Torex Gold Resources Inc. (the “Company” or “Torex”) (TSX: TXG)
provides Q3 2023 update on the development of its Media Luna
Project (“Media Luna”). Unless otherwise stated, progress and
milestones referenced in this press release are as of September 30,
2023.
Jody Kuzenko, President & CEO of Torex,
stated:
“Development of Media Luna continues to track
well to plan, with first concentrate production remaining on track
for late 2024 and commercial production in early 2025. At
quarter-end, the Media Luna Project was 49% complete across
engineering, procurement, underground development/construction, and
surface construction. With 68% of upfront expenditures committed
(including 42% incurred), expenditures to date have tracked
reasonably well to the initial budget of $875 million, noting the
stronger Mexican peso remains a headwind to manage. With $242
million incurred on the project year-to-date, project spending in
2023 is tracking toward the lower end of the annual guided range of
$390 million to $440 million.
“Solid progress was made with respect to
underground development and construction, which included another
notable quarter of advance in the schedule-critical Guajes Tunnel
and mobilization of the underground construction contractor.
Breakthrough of the Guajes Tunnel is expected by year-end, three
months ahead of schedule.
“Significant progress was also made on the
engineering front, which is expected to drive increased procurement
activity through year-end. Surface construction continued with pad
and foundation preparation for several key areas advanced during
the quarter. The pace of construction is set to pick up in Q4 as
concrete works ramp up, larger equipment deliveries to the south
side commence with the completion of the Mazapa bypass road, and
steel erection at the flotation plant begins before year-end.
“The Media Luna Project is now soundly at the
halfway mark and tracking to schedule and budget. With solid
ongoing cash flow from El Limón Guajes and a healthy balance sheet
with strong liquidity, we remain well positioned to execute on the
remainder of the development plan over the next 15 months.”
CAPITAL EXPENDITURES
To date, upfront expenditures have tracked
reasonably well to the initial budget of $874.5 million, noting the
strength of the Mexican peso and general inflationary pressures
have been headwinds to manage. As at quarter-end, $591.2 million of
expenditures had been committed (68%), including $367.0 million
incurred (42%).
Table 1: Media Luna Project – Project
Expenditures (April 1, 2022 through September 30, 2023)
Millions of U.S. dollars |
Project To DateQ3 2023 |
Project expenditures per 2022 Technical Report |
$848.4 |
Adjustment for Q1 2022 underspend |
$26.1 |
Total budgeted spend post March 31, 2022 |
$874.5 |
Expenditures incurred post March 31, 2022 |
($367.0) |
Remaining spend |
$507.5 |
Committed expenditures (inclusive of total project expenditures
incurred to date) |
$591.2 |
Uncommitted expenditures |
$283.3 |
1) Project period commenced on
April 1, 2022; excludes capital expenditures incurred prior to
Board approval on March 31, 2022.2) Project period
is defined as April 1, 2022 through December 31,
2024.3) Excludes borrowing costs capitalized.
During Q3, $98.7 million was invested in the
project, the highest quarterly spend to date. With $242.3 million
invested year-to-date and the level of spending expected to
increase further in Q4 2023, the Company is tracking towards the
low end of the full year guided range of $390 million to $440
million. Quarterly expenditures are expected to remain elevated
through Q3 2024 before declining with the commissioning of the
upgraded processing plant.
To manage the capital expenditure risk related
to a further strengthening of the Mexican peso, the Company has
placed several zero cost collars for a total notional amount of
$103.5 million of peso-related project expenditures. The average
floor price of the collars is 17.38 Mexican pesos per U.S. dollar
and the average ceiling price is 20.0, with the collars covering
the remaining project period (October 2023 and December 2024).
Approximately 40% to 50% of the remaining expenditures are expected
to be denominated in pesos. The initial upfront capital cost of
developing Media Luna assumed a Mexican peso of 20.0, which,
weighted by quarterly expenditures, has averaged 18.4 since the
project commenced on April 1, 2022.
PROJECT COMPLETION
As at quarter-end, development of Media Luna was
tracking to plan, with the project 49% complete, up from 35% at the
end of Q2 2023. Detailed engineering is at the 70% completion mark,
while procurement is 52% complete, with several purchase orders and
contract awards pending at quarter-end. Based on the current
schedule, the tie-in of upgrades to the processing plant are still
on track to occur over a four-week period during the fourth quarter
of 2024, which will allow for commissioning and first concentrate
production in late 2024 and commercial production in early
2025.
Table 2: Media Luna Project – Project Completion
(April 1, 2022 through September 30, 2023)
|
Project To DateQ3 2023 |
Procurement |
52% |
Engineering |
70% |
Underground development/construction |
50% |
Surface construction |
30% |
Total Project |
49% |
Notes to Table1) Physical
progress measured starting as of April 1, 2022; excludes progress
made prior to Board approval on March 31,
2022.2) Project period is defined as April 1, 2022
through December 31, 2024.3) Total Project is
weighted average based on activity levels.
The Company has also added a Media Luna Project
construction update section to its website that includes a gallery
timeline of the project
(https://torexgold.com/assets/projects-media-luna/construction-progress/).
ProcurementDuring the quarter, the Company
executed numerous key purchase orders including the ore/waste pass
grizzlies, press frames and chutes, fabrication of the copper
concentrate building structure, ore bins and associated steel
infrastructure, underground 15 kV electrical cable, as well as
numerous pumps required throughout the processing plant and in the
underground. For the surface plant, several key orders and
contracts were awarded including civil works for the copper
concentrate building, civil works for the 230 kV switchyard, and
site-wide concrete supply and installation contracts. Steel
fabrication packages have been released for both the water
treatment and flotation plant areas in anticipation of beginning to
erect steel for the flotation plant by year-end.
First equipment deliveries of a diesel scoop
truck and a diesel haul truck were made at the end of September.
Delivery of the first electric jumbo is scheduled for December,
with the remainder of the battery electric/diesel fleet expected to
be delivered steadily over the next two years.
EngineeringThe pace of detailed engineering
continued to increase during the third quarter with a focus on
design that supports the advancement of priority construction
activities and purchase orders. Key underground engineering
activities included advancing critical electrical systems design
for procurement, completing critical underground ore and waste
handling infrastructure design for construction, and completion of
the Hazard and Operability Analysis (“HAZOP”) workshops for the
underground facilities. For the surface facilities, the first phase
of flotation area steel, including the pipe rack from grinding and
the water treatment plant, were released for fabrication along with
other process areas being detailed for release to shops. The
balance of the electrical single line diagrams were issued to
finalize equipment requirements. Requests for quotes were sent to
vendors for the remaining surface facilities. HAZOP workshops for
surface facilities were also completed.
Underground Development and ConstructionSteady
progress was made in advancing the Guajes Tunnel and South Portal
Lower. Breakthrough of the Guajes Tunnel on the south side of the
Balsas River is expected in late December, well ahead of the March
2024 breakthrough date assumed in the Technical Report. A majority
of the conveyor table segments are now at site, as are
approximately half of the conveyor belt segments, with the
remainder in transit.
As of the end of September, the Guajes Tunnel
had advanced 5,160 metres and South Portal Lower had advanced 2,325
metres, leaving approximately 970 metres of tunnel advance
remaining until breakthrough.
Figure 1: Breakthrough of Guajes Tunnel expected
in late December (advance rates as at end of September)
Steady progress was also made on ventilation and
in-mine development during the quarter. The second 175 metre
raise has progressed 67% and will be completed in Q4 2023, allowing
for ventilation between the upper and lower parts of the mine. As
of the end of September, there were twenty active headings,
including eleven in Media Luna Lower and nine in Media Luna Upper.
Development in areas of key infrastructure advanced, including
access to the top and bottom of the main ore bins and completion of
the rock breaker #1 and conveyor #3 areas. Vertical development of
the first ore pass also commenced. Some challenges were experienced
with increased water infiltration at the lower section of the
internal ramp which was controlled through established grouting
protocols. Development across all headings continued to advance,
with monthly development rates increasing in the latter half of the
quarter. Overall, ground conditions remain excellent.
Surface ConstructionOn the north side of the
Balsas River, the relocated security structure was completed and
foundation work began in the water treatment plant area. Additional
camp modules to house project staff were also installed. Extension
of the main water management culvert below the area of the new
flotation plant was completed, allowing the final placement of the
remaining civil backfill that extends the flotation area pad.
Relocation of the power distribution and installation of new buried
power conduits around the flotation plant were completed to allow
for the removal of the overhead power lines in Q4 2023. This work
enabled the start of the concrete foundations for the flotation
plant and tower crane to begin.
On the south side of the Balsas River, expansion
of the construction camp pad was completed and additional
two-storey camp modules were placed for occupation in Q4 2023 as
the underground contractor continues to mobilize. Concrete
foundation installation for the backup generator area began and
will be completed in Q4 2023, allowing work to start on the paste
plant foundations. The mine pipeline access drift, specifically for
the paste and return water lines into the mine, was completed. Work
continued on both the Mazapa – San Miguel bypass road and the
Mazapa bridge, with the first concrete headwall completed. This
will be completed in Q4 2023 to accept deliveries of larger
equipment related to both the paste plant and the underground
construction. Both the sedimentation pond and decant
pond dams are nearing completion, with construction of the concrete
spillway started on the sedimentation dam.
Operational ReadinessIn parallel with
development and construction activities, the surface and
underground operational readiness strategy is progressing to plan.
Operational readiness teams are accountable for ensuring that
processes and systems for all new work areas are established and
ready in advance of the handover from the project team to
operations. This includes workforce transition planning and
training, developing the operating strategy (including all standard
operating procedures), maintenance plans for all fixed and mobile
equipment, blend and feed strategies, detailed commissioning plans,
first fills, concentrate shipment logistics, and all other
requirements to ensure a smooth ramp-up to commercial production in
Q1 2025.
PROJECT EXECUTION PLAN
Based on progress made during Q3 2023 and a
detailed review of both the surface and underground schedules
completed late in the quarter, the overall project end dates are
unchanged compared to the prior plan outlined within the inaugural
Media Luna update press release published on February 9, 2023, with
some movement within the plan as set out below.
Figure 2: Project execution plan for the Media
Luna Project
Initiatives to expedite the delivery of the
paste plant filter presses are progressing and the delivery
schedule has been maintained with further initiatives under review.
The Company is also working to expedite the underground electrical
equipment to reduce schedule risk given delivery times for this
equipment are some of the longest for the project. As noted in the
previous Media Luna update, plans for the early installation of the
FeS flotation circuit and water treatment plant have been adjusted.
Given the Company’s success with reducing cyanide consumption
levels over the past several quarters, the business benefits of a
single schedule for construction and commissioning the FeS circuit
and water treatment plant at the same time as the Cu flotation
circuit outweighed the benefits to landing the FeS circuit
early.
In terms of underground development, schedule
gains have been made since the last update as we are now
forecasting the Guajes Tunnel breakthrough in late December.
Consequently, first development ore and first stope have been
rescheduled to facilitate haulage directly through the Guajes
Tunnel to avoid stockpiling and rehandling from the south side.
Given tunnelling is ahead of schedule, installing anchors for the
conveyor tables was rescheduled to post-breakthrough to avoid any
coordination issues with the tunneling and anchoring crews. The
revised execution plan will not impact the installation and
commissioning of the Guajes Tunnel conveyor, which remains on track
for completion in August 2024.
The current project plan relative to the
Technical Report reflects the Company’s estimates for the
completion of key project deliverables. These updated deliverables
have not impacted the overall project schedule given the original
plan had assumed the potential for schedule adjustments and the
possibility for supply chain disruptions.
More detail on the Media Luna Project, including
the feasibility study results, can be found in the Company’s most
recent Technical Report dated effective March 16, 2022, filed on
March 31, 2022 (“Technical Report”).
ABOUT TOREX GOLD RESOURCES
INC.
Torex is an intermediate gold producer based in
Canada, engaged in the exploration, development, and operation of
its 100% owned Morelos Property, an area of 29,000 hectares in the
highly prospective Guerrero Gold Belt located 180 kilometres
southwest of Mexico City. The Company’s principal asset is the
Morelos Complex, which includes the El Limón Guajes (“ELG”) Mine
Complex, the Media Luna Project, a processing plant and related
infrastructure. Commercial production from the Morelos Complex
commenced on April 1, 2016, and an updated Technical Report for the
Morelos Complex was released in March 2022. Torex’s key strategic
objectives are to optimize and extend production from the ELG Mine
Complex, de-risk and advance Media Luna to commercial production,
build on ESG excellence, and to grow through ongoing exploration
across the entire Morelos Property.
FOR FURTHER INFORMATION, PLEASE
CONTACT:
TOREX GOLD RESOURCES INC. |
Jody
Kuzenko |
Dan
Rollins |
President and CEO |
Senior Vice President, Corporate Development & Investor
Relations |
Direct: (647) 725-9982 |
Direct: (647) 260-1503 |
jody.kuzenko@torexgold.com |
dan.rollins@torexgold.com |
QUALIFIED PERSONThe technical
and scientific information in this press release has been reviewed
and approved by Dave Stefanuto, P. Eng, Executive Vice President,
Technical Services and Capital Projects of the Company, and a
qualified person under National Instrument 43-101.
CAUTIONARY NOTES ON FORWARD LOOKING
STATEMENTSThis press release contains “forward-looking
statements” and “forward-looking information” within the meaning of
applicable Canadian securities legislation. Forward-looking
information includes, but is not limited to, statements that: the
Guajes Tunnel breakthrough is expected by year-end; with $242
million incurred on the project year-to-date, project spending is
tracking toward the lower end of the annual guided range of $390
million to $440 million; progress was also made on the engineering
front, which is expected to drive increased procurement activity
through year-end; the pace of construction is set to pick up in Q4
as concrete works ramp up, larger equipment deliveries to the south
side commence with the completion of the Mazapa bypass road, and
steel erection at the flotation plant begins before year-end; the
Media Luna Project is now soundly at the halfway mark and tracking
to schedule and budget; with solid ongoing cash flow from El Limón
Guajes and a healthy balance sheet with strong liquidity, the
Company remains well positioned to execute on the remainder of the
development plan over the next 15 months; quarterly expenditures
are expected to remain elevated through Q3 2024 before declining
with the commissioning of the upgraded processing plant;
approximately 40% to 50% of the remaining expenditures are expected
to be denominated in pesos; based on the current schedule, the
tie-in of upgrades to the processing plant are still on track to
occur over a four-week period during the fourth quarter of 2024,
which will allow for commissioning and first concentrate production
in late 2024 and commercial production in early 2025; the remainder
of the battery electric/diesel fleet expected to be delivered
steadily over the next two years; the surface and underground
operational readiness strategy is progressing to plan including the
workforce transition planning and training, developing the
operating strategy (including all standard operating procedures),
maintenance plans for all fixed and mobile equipment, blend and
feed strategies, detailed commissioning plans, first fills,
concentrate shipment logistics, and all other requirements to
ensure a smooth ramp-up to commercial production in Q1 2025; the
project execution plan for the Media Luna Project; the revised
execution plan will not impact the installation and commissioning
of the Guajes Tunnel conveyor, which remains on track for August
2024; the current project plan relative to the Technical Report
reflects the Company’s estimates for the completion of key project
deliverables; these updated deliverables have not impacted the
overall project schedule given the original plan had assumed the
potential for schedule adjustments and the possibility for supply
chain disruptions; and the Company’s key strategic objectives are
to optimize and extend production from the ELG Mine Complex,
de-risk and advance Media Luna to commercial production, build on
ESG excellence, and to grow through ongoing exploration across the
entire Morelos Property. Generally, forward-looking information can
be identified by the use of forward-looking terminology such as
“expect”, “plan”, “strategy”, “schedule”, “anticipate”, “guide”,
“continue”, “forecast”, or variations of such words and phrases or
statements that certain actions, events or results “will” occur or
are “on track” to occur. Forward-looking information is subject to
known and unknown risks, uncertainties and other factors that may
cause the actual results, level of activity, performance or
achievements of the Company to be materially different from those
expressed or implied by such forward-looking information,
including, without limitation, risks and uncertainties identified
in the technical report (“Technical Report”) titled ELG Mine
Complex Life of Mine Plan and Media Luna Feasibility Study, with an
effective date of March 16, 2022, and a filing date of March 31,
2022 and in the Company’s annual information form (“AIF”) and
management’s discussion and analysis (“MD&A”) or other unknown
but potentially significant impacts. Forward-looking information is
based on the reasonable assumptions, estimates, analyses and
opinions of management made in light of its experience and
perception of trends, current conditions and expected developments
as set out in the Technical Report, AIF and MD&A, and other
factors that management believes are relevant and reasonable in the
circumstances at the date such statements are made. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
the forward-looking information, there may be other factors that
cause results not to be as anticipated. There can be no assurance
that such information will prove to be accurate, as actual results
and future events could differ materially from those anticipated in
such information. Accordingly, readers should not place undue
reliance on forward-looking information. The Company does not
undertake to update any forward-looking information, whether as a
result of new information or future events or otherwise, except as
may be required by applicable securities laws.
Photos accompanying this announcement are available
athttps://www.globenewswire.com/NewsRoom/AttachmentNg/70614923-6580-45b5-9a25-df1f74386b36https://www.globenewswire.com/NewsRoom/AttachmentNg/9f41e842-b587-48d2-b011-6711c688caee
Torex Gold Resources (TSX:TXG)
Historical Stock Chart
From Nov 2024 to Dec 2024
Torex Gold Resources (TSX:TXG)
Historical Stock Chart
From Dec 2023 to Dec 2024