Kenmare Resources plc ("Kenmare" or "the Company")
Kenmare announces short delay in completion of Mineral Separation Plant at the
Moma Project and early implementation of capacity expansion.
Kenmare has today received notification from the contractor constructing the
Moma Titanium Minerals Project of a six week delay to the completion of the
Minerals Separation Plant (MSP). Kenmare also announce that it intends to
execute an expansion of the capacity of its Moma Titanium Minerals Project in
the second half of 2007.
The capacity expansion, which is now in detailed design, will bring the output
of ilmenite, a titanium mineral and Moma's main product, from a steady state
production level of 700,000 tonnes per year to 800,000 tonnes per year. Hence
expected production in 2008 will be 800,000 tonnes of ilmenite, 56,000 tonnes of
zircon and 21,000 tonnes of rutile. The capital involved in this expansion is
estimated to be US$6.5 million, which is available from Kenmare's internal
resources.
In addition, Kenmare also announced that it has today received notification from
the contractor constructing the Moma Titanium Minerals Project of a six week
delay to the completion of the MSP. The MSP, which was due to be completed in
early January 2007, will now be complete around mid February. This delay has
been caused by the late delivery of materials to the project site. The Moma
Project is now 94.5% complete. Construction began in August 2004 with a
contract period running until the 5th of January 2007. It has been running
ahead of schedule until now.
Kenmare's Chairman Charles Carvill said; "We have been signalling for some time
that we intend to expand production at Moma from initial levels. It is very
pleasing to see that engineering design has verified our view that this can be
done in an extremely cost effective manner and that we can move forward so
rapidly. Also, while it is disappointing to hear news of this short delay in
delivery of the MSP, its significance is small seen in context of the overall
project implementation which has gone extremely well.
For more information:
Kenmare Resources plc
Michael Carvill, Managing Director
Tel: + 353 1 671 0411
Mob: + 353 87 674 0110
Conduit PR Ltd
Leesa Peters
Tel: +44 (0) 207 429 6600
Mob: + 44 (0) 781 215 9885
Murray Consultants Ltd
Elizabeth Headon
Tel: + 353 1 498 0300
Mob: +353 87 989 7234
www.kenmareresources.com
25 October 2006
This information is provided by RNS
The company news service from the London Stock Exchange
END
DRLEAXESAFEKFFE
Kenmare Resources (LSE:KMR)
Historical Stock Chart
From Jun 2024 to Jul 2024
Kenmare Resources (LSE:KMR)
Historical Stock Chart
From Jul 2023 to Jul 2024