Sable Offshore Corp. Continues to Coordinate with California Coastal Commission on Maintenance and Repair Work in the Coastal Zone
November 14 2024 - 4:22PM
Business Wire
Today, Sable Offshore Corp. (“Sable”) provided
an update on its ongoing coordination with the California Coastal
Commission (“CCC” or “Commission”) related to Sable’s maintenance
and repair work along the existing Pacific Pipeline Company Las
Flores Pipelines CA-324 and CA-325. The following statement was
issued by Steve Rusch, Vice President of Regulatory &
Environmental Affairs at Sable:
“Maintenance and repair activities that are exempt from Coastal
Act permitting requirements have been conducted on the Las Flores
Pipeline system under the pipeline’s existing Coastal Development
Permits for the last 35+ years, and Sable believes recent work on
the pipelines is within the scope of those historic activities.
Sable has been extremely concerned about environmental risk from
open excavations along the pipeline route since the Coastal
Commission asked Sable to stop all work in the Coastal Zone at the
end of September. Sable and the CCC are now working to agree on the
terms of an interim work plan to fill the open excavations, and
Sable will be prepared to start work immediately to fill those open
excavations in order to protect the environment against erosion in
case of any rain events. Restoring the excavations to their
original condition will be the best way to ensure that the
environment will be protected, which is the highest priority for
the CCC and Sable. Once the CCC approves Sable’s interim work plan,
Sable expects the work will take approximately seven days and Sable
is prepared to start the work immediately. This coordination will
allow for CCC and Sable to progress their discussions regarding how
to proceed with the remaining pipeline maintenance and repair work
in the Coastal Zone, without threat of erosion or other
environmental impact during the onset of any inclement weather. We
appreciate CCC staff’s engagement and efforts to work with us in
trying to arrive at a solution, and share the Commission’s passion
for protecting the environment and coastal resources.”
The Las Flores Pipeline system is 124 miles long and spans
multiple properties. The open excavations with exposed pipe are
limited to nine parcels of land in the Coastal Zone where pipeline
maintenance and repair work already was underway. Outside of the
Coastal Zone, Sable has continued its maintenance and repair
activities along the pipeline to bring it to “as new”
condition.
About Sable
Sable Offshore Corp. is an independent oil and gas company,
headquartered in Houston, Texas, focused on responsibly developing
the Santa Ynez Unit in federal waters offshore California. The
Sable team has extensive experience safely operating in
California.
Forward-Looking Statements
The information in this press release include “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. When used in this press release, the words
“could,” “should,” “will,” “ may,” “ believe,” “ anticipate,” “
intend,” “ estimate,” “expect,” “project,” “continue,” “plan,”
forecast,” “predict,” “potential,” “future,” “outlook,” and
“target,” the negative of such terms and other similar expressions
are intended to identify forward-looking statements, although not
all forward-looking statements will contain such identifying words.
These statements are based on the current beliefs and expectations
of Sable’s management and are subject to significant risks and
uncertainties. Actual results may differ materially from those
described in the forward-looking statements. Factors that could
cause Sable’s actual results to differ materially from those
described in the forward-looking statements include: the ability to
recommence production of the SYU assets and the cost and time
required therefor; global economic conditions and inflation;
increased operating costs; lack of availability of drilling and
production equipment, supplies, services and qualified personnel;
geographical concentration of operations; environmental and weather
risks; regulatory changes and uncertainties; litigation, complaints
and/or adverse publicity; privacy and data protection laws, privacy
or data breaches, or loss of data; our ability to comply with laws
and regulations applicable to our business; and other one-time
events and other factors that can be found in Sable’s Annual Report
on Form 10-K for the year ended December 31, 2023, and any
subsequent Quarterly Report on Form 10-Q or Current Report on Form
8-K, which are filed with the Securities and Exchange Commission
and are available on Sable’s website (www.sableoffshore.com) and on
the Securities and Exchange Commission’s website (www.sec.gov).
Except as required by applicable law, Sable undertakes no
obligation to publicly release the result of any revisions to these
forward-looking statements to reflect the impact of events or
circumstances that may arise after the date of this press
release.
Disclaimers
Non-Producing Assets
The SYU assets have not produced commercial quantities of
hydrocarbons since such assets were shut in during June of 2015
when the only pipeline transporting hydrocarbons produced from such
assets to market ceased operations. There can be no assurance that
the necessary permits will be obtained that would allow the
pipeline to recommence transportation and allow the assets to
recommence production. If production is not recommenced by January
1, 2026, the terms of the asset acquisition with ExxonMobil
Corporation would potentially result in the assets being reverted
to ExxonMobil Corporation without any compensation to Sable
therefor.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20241114706961/en/
Investor Contact: Harrison Breaud Director, Finance &
Investor Relations IR@sableoffshore.com 713-579-8111
Sable Offshore (NYSE:SOC)
Historical Stock Chart
From Oct 2024 to Nov 2024
Sable Offshore (NYSE:SOC)
Historical Stock Chart
From Nov 2023 to Nov 2024