X-ray Transmission
(XRT) machines and associated software to determine their ability
to differentiate between diamonds, coal, carbonaceous shale and
other waste rock. Due to the high carbon content of coal and
carbonaceous shales, they were of greatest concern. The dilution of
ore with carbonaceous shales (and the small, sporadic, coal seams
contained therein) is anticipated to occur during the later stages
of mine life. Testing was conducted by Tomra at their testing
facilities in Germany.
MINING
The currently operating open pit at Karowe is a conventional
load and haul operation. Open pit mine operations are expected to
terminate mid-2025 at an elevation of 713 masl. The mine currently
has over three years of surface stockpiled reserves, which will be
consumed as required while the Underground mine operations ramp up
to commercial production.
The 2019 FS investigated several underground mining methods
based on data and information from an exhaustive field program
conducted in 2018 and 2019 to define mineral resource,
geotechnical, and hydrogeological characteristics necessary for
making informed decisions at a FS-level study.
The inability for natural or preconditioned caving to occur has
resulted in the development of the Long Hole Shrinkage ("LHS") mine
method, which is essentially a fully assisted cave. The method
involves a combination of longhole drilling and blasting to create
a large muck pile within the South Lobe, followed by the managed
drawdown of the blast material through a panel cave extraction
level.
The benefits of the LHS mining method include:
- Highest value ore to be extracted first due to the bottom-up
mining approach;
- Minimal development in weak, water-bearing lithologies near
surface;
- Dilution will be delayed (occurring after the payback period)
as the weaker host rock is not exposed until later in the mine
life;
- Development of the underground mine can occur simultaneously
with the open pit operations;
- Low operating costs;
- Ease of operation after the drilling and blasting phase is
complete and small underground work force requirements;
- Early exclusion of precipitation into the underground workings
until the crown pillar is blasted;
- Significant ability to increase production after the drill and
blast phase is complete; and
- Designed to manage natural caving should it occur.
INFRASTRUCTURE
The UGP at Karowe will include the use of existing and new
infrastructure at the Karowe Mine. Current and planned
infrastructure is designed to support the operation of the mine and
processing plant. Project construction over the past two years has
led to the completion of most of the surface infrastructure
components of the Project.
PERMITTING
Karowe, which has been operating since 2012, completed its
latest Environmental Impact Assessment/ Environmental Management
Plan in 2020 (to incorporate the UGP) and received approval from
the Botswana Department of Environmental Affairs during the same
year.
The mining license was renewed in 2021 for a period of 25 years
and expires on January 3, 2046.
CONCLUSIONS
It is the conclusion of the Qualified Persons ("QPs") that the
FS summarized in this press release contains adequate data and
information to support a FS. Standard industry practices, equipment
and design methods were used in the FS. Since the 2019 FS, the UGP
has advanced considerably in terms of financing, detailed
engineering and construction while the open pit mine and processing
facility have operated well and maintained targeted production.
To date, the QPs are not aware of any fatal flaws for the
UGP.
QUALIFIED PERSON ("QPS")
The FS was prepared under the direction of JDS Energy &
Mining Inc. and by leading independent industry consultants. Mr.
Gord Doerksen P. Eng is the Project manager and responsible for the
study completion and an Independent Qualified Person under National
Instrument 43-101. Dr. J.P. Armstrong, Ph.D. P. Geo., the Company's VP
Technical Services and a Qualified Person under National Instrument
43-101, and Mr. Doerksen have reviewed and approved the contents of
this news release.
The results of the Karowe Underground FS will be summarized in a
Technical Report prepared pursuant to Canadian Securities
Administrators' National Instrument 43-101 that will be filed on
SEDAR+ (https://www.sedarplus.ca) within 45 days of this press
release and will also be available on the Company's website
(https://lucaradiamond.com/).
On behalf of the Board,
William Lamb
President and Chief Executive Officer
Follow Lucara Diamond on Facebook, Instagram, and LinkedIn
ABOUT LUCARA
Lucara is a leading independent producer of large exceptional
quality Type IIa diamonds from its 100% owned Karowe Diamond Mine
in Botswana. The Karowe Mine has
been in production since 2012 and is the focus of the Company's
operations and development activities. Clara Diamond Solutions
Limited Partnership ("Clara"), a wholly-owned subsidiary of Lucara,
has developed a secure, digital sales platform which ensures
diamond provenance from mine to finger. Lucara has an
experienced board and management team with extensive diamond
development and operations expertise. Lucara and its
subsidiaries operate transparently and in accordance with
international best practices in the areas of sustainability, health
and safety, environment, and community relations. Lucara has
adopted the IFC Performance Standards and the World Bank Group's
Environmental, Health and Safety Guidelines for Mining
(2007). Accordingly, the development of the Karowe
Underground Project adheres to the Equator Principles. Lucara is
committed to upholding high standards while striving to deliver
long-term economic benefits to Botswana and the communities in which the
Company operates.
The information is information that Lucara is obliged to make
public pursuant to the EU Market Abuse Regulation and the Swedish
Securities Markets Act. This information was submitted for
publication, through the agency of the contact person set out
above, on March 13, 2024 at
5:00 p.m. Pacific Time.
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS
Certain of the statements made herein contain certain
"forward-looking information" and "forward-looking statements" as
defined in applicable securities laws. Generally, any statements
that express or involve discussions with respect to predictions,
expectations, beliefs, plans, projections, objectives, assumptions
or future events or performance and often (but not always) using
forward-looking terminology such as "expects", "is expected",
"anticipates", "believes", "plans", "projects", "estimates",
"budgets", "scheduled", "forecasts", "assumes", "intends",
"strategy", "goals", "objectives", "potential", "possible" or
variations thereof or stating that certain actions, events,
conditions or results "may", "could", "would", "should", "might" or
"will" be taken, occur or be achieved, or the negative of any of
these terms and similar expressions) are not statements of
historical fact and may be forward-looking statements.
Forward-looking information and statements are based on the
opinions and estimates of management as of the date such statements
are made, and they are subject to several known and unknown risks,
uncertainties and other factors which may cause the actual results,
performance or achievements of the Company to be materially
different from any future results, performance or achievement
expressed or implied by such forward-looking statements, including
risks related to. The Company believes that expectations reflected
in this forward-looking information are reasonable, but no
assurance can be given that these expectations will prove to be
accurate and such forward-looking information included herein
should not be unduly relied upon.
In particular, this release may contain forward looking
information pertaining to the following: potential to and length by
which the UGP will extend the life of mine; updated resource and
reserves for the Karowe Mine, including the Underground and the
total expected life of mine production; estimates of the Company's
production, operating margins and sales volumes for the Karowe
Mine, including the Underground and associated cash flow and
revenues; estimates of the economic benefits of the Underground,
including the timing for the UGP to pay back capital; anticipated
total capital expenditures for the Underground and the schedule to
develop and complete the UGP; continued availability of external
financing; that expected cash flows from open pit operations,
combined with external financing, will be sufficient to complete
construction of the UGP; the ability to integrate the underground
operations seamlessly into the existing infrastructure; the timing
of key construction milestones including shaft sinking activities;
the anticipated mine plan and mining methods; that the decisions
taken to de-risk the UGP will be successful; that the people,
equipment and materials required to build the UGP will be available
when required to maintain the proposed UGP schedule; anticipated
changes in diamond pricing, including trends in supplies and
demands; changes to foreign currency exchange rate; the Company's
adoption of and compliance with internationally recognized
standards including IFC Performance Standards and the Equator
Principles; and other forward looking information.
There can be no assurance that such forward looking statements
will prove to be accurate, as the Company's results and future
events could differ materially from those anticipated in this
forward-looking information as a result of those factors discussed
in or referred to under the heading "Risks and Uncertainties"' in
the Company's most recently filed Annual MD&A and, in the
Company's most recent Annual Information Form available at SEDAR+
at www.sedarplus.ca, as well as the Company's ability to access the
markets and generate revenues at anticipated diamond prices, the
Company's ability to continue to comply with the terms of its debt
financing, changes in general business and economic conditions,
changes in interest and foreign currency rates, the supply and
demand for, deliveries of and the level and volatility of prices of
rough diamonds, costs of power and diesel, acts of foreign
governments and the outcome of legal proceedings, inaccurate
geological and recoverability assumptions (including with respect
to the size, grade and recoverability of mineral reserves and
resources), and unanticipated operational difficulties (including
failure of plant, equipment or processes to operate in accordance
with specifications or expectations, cost escalations,
unavailability of materials and equipment, government action or
delays in the receipt of government approvals, industrial
disturbances or other job actions, adverse weather conditions, and
unanticipated events relating to health safety and environmental
matters).
The foregoing is not exhaustive of the factors that may affect
any of our forward-looking statements. Forward-looking statements
are statements about the future and are inherently uncertain, and
our actual achievements or other future events or conditions may
differ materially from those reflected in the forward-looking
statements due to a variety of risks, uncertainties, and other
factors, including, without limitation, those referred to in this
news release. Accordingly, readers and investors should not place
undue reliance on forward-looking statements. Forward-looking
information and statements are made as of the date of this
disclosure and accordingly are subject to change after such date.
Except as required by law, the Company disclaims any obligation to
revise any forward-looking information and statements to reflect
events or circumstances after the date of such information and
statements. All forward-looking information and statements
contained or incorporated by reference in this news release are
qualified by the foregoing cautionary statements.
SOURCE Lucara Diamond Corp.