RNS Number : 7092F
Ferro-Alloy Resources Limited
26 September 2024
 

26 September 2024

Ferro-Alloy Resources Limited

("Ferro-Alloy" or "the Company" or "the Group")

 

Interim Results for the six months ended 30 June 2024

and

Carbon concentrate and feasibility study update

 

Ferro-Alloy Resources Limited (LSE:FAR), the vanadium producer and developer of the large Balasausqandiq vanadium deposit in Southern Kazakhstan, announces its unaudited interim results for the six months ended 30 June 2024 and provides an update on the results from the testing completed on its carbon concentrate and the Balasausqandiq feasibility study.

Overview

Carbon Concentrate

·    Results from the testing of the Company's carbon concentrate to be produced from the tailings of the Balasausqandiq ore have confirmed the suitability of the concentrate for use in tyre rubber manufacture and other carbon black based rubber applications.

·    The testing has shown that the carbon concentrate can be successfully used as a partial substitute for conventional carbon black filler in a passenger car tyre sidewall compound formulation.

·    A marketing report quantifying the value proposition of the concentrate is being finalised.

Feasibility Study

·    Feasibility study for Phase 1 is ongoing:

Current focus of the study is on the optimisation of the planned tailings storage facility. Site selection is in progress and preliminary capital estimates have been completed on a staged construction basis to refine initial capital spend.

Design capacity of the of the Phase 1 process plant has been increased to 1.65m tonnes throughput per year and the comminution circuit design work has been completed.

Reagent optimisation programme commenced to quantify improvements to the project's expected operational expenditure.

In order to accommodate the increased design capacity of the Phase 1 process plant and the reagent optimisation programme, the Company now expects the feasibility study to be published during Q2 2025.  

 

Operations

·    The Plant operated well during the period. Production in H1 2024 was slightly lower than H1 2023 due to lower overall grades of vanadium and molybdenum contained within the catalysts processed.

·    Commissioned two new drying ovens which allow the conversion of ammonium metavanadate by disassociation into vanadium pentoxide which commands better pricing. The Company is evaluating plans to acquire the equipment to produce vanadium pentoxide flake to access a larger market.

·    Test processing of the nickel-rich residues held at the plant site on a commercial scale did not sufficiently replicate the results achieved in the laboratory and consequently the plant will revert to processing bought-in catalysts during Q4 2024. This decision is partly driven by low metal prices. The Plant may resume treating the residues if metal product prices recover.

·    Research and development are ongoing to determine the suitability of the nickel-rich residues for the production of ferro-nickel.

Financial

·    Total revenues of US$2.1m for the period (H1 2023: US$3.3m) reflect the significant decrease in the price of vanadium pentoxide between the two reporting periods.

·    Overall loss for the period of US$3.99m (H1 2023: loss of US$1.53m).

·    Cash balance of US$2.5m at the period end and US$1.1m as at 20 September 2024.

Corporate

·    During the period, the Company listed and sold a third tranche of bonds with a nominal value of US$5m under the terms of the Kazakhstan Bond Programme on the AIX.

Nick Bridgen, CEO of Ferro-Alloy Resources said:

"The success of the carbon test work programme has confirmed the tremendous value of this product in the manufacture of tyres and in the rubber industry generally. This will be factored into the feasibility study which will also include the increased throughput and reagent optimisation programme.

The current vanadium price is exceptionally low, principally caused by the slow-down of construction in China. This is affecting current results, but the long-term forecasts continue to show a deficit of world production as vanadium redox flow batteries ramp up and China recovers. Historically, when a deficit arises, the price moves up strongly."

ENDS

 

For further information, visit www.ferro-alloy.com or contact:

 

Ferro-Alloy Resources Limited

Nick Bridgen (CEO) / William Callewaert (CFO)

info@ferro-alloy.com

 

Shore Capital 

(Joint Corporate Broker)

 

Panmure Liberum Limited

(Joint Corporate Broker)

Toby Gibbs/Lucy Bowden

 

 

Scott Mathieson/John More

 

+44 207 408 4090

 

 

+44 20 3100 2000

 

St Brides Partners Limited

(Financial PR & IR Adviser)

Ana Ribeiro / Charlotte Page

+44 207 236 1177

 

About Ferro-Alloy Resources Limited:

The Company's operations are all located at the Balasausqandiq deposit in Kyzylordinskoye Oblast in the South of Kazakhstan. Currently the Company has two main business activities:

a) the high grade Balasausqandiq vanadium project (the "Project"); and

b) an existing vanadium concentrate processing operation (the "Existing Operation")    

Balasausqandiq is a very large deposit, with vanadium as the principal product together with several by-products. Owing to the nature of the ore, the capital and operating costs of development are very much lower than for other vanadium projects.    

The most recent mineral resource estimate for ore-body one (of seven) provided an Indicated Mineral Resource of 32.9 million tonnes at a mean grade of 0.62% V2O5 equating to 203,364 contained tonnes of vanadium pentoxide ("V2O5"). In the system of reserve estimation used in Kazakhstan the reserves are estimated to be over 70m tonnes in ore-bodies 1 to 5 but this does not include the full depth of ore-bodies 2 to 5 or the remaining ore-bodies which remain substantially unexplored.  

The Project will be developed in two phases, Phase 1 and Phase 2, with Phase 1 treating 1.65m tonnes per year.

There is an existing concentrate processing operation at the site of the Balasausqandiq deposit. The production facilities were originally created from a 15,000 tonnes per year pilot plant which was then expanded and adapted to recover vanadium, molybdenum and nickel from purchased concentrates. 

The existing operation is located on the same site and uses some of the same infrastructure as the Project, but is a separate operation which will continue in parallel with the development and operation of the Project.

Interim Management Report

The Company is engaged primarily in carrying out a feasibility study into the giant Balasausqandiq vanadium project which is now entering the final stages.

Concurrently, the Company continues to operate a small-scale process plant to produce vanadium, molybdenum and nickel from purchased concentrates.

 

Balasausqandiq feasibility study

Carbon black substitute concentrate

The Company's specialist rubber consultants in the UK have completed testing on the carbon black substitute concentrate and the results have confirmed the suitability of the concentrate for use in tyre rubber manufacture and other carbon black based rubber applications.

The testing undertaken has shown that the carbon concentrate to be produced by the Company from the Balasausqandiq ore tailings can be successfully used as a partial substitute for conventional carbon black filler in a passenger car tyre sidewall compound formulation. The results show that with a substitution of up to 10% it was possible to produce compounds with similar physical properties to that made with a control formulation using 100% N660 carbon black, the most commonly used grade of carbon black for tyre sidewalls. Tyres made with this blended material would, therefore, be expected to deliver similar performance. 

Whilst the data did show that the carbon concentrate, when substituted at levels greater than 10%, produced slightly less of a reinforcing effect in the rubber compound than conventional carbon black, some potential advantages in physical properties were identified which could lead to improvements in tyre rolling resistance and sidewall damage resistance.

Specialist marketing consultants are finalising their report which will advise on marketing and the appropriate pricing of the Company's material.

Processing

The feasibility study has progressed with a primary focus on the optimisation of the tailings storage facility by SRK Consulting (Kazakhstan) Limited. Site selection has continued and a final geophysical survey is underway. Preliminary capital estimates have been completed with a focus on staging the construction of the facility to optimise the initial capital spend.

As soon as the final carbon concentrate and vanadium market reports have been received, SRK will commence the mine planning study.

As communicated last year, the 2023 ore reserve that was estimated for Ore-Body 1 of the Balasausqandiq deposit was 35.4% larger than previously estimated, which lead to a review of the appropriate size of the Phase 1 development plan. The Company has now applied to the Ministry of Industry and Construction of the Republic of Kazakhstan for an amendment to the Company's Subsoil Use Agreement which will have the effect of increasing the annual tonnage to be mined during the life of Phase 1 of the project to 1.65 million tonnes per year (including mining dilution) and to defer certain amounts to be mined prior to and during commissioning. Ongoing discussions with a Working Committee of the Ministry have required re-submission of certain documents relating to environmental provisions, future site restoration plans and industrial safety, prior to approval.

In anticipation of approval, the Company has increased the design capacity of Phase 1 of the process plant to 1.65 million tonnes throughput per year. The upgraded design is being progressed by Tetra Tech Limited and the comminution circuit aspects of the design have been completed.

Concurrently, the Company has engaged SGS Canada Inc to conduct a reagent optimisation programme to identify potential improvements to the metallurgical regimes identified in the previously completed metallurgical programme to take account of current reagent prices and delivery costs.

In addition to these items, the main components of the study currently underway include the ecological study, estimate of capital costs and financial evaluation.

In order to accommodate the increased design capacity of the Phase 1 process plant and the reagent optimisation programme, the Company now expects the feasibility study to be published during Q2 2025.  

 

Operations review

The existing operation

The Company's existing process plant operated well during the period. However, production was slightly lower than the same period in 2023 due to lower overall grades of vanadium and molybdenum contained within the concentrates processed. 

During the period, two new drying ovens were commissioned which allow the Company to convert a proportion of its production into vanadium pentoxide by disassociation of ammonium metavanadate ("AMV"). Currently, the vanadium pentoxide produced by the plant is in the form of powder but the Company plans to acquire equipment for the production of vanadium pentoxide flakes, opening up a larger and slightly higher priced market. The Company has also started to expand the wet-tailings pond to increase pond capacity by almost 50%, potentially allowing an increase in secondary vanadium and molybdenum production from the solutions held in the pond as well as improving product purity.

The Company has previously sold the residues from the treatment of catalysts as a low grade nickel concentrate but, owing to low nickel prices and high transport costs, the Company has chosen to stockpile this material while a process for its further treatment could be developed by the Company's technical department. This process has since been developed allowing a significant amount of the remaining vanadium and molybdenum to be extracted from the residues, raising the overall extraction of these metals from catalysts to very high levels, as well as enriching the nickel content in the remaining residues so that they can be more cost-effectively transported and achieve a higher price. Following good laboratory test results, test processing at a commercial scale during Q3 2024 did not sufficiently replicate the results achieved in the laboratory and consequently the plant will revert to processing bought-in catalysts during Q4 2024. In the event that global metal prices recover to levels that would make the commercial processing of the nickel residues profitable the plant may resume treating the residues either instead of or concurrently with bought-in catalysts.

Research and development work by our technical department is ongoing to determine whether the Company can process the upgraded nickel concentrates to produce ferro-nickel.

Research and development

The Company is participating in three grant-funded research and development projects in Kazakhstan after competitively tendering projects for awards for the most promising opportunities for commercialisation of scientific and scientific-technical activities.

As previously announced, one project is aimed at producing and commercialising mixed vanadium oxides suitable for the production of electrolyte for vanadium redox flow batteries. This project is in conjunction with the Satbayev University in Almaty, Kazakhstan where the electrolytes are produced from Company oxides and tested in a vanadium redox flow battery, following which the agreed plan is for the commercial sale of three tonnes of mixed oxides. The Company plans to position itself to be able to continue supplying into this market on a fully commercial basis according to demand.

A second project is in association with the Kazakhstan National Engineering Academy to build a pilot-scale plant at the existing plant site, in advance of the construction of the mine, to produce a carbon concentrate direct from the Balasausqandiq ore, rather than from the tailings as noted above, and to develop commercial applications.

A third project is working with the Satbayev University on an improved analytical-chemical process in the treatment of ore.

The Company also cooperates with the Satbayev University to offer work experience to promising students, with opportunities for continuing work with the Company.  Not only does this enrich the student experience at the Satbayev University but it also gives the Company a pathway to finding high-quality recruits.

 

Production

During the period the plant processed 19.4% more tonnes of catalyst compared to the prior year. However, as noted above, the overall metal grades of the catalysts treated were less than those during 2023 resulting in 2% and 32% less vanadium and molybdenum production, respectively. The plant produced 11.7 tonnes more nickel during the period in comparison to 2023, representing a 19.3% increase.  

 


2024

2023

2024

2023

2024

2023

Quarter

Tonnes of vanadium pentoxide*

Tonnes of vanadium pentoxide*

Tonnes of molybdenum**

Tonnes of molybdenum**

Tonnes of nickel***

Tonnes of nickel***

Q1

81.6

31.3

7.1

6.5

33.4

9.7

Q2

87.6

141.4

6.9

14.1

38.8

50.8

H1

169.2

172.7

14.0

20.6

72.2

60.5

 

* partly contained in AMV

** contained in ferro-molybdenum

*** contained in nickel concentrate

 

Outlook

Current vanadium prices, as detailed below, are exceptionally low and at a level where it is difficult to forecast overall Group profitability notwithstanding the successful operation of the current process plant and the developments that are being achieved in new processes and improved operations. Nevertheless, the plant is capable of generating a significant contribution to the Group's current overheads which would be incurred as it completes the feasibility study in any case. 

Recent monthly average prices of vanadium pentoxide have been in the bottom 4% of such monthly averages, adjusted for inflation, over the last 24 years. Vanadium prices have been impacted by the slow-down in Chinese construction and the sale of Russian product into China at discounted prices. These conditions are not expected to change in the short term but, in the longer term, they must do so to prevent large company closures and reductions in capacity. Significant tonnages are going to be required for planned large-scale vanadium redox flow batteries, most notably in China, and recently announced changes to Chinese re-bar standards will potentially also act to boost demand. Historically, the vanadium price has been volatile and shortages rapidly translate into rising prices, sometimes to extremely high levels.

Meanwhile, the process plant operations are now running smoothly, and the new equipment, products and increased pond and drying capacity will put the Company in a good position to capitalise on rising prices.

 

Corporate

During the period, the Company listed and sold a third tranche of bonds with a nominal value of US$5m under the terms of the Kazakhstan Bond Programme on the AIX.

 

Product prices in the period

Vanadium Pentoxide

At the start of 2024, the price of vanadium pentoxide was around US5.75/lb, after which the price fluctuated within a band of US$5.00/lb to US$6.00/lb for the entirety of the reporting period under consideration. As at 20 September 2024, the price of vanadium pentoxide was US$5.00/lb.

Ferro-Molybdenum

At the start of 2024, the price of ferro-molybdenum was around US$48/kg, after which it remained at a similar level until the end of April. From May onwards the price fluctuated within a band of US$51/kg to US$55/kg until the end of the reporting period. As at 20 September 2024, the price of ferro-molybdenum was US$50/kg.

 

Earnings and cash flow

The Group generated total revenues of US$2.1m for the period compared to US$3.3m for the first six months of 2023, representing a reduction in overall revenue of US$1.2m. The reduction in revenue reflects the significant decrease in the price of vanadium pentoxide between the two reporting periods (the average price of vanadium pentoxide during the first six months of 2023 was US$9.06/lb in comparison to US$5.58/lb in 2024). Additionally, the Group has undertaken a number of tolling contracts during the period instead of processing its own bought-in concentrates.

The cost of sales for the period under review was US$3.6m in line, given the volumes and nature of concentrates processed, with the first six months of 2023 (2023: US$3.6m).

Administrative expenses for the period were US$1.8m (2023: US$1.3m) representing an increase of US$0.5m mainly attributable to broker commission for the issue of the third tranche of bonds noted above and increased salary costs.

The Group made a loss before and after tax of US$3.99m (2023: loss of US$1.53m).

Net cash outflows used in operating activities were US$2.6m (2023: cash outflow of US$1.0m). Net cash used in investing activities during the period was US$1.1m (2023: cash outflow of US$2.3m). Net cash inflow from financing activities was US$4.5m (2023: cash outflow of US$1.1m) representing the proceeds received from the sale of the third tranche of bonds.

 

Balance sheet review

At the period end, non-current assets totalled US$14.1m (2023: US$11.9m) reflecting the continued capitalisation of expenses incurred by the Group on the development of the Balasausqandiq feasibility study (as an exploration and evaluation asset).

Current assets, excluding cash balances, totalled US$5.1m at the period end compared to US$5.0m for the prior period.

The Group held an aggregate cash balance of US$2.5m at the period end (2023: US$0.6m) and US$1.1m as at 20 September 2024. The board of directors is currently considering the options available to the Group to increase cash levels to ensure the completion of the feasibility study and the support of the ongoing processing operations. An option available to the board would be the issue and sale of a further trance of bonds under the Kazakhstan Bond Programme. 

The Group held non-current liabilities of US$12.4m at the period end (2023: US$ nil) representing the value of the Company's bonds sold since the inception of the Kazakhstan Bond Programme.

Current liabilities at the period end were US$3.9m (2023: US$3.0m) comprising of trade payables and accrued bond interest. 

 

Environmental, social and governance

Both the existing operation and the planned process plant for Balasausqandiq will have a strongly positive environmental impact. The vanadium from production will benefit energy storage in both vanadium redox flow batteries, the front-running technology for fixed ground long-term energy storage, but also potentially in certain technologies for mobile batteries used in electric vehicles.

The CO2 emissions created by our production at Balasausqandiq are expected to be a fraction of most other producers which generally require concentration and high-temperature roasting to liberate the vanadium. The carbon concentrate which we plan to market as a replacement for carbon black is produced without burning hydrocarbons, as is the usual production process.

 

 

Description of principal risks, uncertainties and how they are managed

(a)   Current processing operations

Current processing operations make up a small part of the Company's expected future value but are intended to provide useful cash flows in the near term and allow the Group to gain valuable experience of the vanadium industry. The principal risks of this operation are the prices of its products (vanadium, molybdenum and nickel), availability of vanadium-bearing concentrates and the efficiency of recovery of products from those concentrates.

The Group is constantly reviewing the market opportunities for supplies of vanadium-bearing concentrates from reliable suppliers that can deliver concentrates on a timely basis in order to ensure that the Group does not incur production shortfalls leading to reduced revenues. The Group aims to extract all the useful components of the raw materials so that ultimately no residues remain on site and so that the maximum value is obtained from each tonne treated.  By these means, we aim to be one of the most efficient and lowest cost secondary vanadium treatment plants so that our competitive position reduces the danger of high prices for raw materials making the operation uneconomic.

 

(b)   Balasausqandiq project

The Balasausqandiq project will be a much larger contributor to the Company's value than the current processing operations and is primarily dependent on long-term vanadium prices.

The project is also dependent on raising finance to meet projected capital costs (see below) and the successful construction and commissioning of the project's proposed mine processing facilities. It is not unusual for new mining projects to experience unforeseen problems, incur unexpected costs and be exposed to delays during construction, commissioning, and initial production, all of which could have a material adverse effect on the Company's operations and financial position. The Company has taken steps to mitigate such potential adverse effects by engaging globally recognised engineers and consultants to assist with the development and design of the key elements of the project in addition to the Group's own highly qualified workforce.  

 

(c)    Geopolitical situation

The ongoing invasion of Ukraine by Russia is not directly impacting the Group's operations although current low vanadium pentoxide prices are, in part, likely being driven by Russian producers selling at significant discounts to China. The continued main risk of the conflict is to the Group's import and export transport routes, many of which involve transit through Russia. Whilst these are currently operating without issue, sanctions have been made against Russian and Belarusian vehicles transiting through Europe (but not against vehicles registered in other jurisdictions in the region such as Kazakhstan). There is a risk that further sanctions might prevent transit through Russia. The Company continues to review alternative transit routes for raw material imports and product exports through the West of Kazakhstan, either via the Caspian Sea or overland south of the Caspian Sea.  Routes to China are working normally.

With respect to the global sanctions imposed on certain Russian entities and individuals, the Group monitors the implications of those sanctions on the Group's trading activities on an ongoing basis.

 

(d)   Financing risk

The Balasausqandiq project will require substantial funds to be raised in debt and equity which will be dependent upon market conditions at the time and the successful completion of the Phase 1 feasibility study.

In March of 2021 the Company signed an investment agreement with Vision Blue Resources Limited ("Vision Blue"). Under the terms of this agreement and in addition to Vision Blue's participation in the 2022 equity fundraise, investments totalling US$14.3m have already been made and Vision Blue has the right to subscribe a further US$2.5m at the original deal price of 9 pence per share at any time up to two months after the announcement of the Phase 1 feasibility study. Vision Blue also has further options to subscribe up to US$30m at higher prices to partially finance the construction of the project.

The favourable financial and other characteristics of the project determined by studies so far completed give the Directors confidence that the outcome of the Phase 1 feasibility study will be successful. Initial discussions with potential providers of debt finance have been encouraging.

 

(e)   Climate change risk

The Group has not identified any particular climate change related scenarios that would likely have a significant impact on the Balasausqandiq project or the existing operation. The existing operation already functions in an environment that is subject to extreme weather conditions and is, therefore, considered to have a strong resilience to existing and future climate-related scenarios.

 

(f)    Risks associated with the developing nature of the Kazakh economy

According to the World Bank, Kazakhstan has transitioned from lower-middle-income to upper-middle-income status in less than two decades. Kazakhstan's regulatory environment has similarly developed and the Company believes that the period of rapid change and high risk is coming to an end.  Nevertheless, the economic and social regulatory environment continues to develop and there remain some areas where regulatory risk is greater than in developed economies.

 

(g)   Commodity price risk:

As already noted above, the success of the Company is dependent upon the long-term prices of the products to be produced by the planned mine processing facilities. As a result of there being no formally established trading markets for the Company's principal products from the project, there is a risk that price fluctuations and volatility for these products may have an adverse impact on the Company's future financial performance.

 

 

Directors' Responsibility Statement

 

We confirm that to the best of our knowledge:

a.    the condensed set of unaudited financial statements which have been prepared in accordance with IAS 34 'Interim Financial Reporting' give a true and fair view of the assets, liabilities, financial position and profit or loss of the Company and its undertakings included in the consolidation as a whole, as required by DTR 4.2.4R;

b.    the interim management report includes a fair review of the information required by DTR 4.2.7R; and

c.     the interim management report includes a fair review of the information required by DTR 4.2.8R.

 

This interim financial report for the six months ended 30 June 2024 has been approved by the Board and signed on its behalf by:

 

 

 

William Callewaert

Director

25 September 2024



 

Ferro-Alloy Resources Limited

Condensed unaudited Statement of Profit or Loss and Other Comprehensive Income
for the six months ended 30 June 2024

       

Note

Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited   six-month period ended 30 June 2023 $000

 

Audited year
ended
31 December 2023
$000

 

Revenue from customers (pricing at shipment)

2

2,170


3,410


6,164

 

     Other revenue (adjustments to price after delivery and fair value changes)

2

(21)


(96)


(448)

 

Total revenue

2

2,149


3,314


5,716

 

Cost of sales

3

(3,622)


(3,565)


(6,769)

 

Gross (loss) / income


(1,473)

 

(251)

 

(1,053)


Other income

4

7


13


20

 

Administrative expenses

5

(1,850)


(1,337)


(3,371)

 

Distribution expenses


(58)


(66)


(193)

 

Other expenses

6

(24)


(47)


(471)

 

Loss from operating activities


(3,398)

 

(1,688)

 

(5,068)

 

Net finance (cost) / income

8

(593)


158


(183)

 

Loss before income tax


(3,991)

 

(1,530)

 

(5,251)

 

 

Income tax


-

 

-

 

-

 

Loss for the period


(3,991)

 

(1,530)

 

(5,251)

 

 


 

 

 

 

 

 

Other comprehensive (loss) / income

Items that may be reclassified subsequently to profit or loss

 

 

 

 

 

 

Exchange differences arising on translation of foreign operations


(761)

 

496

 

39

 

Total comprehensive loss for the period


(4,752)

 

(1,034)

 

(5,212)

 

Loss per share (basic and diluted)

16

(0.008)

 

(0.003)

 

(0.012)

 

 

These condensed unaudited financial statements were approved by the directors on 25 September 2024 and signed by:

_____________________________ 

William Callewaert

Director

 



 

 

Ferro-Alloy Resources Limited

Condensed unaudited Statement of Financial Position
for the six months ended 30 June 2024


 

 

 

 

 

 

 

 

 


Note

 

Unaudited
3
0 June 2024
$000

 

Unaudited
3
0 June 2023
$000

 

 

 

Audited 31 December 2023
$000

ASSETS


 

 

 

 

 

 

 

 

Non-current assets










Property, plant and equipment

9


5,404


6,072




5,951

Exploration and evaluation assets

10


7,836


5,581




7,145

Intangible assets

11


20


20




20

Prepayments

14


853


185




888

Total non-current assets


 

14,113

 

11,858

 

 

 

14,004

 










Current assets










Inventories

12


1,800


2,015




1,983

Trade and other receivables

13


2,152


1,892




1,316

Prepayments

14


1,166


1,115




762

Cash and cash equivalents

15


2,528


606




1,952

Total current assets


 

7,646

 

5,628

 

 

 

6,013

Total assets


 

21,759

 

17,486

 

 

 

20,017

 










EQUITY AND LIABILITIES










Equity










Share capital



55,027


50,827




55,027

Convertible loan notes

16


-


4,019




-

Additional paid-in capital



397


397




397

Share-based payment reserve



20


5




20

Foreign currency translation reserve



(4,883)


(3,665)




(4,122)

Accumulated losses



(45,097)


(37,204)




(41,106)

Total equity


 

5,464

 

14,379

 

 

 

10,216

 










Non-current liabilities










Loans and borrowings

17


12,396


-




7,393

Provisions



30


33




31

Total non-current liabilities


 

12,426

 

33

 

 

 

7,424







Current liabilities










Trade and other payables

18


3,636


3,074




2,141

Deferred income

19


-


-




102

Interest payable

17


233


-




134

Total current liabilities


 

3,869

 

3,074

 

 

 

2,377

Total liabilities


 

16,295

 

3,107

 

 

 

9,801

Total equity and liabilities


 

21,759

 

17,486

 

 

 

20,017

 

Ferro-Alloy Resources Limited

Condensed unaudited Statement of Changes in Equity
for the six months ended 30 June 2024

 

 

Share
capital
$000

 

Convertible
 loan notes
$000

 

Additional paid in capital
$000

 

Share-based
payment
reserve
$000

 

Foreign currency translation reserve
$000

 

Accumulated
losses
$000

 

Total
$000

Balance at 1 January 2023

50,827


4,019


397


5


(4,161)


(35,674)


15,413

Loss for the year

-


-


-


-


-


(1,530)


(1,530)

Other comprehensive income











 


 

Exchange differences arising on translation of foreign operations

-


-


-


-


496


-


496

Total comprehensive loss for the year

-

 

-

 

-

 

-

 

496

 

(1,530)

 

(1,034)

Transactions with owners, recorded directly in equity














Shares issued, net of issue costs

-


-


-


-


-


-


-

Other transactions recognised directly in equity

-


-


-


-


-


-


-

Balance at 30 June 2023

50,827

 

4,019

 

397

 

5

 

(3,665)

 

(37,204)

 

14,379

Balance at 31 December 2023

55,027

 

-

 

397

 

20

 

(4,122)

 

(41,106)

 

10,216

Balance at 1 January 2024

55,027


-


397


20


(4,122)


(41,106)


10,216

Loss for the period

-


-


-


-


-


(3,991)


(3,991)

Other comprehensive loss











 


 

Exchange differences arising on translation of foreign operations

-


-


-


-


(761)


-


(761)

Total comprehensive loss for the period

-

 

-

 

-


-

 

(761)

 

(3,991)

 

(4,752)

Transactions with owners, recorded directly in equity














Shares issued, net of issue costs

-


-


-


-


-


-


-

Other transactions recognised directly in equity

-


-


-


-


-


-


-

Balance at 30 June 2024

55,027

 

-

 

397

 

20

 

(4,883)

 

(45,097)

 

5,464

Ferro-Alloy Resources Limited

Condensed unaudited Statement of Cash Flows
for the six months ended 30 June 2024


 


Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Audited
year ended
31 December 2023
$000


 

Cash flows from operating activities

Note







Loss for the period

 

 

(3,991)

 

(1,530)

 

(5,251)

Adjustments for:







 

Depreciation and amortisation

3, 5


391


210


476

Write-off of property, plant and equipment



3


-


1

Write-down of inventory to net realisable value



-


-


254

Write-off of non-refundable VAT







30

Share-based payment expense



-


-


15

Net finance cost / (income)

8


593


(158)


183

Cash used in operating activities before changes in working capital



(3,004)

 

(1,478)


(4,292)

Change in inventories



183


(387)


(609)

Change in trade and other receivables



(836)


(741)


(195)

Change in prepayments



(369)


884


534

Change in trade and other payables



1,495


683


(622)

Change in deferred income

19


(102)


-


102

Net cash used in operating activities



(2,633)

 

(1,039)

 

(5,082)

 








Cash flows from investing activities








Acquisition of property, plant and equipment

9


(135)


(773)


(978)

Acquisition of exploration and evaluation assets

10


(1,002)


(1,481)


(2,931)

Acquisition of intangible assets

11


(1)


(1)


(1)

Proceeds on fixed asset disposal







-

Net cash used in investing activities



(1,138)

 

(2,255)

 

(3,910)

 








Cash flows from financing activities








Proceeds / (repayment) from borrowings

17


5,003

(1,112)


6,672

Interest paid

17


(523)


(32)


(157)

Net cash used in financing activities

 



4,480

 

(1,144)

 

6,515

 








Net increase / (decrease) in cash and cash equivalents



709

 

(4,438)

 

(2,477)

Cash and cash equivalents at the beginning of year

15


1,952


4,331


4,331

Effect of movements in exchange rates on cash and cash equivalents

 



(133)


713


98

Cash and cash equivalents at the end of the period



2,528

 

606

 

1,952

 

 

Notes to the Condensed unaudited Financial Statements for the six months ended 30 June 2024

1          (a) Basis of preparation

These Condensed unaudited Financial Statements have been prepared in accordance with IAS34 'Interim Financial Reporting' and International Financial Reporting Standards as adopted by the European Union ("IFRS") on a going concern basis.

The same accounting policies and basis of preparation have been followed as adopted in the annual financial statements of the Group which were published on 29 April 2024.

(b) Going concern

The Directors have reviewed the Group's cash flow forecasts for a period of at least 12 months from the date of approval of the financial statements, together with sensitivities and mitigating actions. In addition, the Directors have given specific consideration to the continued risks and uncertainties associated with the geopolitical situation with respect to Russia and Ukraine.

The Group now has the facilities and capacity in place to operate profitably and although the amount of those profits available to fund the Group's ongoing overhead costs may vary with metal prices and other factors, the Directors are confident that the Company has sufficient resources to continue as a going concern for at least the next 12 months.

 

(c) Use of estimates and judgements

Preparing the financial statements requires management to make judgements, estimates and assumptions that affect the application of accounting policies and the reported amounts of assets and liabilities, income and expenses. Actual results may differ from these estimates.

Estimates and underlying assumptions are reviewed on an ongoing basis. Revisions to accounting estimates are recognised in the period in which the estimates are revised and in any future periods affected.

Carrying value of processing operations

The Directors have tested the existing operation's property, plant and equipment ("PP&E") for impairment (Note 9) at 30 June 2024. In doing so, net present value cash flow forecasts were prepared using the value in use method which required key estimates including vanadium pentoxide and ferro-molybdenum prices, production including the impact of ongoing PP&E maintenance costs and an appropriate discount rate.  Key estimates included:

·    Production volumes of 72 tonnes per month of vanadium pentoxide (or equivalent as AMV) and 12 tonnes of molybdenum (as ferro-molybdenum) from 2025 thereafter.

·    Average prices of vanadium pentoxide of US$5.50/lb and ferro-molybdenum of US$51/kg in 2024 and thereafter, reflecting management estimates having consideration of market commentary less a discount, and used by the Company as a long-term assumption for other planning purposes.

·    Discount rate of 14.7% post tax in real terms.

Based on the key assumptions set out above, the recoverable amount of PP&E (US$8.9m) exceeds its carrying amount (US$5.4m) by US$3.5m and, therefore, PP&E has not been impaired.

Inventories (Note 12)

The Group holds material inventories which are assessed for impairment at each reporting date. The assessment of net realisable value requires consideration of future cost to process and sell and spot market prices at the period end less applicable discounts. The estimates are based on market data and historical trends.

Exploration and evaluation assets (Note 10)

The Group holds material exploration and evaluation assets and judgement is applied in determining whether impairment indicators exist under the Group's accounting policy. In determining that no impairment indicator exists management have considered the Competent Person's Report on the asset, the strategic plans for exploration and future development and the status of the Subsoil Use Agreement ("SUA").  Judgement was required in determining that a current application for deferral of obligations under the SUA will be granted and management anticipate such approvals being provided given their understanding of the Kazakh market and plans for the asset.

(d) Unaudited status

These Condensed unaudited Financial Statements have not been audited or reviewed by the Group's auditor.

 



 

2          Revenue

 

Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Audited
year ended
31 December 2023
$000

Sales of vanadium products

1,264


2,340


3,308

Sales of ferro-molybdenum

720


955


2,698

Sales of nickel products

-


109


143

Tolling revenue

179


-


-

Service revenue

7


6


15

Total revenue from customers under IFRS 15

2,170

 

3,410

 

6,164

Other revenue (adjustments to price after delivery and fair value changes)

(21)


(96)


(448)

Total revenue

2,149

 

3,314

 

5,716

 

             Vanadium products

Under certain sales contracts the single performance obligation is the delivery of AMV to the designated delivery point at which point possession, title and risk on the product transfers to the buyer. The buyer makes an initial provisional payment based on volumes and quantities assessed by the Company and market spot prices of vanadium pentoxide for AMV at the date of shipment. The final payment is received once the product has reached its final destination with adjustments for quality / quantity and pricing. The final pricing is based on the historical average market prices during a quotation period based on the date the product reaches the port of destination and an adjusting payment or receipt will be made to the revenue initially received. Where the final payment for a shipment made prior to the end of an accounting period has not been determined before the end of that period, the revenue is recognised based on the spot price that prevails at the end of the accounting period.

Other revenue related to the change in the fair value of amounts receivable and payable under the sales contracts between the date of initial recognition and the period end resulting from market prices are recorded as other revenue.

 

3          Cost of sales


Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Audited
year ended
31 December 2023
$000

Materials

2,438


2,651


4,832

Wages, salaries and related taxes

659


538


1,128

Depreciation

355


190


425

Electricity

60


42


94

Other

110


144


290


3,622

 

3,565

 

6,769

 

4          Other income

 


Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Audited
year ended
31 December 2023
$000

Currency conversion gain

3


8


8

Other (sales of equipment)

4


5


12


7

 

13

 

20

5          Administrative expenses


Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Audited
year ended
31 December 2023
$000

Wages, salaries and related taxes

955


867


2,023

Professional services

120


61


315

Taxes other than income tax

-


-


18

Listing and financing expenses

356


97


155

Audit

107


126


125

Materials

22


24


48

Rent

37


17


40

Depreciation and amortisation

36


20


51

Insurance

43


2


44

Bank fees

5


12


23

Travel expenses

23


13


89

Communication and information services

9


8


30

Other

137


90


410


1,850

 

1,337

 

3,371

 

6          Other expenses


Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Audited
year ended
31 December 2023
$000

Currency conversion loss

20


27


59

Write-down of inventory to net realisable value

-


-


254

Write-down of obsolete assets

-


-


1

Share-based payment expense

-


-


15

Other

4


20


142


24

 

47

 

471

 

7          Personnel costs


Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Audited
year ended
31 December 2023
$000

Wages, salaries and related taxes

1,702


1,610


3,232


1,702

 

1,610

 

3,232

Personnel costs of US$537,000 (2023: US$495,000) have been charged to cost of sales, US$955,000 (2023: US$867,000) to administrative expenses and US$210,000 (2023: US$248,000) were charged to cost of inventories which were not yet sold as at the end of the period.

 

8          Finance costs


Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Audited
year ended
31 December 2023
$000

Net foreign exchange gain

(28)


(175)


(83)

Interest expense on financial liabilities (bonds)

621


17


266

Net finance cost / (income)

593

 

(158)

 

183

 

9              Property, plant and equipment

 

Land and buildings
$000

 

Plant and equipment
$000

 

Vehicles
$000

 

Computers
$000

 

Other
$000

 

Construction in progress
$000

 

Total
$000

Cost














Balance at 1 January 2023

1,959


2,723


458


43


174


3,448


8,805

Additions

-


254


-


1


8


510


773

Transfers

255


46


-


-


-


(301)


-

Disposals

-


(4)


-


-


(5)


-


(9)

Foreign currency translation difference

35


51


10


-


3


64


163

Balance at 30 June 2023

2,249

 

3,070

 

468

 

44

 

180

 

3,721

 

9,732

Balance at 31 December 2023

5,015


3,822


522


49


256


242


9,906

Additions

-


81


-


2


-


52


135

Transfers

-


194


-


-


-


(194)


-

Disposals

-


(3)


-


-


(1)


-


(4)

Foreign currency translation difference

(179)


(150)


(19)


(1)


(9)


(2)


(360)

Balance at 30 June 2024

4,836

 

3,944

 

503

 

50

 

246

 

98

 

9,677

 

Depreciation














 














 














Balance at 1 January 2023

708


2,256


322


28


57


-


3,371

Depreciation for the period

45


165


16


2


7


-


235

Disposals

-


(4)


-


-


(5)


-


(9)

Foreign currency translation difference

12


41


7


1


2


-


63

Balance at 30 June 2023

765

 

2,458

 

345

 

31

 

61

 

-

 

3,660

Balance at 31 December 2023

851

 

2,621

 

361

 

33

 

89

 

-

 

3,955

Balance at 1 January 2024

851


2,621


361


33


89


-


3,955

Depreciation for the period

226


227


17


3


10


-


483

Disposals

-


(1)


-


-


-


-


(1)

Foreign currency translation difference

(41)


(104)


(14)


(1)


(4)


-


(164)

Balance at 30 June 2024

1,036

 

2,743

 

364

 

35

 

95

 

-

 

4,273

Carrying amounts














At 1 January 2023

1,251

 

467

 

136

 

15

 

117

 

3,448

 

5,434

At 30 June 2023

1,484

 

612

 

123

 

13

 

119

 

3,721

 

6,072

At 31 December 2023

4,164

 

1,201

 

161

 

16

 

167

 

242

 

5,951

At 30 June 2024

3,800

 

1,201

 

139

 

15

 

151

 

98

 

5,404

 

Depreciation expense of US$355,000 (2023: US$190,000) has been charged to cost of sales, excluding cost of finished goods that were not sold at year-end, US$36,000 (2023: US$20,000) to administrative expenses, and US$96,000 has been charged to the cost of finished goods that were not sold at the end of the period (2023: US$67,000).

Construction in progress relates to upgrades to the processing plant associated with the expansion of the facility.

10      Exploration and evaluation assets

The Group's exploration and evaluation assets relate to the Balasausqandiq deposit. During the six month period ended 30 June 2024, the Group capitalised the costs of technical design, sample test-work and project management costs, all relating to the Company's Stage 1 feasibility study. As at 30 June 2024, the carrying value of exploration and evaluation assets was US$7.8m (2023: US$5.6m).


Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Audited
year ended
31 December 2023
$000

Balance at 1 January

7,145


4,208


4,208

Additions (Stage 1 feasibility study)

1,002


1,481


2,931

Foreign currency translation difference

(311)


(108)


6

Balance at 30 June / 31 December

7,836

 

5,581

 

7,145

 

 

11        Intangible assets


Mineral rights
$000

 

Patents
$000

 

Computer software
$000

 

Total
$000

Cost

 

 

 

 

 



Balance at 1 January 2023

83


32


3


118

Additions

-


1


-


1

Foreign currency translation difference

1


1


-


2

Balance at 30 June 2023

84


34


3


121

Balance at 31 December 2023

84


34


3


121

 



 

 

 



Balance at 1 January 2024

84


34


3


121

Additions

-


1


-


1

Foreign currency translation difference

(3)


(1)


-


(4)

Balance at 30 June 2024

81


34


3


118

 

 

 



 

 

 



Amortisation



 

 

 



Balance at 1 January 2023

83


13


3


99

Amortisation for the year

-


1


-


1

Foreign currency translation difference

1


-


-


1

Balance at 30 June 2023

84


14


3


101

Balance at 31 December 2023

84


14


3


101

 



 





Balance at 1 January 2024

84


14


3


101

Amortisation for the year

-


1


-


1

Foreign currency translation difference

(3)


(1)


-


(4)

Balance at 30 June 2024

81


14


3


98

 








Carrying amounts



 





At 1 January 2023

-

 

19

 

-

 

19

At 30 June 2023

-

 

20

 

-

 

20

At 31 December 2023

-

 

20

 

-

 

20

At 30 June 2024

-

 

20

 

-

 

20

 

During the six months ended 30 June 2024 and 2023, amortisation of intangible assets was charged to administrative expenses.

 

12        Inventories

 

 

 


Unaudited
30 June 2024
$000

 

 

 

Unaudited    30 June 2023 $000

 

Audited 31 December 2023
$000

 

Raw materials and consumables


815


1,422


1,456

 

Finished goods


975


584


517

 

Work in progress


10


9


10

 


 

1,800


2,015

 

1,983

 





 

 

 

 

 

During the six months ended 30 June 2024, inventories expensed to profit and loss amounted to US$2.4m (six months period ended 30 June 2023:US$2.7m).

 

13        Trade and other receivables

 

Current

Unaudited
30 June 2024

$000

 

Unaudited
30 June 2023

 

Audited 31 December 2023


 

$000

 

$000

Trade receivables from third parties

1,215

 

920


264

Due from employees

20

 

55


66

VAT receivable

918


920


1,049

Other receivables

63


64


4


2,216

 

1,959

 

1,383

Expected credit loss provision for receivables

(64)


(67)


(67)

 

2,152

 

1,892

 

1,316

 

The expected credit loss provision for receivable relates to credit impaired receivables which are in default and the Group considers the probability of collection to be remote given the age of the receivable and default status.

 

14        Prepayments

 

Unaudited
30 June 2024
$000

 

Unaudited
30 June 2023
$000

 

Audited 31 December 2023
$000

Non-current

Prepayments

 

853


 

185


 

888

 

853


185

 

888

Current






Prepayments for goods and services

1,166


1,115


762


1,166


1,115

 

762

 

 

15        Cash and cash equivalents


Unaudited
30 June 2024
$000

 

Unaudited
30 June 2023
$000

 

Audited 31 December 2023
$000

Cash at current bank accounts

551

 

592


1,488

Cash at bank deposits

1,976

 

13


417

Petty cash

1

 

1


47

Cash and cash equivalents

2,528

 

606

 

1,952

 

 

16        Equity

(a)       Share capital

 

Number of shares unless otherwise stated                                                           Ordinary shares

 

Unaudited
30 June 2024

 

Unaudited
30 June 2023

 

Audited 31 December 2023

Par value

-


-


-

Outstanding at beginning of year

483,222,238


449,702,150


449,702,150

Shares issued

-


-


33,520,088

Outstanding at end of period

483,222,238

 

449,702,150

 

483,222,238

 

Ordinary shares

All shares rank equally. The holders of ordinary shares are entitled to receive dividends as declared from time to time and are entitled to one vote per share at meetings of the Company.

The Company did not issue any ordinary shares during the period. During 2023, the convertible loan notes held by Vision Blue were converted into equity under the terms of the Convertible Loan Note agreement in place between the Company and Vision Blue. Further information can be found in the Company's 2023 Annual Report.

Reserves

Share capital: Value of shares issued less costs of issuance.  

Convertible loan notes: Further investment rights at issue price.

Additional paid in capital: Amounts due to shareholders which were waived.

Share-based payment: Share options issued during the period.

Foreign currency translation reserve: Foreign currency differences on retranslation of results from functional to presentational currency and foreign exchange movements on intercompany balances considered to represent net investments which are considered as permanent equity.

Accumulated losses: Cumulative net losses.

(b)       Dividends

No dividends were declared for the six months ended 30 June 2024 (2023: US$ nil).

(c)       Loss per share (basic and diluted)

The calculation of basic and diluted loss per share has been based on the loss attributable to ordinary shareholders and the weighted-average number of ordinary shares outstanding. There are no convertible bonds and convertible preferred stock, so basic and diluted losses are equal.

(i)        Loss attributable to ordinary shareholders (basic and diluted)


Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Loss for the period, attributable to owners of the Company

(3,991)


(1,530)


(5,251)

Loss attributable to ordinary shareholders

(3,991)

 

(1,530)

 

(5,251)

(ii)       Weighted-average number of ordinary shares (basic and diluted)

Shares

Unaudited
six-month
period ended
30 June 2024

 

Unaudited
six-month
period ended
30 June 2023

 

Issued ordinary shares at 1 January (after subdivision)

483,222,238


449,702,150


449,702,150

Effect of shares issued (weighted)

-


-


3,857,106

Weighted-average number of ordinary shares at period / year end

483,222,238

 

449,702,150

 

453,559,256

 

 

 

 

 

 

Loss per share of common stock attributable to the Company:

(Basic and diluted / US$)

(0.0083)


(0.0034)


 

17        Loans and borrowings

In 2023 the Company launched a US$20m bond programme in Kazakhstan ("the Programme") and issued two tranches of unsecured corporate bonds under the Programme with effective interest rates of 9.2% and 10.4%, respectively. In 2024, the Company issued a third tranche of bonds under the Programme with an effective interest rate of 11.5%.

With respect to the first tranche of bonds (2023), investors have subscribed for a total of 1,500 bonds with a nominal value of US$2,000 each. These bonds are unsecured, have a three-year term and bear a coupon rate of 9%, paid twice-yearly. The bonds have been listed on AIX with ISIN number KZX000001474.

With respect to the second tranche of bonds (2023), investors have subscribed for a total of 50,000 bonds with a nominal value of US$100 each. These bonds are unsecured, have a three-year term and bear a coupon rate of 10%, paid quarterly. The bonds have been listed on AIX with ISIN number KZX000001623.

With respect to the third tranche of bonds (2024), investors have subscribed for a total of 50,000 bonds with a nominal value of US$100 each. These bonds are unsecured, have a three-year term and bear a coupon rate of 11%, paid quarterly. The bonds have been listed on AIX with ISIN number KZX000001946.

 

 

Unaudited
30 June 2024
$000

 

Unaudited
30 June 2023
$000

 

Audited 31 December 2023
$000

Non-current liabilities

Bonds payable

 

12,396


 

-


 

7,393

 

12,396

 

-

 

7,393

 

Current liabilities

 

 


 

 


 

 

Interest payable

233

 

-


134

 

233

 

-

 

134

 

Non-cash transactions from financing activities are shown in the reconciliation of liabilities from financing transactions below:

 

 

 

 

 

 

Unaudited
six-month
period ended
30 June 2024
$000

 

 

 

Unaudited
six-month
period ended
30 June 2023
$000

 

 

 

 

Audited year ended 31 December 2023
$000

At 1 January

7,527

 

1,127

 

1,127

Cash flows:






-Interest paid

(523)


(32)


(157)

-Repayment of loans and borrowings

-


(1,112)


(1,112)

-Proceeds from loans and borrowings

5,003


-


7,784

Total

12,007

 

(17)

 

7,642

 

Non-cash flows






-     Interest accruing in the period

622


17


273

-     Bond discount / premium

-


-


(388)

At 30 June / 31 December

12,629

 

-

 

7,527

 

 

18        Trade and other payables


Unaudited
30 June 2024
$000

 

Unaudited
30 June 2023
$000

 

Audited 31 December 2023
$000

Trade payables

2,565


2,550


1,781

Debt to directors/key management (Note 22)

-


11


79

Debt to employees

242


154


192

Other taxes

52


225


72

Advances received

777


134


17

 

3,636

 

3,074

 

2,141

 

 



 

19        Deferred income


Unaudited
30 June 2024
$000

 

Unaudited
30 June 2023
$000

 

Audited 31 December 2023
$000

Government grants

-


-


102

 

-

 

-

 

102

 

During 2023, the Group was awarded grant funding by the Kazakhstan Science Fund for the development of technology for the production of mixed vanadium oxides for use in vanadium redox flow batteries.      

 

20        Contingencies

(a)       Insurance

The insurance industry in the Kazakhstan is in a developing state and many forms of insurance protection common in other parts of the world are not yet generally or economically available. The Group does not have full coverage for its plant facilities, business interruption or third party liability in respect of property or environmental damage arising from accidents on Group property or relating to Group operations. There is a risk that the loss or destruction of certain assets could have a material adverse effect on the Group's operations and financial position.

(b)       Taxation contingencies

The taxation system in Kazakhstan is relatively new and is characterised by frequent changes in legislation, official pronouncements and court decisions which are often unclear, contradictory and subject to varying interpretations by different tax authorities. Taxes are subject to review and investigation by various levels of authorities which have the authority to impose severe fines, penalties and interest charges. A tax year generally remains open for review by the tax authorities for five subsequent calendar years but under certain circumstances a tax year may remain open for longer.

These circumstances may create tax risks in Kazakhstan that are more significant than in other countries. Management believes that it has provided adequately for tax liabilities based on its interpretations of applicable tax legislation, official pronouncements and court decisions. However, the interpretations of the relevant authorities could differ and the effect on these consolidated financial statements, if the authorities were successful in enforcing their interpretations, could be significant.

There are no tax claims or disputes at present.

 

21        Segment reporting

The Group's operations are split into three segments based on the nature of operations: processing, subsoil operations (being operations related to exploration and mining) and corporate segment for the purposes of IFRS 8 Operating Segments. The Group's assets are primarily concentrated in the Republic of Kazakhstan and the Group's revenues are derived from operations in, and connected with, the Republic of Kazakhstan.

Unaudited six-month period ended 30 June 2024


 

 

 



Processing
$000

 

Subsoil
$000


Corporate
$000

 

Total
$000

Revenue


2,149


-


-


2,149

Cost of sales


(3,622)


-


-


(3,622)

Other income


6


-


1


7

Administrative expenses


(475)


(42)


(1,333)


(1,850)

Distribution & other expenses


(82)


-


-


(82)

Finance costs


217


-


(810)


(593)

Loss before tax


(1,807)

 

(42)

 

(2,142)

 

(3,991)

 

Unaudited six-month period ended 30 June 2023

 

 



Processing
$000

 

Subsoil
$000


Corporate
$000

 

Total
$000

Revenue


3,314


-


-


3,314

Cost of sales


(3,565)


-


-


(3,565)

Other income


8


-


5


13

Administrative expenses


(402)


(24)


(911)


(1,337)

Distribution & other expenses


(113)


-


-


(113)

Finance costs


(40)


-


198


158

Loss before tax


(798)

 

(24)

 

(708)

 

(1,530)

 

Audited year ended 31 December 2023

 

 


 

 

 



Processing
$000

 

Subsoil
$000


Corporate
$000

 

Total
$000

Revenue


5,716


-


-


5,716

Cost of sales


(6,769)


-


-


(6,769)

Other income


15


-


5


20

Administrative expenses


(1,130)


(41)


(2,200)


(3,371)

Distribution & other expenses


(649)


-


(15)


(664)

Finance costs


(139)


-


(44)


(183)

Loss before tax


(2,956)

 

(41)

 

(2,254)

 

(5,251)

 

 

Included in revenue arising from processing  are revenues of US$2.2m (2023: US$3.1m) which arose from sales to four of the Group' largest customers. No other single customer contributes 10 per cent or more to the Group's revenue.

All of the Group's assets are attributable to the Group's processing operations.

Sales to the Group's largest customers during the six months ended 30 June 2024 were as follows:

 

Customer A                                                                                        US$ 1.0m (45%) (2023:US$ 1.5m)

Customer B                                                                                        US$ 0.4m (17%) (2023: US$1.5m)

Customer C                                                                                        US$ 0.4m (20%) (2023: US$ 0.1m)

Customer D                                                                                        US$ 0.4m (18%) (2023: nil)

 

 

22        Related party transactions

Transactions with management and close family members

Management remuneration

Key management personnel received the following remuneration during the year, which is included in personnel costs (see Note 5):



Unaudited
six-month
period ended
30 June 2024
$000

 

Unaudited
six-month
period ended
30 June 2023
$000

 

Audited year ended 31 December 2023 $000

Wages, salaries and related taxes


538


474


1,114

 

The amount of wages and salaries outstanding at 30 June 2024 is equal to US$ nil (2023: US$11,000).

 

Other

The Company is party to a sub-let agreement between Turian Sports Horses Limited as head lessee and NH Limited as landlord for the rental of office space in Guernsey. Turian Sports Horses Limited is wholly owned by James Turian, one of the Company's directors and NH Limited is owned by James Turian and Sharon Turian, equally. Sums paid to NH Limited during the six months ended 30 June 2024 were US$7,214 (2023: US$10,667).

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
IR BELLLZKLXBBK
Ferro-alloy Resources (LSE:FAR)
Historical Stock Chart
From Nov 2024 to Dec 2024 Click Here for more Ferro-alloy Resources Charts.
Ferro-alloy Resources (LSE:FAR)
Historical Stock Chart
From Dec 2023 to Dec 2024 Click Here for more Ferro-alloy Resources Charts.