Armadale, the AIM quoted investment
company focused on natural resource projects, provides an update on
work at the Canyon Silver project and on the Mahenge Graphite
Project.
Canyon Silver Project
The Company has made significant
progress in opening up the historic workings at Canyon Silver
project for further evaluation and sampling. However, overall
progress has been slower than planned as the ground conditions have
been more difficult than expected. Further sampling will be carried
out after the reopening is complete, allowing the Company to access
the potential of the project. As announced on 18 June 2024, initial
assay results at the project produced high grade mineralisation of
up to 1010 g/t silver and 18% lead.
The work carried out at the project
since re-commencing work includes:
Ø Widening
of the first 100 feet of the Canyon Silver No 2 Tunnel from 4 x 5
feet to 8 x 8 feet to allow passage of essential equipment. This
tunnel was driven by hand in 1892 to intersect the Formosa Vein
that outcropped c. 100 feet above it. This widening included some
timbering and a large amount of barring down and rock-bolting to
make it safe and usable for all activities. A Slusher station,
Geophysical station, Diamond Drilling pad and small trackless
operation can now be safely and effectively performed
here.
Ø Recommissioning of the 1905 winze in the number 2 tunnel. All
new timbering and steel ladders have been installed. This winze
bottom was cleaned by hand of 35 feet of accumulated rock and
debris that had built up since 1930. The winze is now completely
equipped, safe and fully useable. allowing safe passage down into
the No 3 Level 'parallel portal tunnel'. As the winze was sunk on
the Formosa vein, that vein is in full accessible view all the way
down the 100 ft between No 2 and 3 Levels.
Ø Outside
the No 3 Portal, the original Change Room building and Compressor
and Generator Room have been completely rebuilt. However,
electrical and plumbing will only be installed when continuous
year-round operations are in progress.
Ø The
Original CSM 'outside' main haulage and entry road has now been
re-established, being fully rebuilt and graded from No 3 Portal
down to the base of the property, when the required permit is
approved a 30 ton bridge will be placed to allow for a complete
circular '1 way always' route to and from the mine.
Ø The new
'No 1 Portal and above' "road" is proceeding rapidly. This
had to be cut into virgin, difficult, steep
mountainside.
Mahenge Graphite Project
The Company is closely monitoring the
progress of graphite companies in Tanzania and is encouraged by the
increased recent progress towards achieving project development
funding in the country. Funding for mine development has been
difficult over the last several years across the junior mining
sector and the company is actively looking for ways to maximise the
value of the project.
Competent Person statement
The information in this announcement
that relates to exploration results is based on information
compiled by Mr Matt Bull, a competent person, who is a Member of
the Australian Institute of Geoscientists. Mr Bull has sufficient
experience which is relevant to the style of mineralisation and
type of deposit under consideration and to the activity which he is
undertaking to qualify as a competent person as defined in the 2012
Edition of the "Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves". Mr Bull consents to
the inclusion in the report of the matters based on his information
in the form and context in which it appears.
Enquiries:
|
|
Armadale Capital Plc
Matt Bull, Executive
Director
Greg Entwistle Non-Executive
Director
Tim Jones, Company
Secretary
|
+44 (0) 20 7236 1177
|
|
|
Nomad and Broker: Cavendish Capital Markets
Ltd
Neil McDonald / Seamus
Fricker
|
+44 (0) 20 7220 0500
|