Endeavour Silver Corp.
("Endeavour" or the
"Company") (NYSE: EXK; TSX: EDR) is
pleased to provide a Q2 2024 construction progress update for its
Terronera Project in Jalisco state, Mexico. A photo gallery
presentation accompanies this news release and can be found
here or on the Company website at
Terronera Project Progress Photos. All dollar ($)
references in this news release are United States dollars.
The Terronera project continued to make
significant progress in the second quarter, as concrete and
structural steel work are nearing completion on the Upper Plant
Platform for areas including crushing, coarse-ore storage,
grinding, flotation, and thickening. The Project remains on track
for commissioning in Q4 2024 as major mechanical installations
continued to advance on schedule.
"Construction is well past the halfway mark, and
site activities are beginning to peak," commented Don Gray, Chief
Operating Officer. "We are very pleased with the advance at the
Upper Platform, which should be ready for dry commissioning in Q3
2024. We are concentrating resources on the Lower Platform to
finalize earthworks and begin concrete works in early Q3.
Underground mine development continues advancing in line with
expectations as we accessed ore in Q2. We are extremely pleased
with our Terronera team and their progress. With project completion
in sight, our focus has expanded to implementing our business
readiness plan as we prepare for operating Endeavour's next core
asset."
Q2 2024 Construction and Development
Highlights
As of June 30, 2024, site works and activities
included:
- Safety – The highest workplace priority is the health and
safety of our employees and contractors, with a commitment to
provide the tools, training, and resources needed to identify risks
and apply effective controls. Recently, underground operations
increased rescue brigade participation by 40%, and two
self-contained mine refuge stations were installed.
- Progress – Overall project progress (mine development and
surface construction) reached 64.5% completion, with more than $204
million (1) of the project's budget spent to date. Project
commitments total $260 million (1,2), 96% of the $271 million
capital budget.
- Engineering – Efforts have transitioned to construction
support. During the quarter, a detailed design was completed for
the tailing storage facility, Portal 2 waste dump, and the Lower
Platform excavation.
- Mine Development – Over the quarter, over 1,270 meters were
developed underground, totaling nearly 4,500 meters.
- Upper Platform Plant Site – Surface mill and infrastructure
construction is 88% complete and progressing on schedule. Concrete
work and structural steel erection are 100% complete.
- Primary Crusher – Structural and mechanical construction is
complete on the conveyor and apron feeder support steel, and the
apron feeder was placed in position. Conveyors are belted, and
belts vulcanized. Cabling and terminations are ongoing.
- Coarse Ore Stockpile and Reclaim ("COS") Tunnel – SAG Feed
Conveyor and belt were installed. Piping, electrical, and
instrumentation are ongoing.
- Grinding – SAG and ball mill are installed. Piping, mechanical,
electrical, and instrumentation are ongoing.
- Flotation – Piping, mechanical, electrical, and instrumentation
are ongoing. Flotation equipment, including blowers, instruments,
and valves, is expected to be procured in early Q3.
- Tailing Thickener – The Tailings thickener is complete and
signed off. Some steel modifications, such as piping, mechanical,
electrical, and instrumentation, are ongoing. Procurement
monitoring of some equipment (tanks), instruments, and valves is
ongoing.
- Lower Facilities Platform and Tailing Storage Facility –
Excavation for the tailing storage facility embankment key trench
was over 95% complete, and the Lower Platform area was nearly 50%
complete. Concrete work on the lower platform is scheduled to start
in early Q3.
- Procurement – Bulk materials purchase orders have been
released, and lead times are aligned with the current schedule. The
Procurement team has focused on critical path purchases, such as
electrical components and transfer chutes, and reducing bulk
material lead times to increase schedule float.
- Onsite Personnel – At the end of Q2, the workforce increased to
over 190 Endeavour employees and over 700 contractor workers.
- Community Relations – Local community support continues to be a
major commitment. A plant-operator training program for local
community members has been established. The Company is also
preparing a comprehensive training and support services plan for
groups and individuals seeking to form businesses that can provide
local goods and services.
- Environmental – Environmental and social impact assessment
initiatives continue and will be presented in early Q3 (July 2024),
with a 3-month delay compared to the schedule outlined under the
Equator Principles requirements for project loan financing.
Next Steps and Planning
The Terronera Project remains on track for
commissioning in Q4 2024.
For Q3 2024, surface construction will continue
to focus on mechanical, piping, and electrical installations.
Completing the Lower Platform excavation is anticipated to be no
later than mid-Q3 2024. Concrete work for the tailing and
concentrate filtration areas is expected to begin in early Q3 2024,
with the LNG and power generation areas to follow. The Company
anticipates commissioning using temporary power with the LNG and
power generation to be operational subsequent to commissioning. The
temporary power has been planned and is expected to be available
for Q4. Concentrate and tailing filtration structural, mechanical,
and electrical installations will commence as concrete work is
completed.
Mine development in Portals 1, 2, and 4 declines
will continue, with a test long-hole stop being developed in Q3
2024. Initial long-hole production is planned for early Q4,
followed by cut-and-fill mining; ore will be stockpiled for mill
ramp-up. At La Luz, development activities are anticipated to begin
in Q3, with the portal being constructed and the ramp to ore access
being advanced in Q4.
The critical path remains the TSF, Lower
Platform construction, and the advancing underground mine.
Visit www.terronera.com, our dedicated project
website, to stay informed on the ongoing development at Terronera.
Explore updates, learn about our commitment to environmental
stewardship, and discover the positive impacts on local
communities.
About Endeavour Silver:
Endeavour is a mid-tier precious metals company committed to
sustainable and responsible mining practices. With operations in
Mexico and the development of the new cornerstone mine in Jalisco
State, the Company aims to contribute positively to the mining
industry and the communities in which it operates. In addition,
Endeavour has a portfolio of exploration projects in Mexico, Chile,
and the United States, which has helped it achieve its goal of
becoming a premier senior silver producer.
Contact Information
Allison Pettit, Director of Investor RelationsTel: (604) 640
4804Email: apettit@edrsilver.comWebsite: www.edrsilver.com
Follow Endeavour Silver on Facebook, X,
Instagram and LinkedIn
Footnote:
- Financial
figures are based on a preliminary estimate. Final unaudited
figures will be released with the Q2 2024 financial statements on
August 1, 2024.
- Project
commitments include total project expenditures.
Cautionary Note Regarding
Forward-Looking Statements
This news release contains "forward-looking
statements" within the meaning of the United States Private
Securities Litigation Reform Act of 1995 and "forward-looking
information" within applicable Canadian securities legislation.
Such forward-looking statements and information herein include but
are not limited to statements regarding the development and
financing of the Terronera Project, including capital cost
estimates, the anticipated timing of the project construction,
Terronera's forecasted operations, costs and expenditures, and the
timing and results of various related activities. The Company does
not intend to and does not assume any obligation to update
forward-looking statements or information other than as required by
applicable law.
Forward-looking statements or information
involve known and unknown risks, uncertainties, and other factors
that may cause Endeavor's actual results, level of activity,
production levels, performance, or achievements, and its operations
to be materially different from those expressed or implied by such
statements. Such factors include but are not limited changes in
production and costs guidance; the ongoing effects of inflation and
supply chain issues on mine economics; national and local
governments, legislation, taxation, controls, regulations and
political or economic developments in Canada, Chile, the USA and
Mexico; financial risks due to precious metals prices; operating or
technical difficulties in mineral exploration, development and
mining activities; risks and hazards of mineral exploration,
development and mining; the speculative nature of mineral
exploration and development; risks in obtaining necessary licenses
and permits; satisfaction of conditions precedent to drawdown under
the project loan debt facility; the ongoing effects of inflation
and supply chain issues on the Terronera Project economics;
fluctuations in the prices of silver and gold, fluctuations in the
currency markets (particularly the Mexican peso, Chilean peso,
Canadian dollar and US dollar); and challenges to the Company's
title to properties; as well as those factors described in the
section "risk factors" contained in the Company's most recent form
40F/Annual Information Form filed with the SEC and Canadian
securities regulatory authorities.
Forward-looking statements are based on
assumptions management believes to be reasonable, including but not
limited to the continued operation of the Company's mining
operations, no material adverse change in the market price of
commodities forecasted Terronera mine economics as of 2024, mining
operations will operate, and the mining products will be completed
under management's expectations and achieve their stated production
outcomes, and such other assumptions and factors as set out herein.
Although the Company has attempted to identify important factors
that could cause actual results to differ materially from those
contained in forward-looking statements or information, other
factors may cause results to be materially different from those
anticipated, described, estimated, assessed, or intended. There can
be no assurance that any forward-looking statements or information
will be accurate, as actual results and future events could differ
materially from those anticipated in such statements or
information. Accordingly, readers should not place undue reliance
on forward-looking statements or information.
Endeavour Silver (TSX:EDR)
Historical Stock Chart
From Oct 2024 to Nov 2024
Endeavour Silver (TSX:EDR)
Historical Stock Chart
From Nov 2023 to Nov 2024