VANCOUVER, BC, May 10, 2024 /PRNewswire/ -- (TSX: LUC) (BSE:
LUC) (Nasdaq Stockholm: LUC) Please view PDF version
Lucara Diamond Corp. ("Lucara" or the "Company") today reports
its results for the quarter ended March 31,
2024. All amounts are in U.S. dollars unless otherwise
noted.
Q1 2024 HIGHLIGHTS:
- The Karowe Mine has operated continuously for over three years
without a lost time injury.
- The recovery of a 320-carat top light brown gem quality
diamond, a 166-carat Type IIa diamond, followed by the recovery of
a 111-carat Type IIa diamond in Q1 2024.
- In January 2024, the successful
execution of an amended project financing debt package of
$220 million (the "Rebase
Amendments") to amend the repayment profile in line with the rebase
schedule released in July 2023 for
the Karowe Underground Project ("Karowe UGP").
- On February 18, 2024, the Company
announced the signing of a new ten-year diamond sales agreement
("NDSA") with HB Trading BV ("HB") in respect of all qualifying
diamonds produced in excess of 10.8 carats from the Karowe
Mine.
- Total revenue of $41.1 million
(Q1 2023: $42.8 million) was achieved
in the quarter which is reflective of a combination of the timing
of production and quantity of large goods recovered and delivered
to HB.
- During Q1 2024, a total of 93,560 carats of rough diamonds (Q1
2023: 83,374) from Karowe were sold through the Company's three
sales channels, generating revenue of $36.2
million before top-up payments of $4.9 million (Q1 2023: $34.7 million before top-up payments of
$6.6 million).
- Operating cost per tonne processed(1) was
$26.00, a decrease of 2% over the Q1
2023 cost per tonne processed of $26.65. The continued impact of inflationary
pressures, particularly labour, has been well managed by the
operation. A strong US dollar (+5%) continues to offset a small
increase in costs over the comparable period.
(1)
|
See "Non-IFRS
Financial Performance Measures"
|
William Lamb, President & CEO
commented: "Our Karowe diamond mine delivered another solid
operational quarter, continuing its track record of sustainable
diamond production from this world-class asset. The Company's
high-value diamond production forecast remains robust, underpinned
by our focus on operating practices aligned with leading
environmental, social and governance standards.
Work on the underground expansion project at Karowe also
progressed well during the quarter. This key growth initiative
remains on track with the rebase schedule and budget, positioning
us to access the higher-value ore from the underground portion of
the ore body, early in 2028.
While the diamond market remained relatively stable in Q1, we
observed some cautious sentiment due to the broader macroeconomic
climate of high inflation and interest rates impacting consumer
demand in certain regions. However, the fundamental supply and
demand dynamics continue to favour natural diamonds over the
long-term as new mine supply remains constrained.
Lucara is well-positioned with our exceptional diamond
production profile and our innovative process facilities and sales
mechanisms to navigate this environment. We will continue executing
our growth strategy while maintaining financial discipline to
create sustained value for all our stakeholders."
REVIEW FOR THE QUARTER ENDED MARCH 31,
2024
- Operational highlights from the Karowe Mine for Q1 2024
included:
- Ore and waste mined of 0.8 million tonnes ("Mt") (Q1 2023:
0.5Mt) and 0.2 million tonnes (Q1 2023: 0.8Mt), respectively.
- 0.7 million tonnes (Q1 2023: 0.7Mt) of ore processed.
- A total of 89,145 carats recovered, including 7,534 carats from
the processing of historic recovery tailings, (Q1 2023: 89,640
carats) at a recovered grade of 11.7 carats per hundred tonnes
("cpht") of direct milled ore (Q1 2023: 12.8 cpht).
- A total of 160 Specials (defined as stones larger than 10.8
carats) were recovered, with three diamonds greater than 100 carats
including one diamond greater than 300 carats.
- Recovered Specials equated to 5.1% of the total recovered
carats from direct milling ore processed during Q1 2024 (Q1 2023:
4%).
- The Karowe Mine has operated continuously for over three
years without a lost time injury.
- The twelve-month Total Recordable Injury Frequency Rate of 0.30
(Q1 2023: 0.36) at the end of Q1 2024 reflects a continued focus on
leading indicators and safe performance.
- Financial highlights for the three months ended March 31, 2024 included:
- Revenues of $41.1 million (Q1
2023: $42.8 million) were achieved
despite a weaker rough diamond market. First quarter pricing
stabilized in smaller goods and increases of 4% were observed
compared to the fourth quarter of 2023. Revenue reflects the
weighting of Lucara's revenue towards larger goods where
pricing is heavily impacted by the individual goods delivered in a
period. A 33% increase in the average price of larger goods sold
was observed from the fourth quarter of 2023 and 18% from the first
quarter of 2023. The price of goods in this size category are
significantly impacted by the natural variability in quality of the
recovered goods in any individual period. Revenue against plan was
impacted by the quantity of larger goods delivered in Q1 2024.
- Operating margins of 51% were achieved (Q1 2023: 57%). A strong
operating margin continues to be achieved through cost reduction
initiatives assisted by a strong U.S. dollar.
- Adjusted EBITDA(1) was $12.7
million (Q1 2023: $15.3
million), with the decrease attributable to the changes in
revenue and operating expenses.
- Net loss was $7.9 million (Q1
2023: net income of $1.0 million),
resulting in a loss per share of $0.02 (Q1 2023: earnings of $0.00). The significant change to a net loss is
due to the loss on extinguishment of debt of $10.5 million incurred in Q1 2024 in conjunction
with recognizing the amendments to the debt package.
- Cash outflows from operating activities was $4.2 million (Q1 2023: cash flow generated of
$20.4 million). Operating cash flow
per share(1) generated, before working capital
adjustments, was consistent at $0.03
(Q1 2023: $0.03)
- Cash position and liquidity at March 31,
2024:
- Cash and cash equivalents of $13.2
million.
- Working capital deficit (current assets less current
liabilities) of $0.3 million.
- Cost overrun account balance ("CORA") of $37.0 million.
- $140.0 million drawn on the
$190.0 million Project Loan ("Project
Loan") for the Karowe UGP.
- $25.0 million drawn on the
$30.0 million working capital
facility ("WCF").
- The total debt drawn at the end of Q1 2024 was $165.0 million compared to $125.0 million at December
31, 2023. The increase in debt drawn during Q1 2024 largely
resulted as the Company did not have access to the Project Loan and
WCF from June 2023 until January 2024 when the project finance debt
package was finalized.
(1)
|
See "Non-IFRS
Financial Performance Measures"
|
DIAMOND MARKET
The long-term outlook for natural diamond prices remains
positive, anchored on improving fundamentals around supply and
demand as many of the world's largest mines reach their end of
life. In the short-term, De Beers, the largest diamond
producer by value reduced their production guidance by up to 3.0
million carats, for 2024, to assist with stabilizing the diamond
market. During the quarter, the G7 sanctions on the importation of
Russian diamonds greater than one carat went into effect at the
beginning of March and some trade delays were noted in the
industry. The new procedures require all rough diamonds larger than
1.0 carat to be processed through the Antwerp World Diamond Centre
for validation of point of origin. The Company sees this as
short-term support for diamond pricing as this, together with the
reduction in production volumes from De Beers, will result in lower
volumes of higher value goods being available in the market.
Sales of lab-grown diamonds increased steadily through 2023 and
into Q1 2024 with many smaller retail outlets increasingly adopting
these diamonds as a product. In Q1 2024, this market underwent
further change with a number of major brands confirming that they
would not market lab-grown stones. The overall long-term impact
will support the natural diamond market as the Company expects a
division between the natural and lab-grown diamond market. The
longer-term market fundamentals for natural diamonds remain
positive, pointing to continued price growth as demand is expected
to outstrip future supply, which is now declining globally.
2024 OUTLOOK
This section of the press release provides management's
production and cost estimates for 2024. These are
"forward-looking statements" and subject to the cautionary note
regarding the risks associated with forward-looking statements.
Diamond revenue guidance does not include revenue related to the
sale of exceptional stones (an individual rough diamond which sells
for more than $10.0 million), or the
Sethunya. No changes have been made to the guidance released in
November 2023.
Karowe Diamond
Mine
|
Full Year –
2024
|
In millions of U.S.
dollars unless otherwise noted
|
|
Diamond revenue
(millions)
|
$220 to $250
|
Diamond sales
(thousands of carats)
|
345 to 375
|
Diamonds recovered
(thousands of carats)
|
345 to 375
|
Ore tonnes mined
(millions)
|
2.8 to 3.2
|
Waste tonnes mined
(millions)
|
0.8 to 1.4
|
Ore tonnes processed
(millions)
|
2.6 to 2.9
|
Total operating cash
costs(1) including waste mined (per tonne
processed)
|
$28.50 to
$35.50
|
Underground
Project
|
Up to $100
million
|
Sustaining
capital
|
Up to $10
million
|
Average exchange rate –
USD/Pula
|
12.5
|
(1)
|
Operating cash costs
are a non-IFRS measure. See "Non-IFRS Financial Performance
Measures".
|
The Company had expected higher diamond recoveries and diamond
quality during Q4 2023 and Q1 2024. This reflects the natural
variability in the resource production in both recovery and diamond
quality and were it to continue, this may impact revenue guidance
for 2024. The Company has seen diamond recoveries and quality
improve during April 2024.
DIAMOND SALES
Karowe diamonds are sold through three sales channels: through
the HB sales agreement, on the Clara digital sales platform and
through quarterly tenders.
HB SALES AGREEMENT FOR +10.8 CARAT DIAMOND PRODUCTION FROM
KAROWE
For the three months ended March 31,
2024, the Company recorded revenue of $23.2 million from the HB arrangements (inclusive
of top-up payments of $4.9 million),
as compared to revenue of $24.5
million (inclusive of top-up payments of $6.6 million) for the three months ended
March 31, 2023. The volume of carats
delivered to HB was lower in the first quarter of 2024 than
planned. The volume recognized as revenue in Q1 2024 was impacted
by the timing of goods delivered as well as the number of stones
greater than +10.8 carats recovered in the period. The plant
performance remained strong with a 97% recovery factor achieved in
Q1 2024; however, the weight percentage of recovered specials was
lower than plan.
Recovered Specials for the quarter equated to 5.1% by weight of
total recovered carats from ore processed during Q1 2024, with 89%
of carats recovered coming from the South Lobe, 7% recovered from
the Centre Lobe, and 4% recovered from mixed ore (Q1 2023: 4.0%;
64% Centre and North, 36% South Lobe ore). Natural variability in
the quality profile of the +10.8ct stones in any production period
or fiscal quarter results in fluctuations in recorded revenue and
associated top-ups.
The average price of goods delivered in the first quarter of
2024 remained strong and is directly comparable to the value
delivered in the first quarter of 2023. Top-ups in the first
quarter continue to be received from goods delivered in prior
periods under the November 2022
diamond sales agreement with HB. As a result of these factors,
revenue to HB was consistent at 57% of total revenue recognized in
the first quarter of 2024 (Q1 2023: 57%). The product mix in Q1
2024 was predominantly from the South Lobe ore body, with some
contribution from the Centre Lobe.
The Company had expected higher diamond recoveries and diamond
quality during Q4 2023 and Q1 2024. This decrease in both
recovery and diamond quality contributed to the Company's
additional working capital facility draw during the quarter.
Under the HB agreement payment for diamonds delivered under a value
of $2.0 million is 60 days and for
diamonds of value greater than $2.0
million is 120 days. The Company has seen diamond
recoveries and quality improve during Q2 2024, however due to the
payment terms of the HB agreement these funds will not be received
until Q3 2024 which has strained cash flows during Q2. As a
result, the Company drew $25.0
million from the project loan to fund its underground
development.
The large stone diamond market fundamentals continued to support
healthy prices from the multi-year highs observed at the peak in Q1
2022, despite an overall softening of demand in the market.
CLARA SALES PLATFORM
Total volume transacted on the platform was $4.9 million in Q1 2024 (Q1 2023: $5.3 million), with non-Karowe goods representing
33% of the total sales volume transacted. Prices trended flat
during the first quarter of 2024 following a small uptick in
pricing in December 2023 with a
resumption of purchasing across most size categories. The number of
buyers on the platform reached 106 as of March 31, 2024.
QUARTERLY TENDER
A total of 88,275 carats were sold in the Q1 2024 tender,
generating revenues of $13.0 million
or $147 per carat (Q1 2023 tender:
$12.9 million from the sale of 77,750
carats or $166 per carat). Following
a rebound in the fourth quarter of 2023, prices trended mostly flat
across most size categories at tender. Like-for-like, prices were
up 4% from December 2023 on all goods
sold less than 10.8 carats, including on Clara.
KAROWE UNDERGROUND EXPANSION UPDATE
The Karowe UGP is designed to access the highest value portion
of the Karowe orebody, with initial underground carat production
predominantly from the highest value eastern magmatic/pyroclastic
kimberlite (south) ("EM/PK(S)") unit. The Karowe UGP is expected to
extend mine life to at least 2040.
On July 16, 2023, an update to the
Karowe UGP schedule and budget was announced (link to news
release). The anticipated commencement of production from the
underground is H1 2028. The revised forecast of costs at completion
is $683.0 million (including
contingency). As at March 31, 2024,
capital expenditures of $332.5
million had been incurred and further capital commitments of
$64.4 million had been
made.
With the update, the Karowe Mine production and cash flow models
were updated for the revised project schedule and cost estimate.
Open pit mining will continue until mid-2025 and provide mill feed
during this time. Stockpiled material (North, Centre, South Lobe)
from working stocks and life of mine stockpiles will provide
uninterrupted mill feed until late 2026 when Karowe UGP development
ore will begin to offset stockpiles with high-grade ore from the
underground production feed planned for H1 2028. The long-term
outlook for diamond prices, combined with the potential for
exceptional stone recoveries and the continued strong performance
of the open pit could mitigate the modelled impact on project cash
flows due to the changes in schedule. The Company continues to
explore opportunities to further mitigate the modelled impact.
During the three months ended March 31,
2024, a total of $17.9 million
was spent on the Karowe UGP development, surface infrastructure and
ongoing shaft sinking activities. The following activities were
completed during Q1 2024, including:
- Main sinking in the production and ventilation shafts:
- The ventilation shaft reached 426 metres below collar, with a
planned final depth of 731 metres. The shaft is approximately 19
days ahead of the July 2023 schedule
update (combined vertical and lateral metres).
- The production shaft reached 449 metres below collar, with a
planned final depth of 765 metres. The production shaft is
approximately 15 days behind the July
2023 schedule update (combined vertical and lateral), with 9
days gained during the first quarter of 2024. The production shaft
is not a critical path schedule item.
- During Q1 2024, the first shaft stations at the 670-level were
engaged in lateral development at 348 metres below collar
(666 masl). The first lateral connection between the two
shafts (670 level) was completed. Electrical and dewatering sump
excavation was completed, and construction of equipment was carried
out as a concurrent activity during shaft sinking.
- During Q1 2024, the ventilation shaft sank 78 metres, completed
three probe hole covers, continued the 670-level station
development and replaced the initial winder kibble ropes. Total
lateral development in Q1 2024 was 141 metres.
- Production shaft activities included sinking a total of 101
metres, completion of four probe hole covers, lateral development
on the 670-level station and replacement of the initial
winder kibble ropes. A total of 26 metres of lateral
development was completed.
- Sinking and lateral development during the first quarter took
place in the Thalbala mudstone and the Tlapana carbonaceous
material. Water encountered in the core holes was derived from
Granites. A mini grout cover was completed in the production shaft
and sinking continued.
- Construction of the permanent bulk air coolers at the
production shaft continued with completion expected in Q2 2024.
Planning for a surface dam for the water during production
commenced.
- Detailed engineering and fabrication of the permanent men and
materials winder continued during the quarter, representing the
last major component for the permanent winders.
- Preparation of tender documents for the underground lateral
development work.
- Mining engineering advanced with a focus on supporting shaft
sinking, underground infrastructure engineering and finalizing
level plans.
- During Q1 2024, the UGP achieved a twelve-month rolling Total
Recordable Injury Frequency Rate of 0.65. Project to date Total
Recordable Injury Frequency Rate at March
31, 2024 was 0.56.
The capital cost expenditure for the underground expansion in
2024 is up to $100 million – see
"2024 Outlook" below.
Activities planned for the Karowe UGP in Q2 2024 include the
following:
- Sinking within the ventilation and production shafts to the
470-level.
- Sink through the Mea formation into Granites and commence
470-level station development and lateral development.
- Planned cover drill campaigns in the ventilation and production
shafts. Sinking planned for the second quarter will move through
the Mea formation into the Granite lithologies. Probe hole grouting
campaigns are planned in each shaft in the period.
- Procurement of underground equipment, including an additional
Load, Haul, Dump Aardvark for the production shaft station
development. Major components of the Crusher and sinking pumps will
be delivered to site.
- Commissioning of the permanent bulk air cooler system.
- Launch of the tender process for the underground lateral
development work.
- Continuation of detailed design and engineering of the
underground mine infrastructure and layout.
- Finalise engineering of the permanent men and materials winder.
Commence earthworks for winder.
FINANCIAL HIGHLIGHTS – Q1 2024
|
Three
months
ended March 31,
|
|
In millions of U.S.
dollars, except carats or otherwise noted
|
|
2024
|
2023
|
|
|
|
|
|
|
|
|
Revenues
|
|
|
|
$
|
41.1
|
42.8
|
Operating
expenses
|
|
|
|
|
(20.2)
|
(18.3)
|
Net (loss) income for
the period
|
|
|
|
|
(7.9)
|
1.0
|
(Loss) earnings per
share (basic and diluted)
|
|
|
|
|
(0.02)
|
0.00
|
Operating cash flow per
share(1)
|
|
|
|
|
0.03
|
0.03
|
Cash on hand
|
|
|
|
|
13.2
|
31.2
|
Cost overrun facility
(restricted cash)
|
|
|
|
|
37.0
|
18.0
|
Amounts drawn on
working capital facility(2)
|
|
|
|
|
25.0
|
23.0
|
Amounts drawn on
Project Loan
|
|
|
|
|
140.0
|
90.0
|
Revenue from the sale
of Karowe diamonds
|
|
|
|
|
39.5
|
41.2
|
Carats sold from
Karowe
|
|
|
|
|
93,560
|
83,374
|
(1)
|
Operating cash flow
per share before working capital adjustments is a non-IFRS measure.
See "Use of Non-IFRS Performance Measures" below.
|
(2)
|
Excludes amounts
drawn from the Clara revolving credit facility.
|
QUARTERLY RESULTS OF OPERATIONS – KAROWE MINE
|
UNIT
|
Q1-24
|
Q4-23
|
Q3-23
|
Q2-23
|
Q1-23
|
Sales
|
|
|
|
|
|
|
Revenues from the sale
of Karowe diamonds
|
US$M
|
39.5
|
36.3
|
56.2
|
38.6
|
41.3
|
Karowe carats
sold
|
Carats
|
93,560
|
111,523
|
111,673
|
72,717
|
83,374
|
|
|
|
|
|
|
|
Production
|
|
|
|
|
|
|
Tonnes mined
(ore)
|
Tonnes
|
809,999
|
607,101
|
869,188
|
682,636
|
541,400
|
Tonnes mined
(waste)
|
Tonnes
|
386,849
|
456,880
|
954,226
|
907,051
|
761,295
|
Tonnes processed
|
Tonnes
|
698,870
|
703,472
|
724,640
|
720,345
|
700,678
|
Average grade
processed(1)
|
cpht
(*)
|
11.7
|
14.0
|
13.6
|
12.6
|
12.8
|
Carats
recovered(1)
|
Carats
|
81,611
|
98,177
|
98,311
|
90,497
|
89,640
|
|
|
|
|
|
|
|
Costs
|
|
|
|
|
|
|
Operating cost per
tonne of ore processed(2)
|
US$
|
26.00
|
31.96
|
28.62
|
27.97
|
26.65
|
|
|
|
|
|
|
|
Capital
Expenditures
|
|
|
|
|
|
|
Sustaining capital
expenditures
|
US$M
|
1.8
|
8.0
|
3.2
|
2.4
|
0.8
|
Underground expansion
project(3)
|
US$M
|
17.9
|
28.0
|
20.3
|
22.5
|
30.5
|
(*)
|
carats per hundred
tonnes
|
(1)
|
Average grade
processed is from direct milling carats and excludes carats
recovered from re-processing historic recovery tailings from
previous milling.
|
(2)
|
Operating cost per
tonne of ore processed is a non-IFRS measure. See "Use of Non-IFRS
Performance Measures" below.
|
(3)
|
Excludes qualifying
borrowing cost capitalized in each quarter.
|
ANNUAL MEETING INFORMATION
The Company's annual general and special meeting of shareholders
will be held at the office of Blake, Cassels & Graydon LLP,
1133 Melville Street, Suite 3500, Vancouver, BC V6E 4E5, Canada on May 10,
2024 at 10:00 a.m.
Pacific.
CONFERENCE CALL
The Company will host a conference call and webcast to discuss
the results on Friday, May 10, 2024
at 6:00am Pacific, 9:00am Eastern, 2:00pm UK, 3:00pm
CET.
To join the conference call please use the following link
https://emportal.ink/4arz7Nw or the phone numbers listed
below.
Conference ID:
35323198 / Lucara Diamond
Dial-In Numbers:
Toll Free Participant Dial-In North America (+1)
888 390 0605
UK Toll Free
0800
652 2435
Local Vancouver
(+1) 416 764
8609
Webcast:
To view the live webcast presentation,
please log on using this direct link:
https://app.webinar.net/xMgd9elnpVN
The presentation slideshow will also be available in PDF format
for download from the Lucara website (Link to presentation).
Conference Replay:
A replay will be available
until May 17, 2024. The pass code for
the replay is: 085076 #.
Replay number (Toll Free North America) (+1) 888 390
0541
Replay number (Local)
(+1) 416 764 8677
On behalf of the Board,
William Lamb
President and Chief Executive Officer
Follow Lucara Diamond on Facebook, Instagram, and LinkedIn
ABOUT LUCARA
Lucara is a leading independent producer of large exceptional
quality Type IIa diamonds from its 100% owned Karowe Diamond Mine
in Botswana. The Karowe Mine has
been in production since 2012 and is the focus of the Company's
operations and development activities. Clara Diamond Solutions
Limited Partnership ("Clara"), a wholly-owned subsidiary of Lucara,
has developed a secure, digital sales that ensures diamond
provenance from mine to finger. Lucara has an experienced
board and management team with extensive diamond development and
operations expertise. Lucara and its subsidiaries operate
transparently and in accordance with international best practices
in the areas of sustainability, health and safety, environment, and
community relations. Lucara has adopted the IFC Performance
Standards and the World Bank Group's Environmental, Health and
Safety Guidelines for Mining (2007). Accordingly, the
development of the Karowe UGP adheres to the Equator Principles.
Lucara is committed to upholding high standards while striving to
deliver long-term economic benefits to Botswana and the communities in which the
Company operates.
The information is information that Lucara is obliged to make
public pursuant to the EU Market Abuse Regulation and the Swedish
Securities Markets Act. This information was submitted for
publication, through the agency of the contact person set out
above, on May 9, 2024 at 6:00pm Pacific Time.
NON-IFRS FINANCIAL PERFORMANCE MEASURES
This news release refers to certain financial measures, such as
adjusted EBITDA, adjusted operating earnings, operating cash flow
per share, operating margin per carat sold and operating cost per
tonne of ore processed, which are not measures recognized under
IFRS and do not have a standardized meaning prescribed by IFRS.
These measures may differ from those made by other corporations and
accordingly may not be comparable to such measures as reported by
other corporations. These measures have been derived from the
Company's financial statements, and applied on a consistent basis,
because the Company believes they are of assistance in the
understanding of the results of operations and financial position.
Please refer to the Company's MD&A for the quarter ended
March 31, 2024 for an explanation of
non-IFRS measures used.
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS
Certain of the statements made and contained herein and
elsewhere constitute "forward-looking information" and
"forward-looking statements" as defined in applicable securities
laws. Generally, any statements that express or involve discussions
with respect to predictions, expectations, beliefs, plans, budgets,
schedules, goals, strategy, projections, objectives, assumptions or
future events or performance and often (but not always) using
forward-looking terminology such as "expects", "is expected",
"anticipates", "believes", "intends", "estimates", "potential",
"possible" and similar expressions, or statements that certain
actions, events, conditions or results "would", "will", "may",
"might", "could" or "should" be taken, occur or be achieved or the
negative of any of these terms and similar expressions) are not
statements of historical fact and may be forward-looking
statements.
Forward-looking statements are based on the opinions and
estimates of management as of the date such statements are made,
and they are subject to a number of known and unknown risks,
uncertainties and other factors which may cause the actual results,
performance or achievements of the Company to be materially
different from any future results, performance or achievement
expressed or implied by such forward-looking statements, including
risks related thereto. The Company believes that expectations
reflected in this forward-looking information are reasonable, but
no assurance can be given that these expectations will prove to be
accurate and such forward-looking information included herein
should not be unduly relied upon.
In particular, forward-looking information and forward-looking
statements in this news release may include, but are not limited
to, information or statements of projected capital costs associated
with the Karowe UGP and any conditions for borrowing at the
time of a borrowing request, and that the facilities are not
otherwise terminated or accelerated due to an event of default, the
Company's ability to comply with the terms of the facilities which
are required to construct the Karowe UGP, that expected cash flow
from operations, combined with external financing will be
sufficient to complete construction of the Karowe UGP, economic and
geopolitical risks, including the potential impacts from the
ongoing conflict between Russia
and Ukraine and the resulting
indirect economic impacts that strict economic sanctions have,
expectations regarding longer-term market fundamentals and price
growth, the disclosure under "2024 Outlook", expectations regarding
top-up payments, processing expectations, expectations that the
Karowe UGP will extend mine life, forecasts of additional revenues,
estimated capital costs, production and cost estimates, tax rates,
expectations regarding the scheduling of activities for the Karowe
UGP in 2024 and in future, that the estimated timelines to achieve
mine ramp up and full production from the Karowe UGP can be
achieved, the economic potential of a mineralized area, the size
and tonnage of a mineralized area, anticipated sample grades or
bulk sample diamond content, future production activity, the future
price and demand for, and supply of, diamonds, future forecasts of
revenue and variable consideration in determining revenue,
estimation of mineral resources, exploration and development plans,
cost and timing of the development of deposits and estimated future
production, currency exchange rates, success of exploration,
requirements for and availability of additional capital, capital
expenditures, operating costs, the completion of transactions, and
the profitability of Clara and the Clara Platform, the benefits to
the Company of diamond supply agreements with HB and the ability to
generate better prices from the sale of the Company's +10.8 carat
production as a polished stone.
There can be no assurance that such forward looking statements
will prove to be accurate, as the Company's results and future
events could differ materially from those anticipated in this
forward-looking information as a result of those factors discussed
in or referred to under the heading "Risks and Uncertainties" in
the Company's most recent MD&A and in the Company's most recent
Annual Information Form, both available at SEDAR+ at
www.sedarplus.ca, as well as changes in general business and
economic conditions, the ability to continue as a going concern,
changes in interest and foreign currency rates, changes in
inflation, the supply and demand for, deliveries of and the level
and volatility of prices of rough diamonds, costs of power and
diesel, impacts of potential disruptions to supply chains, acts of
foreign governments and the outcome of legal proceedings,
inaccurate geological and recoverability assumptions (including
with respect to the size, grade and recoverability of mineral
reserves and resources), and unanticipated operational difficulties
(including failure of plant, equipment or processes to operate in
accordance with specifications or expectations, cost escalations,
unavailability of materials and equipment, government action or
delays in the receipt of government approvals, industrial
disturbances or other job actions, adverse weather conditions, and
unanticipated events relating to health safety and environmental
matters).
Accordingly, readers are cautioned not to place undue reliance
on these forward-looking statements which speak only as of the date
the statements were made, and the Company does not assume any
obligations to update or revise them to reflect new events or
circumstances, except as required by law.
Contact: Vancouver:
Hannah Reynish, Investor Relations & Communications, +1
604 674 0272| info@lucaradiamond.com; Sweden: Robert
Eriksson, Investor Relations & Public Relations, +46 701
112615 | reriksson@rive6.ch; UK Public Relations: Charles Vivian / Jos Simson, Tavistock, +44 778 855 4035 |
lucara@tavistock.co.uk
View original
content:https://www.prnewswire.co.uk/news-releases/lucara-announces-q1-2024-results-progress-on-underground-expansion-302141923.html