Bitdeer Technologies Group (NASDAQ: BTDR)
(“
Bitdeer” or the “
Company”), a
world-leading technology company for blockchain and
high-performance computing, today announced its unaudited mining
and operations updates for February 2025.
Operational Update
- Self-mined Bitcoin: 110 bitcoins, down
from January 2025 due to less days in February.
- Mining Rig Manufacturing and R&D:
- SEALMINER A1:
- Mass production of approximately 3.7 EH/s of mining rigs is
nearly finalized.
- 0.7 EH/s are energized, 0.4 EH/s have been delivered for
installation, 0.2 EH/s are in-transit to datacenters, 2.3 EH/s have
been produced and ready for shipment and 0.1 EH/s remain in
production. We expect to ship all remaining mining machines to
mining facilities in March 2025.
- SEALMINER A2:
- Production of approximately 35 EH/s are expected to be
completed in October 2025, of which 0.6 EH/s have been produced and
are ready for shipment. We expect approximately another 1 EH/s to
be manufactured in March 2025.
- Approximately 7 EH/s out of the 35 EH/s of SEALMINER A2s
allocated for external sales are expected to begin shipment in
March 2025.
- Recently, certain customers have requested to delay their final
payment for SEALMINER A2s due to lower Bitcoin price. Furthermore,
they have also requested alternative purchase options for future
generations of SEALMINER machines. As such, Bitdeer plans to
redirect SEALMINER A2s previously allocated for external sale to
self-mining to avoid idle inventory. However, the Company is
confident that all 7 EH/s will be sold in the near future.
- While allowing customers to delay final payment, Bitdeer will
retain customers’ down payment on SEALMINER A2s.
- SEALMINER A3:
- SEAL03 sample wafers achieved an energy efficiency of 9.7 J/TH
at the chip level during chip verification and prototype testing
while running at low voltage, ultra power-saving mode.
- SEALMINER A4:
- SEAL04 R&D remains on track to achieve an expected chip
efficiency of approximately 5 J/TH with anticipated initial
tape-out in Q3 2025.
- HPC/AI:
- Discussions are ongoing with multiple development partners and
potential end users for select large scale sites in U.S. for
HPC/AI.
- Hosting:
- Client-hosted machines decreased by 17,000 units or 1.7 EH/s in
February, due to customers kept disposing their less efficient
mining rigs.
- Infrastructure:
- Tydal, Norway, 40 MW phase 1 expansion energization application
has entered into the fast track for final regulatory approval.
- Rockdale, Texas, USA, 100 MW hydro-cooling conversion is on
track to commence phased energization in March 2025, of which
approximately half of the capacity will be used for operating
SEALMINER A1 Hydro-cooled machines. As of the date of this report,
more than 500 units of SEALMINER A1 Hydro-cooled machines have
already been energized, running stably with very low defective rate
and the Company expects more SEALMINER A1 Hydro-cooled and
SEALMINER A2 series mining rigs will be delivered to Rockdale,
Texas in March 2025.
- Clarington Phase 2, Ohio, USA, 304 MW is still pending approval
and in negotiation with the landlord.
- Jigmeling, Bhutan, 500 MW construction is on track with the
primary substation expected to be completed by the end of March
2025.
- Share Repurchase:
- Completed the repurchased approximately US$9 million of the
Company’s Class A ordinary shares at the end of February 2025 while
the share price dropped significantly.
- The Company’s board of directors approved a new share
repurchase program to repurchase up to additional US$20 million
worth of its Class A ordinary shares effective from February 28,
2025 through February 28, 2026.
Management Commentary
We expect nearly all SEALMINER A1s to be energized during March
and April 2025. Further, we remain focused on executing our chip
roadmap on SEALMINER A2 and SEALMINER A3. We will leverage our
massive 2.6 GW power portfolio for HPC/AI. We have advanced
discussions with multiple development partners and potential end
users for selecting large scale sites in U.S. and hope to provide
an update to investors in the coming months.
Production and Operations Summary
Metrics |
Feb 2025 |
Jan 2025 |
Dec 2024 |
Total hash rate under management1
(EH/s) |
20.9 |
22.4 |
21.6 |
- Proprietary hash rate |
9.4 |
9.2 |
8.9 |
• Self-mining |
9.0 |
8.7 |
8.5 |
• Cloud Hash Rate |
- |
- |
- |
• Delivered but not hashing |
0.4 |
0.5 |
0.4 |
- Hosting |
11.5 |
13.2 |
12.7 |
Mining machines under management |
163,000 |
179,000 |
175,000 |
- Self-owned2 |
88,000 |
87,000 |
85,000 |
- Hosted |
75,000 |
92,000 |
90,000 |
Bitcoins mined (self-mining only) |
110 |
126 |
145 |
Bitcoin held3 |
1,039 |
724 |
594 |
1 Total hash rate under management as of
February 28, 2025 across the Company’s three primary business
lines: Self-mining, Cloud Hash Rate, and Hosting.
- Self-mining refers to cryptocurrency mining
for the Company’s own account, which allows it to directly capture
the high appreciation potential of cryptocurrency.
- Cloud Hash Rate offers hash rate subscription
plans and shares mining income with customers under certain
arrangements. The Cloud Hash Rate stated above reflects the
contracted hash rate with customers at month-end.
- Hosting encompasses a one-stop mining machine
hosting solution including deployment, maintenance, and management
services for efficient cryptocurrency mining.
2 Self-owned mining machines are for the
Company’s self-mining business and Cloud Hash Rate business.3
Bitcoins held do not include the Bitcoins from
deposits of the customers.
Additional Details Regarding CEO’s Rule 10b5-1
PlanAs previously announced on February 25, 2025, Chairman
of the Board and Chief Executive Officer, Jihan Wu, has adopted a
plan to sell up to 4 million ordinary shares of the Company on
multiple pre-determined dates starting in March 2025 and ending no
later than the earlier of June 15, 2025 or the date that the
aggregate number of ordinary shares sold under the Plan reaches 4
million. The plan was designed to comply with Rule 10b5-1 under the
Securities Exchange Act of 1934, as amended (the “plan”). The
Company was informed of the terms of the plan as follows:
- 1 million Class A ordinary shares may be sold under the plan if
the price per share is $16.5 or higher,
- 2 million shares may be sold under the plan if the price per
share is $26.7 or higher,
- 3 million shares may be sold under the plan if the price per
share is $43.2 or higher, and
- 4 million shares may be sold under the plan if the price per
share is $69.9 or higher.
- The number of shares to be sold under the plan on each trading
day shall not exceed 8% of the reported daily trading volume of the
shares on such day.
Infrastructure Construction Update
Rockdale, Texas – 100 MW Hydro-cooling
conversion energization commenced:
- Cooling system will be delivered and installed in phases in Q1
2025.
- Energization began in early March 2025.
- Planning for energization in accordance with the phase of
delivery of mining rigs.
Tydal, Norway – 175 MW site expansion
anticipated to be fully energized by mid-2025:
- Installation of the transformers has been completed, with the
delivery and installation of electrical equipment currently in
progress. Additionally, the procurement and delivery of containers
and hydro-cooling systems are underway, and drainage systems
construction is ongoing.
- Tydal, Norway Phase 1 40 MW expansion pending regulatory
approval. Energization of the full 175 MW site is expected to occur
no later than mid-2025, subject to regulatory approval.
Massillon, Ohio – 221 MW site construction has
begun ahead of schedule:
- Substation construction is underway and is expected to be
completed in Q3 2025.
- Building design is completed and construction has begun earlier
than expected, estimated to be completed in phases between Q3 and
Q4 2025.
- Estimated energization is expected to be completed in phases
over Q3 and Q4 2025.
Clarington Phase 2, Ohio – 304 MW is still
pending approval and in negotiation with the landlord.
Jigmeling, Bhutan – 500 MW site is progressing
well, with the following key milestones achieved:
- Construction of transformer and container foundations in
progress and will be completed in phases, with the last phase
expected by the end of March 2025.
- 132kv/140MW and 220kv/360MW substation designs are completed,
and construction will be completed in phases over Q1 and Q2
2025.
- Orders for the procurement of transformers and electrical
equipment have been placed, with delivery and installation work to
be completed in phases over Q1 and Q2 2025.
- Procurement and delivery of containers and hydro-cooling
systems are in progress, will be completed in phases over Q1 and Q2
2025.
Fox Creek, Alberta – 101 MW site acquired in
Alberta sits on 19 acres is fully licensed and permitted:
- Acquisition includes all permits and licenses to construct an
on-site natural gas power plant, as well as approval for a 99 MW
grid interconnection with Alberta Electric System Operator
(“AESO”).
- Bitdeer will develop and construct the power plant in
partnership with a leading Engineering, Procurement and
Construction (“EPC”) company and is expected to be energized by Q4
2026.
Site / Location |
Capacity (MW) |
Status |
Timing4 |
Electrical capacity |
|
|
|
- Rockdale, Texas |
563 |
Online |
Completed |
- Knoxville, Tennessee |
86 |
Online |
Completed |
- Wenatchee, Washington |
13 |
Online |
Completed |
- Molde, Norway |
84 |
Online |
Completed |
- Tydal, Norway |
50 |
Online |
Completed |
- Gedu, Bhutan |
100 |
Online |
Completed |
Total electrical capacity |
8955 |
|
|
Pipeline capacity |
|
|
|
- Tydal, Norway Phase 1 |
40 |
In progress |
Pending Regulatory Approval |
- Tydal, Norway Phase 2 |
135 |
In progress |
Mid 2025 |
- Massillon, Ohio |
221 |
In progress |
Q4 2025 |
- Clarington, Ohio Phase 1 |
266 |
In progress |
Q3 2025 |
- Clarington, Ohio Phase 2 |
304 |
Pending approval |
Estimate 2026 |
- Jigmeling, Bhutan |
500 |
In progress |
Mid-to-late 2025 |
- Rockdale, Texas |
179 |
In planning |
Estimate 2026 |
- Alberta, Canada |
99 |
In planning |
Q4 2026 |
Total pipeline capacity |
1,744 |
|
|
Total global electrical capacity |
2,639 |
|
|
4 Indicative timing. All timing references are to calendar
quarters and years.5 Figures may not add up due to rounding.
Upcoming Conferences and Events
- March 11 – 12, 2025: Cantor Global Technology
Conference in New York City
- March 16 – 18, 2025: 37th Annual ROTH Growth
Conference in Dana Point, California
- March 18 – 20, 2025: Jefferies 6th Asia Forum
in Hong Kong
- April 8, 2025: JonesResearch Healthcare and
Technology Innovation Conference in Las Vegas, Nevada
- May 21 – 22, 2025: B. Riley 25th Annual
Investor Conference in Marina del Rey
- May 28, 2025: Orange Group 2nd Annual
Sell-side and Buy-side Conference during Bitcoin 2025 in Las Vegas,
Nevada
About Bitdeer Technologies Group
Bitdeer is a world-leading technology company
for blockchain and high-performance computing. Bitdeer is committed
to providing comprehensive computing solutions for its customers.
The Company handles complex processes involved in computing such as
equipment procurement, transport logistics, datacenter design and
construction, equipment management, and daily operations. The
Company also offers advanced cloud capabilities to customers with
high demand for artificial intelligence. Headquartered in
Singapore, Bitdeer has deployed datacenters in the United States,
Norway, and Bhutan. To learn more,
visit https://ir.bitdeer.com/ or follow Bitdeer on X @
BitdeerOfficial and LinkedIn @ Bitdeer Group.
Investors and others should note that Bitdeer
may announce material information using its website and/or on its
accounts on social media platforms, including X, formerly known as
Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages
investors and others to review the information it posts on the
social media and other communication channels listed on its
website.
Forward-Looking Statements
Statements in this press release about future expectations,
plans, and prospects, as well as any other statements regarding
matters that are not historical facts, may constitute
“forward-looking statements” within the meaning of The Private
Securities Litigation Reform Act of 1995. The words “anticipate,”
“look forward to,” “believe,” “continue,” “could,” “estimate,”
“expect,” “intend,” “may,” “plan,” “potential,” “predict,”
“project,” “should,” “target,” “will,” “would” and similar
expressions are intended to identify forward-looking statements,
although not all forward-looking statements contain these
identifying words. Actual results may differ materially from those
indicated by such forward-looking statements as a result of various
important factors, including factors discussed in the section
entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as
well as discussions of potential risks, uncertainties, and other
important factors in Bitdeer’s subsequent filings with
the U.S. Securities and Exchange Commission. Any
forward-looking statements contained in this press release speak
only as of the date hereof. Bitdeer specifically disclaims any
obligation to update any forward-looking statement, whether due to
new information, future events, or otherwise. Readers should not
rely upon the information on this page as current or accurate after
its publication date.
For investor and media inquiries, please
contact:
Investor RelationsOrange GroupYujia
ZhaibitdeerIR@orangegroupadvisors.com
Public RelationsBlocksBridge ConsultingNishant
Sharmabitdeer@blocksbridge.com
Bitdeer Technologies (NASDAQ:BTDR)
Historical Stock Chart
From Mar 2025 to Apr 2025
Bitdeer Technologies (NASDAQ:BTDR)
Historical Stock Chart
From Apr 2024 to Apr 2025