Bitdeer Announces December 2024 Production and Operations Update
January 08 2025 - 7:00AM
Bitdeer Technologies Group (NASDAQ: BTDR)
(“
Bitdeer” or the “
Company”), a
world-leading technology company for blockchain and
high-performance computing, today announced its unaudited mining
and operations updates for December 2024.
Operational Update
- Self-mined Bitcoin: 145 Bitcoins.
- Mining Rig Manufacturing and R&D:
- SEALMINER A1: Mass production of approximately 3.7 EH/s of
mining rigs remains on track with 0.3 EH/s powered on, 0.3 EH/s
delivered for installation, 0.6 EH/s in-transit to data centers and
2.5 EH/s in production.
- SEALMINER A2:
- Production of approximately 35 EH/s of mining rigs through Q3
2025 remains on track. First trial batch of Air cooling rigs are
expected to be delivered to our mining datacenters for testing in
January 2025.
- ~29,000 units (~7 EH/s out of the 35 EH/s) of SEALMINER A2s
allocated for external sale (both Air cooling and Hydro cooling),
have been ordered by customers, including the full receipt of
related down payments from customers. These mining rigs are
expected to begin shipment in March through Q2 2025.
- SEALMINER A3:
- SEAL03 initial tape-out sample wafers with an expected chip
efficiency of 10 J/TH are expected in Q1 2025.
- SEALMINER A4:
- SEAL04 R&D remains on track to achieve industry leading
efficiency of 5 J/TH with anticipated initial tape-out in Q3
2025.
- HPC/AI:
- Discussions are ongoing with multiple development partners and
potential end users for selected sites.
- Bitdeer AI cloud services powered by NVIDIA DGX SuperPod with
H100 systems maintained an average utilization rate of
approximately 90% for the month.
- Co-hosted VLM Bootcamp with NVIDIA for participants to explore
and create with VLM via Bitdeer AI Studio.
- Hosting:
- Client-hosted machines decreased by 2,000 units while overall
hashrate increased by 0.8 EH/s due to higher efficiency machines
hosted by clients.
- Infrastructure:
- Tydal, Norway, 40 MW phase 1 expansion has completed
installation of transformers, with delivery and installation of
electrical equipment currently in progress. The energization is
currently pending for regulatory approval.
- Rockdale, Texas, USA, 100 MW hydro-cooling conversion is on
track for phased completion during Q1 2025.
- Jigmeling, Bhutan, 500 MW construction is on track with the
primary substation expected to be completed by Q1 2025.
- Massillon, Ohio, USA, 221 MW substation construction started
and is expected to be completed in Q3 2025. Building design is
completed and construction is underway, expected to be completed in
phases between Q3 and Q4 2025.
- 1.1 GW of new power capacity is on track to come online in
2025.
- Financing:
- Full repayment of the outstanding principal balance of US$10
million of the senior secured notes issued to sellers in the
previously announced acquisition of TROLL HOUSING AS and TYDAL DATA
CENTER AS.
Management Commentary
“2025 is poised to be a transformative year for Bitdeer, marked
by many exciting milestones,” stated Linghui Kong, Chief Business
Officer of Bitdeer. “With the mass production of our SEALMINER A1
and A2 well underway, we are set to significantly expand our
self-mining hashrate and commence miner sales to third party
customers. Looking ahead, the planned releases of SEALMINER A3 and
A4 in 2025 further strengthen our position to become an industry
leading supplier in the multi-billion dollar ASICs market. Further,
we are on track to energize over 1.1 GW of our 2.5 GW power
portfolio over the next twelve months. Sustaining this momentum
across multiple initiatives is a testament to our team’s dedication
and belief in our mission. As we move into 2025, we are eager to
solidify Bitdeer’s position as a leader in the crypto industry as
well as the broader technology sector.”
Production and Operations Summary
Metrics |
Dec 2024 |
Nov 2024 |
Dec 2023 |
Total hash rate under management1
(EH/s) |
21.6 |
20.7 |
21.0 |
- Proprietary hash rate |
8.9 |
8.8 |
8.4 |
• Self-mining |
8.5 |
8.2 |
6.7 |
• Cloud Hash Rate |
0.0 |
0.2 |
1.7 |
• Delivered but not hashing |
0.4 |
0.4 |
- |
- Hosting |
12.7 |
11.9 |
12.6 |
Mining machines under management |
175,000 |
178,000 |
215,000 |
- Self-owned2 |
85,000 |
86,000 |
86,000 |
- Hosted |
90,000 |
92,000 |
129,000 |
Bitcoins mined (self-mining only) |
145 |
150 |
434 |
Bitcoins held3 |
594 |
443 |
43 |
1 Total hash rate under management as of
December 31, 2024 across the Company’s three primary business
lines: Self-mining, Cloud Hash Rate, and Hosting.
- Self-mining refers to cryptocurrency mining
for the Company’s own account, which allows it to directly capture
the high appreciation potential of cryptocurrency.
- Cloud Hash Rate offers hash rate subscription
plans and shares mining income with customers under certain
arrangements. The Cloud Hash Rate stated above reflects the
contracted hash rate with customers at month-end. However,
throughout the month, the Cloud Hash Rate may transition to
Self-mining hash rate if customers opt to not make their monthly
electricity payments for various reasons.
- Hosting encompasses a one-stop mining machine
hosting solution including deployment, maintenance, and management
services for efficient cryptocurrency mining.
2 Self-owned mining machines are for the
Company’s self-mining business and Cloud Hash Rate business.3
Bitcoins held do not include the Bitcoins from
deposits of the customers.
Infrastructure Construction Update
Rockdale, Texas – 100 MW Hydro-cooling
conversion to be energized in phases in Q1 2025:
- Cooling system will be delivered and installed in phases in Q1
2025.
- Planning for phased energization between January and March
2025.
Tydal, Norway – 175 MW site expansion
anticipated to be fully energized by mid-2025:
- Installation of the transformers has been completed, with the
delivery and installation of electrical equipment currently in
progress. Additionally, the procurement and delivery of containers
and hydro-cooling systems are underway, and drainage systems
construction is ongoing.
- Tydal, Norway Phase 1 40 MW expansion pending regulatory
approval. Energization of the full 175 MW site is reasonably
expected to be no later than mid-2025.
Massillon, Ohio – 221 MW site construction has
begun ahead of schedule:
- Substation construction is underway and is expected to be
completed in Q3 2025.
- Building design is completed and construction has begun earlier
than expected, estimated to be completed in phases between Q3 and
Q4 2025.
- Estimated energization timeline remains on track for
mid-to-late 2025.
Jigmeling, Bhutan – 500 MW site is progressing
well, with the following key milestones achieved:
- Construction of transformer and container foundations in
progress and will be completed in phases, with the last phase
expected by the end of February 2025.
- 132kb/140MW and 220kv/360MW substation designs are completed
with construction anticipated to be ready by the end of Q1
2025.
- Orders for the procurement of transformers and electrical
equipment have been placed, with delivery and installation work to
be completed in phases over Q1 and Q2 2025.
- Procurement and delivery of containers and hydro-cooling
systems are in progress, with completion in phases by the end of Q1
2025.
Site / Location |
Capacity (MW) |
Status |
Timing4 |
Electrical capacity |
|
|
|
- Rockdale, Texas |
563 |
Online |
Completed |
- Knoxville, Tennessee |
86 |
Online |
Completed |
- Wenatchee, Washington |
13 |
Online |
Completed |
- Molde, Norway |
84 |
Online |
Completed |
- Tydal, Norway |
50 |
Online |
Completed |
- Gedu, Bhutan |
100 |
Online |
Completed |
Total electrical capacity |
8955 |
|
|
Pipeline capacity |
|
|
|
- Tydal, Norway Phase 1 |
40 |
In progress |
Pending Regulatory Approval |
- Tydal, Norway Phase 2 |
135 |
In progress |
Mid 2025 |
- Massillon, Ohio |
221 |
In progress |
Mid-to-late 2025 |
- Clarington, Ohio Phase 1 |
266 |
In progress |
Q3 2025 |
- Clarington, Ohio Phase 2 |
304 |
Pending approval |
Estimate 2026 |
- Jigmeling, Bhutan |
500 |
In progress |
Mid-to-late 2025 |
- Rockdale, Texas |
179 |
In planning |
Estimate 2026 |
Total pipeline capacity |
1,645 |
|
|
Total global electrical capacity |
2,540 |
|
|
4 Indicative timing. All timing references are to calendar
quarters and years.5 Figures may not add up due to rounding.
Upcoming Conferences and Events
- January 14-17, 2025: 27th Annual Needham Growth Conference in
New York City
- Management Presentation is scheduled for 9:30 am ET on January
15, 2025 and can be viewed at this link.
About Bitdeer Technologies Group
Bitdeer is a world-leading technology company
for blockchain and high-performance computing. Bitdeer is committed
to providing comprehensive computing solutions for its customers.
The Company handles complex processes involved in computing such as
equipment procurement, transport logistics, datacenter design and
construction, equipment management, and daily operations. The
Company also offers advanced cloud capabilities to customers with
high demand for artificial intelligence. Headquartered in
Singapore, Bitdeer has deployed datacenters in the United States,
Norway, and Bhutan. To learn more,
visit https://ir.bitdeer.com/ or follow Bitdeer on X @
BitdeerOfficial and LinkedIn @ Bitdeer Group.
Investors and others should note that Bitdeer
may announce material information using its website and/or on its
accounts on social media platforms, including X, formerly known as
Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages
investors and others to review the information it posts on the
social media and other communication channels listed on its
website.
Forward-Looking Statements
Statements in this press release about future expectations,
plans, and prospects, as well as any other statements regarding
matters that are not historical facts, may constitute
“forward-looking statements” within the meaning of The Private
Securities Litigation Reform Act of 1995. The words “anticipate,”
“look forward to,” “believe,” “continue,” “could,” “estimate,”
“expect,” “intend,” “may,” “plan,” “potential,” “predict,”
“project,” “should,” “target,” “will,” “would” and similar
expressions are intended to identify forward-looking statements,
although not all forward-looking statements contain these
identifying words. Actual results may differ materially from those
indicated by such forward-looking statements as a result of various
important factors, including factors discussed in the section
entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as
well as discussions of potential risks, uncertainties, and other
important factors in Bitdeer’s subsequent filings with
the U.S. Securities and Exchange Commission. Any
forward-looking statements contained in this press release speak
only as of the date hereof. Bitdeer specifically disclaims any
obligation to update any forward-looking statement, whether due to
new information, future events, or otherwise. Readers should not
rely upon the information on this page as current or accurate after
its publication date.
For investor and media inquiries, please
contact:
Investor RelationsOrange GroupYujia
ZhaibitdeerIR@orangegroupadvisors.com
Public RelationsBlocksBridge ConsultingNishant
Sharmabitdeer@blocksbridge.com
Bitdeer Technologies (NASDAQ:BTDR)
Historical Stock Chart
From Dec 2024 to Jan 2025
Bitdeer Technologies (NASDAQ:BTDR)
Historical Stock Chart
From Jan 2024 to Jan 2025