TORONTO,
Feb. 26,
2024 /CNW/ - Argonaut Gold Inc. (TSX: AR) (the
"Company", "Argonaut Gold" or "Argonaut") announces today the
Company's 2024 guidance including production, cost per ounce as
well as capital and exploration expenditure forecasts.
Consolidated gold production for 2024, including
the Mexican operations, is expected to be in the range of 225,000
and 250,000 gold equivalent ounces ("GEOs"), an increase of 13% to
25% over 2023 production. Cost of sales and cash costs per ounce of
gold sold are expected to be similar to 2023, while
all-in-sustaining costs per ounce sold are expected to be higher
than 2023 due to the increase in sustaining capital at Magino and
Florida Canyon. Higher sustaining costs at Magino are related to
the completion of the tailings management facility. At Florida
Canyon, higher sustaining costs are due to the construction of the
third heap leach pad.
In 2023, Argonaut achieved a significant
milestone with the commissioning of its flagship asset, the Magino
mine. Ramp up continues into 2024 and the mining and milling rates
are expected to be in line with Magino's NI 43-101
Technical Report 2022 ("Technical Report") in the second half
of 2024. Analysis to-date shows that total contained gold is
projected to be within 1% of the reserve model compared to grade
control polygons. While we believe the block model properly
estimates the grade of the ore, the mine site is experiencing
higher dilution rates than anticipated in the Technical Report due
to challenges with selectively mining the high-grade parts of the
ore body. As a result of the higher dilution than previously
modeled in the high-grade areas of the deposit, the average grade
to the mill is expected to be approximately 5 to 10% lower than in
the Technical Report over the next 2 to 3 years; however,
life-of-mine grades and ounces are not expected to be impacted. The
Company expects to have an updated technical report with the latest
findings filed in the second half of 2024.
"Over the last few months, we have analyzed our
mining practices and grade and tonnes modeled and delivered to the
process plant, in great detail. We have learned that selectively
mining the high-grade portion of the deposit to the extent
predicted in the Technical Report, in the initial three years, may
not be achievable. In 2024, lower grades due to pit sequencing
coupled with lower mining and processing rates in the first half of
the year are expected to be offset by higher mill throughput in the
second half of the year following the completion of optimization
work underway in the first half of the year and improvements in
mill availability," stated Marc
Leduc, Chief Operating Officer of Argonaut Gold. "Notably,
gold recoveries are on plan, while unit costs are expected to be
higher in 2024 relative to the Technical Report but decline over
the following 12 to 18 months as we continue to work through the
ramp up process."
"Operationally, our near-term focus continues to
be the ramp up of the Magino mine. The medium-term goal is to
expand the reserve base and mill throughput in order to increase
production to the 200,000 to 250,000 ounce per year range, while
reducing the cost structure. Given the grade of the deposit, scale
is important to drive strong free cash flows. We anticipate
completing a re-financing of our current debt package by the end of
the first quarter to provide sufficient liquidity during this
ramp-up phase and for our future growth objectives," stated
Richard Young, President and Chief
Executive Officer.
2024 OUTLOOK
The following table outlines the Company's 2024
outlook for key operating and financial statistics:
|
|
Magino
Mine
|
Florida Canyon
Mine
|
La Colorada
Mine
|
San Agustin
Mine
|
El Castillo
Mine
|
Consolidated
Guidance
|
Operating Results
|
Ore Mined
|
('000t)
|
5,200 -
6,000
|
9,800 -
10,800
|
-
|
6,800 -
7,100
|
-
|
|
Waste Mined
|
('000t)
|
15,300 -
17,500
|
10,900 -
11,900
|
-
|
5,800 -
6,100
|
-
|
|
Total Mined
|
('000t)
|
20,500 -
23,500
|
20,700 -
22,700
|
-
|
12,600 -
13,200
|
-
|
|
Grade mined
|
(g/t)
|
0.95 -
1.00
|
0.27 -
0.29
|
-
|
0.45 -
0.50
|
-
|
|
Contained oz
mined
|
(oz)
|
160,000 -
195,000
|
85,000 -
100,000
|
-
|
100,000 -
115,000
|
-
|
|
Strip ratio
|
w/o
|
2.92 -
2.94
|
1.10 -
1.11
|
-
|
0.85 -
0.86
|
-
|
|
Crushed
tonnes
|
('000t)
|
-
|
5,600 -
6,500
|
-
|
6,800 -
7,100
|
-
|
|
ROM tonnes
|
('000t)
|
-
|
3,800 -
4,400
|
-
|
-
|
-
|
|
Total
Placed/milled
|
('000t)
|
3,500 -
3,600
|
9,400 -
10,900
|
-
|
6,800 -
7,100
|
-
|
|
Crushed
grade
|
(g/t)
|
-
|
0.30 -
0.36
|
-
|
0.45 -
0.50
|
-
|
|
ROM grade
|
(g/t)
|
-
|
0.13 -
0.18
|
-
|
-
|
-
|
|
Processed
grade
|
(g/t)
|
1.10 -
1.20
|
0.27 -
0.29
|
-
|
0.45 -
0.50
|
-
|
|
Recovery
rate
|
%
|
90% - 92%
|
59 - 61%
|
-
|
37% - 39%
|
-
|
|
Recoverable
Placed
|
(oz)
|
-
|
50,000 -
62,000
|
-
|
35,000 -
40,000
|
-
|
|
GEO's
produced
|
(oz)
|
120,000 -
130,000
|
63,000 -
70,000
|
5,000 -
6,000
|
35,000 -
40,000
|
2,000 -
4,000
|
225,000 - 250,000
|
Cost of
sales
|
$/oz sold
|
1,400 -
1,550
|
1,850 -
1,950
|
1,950 -
2,050
|
1,950 -
2,050
|
1,100 -
1,200
|
1,650 - 1,750
|
Cash cost
|
$/oz sold
|
1,050 -
1,200
|
1,575 -
1,675
|
1,600 -
1,700
|
1,650 -
1,750
|
1,100 -
1,200
|
1,350 - 1,450
|
All-in sustaining
cost
|
$/oz sold
|
1,650 -
1,800
|
2,350 -
2,450
|
1,600 -
1,700
|
1,800 -
1,900
|
1,100 -
1,200
|
1,950 - 2,050
|
Production
cost
|
$000s
|
140,000 -
145,000
|
110,000 -
113,000
|
9,000 -
10,000
|
65,000 -
72,000
|
2,200 -
4,600
|
326,200 - 344,600
|
Cost Per Tonne
|
Mining
|
$/t
|
3.55 -
3.85
|
2.05 -
2.35
|
-
|
2.20 -
2.50
|
-
|
|
Mining (ore
tonne)
|
$/t
|
13.95 -
14.25
|
4.35 -
4.65
|
-
|
4.10 -
4.40
|
-
|
|
Crushing
|
$/t
|
|
2.25 -
2.55
|
-
|
1.15 -
1.45
|
-
|
|
Processing
|
$/t
|
13.20 -
13.50
|
1.65 -
1.95
|
-
|
3.35 -
3.65
|
-
|
|
G&A
|
$/t
|
7.65 -
7.85
|
1.80 -
2.00
|
-
|
1.20 -
1.40
|
-
|
|
Capital Expenditures
|
Sustaining Capital
(including leases)
|
$ million
|
61,000 -
63,000
|
39,000 -
40,000
|
-
|
6,500 -
7,000
|
-
|
106,500 - 110,000
|
Construction
Capital
|
$ million
|
2,900 -
3,000
|
10,000 -
11,000
|
-
|
-
|
-
|
12,900 - 14,000
|
Capital
Stripping
|
$ million
|
-
|
15,000 -
16,000
|
-
|
-
|
-
|
15,000 - 16,000
|
Reclamation &
Other
|
$ million
|
-
|
7,000 -
7,500
|
-
|
-
|
3,500 -
3,800
|
10,500 - 11,300
|
Capitalized
Exploration
|
$ million
|
14,000 -
15,000
|
|
-
|
-
|
-
|
14,000 - 15,000
|
Magino:
- The mine is expected to complete the implementation of a fleet
management system in H1-2024, which is expected to improve grade
control, mining accuracy and productivity.
- Four additional haul trucks and a PC3000 shovel are expected to
be added to the mobile equipment fleet in the first and second
quarters, respectively, increasing hauling and loading
capacity.
- As a result of the new equipment being added to the mobile
fleet, mining rates are on track to increase through the first half
of 2024, from 50,500 tonnes per day in December 2023 to a daily average of 65,000 tonnes
per day by the second half of the year improving high-grade ore
release.
- Total contained gold is projected to be within 1% of the
reserve model relative to the grade control polygons through to the
end of April 2024 (extent of current
grade control drilling). However, gold grades to the mill are
expected to be 5 to 10% lower than presented in the Technical
Report over the next 2 to 3 years due to higher anticipated
dilution resulting from lower ore selectivity.
- Mill optimization work, underway in the first half of 2024, is
expected to lead to increased throughput rates in the range of
+10%, offsetting the anticipated lower gold grades to the mill in
the early years, putting the mine on track to meet the Technical
Report monthly and annual production rates by the end of 2024.
- Mill recovery rates are in line with Technical Report design
rates, however, throughput rates are expected to remain below
nameplate capacity of 10,000 tonnes per day through the first half
of the year due largely to lower availability as the process team
continues to address poor quality components and consumables in the
mill that have caused significant unplanned downtime.
- The mill modifications and changes are expected to increase
both tonnes per operating hour as well as availability, putting the
mill on track for daily throughputs above nameplate capacity by the
fourth quarter of 2024.
- Cost per tonne mined is more than $1.00 per tonne higher than the Technical Report
for 2024, largely due to higher labour costs, grade control and
drill & blast costs and diesel prices.
- Labour rates have increased since the latest Technical Report
due to inflation and scarcity of technical personnel with the large
number of mining projects under construction in Ontario.
- The mine has offset the labour shortage with contractors until
permanent employees are hired; contractor costs increase cost per
tonne by $0.30.
- Grade control and drill & blast costs are expected to move
closer to the Technical Report over the next 12 to 18 months as the
mining team makes improvements.
- Processing costs are also higher than the Technical Report.
This is largely due to higher labour, consumable, and compressed
natural gas ("CNG") costs.
- General and administration costs are also significantly higher
than the Technical Report due to a larger portion of the employee
base residing in the camp as well as higher environmental and
safety costs.
- Sustaining capital expenditures include the completion of the
Tailings Management Facility 1B,
completion of the assay lab, and other infrastructure and major
spare components, which were deferred from the original capital
cost estimate to conserve cash during the construction of the
mine.
- The target for the reserve development expenditures in 2024 are
anticipated to add between 500,000 and 1 million ounces to
estimated mineral reserves by the end of year.
- An updated NI 43-101 Technical Report is planned for the
second half of 2024, reflecting the updated mineral resources and
mineral reserves as well as planned mill expansion.
Florida Canyon
- In 2023, Florida Canyon reported its highest production total
in 19 years.
- For 2024 production, material movement and grades are expected
to be similar to 2023.
- Ore placed on the leach pad is expected to be approximately 20%
lower than last year but ounce production is expected to be only
marginally lower benefiting from the additional process capacity
being added in 2024 as part of the construction of the third leach
pad, which will allow the drawdown of inventory which built up in
2023 due to limited processing capacity.
- Overall operating costs will be slightly higher than 2023 due
to increases in waste stripping, equipment maintenance and employee
compensation. These higher costs, combined with lower ore tons will
increase unit costs for mining, processing and administration by
approximately 10% when compared to 2023.
- In 2024, sustaining capital costs are largely related to the
construction of a third leach pad and additional processing
capacity to increase the flow rates to begin drawdown of the large
inventory of gold placed on the pads.
- Exploration expenditures have been reduced to allow the team to
update the geologic model based on oxide and sulphide drilling in
2023 and the large volume of historical work done over the last 30
years.
Mexico Operations
- For 2024, the San Agustin mine
in Mexico is expected to remain
operating. However, La Colorada
has been placed on care and maintenance due to the large capital
required to pre-strip the mine. El
Castillo is in reclamation.
- San Agustin's production
guidance include the assumption of receipt of the necessary federal
permits to mine the remaining reserves by mid-year, following the
acquisition of the land in the third quarter of 2023.
- Residual leaching will take place at both La Colorada and El
Castillo in 2024.
- For 2024, the Mexican operations are expected to be largely
breakeven from a cash flow perspective.
- A financial advisor has been appointed to assess strategic
alternatives for the Mexican operations, including the sale of one
or more of the assets.
Qualified Person, Technical Information
The technical information contained in this press
release has been prepared under the supervision of, and has been
reviewed and approved by Mr. Marc
Leduc, P.Eng. Chief Operating Officer; a Qualified Person as
defined by National Instrument 43-101 – Standards of Disclosure for
Mineral Projects ("NI 43-101"). For further information on the
Magino Mine, please see the technical report titled Magino Gold
Project, Ontario, Canada, NI
43-101 Technical Report, Mineral Resource and Mineral Reserve
Update dated March 3, 2022 (effective
date of February 14, 2022) on the
Company's website www.argonautgold.com or on www.sedarplus.ca.
About Argonaut Gold
Argonaut Gold is a Canadian-based gold producer
with a portfolio of operations in North
America. Focused on becoming a low-cost, mid-tier gold
producer, the Company's flagship asset, Magino Mine, is expected to
become Argonaut's largest and lowest cost mine. The Company is
pursuing potential for re-development and additional growth at the
Florida Canyon Mine in Nevada,
USA. Together, the Magino and Florida Canyon mines are the
Company's cornerstone assets that will drive Argonaut through this
pivotal growth stage. The Company also has one additional operating
mine in Mexico, the San Agustin
Mine in Durango. Argonaut Gold trades on the Toronto Stock Exchange
(TSX) under the ticker symbol "AR".
Cautionary Note Regarding Forward-Looking
Statements
This press release contains certain
"forward-looking statements" under applicable Canadian securities
laws concerning the business, operations and financial performance
and condition of Argonaut Gold. Except for statements of historical
fact relating to Argonaut, all statements included herein are
forward-looking statements. The words "believe", "expect",
"strategy", "target", "plan", "scheduled", "commitment"
"opportunities", "guidance", "project", "continue", "on track",
"estimate", "growth", "forecast", "potential", "future", "extend",
"planned", "will", "could", "would", "should", "may" and similar
expressions typically identify forward-looking
statements.
Forward-looking statements and forward-looking
information include, but are not limited to statements with respect
to: consolidated gold production and associated costs in 2024,
mining and milling rates as well as average grades anticipated in
2024 as well as projections over the 12 to 18 months following
2024, implementation of the fleet management system and its
impacts, commissioning of additions to the fleet, improving high
grade ore release, throughput rates relative to nameplate mill
capacity, anticipated impacts of mill modifications, reserve
development targeting 500,000 to 1,000,000 ounces to reserves by
the end of 2024, releasing an updated NI 43-101 in the second half
of 2024, Florida Canyon material movement and grades in 2024 being
similar to 2023, the San Agustin
mine to continue operating, receipt of the necessary federal
permits to mine the remaining reserves at San Agustin, residual leaching taking place at
La Colorada and El Castillo, and the Mexican operations being
largely breakeven from a cash flow perspective in 2024.
Forward-looking statements are necessarily
based on the opinions and estimates of management at the date the
statements are made and are based on a number of assumptions and
subject to a variety of risks and uncertainties and other factors
that could cause actual events or results to differ materially from
those projected in the forward-looking statements. Many of these
assumptions are based on factors and events that are not within the
control of Argonaut and there is no assurance they will prove to be
correct.
Factors that could cause actual results to
vary materially from results anticipated by such forward-looking
statements include but are not limited to the availability and
changing terms of financing, variations in ore grade or recovery
rates, changes in market conditions, changes in inflation, risks
relating to the availability and timeliness of permitting and
governmental approvals; risks relating to international operations,
fluctuating metal prices and currency exchange rates, changes in
project parameters, the possibility of project cost overruns or
unanticipated costs and expenses, risks related to the anticipated
performance of material equipment, the impact of COVID-19 and other
human health concerns and the impact and effectiveness of
governmental responses to them, labour disputes and other risks of
the mining industry, failure of plant, equipment or processes to
operate as anticipated.
These factors are discussed in greater detail
in Argonaut's most recent Annual Information Form dated
March 31, 2023 and in the most recent
Management's Discussion and Analysis for the three and nine months
ended September 30, 2023, both filed
under the Company's issuer profile on SEDAR+, which also provide
additional general assumptions in connection with these statements.
Argonaut cautions that the foregoing list of important factors is
not exhaustive. Investors and others who base themselves on
forward-looking statements should carefully consider the above
factors as well as the uncertainties they represent and the risk
they entail.
Although Argonaut has attempted to identify
important factors that could cause actual actions, events or
results to differ materially from those described in
forward-looking statements, there may be other factors that cause
actions, events or results not to be anticipated, estimated or
intended. There can be no assurance that forward-looking statements
will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements.
Argonaut undertakes no obligation to update forward-looking
statements if circumstances or management's estimates or opinions
should change except as required by applicable securities laws. The
reader is cautioned not to place undue reliance on forward-looking
statements. Statements concerning mineral reserve and resource
estimates may also be deemed to constitute forward-looking
statements to the extent they involve estimates of the
mineralization that will be encountered if the property is
developed. Comparative market information is as of a date prior to
the date of this document. Further, the forward-looking statements
included herein speak only as of the date of this press
release.
SOURCE Argonaut Gold Inc.