TSX:ORV
TORONTO, Jan. 16,
2025 /PRNewswire/ -- Orvana Minerals
Corp. (TSX: ORV) (the "Company" or "Orvana") is pleased
to provide a progress update for construction and financing
activities at Don Mario (Bolivia)
and to report production and exploration updates for the first
quarter of fiscal year 2025 ("Q1 FY2025) ending December 31, 2024 from Orovalle (Spain).
Don Mario – Oxides Stockpile Project
- The Company's Bolivian subsidiary, Empresa Minera Paitití, S.A.
(EMIPA) has obtained key permits for the plant expansion at Don
Mario and construction has commenced.
- Construction activities to-date have focused on site
preparations and earthworks for the plant expansion area, including
the concrete foundation work.
- Contracting and fabrication of structural steel, tanks and key
process equipment is now underway.
- All activities are advancing on schedule and as of December 31, 2024, the project is approaching
3.5% completion.
- To-date, approximately 118,496 project hours have been worked
and there have been no reportable injuries or environmental
incidents.
- There are currently 150 construction personnel at site.
- Based on recent contractor and vendor quotations, the Company
is updating capital cost estimates, and will provide updates when
further material information becomes available.
- The Company expects to complete construction by the end of
calendar year 2025, conditional on securing the remaining required
balance of the funding during the first half of 2025.
- Further information about the project is contained in the
Company's technical report dated March 15,
2022 entitled "National Instrument 43-101 Technical Report
for the Don Mario Property, Eastern
Bolivia," which is available under the Company's profile on
SEDAR+ and on the Company's website.
Juan Gavidia, CEO of Orvana,
commented, "We are pleased with progress through the first
quarter of construction. The project is on track for commercial
production by early 2026, which will be a transformative event for
our Company."
Orovalle - Q1 FY2025 Production Results
- 7,631 gold ounces produced, on track to meet fiscal year 2025
guidance of 37,000 - 41,000 Oz.
- 1.1 million copper pounds produced, on track to meet fiscal
year 2025 guidance of 2,400 – 2,700 K
lbs.
|
|
Q1
FY2025
|
Q4
FY2024
|
Q1
FY2024
|
FY 2025
Guidance
|
Ore milled
(tones)
|
|
118,649
|
139,275
|
130,267
|
|
Gold equivalent
(oz)(1)
|
|
9,694
|
11,862
|
9,550
|
|
Gold
|
|
|
|
|
|
Grade (g/t)
|
|
2.16
|
2.39
|
2.09
|
|
Recovery (%)
|
|
92.7
|
92.5
|
91.5
|
|
Production (oz)
|
|
7,631
|
9,888
|
7,994
|
37,000 -
41,000
|
Copper
|
|
|
|
|
|
Grade (%)
|
|
0.48
|
0.41
|
0.32
|
|
Recovery (%)
|
|
85.5
|
75.4
|
76.3
|
|
Production (K
lbs)
|
|
1,068
|
961
|
702
|
2,400 -
2,700
|
Silver
|
|
|
|
|
|
Grade (g/t)
|
|
10.78
|
8.90
|
6.77
|
|
Recovery (%)
|
|
81.0
|
75.0
|
72.0
|
|
Production (oz)
|
|
33,306
|
29,864
|
20,393
|
|
(1) Gold Equivalent Ounces ("GEO")
were calculated using the following average market
prices:
|
|
Q1 FY2025:
_$2,661.61/oz Au, $31.34/oz Ag, $4.16/lb Cu
|
|
Q4 FY2024:
_$2,476.80/oz Au, $29.42/oz Ag, $4.17/lb Cu
|
|
Q1 FY2024:
_$1,975.87/oz Au, $23.23/oz Ag, $3.71/lb Cu
|
GEO is a Non-GAAP Financial Performance Measure. For further
information and detailed reconciliations, please see the "Non-GAAP
Financial Performance Measures" section of the Company's FY2024
MD&A.
Orovalle – Q1 FY2025 Drilling Update
Drilled
Meters
|
Infill
|
Brownfield
|
Greenfield
|
TOTAL
|
El Valle
Boinás
|
|
|
|
|
Area 208
(A2)
|
1,042
|
1,436
|
-
|
2,478
|
Breccia East
(BX)
|
330
|
-
|
-
|
330
|
Ortosa-Godán
|
-
|
-
|
497
|
497
|
TOTAL
|
1,372
|
1,436
|
497
|
3,304
|
El Valle Boinás
The drilling program in Q1 FY2025 was focused on Area 208, oxide
orebody, to continue defining new inferred resources and targeting
to convert inferred resources into indicated resources.
Area 208 structure is located into limestone in deeper levels,
dipping to the east. Mineralization in the sections drilled is
related with porphyry dikes which are intersected by faults and it
has an important width below 300 level. Oxide skarn, massive
sulphides, polymictic breccias, fault zones and silicified zones
were intersected with the drill holes providing interesting
intersections. In particular, drill hole 24A21957 intercepted 80.9
meters with 8.36 g/t Au (see full list of intercepts in Figure 1).
The structure remains open at deeper levels to the east.
Drilling program in the second quarter will continue focused on
Area 208.
Ortosa-Godán
Ortosa-Godan Project is located three kilometers northwest of
our Carlés mine, and within the same gold belt. The exploration
program is focused on Godán where the last drilling program proved
the presence of mineralization in the contact between the intrusive
and sedimentary rocks with calcic skarn bands dipping 60-70º ESE
over 200 meters of strike potential.
Current drilling program was started at the end of October.
First drill hole continues in progress and it is expected that will
be completed by the end of January. Target is to extend skarn
mineralization 200 m deeper.
According to current drilling information and based on the dip
and mineralization of the skarn, there is a potential connection
with Carlés skarn.
Quality Control
Greenfield drill hole samples were sent to an external
laboratory (ALS Laboratory) for analyses. Infill and brownfield
drill holes samples were analyzed in Orovalle's Laboratory.
Sample preparation was carried out at the El Valle facility. All
diamond core samples have been prepared using the following
procedure, once split:
The core samples are dried at a temperature of 105ºC and then
crushed through a jaw crusher to 70%<6 mm. The coarse-crushed
sample is further reduced to 70%<425 microns using an LM5
bowl-and-puck pulverizer. An Essa rotary splitter is used to take a
450 g to 550 g sub-sample of each split for pulverizing. The
remaining reject portion is bagged and stored. The sample is
reduced by 85% to a nominal -200 mesh using an LM2 bowl-and-puck
pulverizer. 150 g sub-samples are split using a special
vertical-sided scoop to cut channels through the sample which has
been spread into a pancake on a sampling mat. Samples are
then sent to the laboratory for gold and base metal analysis.
Leftover pulp is bagged and stored.
After sample preparation, 30g samples are analyzed for Au by
fire assay with an atomic absorption spectroscopy (AAS) finish and
one-gram samples for Ag, As, Bi, Cu, Hg, Pb, Sb, Se, and Zn by
ICP-optical emission spectroscopy (ICP-OES) after an aqua regia
digestion.
For A208 core samples is used a 1000 g sub-sample of each split
and 250 g sub-samples are split. 50 g samples are twice analyzed.
In case of the twice analysis don´t match, a metalling screening
method is used to confirm the grade.
In case of the samples sent to an external laboratory, 30 g
samples are analyzed for Au by fire assay with an atomic absorption
(Au AA-25) and 35 elements by ICP (ME-ICP41) after an aqua regia
digestion. When Au and Ag values are >100 ppm and Cu and As
values are >10,000 ppm, specific analysis methods are used to
determinate the final grade.
The reported work has been completed using industry standard
procedures, including a quality assurance/quality control ("QA/QC")
program consisting of the insertion of certified reference
material, blanks and duplicates samples into the sample stream.
The exploration update was prepared under the supervision of
Guadalupe Collar Menéndez, a qualified person for the purposes of
NI 43-101 and an employee of Orovalle Minerals S.L., a subsidiary
of Orvana
Financial Performance & FY2025 Guidance:
Q1 FY2025 financial highlights will be released with the first
quarter financials, expected mid-February, 2025.
ABOUT ORVANA – Orvana is a multi-mine gold-copper-silver
company. Orvana's assets consist of the producing El Valle and
Carlés gold-copper-silver mines in northern Spain, the Don Mario gold-silver property in
Bolivia, and the Taguas property
located in Argentina. Additional
information is available at Orvana's website (www.orvana.com).
Cautionary Statements – Forward-Looking
Information
Certain statements in this presentation constitute
forward-looking statements or forward-looking information within
the meaning of applicable securities laws ("forward-looking
statements"). Any statements that express or involve discussions
with respect to predictions, expectations, beliefs, plans,
projections, objectives, assumptions, potentials, future events or
performance (often, but not always, using words or phrases such as
"believes", "expects", "plans", "estimates" or "intends" or stating
that certain actions, events or results "may", "could", "would",
"might", "will", "are projected to" or "confident of" be taken or
achieved) are not statements of historical fact, but are
forward-looking statements.
The forward-looking statements herein relate to, among other
things, Orvana's ability to achieve improvement in free cash flow;
the ability to maintain expected mining rates and expected
throughput rates at El Valle Plant; the potential to extend the
mine life of El Valle and Don Mario beyond their current
life-of-mine estimates including specifically, but not limited to,
Orvana's ability to optimize its assets to deliver shareholder
value; estimates of future production (including without
limitation, production guidance), operating costs and capital
expenditures; mineral resource and reserve estimates; statements
and information regarding future feasibility studies and their
results; future transactions; future metal prices; the ability to
achieve additional growth and geographic diversification; and
future financial performance, including the ability to increase
cash flow and profits; future financing requirements; mine
development plans; the possibility of the conversion of inferred
mineral resources to mineral reserves; and Orovalle's ability to
finalize the definitive Collective Bargain Agreement.
Forward-looking statements are necessarily based upon a
number of estimates and assumptions that, while considered
reasonable by the Company as of the date of such statements, are
inherently subject to significant business, economic and
competitive uncertainties and contingencies, which includes,
without limitation, as particularly set out in the notes
accompanying the Company's most recently filed financial
statements. The estimates and assumptions of the Company contained
or incorporated by reference in this news release, which may prove
to be incorrect, include, but are not limited to the various
assumptions set forth herein and in Orvana's most recently filed
Management's Discussion & Analysis and Annual Information Form
in respect of the Company's most recently completed fiscal year
(the "Company Disclosures") or as otherwise expressly incorporated
herein by reference as well as: there being no significant
disruptions affecting operations, whether due to labour
disruptions, supply disruptions, power disruptions, damage to
equipment or otherwise; permitting, development, operations,
expansion and acquisitions at El Valle, Don Mario and Taguas being
consistent with the Company's current expectations; political
developments in any jurisdiction in which the Company operates
being consistent with its current expectations; certain price
assumptions for gold, copper and silver; prices for key supplies
being approximately consistent with current levels; production and
cost of sales forecasts meeting expectations; the accuracy of the
Company's current mineral reserve and mineral resource estimates;
labour and materials costs increasing on a basis consistent with
Orvana's current expectations; and the availability of necessary
funds to execute the Company's plan. Without limiting the
generality of the foregoing, this news release also contains
certain "forward-looking statements" within the meaning of
applicable securities legislation, including, without limitation,
references to the results of the Company's exploration activities,
including but not limited to, drilling results and analyses,
mineral resource estimation, conceptual mine plan and operations,
internal rate of return, sensitivities, taxes, net present value,
potential recoveries, design parameters, operating costs, capital
costs, production data and economic potential; the timing and costs
for production decisions; permitting timelines and requirements;
exploration and planned exploration programs; and the Company's
general objectives and strategies.
A variety of inherent risks, uncertainties and factors, many
of which are beyond the Company's control, affect the operations,
performance and results of the Company and its business, and could
cause actual events or results to differ materially from estimated
or anticipated events or results expressed or implied by forward
looking statements. Some of these risks, uncertainties and factors
include: the potential impact of global health and global economic
conditions on the Company's business and operations, including: our
ability to continue operations; and our ability to manage
challenges presented by such conditions; the general economic,
political and social impacts of the continuing conflict
between Russia and Ukraine, our ability to support the
sustainability of our business including through the development of
crisis management plans, increasing stock levels for key supplies,
monitoring of guidance from the medical community, and engagement
with local communities and authorities; fluctuations in the price
of gold, silver and copper; the need to recalculate estimates of
resources based on actual production experience; the failure to
achieve production estimates; variations in the grade of ore mined;
variations in the cost of operations; the availability of qualified
personnel; the Company's ability to obtain and maintain all
necessary regulatory approvals and licenses; Orovalle's ability to
complete the permitting process of the El Valle Tailings Storage
Facility increasing the storage capacity; Orovalle's ability to
complete the stabilization project of the legacy open pit wall; the
Company's ability to use cyanide in its mining operations; risks
generally associated with mineral exploration and development,
including the Company's ability to continue to operate the El Valle
and/or ability to resume operations at the Carlés Mine; the
Company's ability to successfully implement an acid leaching
circuit and ancillary facilities to process the current oxides
stockpiles at Don Mario; the Company's ability to successfully
carry out development plans at Taguas; sufficient funding to carry
out exploration and development plans at Taguas and to process the
oxides stockpiles at Don Mario; EMIPA's ability to finalize the OSP
financial model and subsequently complete the required funding for
the OSP; the Company's ability to acquire and develop mineral
properties and to successfully integrate such acquisitions; the
Company's ability to execute on its strategy; the Company's ability
to obtain financing when required on terms that are acceptable to
the Company; challenges to the Company's interests in its property
and mineral rights; current, pending and proposed legislative or
regulatory developments or changes in political, social or economic
conditions in the countries in which the Company operates; general
economic conditions worldwide; the challenges presented by global
health conditions; fluctuating operational costs such as, but not
limited to, power supply costs; current and future environmental
matters; and the risks identified in the Company's disclosures.
This list is not exhaustive of the factors that may affect any of
the Company's forward-looking statements and reference should also
be made to the Company's Disclosures for a description of
additional risk factors.
Any forward-looking statements made herein with respect to
the anticipated development and exploration of the Company's
mineral projects are intended to provide an overview of
management's expectations with respect to certain future activities
of the Company and may not be appropriate for other purposes.
Forward-looking statements are based on management's current plans,
estimates, projections, beliefs and opinions and, except as
required by law, the Company does not undertake any obligation to
update forward-looking statements should assumptions related to
these plans, estimates, projections, beliefs and opinions change.
Readers are cautioned not to put undue reliance on forward-looking
statements. The forward-looking statements made in this information
are intended to provide an overview of management's expectations
with respect to certain future operating activities of the Company
and may not be appropriate for other purposes.
Photo -
https://mma.prnewswire.com/media/2599658/Orvana_Minerals_Corp__ORVANA_PROVIDES_CONSTRUCTION_UPDATE_FOR_DO.jpg
Logo -
https://mma.prnewswire.com/media/2599656/Orvana_Minerals_Corp__ORVANA_PROVIDES_CONSTRUCTION_UPDATE_FOR_DO.jpg
View original
content:https://www.prnewswire.co.uk/news-releases/orvana-provides-construction-update-for-don-mario-bolivia-and-reports-q1-fy2025-production-from-orovalle-spain-302352849.html