This announcement contains
inside information
12 February 2025
Ironveld
PLC
("Ironveld" or the
"Company")
Operational
Update
Ironveld PLC ("Ironveld" or the
"Company"), the owner of a High Purity Iron ("HPI"), Vanadium, and
Titanium project located on the Northern Limb of the Bushveld
Complex in Limpopo Province, South Africa, is pleased to announce
an operational update regarding key milestones achieved by the
Company in relation to its DMS grade magnetite plant.
DMS
Grade Magnetite Plant Progress
Significant progress has been made
on the construction of the plant to produce DMS grade Magnetite,
with key milestones already achieved:
· Site
preparation completed - including satisfaction of Health and
Safety requirements, perimeter security in place, and construction
of concrete support slabs and stockpiling of material for the
bagging plant is now complete.
· Generator acquired and delivered to the mine site for
plant operations.
· Contracts for all electrical works finalised and fully
paid.
· Delivery and
installation of the milling plant, including mill, cradles,
Mill Motor Control Centre and associated equipment secured, along
with all necessary materials and labour for the plant installation
and initial test production run.
On-site work is well underway, and
the Company remains on track to commence commissioning the
plant during February 2025. Following initial sample production,
the plant will ramp up to 24-hour operations, targeting an
initial output of 5,000 tonnes ("t") per month. Capacity will
increase to 15,000t per month after installation and
commissioning of a second, larger ball mill in March/April
2025.
Ironveld's mining team has now been
mobilised to site, where stockpiles of pre-mined ore will be used
for commissioning and initial production work, following which
mining of fresh ore for continuing production will be
undertaken.
Offtake Agreements
· A firm initial offtake agreement has been secured
for 500t per month, with demand from this end user estimated
at around 1,000t per month.
· A tender bid
is currently being prepared for an additional 5,000t - 7,500t
per month, with strong confidence in securing this contract due to
the significantly lower logistical costs versus competitors,
enabled by the close proximity of Ironveld's plant to the
buyer.
· Other
strong expressions of interest are currently being reviewed from
both DMS traders and end users.
Smelter Activities
Technical work is underway relating to the detailed design of
the Water Atomised Powder pilot plant at the Rustenburg smelter.
This work is being performed by a third party with extensive
experience of the process, including producing water atomised iron
and platinum powders. It is expected that the design work will be
completed on schedule in March 2025.
Accounts Update
On 2 January 2025, following a delay
to the publication of the Company's audited accounts for the year
ended 30 June 2024 ("FY24 Accounts"), the Company's shares were
temporarily suspended from trading on AIM in accordance with AIM
Rule 19. Since this time the Company and its advisers have advanced
the workstreams required to complete the audit process, although
these remain in progress. The Company is working to publish the
FY24 Accounts as soon as possible, following which trading in
Ironveld's shares is expected to resume.
Further updates will be provided as
required.
Kris Andersson, CEO of Ironveld,
commented: "I am very pleased with the progress that we
have made on all operational fronts. The successful completion of
the DMS plant is expected soon and will begin to generate cash flow
for the Company shortly thereafter. The plant is designed to
initially produce 5,000 tonnes per month of finished product, but
with future improvements that we have planned, we will be able to
triple production to 15,000 tonnes. We are also making good
progress on the Water Atomised Powder designs, which will offer
exciting further upsides. We are making good progress towards the
completion of our report and accounts. Our structure in South
Africa involves 7 subsidiary companies, which optimises the
administration of our wide-ranging operations, from mining through
mineral processing to smelting and sale of final products. Our
engagement of new auditors, refreshing our local audit team after
12 years, has been good and, whilst it has taken longer than we had
anticipated, we anticipate being in a position to publish our
accounts soon. In the meantime, I would like to thank shareholders
for their patience and support.
I look forward to keeping
the market updated on what is an exciting period for the
Company."
For
further information, please contact:
Ironveld plc
Kristoffer Andersson, Chief
Executive Officer
|
|
c/o BlytheRay
+44 20 7138 3204
|
Cavendish Capital Markets Limited (Nomad and
Broker)
Derrick Lee / Adam Rae
|
|
+44 20 7220 0500
|
Turner Pope Investments (TPI) Ltd (Joint
Broker)
Andrew Thacker / James
Pope
|
|
+44 20 3657 0050
|
BlytheRay
Tim Blythe / Megan Ray
|
|
+44 20 7138 3204
|