TIDMCGH

RNS Number : 6552Z

Chaarat Gold Holdings Ltd

25 May 2021

25 May 2021

Chaarat Gold Holdings Limited

("Chaarat" or "the Company")

Tulkubash Feasibility Study Update

Chaarat (AIM:CGH), the AIM-quoted gold mining Company with an operating mine in Armenia and assets at various stages of development in the Kyrgyz Republic, is pleased to provide an updated JORC compliant bankable feasibility study (the "2021 BFS") for its Tulkubash Oxide Gold Project ("Tulkubash") independently prepared by LogiProc (Pty) Ltd in South Africa. The 2021 BFS is based on the 2019 BFS which was also prepared by LogiProc (Pty) Ltd and includes updates on all sections.

The 2021 BFS confirms robust economics for the development of an open-pit mining heap leach operation. A more conservative model was used to develop the latest Mineral Resource estimate as part of this update. Despite a 25% increase in the overall Mineral Resource, the approach to the updated model has resulted in a slight reduction in ounces contained in the Measured and Indicated categories, with this mineralisation now classified as Inferred. Infill drilling is planned, as part of the 2021 exploration programme, to focus on converting Inferred resources into Measured and Indicated. This conversion could also improve the current 5-year life of mine ("LOM").

Chaarat is in the process of commencing exploration works for the 2021 season and is in continued discussions to complete the financing package which the Company expects could be affected by the current events in the mining sector in the country. Resumption of full construction activity will be dependent on the timing to complete project financing. Delays due to the longer than expected COVID-19 movement restrictions and political situation during 2020 and early 2021 as well as the expected timeline on project financing have resulted in expected first gold from Tulkubash being now targeted for H2 2023.

A webcast and conference call to discuss the 2021 BFS update results will be held tomorrow, 26 May 2021, at 9:00 am BST. Participants can access the presentation by registering here: https://us02web.zoom.us/webinar/register/WN_qUj1mwqbQAmRQmEda3eXmQ .

The full 2021 BFS study will be available on the Chaarat website and can be accessed here: https://www.chaarat.com/kyrgyzstan/tulkubash/

Project Highlights

   -      Conventional open pit mining followed by standard heap leach processing 

- Gold reserves of 571,100 ounces ("oz") and silver reserves of 845,700 oz mined over a current five-year Life of Mine ("LOM")

- Average annual gold production of 95,190 oz and average annual silver production of 140,940 oz

   -      Heap leach facility processing an annual capacity of 5 million tonnes 

- Average head grade of gold at 0.85 g/t and silver at 1.26 g/t at a gold cut-off grade of 0.23 g/t based on $1,450 gold price

   -      Recovery of 73.4% 

- LOM does not include the potential additional JORC compliant Inferred material or any potential future exploration success.

Financial Highlights

 
 In USD                   2021 BFS             Sensitivity 
                           Au @ USD 1,450/oz    Au @ USD 
                           Ag @ USD 17.50/oz    1,800/oz 
                                                Ag @ USD 
                                                27.00/oz 
 Pre-Production 
  Capital Cost                      115 million 
                         --------------------------------- 
 LOM All In Sustaining            866/oz produced 
  Cost ("AISC") 
                         --------------------------------- 
 LOM Operating 
  Cash Flow                      266m             352m 
                         -------------------  ------------ 
 Average Operating 
  Cash Flow p.a.                 44m               59m 
                         -------------------  ------------ 
 LOM Operating 
  Cash Flow margin               44%               47% 
                         -------------------  ------------ 
 Post-tax NPV(5%)                85m              151m 
                         -------------------  ------------ 
 IRR                             25%               38% 
                         -------------------  ------------ 
 

Update from June 2019 BFS

- The 2019 BFS has been updated to account for the following changes, including but not limited to:

o A more robust and reliable resource and reserve estimate

o Improved project cost estimate accuracy (from +/-15% certainty to +/-10% certainty)

o Incorporation of latest engineering studies and assessment to the heap leach design

o Additional work carried out regarding environmental assessments, management controls and the latest social impact studies

o Revised project economics based on the above points and to reflect the latest long term commodity price expectations

- Chaarat has also undergone an independent third-party review of the 2021 BFS and ESIA with SLR Consulting Ltd. (formerly RPA Inc., "SLR"), a leading international mining, environmental and social consultancy.

- The key changes are summarised in the table below and explained in more detail later in this section.

 
                      2019 BFS     2021 BFS 
 Gold price          $ 1,300/oz   $ 1,450/oz   +11% 
                    -----------  -----------  ----- 
 Silver price        $ 16.00/oz   $ 17.50/oz   +9% 
                    -----------  -----------  ----- 
 Ore Reserves         658 koz      571 koz     -13% 
                    -----------  -----------  ----- 
 Strip ratio            2.64         2.59      -2% 
                    -----------  -----------  ----- 
 Mine life             5.3 y        4.8 y      -7% 
                    -----------  -----------  ----- 
 Gold grade             0.92         0.85      -7% 
                    -----------  -----------  ----- 
 Gold recovery         68.9%        73.6%      +7% 
                    -----------  -----------  ----- 
 Post-tax NPV(5%)      $ 70m        $ 85m      +23% 
                    -----------  -----------  ----- 
 IRR                    20%          25%       +25% 
                    -----------  -----------  ----- 
 

Resource and Reserves

The updated resource model was developed using tighter drill spacing for classification purposes. This change reflects the decisions by management to ensure a more robust and conservative approach to resource modelling than had been previously applied. These changes also incorporate recommendations based on previous reviews by SLR, and WAI who assisted Chaarat with the updated resource model.

The Mineral Resource estimate increased to 49.9Mt grading 0.73g/t gold containing 1,177koz of gold from 24.3Mt grading 1.21g/t gold containing 944 thousand ounces of gold ("koz"), an increase of 24.7% in contained gold.

The Tulkubash Mineral Resource is not constrained to one single pit area but comprises the main, mid and east pit areas as well as some early exploration satellites along strike. In the previous 2019 BFS the reserve estimate included ore from main, mid and east pits. Subsequently and in tandem with guidance received from SLR and WAI the more conservative 2021 BFS reclassified the east pit and some deeper mineralisation in the main pit from Indicated to Inferred and Inferred to unclassified material. These have not been converted to Mineral Reserves in the 2021 BFS.

As a result of the gold price change, cut-off grade was adjusted to 0.23g/t in the latest resource. The decrease in Ore Reserves and grade is partially offset by the increase in gold recoveries in the updated mine model achieved through additional metallurgical testing performed by ALS Steward in 2019.

The following table shows the changes from the Mineral Resources defined in the 2019 BFS by category:

Tulkubash Constrained Resource table

 
 Classification    Quantity   Grade    Contained   Change from    Tonnes (%)  Change from  Metal (%) 
                     (M/t)      Au         Au      2019 - Tonnes               2019 Metal 
                               (g/t)     (koz)         (Mt)                      (koz) 
================  =========  =======  ==========  ==============  ==========  ===========  ========= 
    Measured                                          (5.27)        (100)%       (216)      (100)% 
                  =========  =======  ==========  ==============  ==========  ===========  ========= 
    Indicated        28.5      0.86       789          10.4          +58%         87         +12% 
                  =========  =======  ==========  ==============  ==========  ===========  ========= 
    Measured 
  and Indicated      28.5      0.86       789          5.2           +22%        (129)       (14)% 
                  =========  =======  ==========  ==============  ==========  ===========  ========= 
    Inferred         21.4      0.56       388          20.5         +135%         362       +1,381% 
================  =========  =======  ==========  ==============  ==========  ===========  ========= 
      Total          49.9      0.73      1,177         25.7         +106%         233        +25% 
================  =========  =======  ==========  ==============  ==========  ===========  ========= 
 

The impact of the reduction in Measured and Indicated Resources has resulted in the Tulkubash Reserve decreasing from 22.2Mt of ore at 0.92g/t Au in the previous estimate to 20.9Mt of ore at 0.85g/t Au. Contained gold ounces dropped from 658koz to 571koz for the 2021 Reserve. Grade reduction is the result of lower cut off and the reclassification of higher-grade materials from the Mid and East pit areas.

The following table shows the changes in reserves by category and by pit area. Maps illustrating the various areas will be presented in the Webcast presentation tomorrow and are shown in the full 2021 BFS study in section 9 Exploration and section 16 Mining Methods.

Tulkubash Reserve changes by Category and area

 
 Category    Quantity   Grade    Content   Change from    Tonnes  Change from  Metal (%) 
               (Mt)      (g/t)    (koz)    2019 - Tonnes    (%)    2019 Metal 
                                               (Mt)                  (koz) 
==========  =========  =======  ========  ==============  ======  ===========  ========= 
  Proven                                      (6.8)       (100)%     (206)      (100)% 
            =========  =======  ========  ==============  ======  ===========  ========= 
 Probable      20.9      0.85      571         5.5         +36%       120         27% 
            =========  =======  ========  ==============  ======  ===========  ========= 
    P&P        20.9      0.85      571        (1.3)        (6)%      (86)        (13)% 
==========  =========  =======  ========  ==============  ======  ===========  ========= 
 
 
 Mining                  Ore (%)   Metal    Metal 
  Area        Ore (Mt)              (koz)     (%) 
 Main Zone      1.4        +8%      15.8     +3% 
             ---------  --------  -------  ------- 
  Mid Zone     (1.6)      (53)%    (48.7)   (59)% 
             ---------  --------  -------  ------- 
 East Zone     (1.2)     (100)%    (53.0)   (100)% 
             ---------  --------  -------  ------- 
   Total       (1.3)      (6)%     (85.9)   (13)% 
             ---------  --------  -------  ------- 
 

Capex and Opex

Initial Capital Expenditures ("CAPEX") prior to first gold have increased from USD 110 million to USD 115 million. The change is mainly due to a change in the sequencing of the heap leach facility ("HLF") construction which has brought forward spending previously allocated to deferred CAPEX (USD 3 million change). This is a shift in timing of the costs and does not increase the overall LOM CAPEX of the project. The additional USD 2 million increase is related to upgrades identified to being necessary to the camp and mobile fleet equipment workshop.

The site based OPEX has also undergone a review and as a result, the unit cost for mining, processing and owners cost was optimised and is about USD 0.55/t ore lower (-4%). This is mainly the result of design work to optimize the mine haulage scheme.

Financials

The post-tax NPV based on a real discount rate of 5% has increased from USD 70 million to USD 85 million based on 2021 BFS adjustments and revised long term gold pricing. The IRR has increased from 20% in the 2019 BFS to 25% in the 2021 BFS. The increase in project economics is mainly driven by an increase in the underlying commodity price assumptions which reflect the long-term consensus estimate as at April 2021.

2021 Tulkubash Exploration programme

A key focus of the 2021 exploration and drill programme will be to target the areas of the deposit recently reclassified in the 2020 resource model. Approximately 1,800 meters of infill drilling are planned in 14 locations will target areas of known high probability mineralization in the areas previously referred to as mid and east pit.

In addition, the 2021 exploration programme also will focus on areas to the north east of the current resources that indicate good potential for further increasing the reserve base over the next few years. Exploration will utilize a mix of drilling and trenching, Exploration of the broader license area using drone based geophysical techniques will be carried out to allow Chaarat to enhance its understanding of the potential of the remaining license area yet to be explored.

Construction Update

Delays due to the longer than expected COVID-19 movement restrictions and political situation during 2020 and early 2021 together with delays on anticipated timing of the project financing has resulted in the Company now expecting first gold production in H2 2023.

The Tulkubash project requires two full construction seasons to finalise all construction activities. This timing is impacted by the winter weather conditions in the Chatkal region, affecting concrete works and access to larger construction vehicles in the winter months.

Work has started to clear snow and repair roads. Mobilisation of personnel for exploration work will commence end of May. Full stage construction activities will commence once project financing is complete.

Project Financing Update

The Company completed an equity fundraise in February 2021 including USD 30m of new capital of which the majority will be allocated to the construction of the Tulkubash project.

Chaarat is progressing to secure a project finance facility that, together with the cash on hand, will fully fund the USD 115 million required for the construction of Tulkubash. It is envisioned that the debt facility would comprise standard project finance conditions, including the requirement that equity is spent before debt drawdowns. This means that the first drawdown of the debt is envisaged to be required in 2022 with the equity portion used for the 2021 work.

While all workstreams on the debt financing have continued to progress and the Company has been targeting completion in H1 2021, the recent events in the mining sector in the Kyrgyz Republic may defer the closing of such facility.

Chaarat is in advanced discussions with financing counterparties who are completing their due diligence requirements and financing documentation. While Chaarat is exploring traditional project financing for a standalone project finance solution for Tulkubash, the Company is also considering a comprehensive refinancing of its current debt outstanding and financing of the Tulkubash project through a fixed income debt instrument. This may result in Chaarat initiating a series of fixed income investor meetings to explore the viability of such an instrument. The proceeds from this potential financing would be used for refinancing of existing debt and to finance the project costs related to the Tulkubash gold project.

Political situation in Kyrgyz Republic

The current disagreement between the government of the Kyrgyz Republic and Centerra Gold Inc. has not affected the general business climate in country. As advised by various government spokespersons, the issue is specific to the details around the long-standing agreement to operate the Kumtor mine and is in no way reflective of the relationship of other businesses operating in the country.

All such discussions have no impact on any of Chaarat's operations or activities in country. Chaarat maintains strong relations with its communities and government representatives and has received positive feedback on its operations in country from the new government during the latest visits and meetings.

However, the extensive media coverage of the discussions between Centerra and the Kyrgyz Republic is expected to be negatively perceived by potential future debt or equity investors and possibly result in a delay in the project financing.

Artem Volynets, Chief Executive Officer, commented:

"The 2021 BFS provides a robust and conservative resource and reserve estimate for Tulkubash and incorporates the latest updated cost and macro estimates. In accordance with the study, construction will require a further two seasons to complete, meaning first gold is now expected in H2 2023. Our key milestone is to secure the project debt financing for a fully funded project and execute on the construction plan with full speed. Given the recent events in the Kyrgyz Republic, we are cautious on closing the debt financing within the next month as financiers will assess the country situation further and may want to hold until the situation is clearer.

I am proud of the team and the continuous work on the environmental and social aspects of the project over the past years. The baseline studies, thorough assessment of data and the social engagements over the past years were well structured and executed to international best practise standards.

Despite the adjustment in reserves and the unfortunate delay in the project schedule, the Tulkubash project shows strong project economics, with further upside at current price levels, and confirms that there is significant upside potential in LOM extensions. We will be targeting high potential areas classified as Inferred Resources early in the 2021 exploration programme. "

Tulkubash Mineral Resource Statement

 
     Classification        Quantity   Grade Au   Contained 
                             (M/t)      (g/t)     Metal Au 
                                                   (koz) 
========================  =========  =========  ========== 
        Measured 
                          =========  =========  ========== 
        Indicated           28.51       0.86        789 
                          =========  =========  ========== 
 Measured and Indicated     28.51       0.86        789 
                          =========  =========  ========== 
        Inferred            21.41       0.56        388 
========================  =========  =========  ========== 
 

Notes:

1. Numbers are rounded in accordance with disclosure guidelines and may not sum accurately;

2. The Mineral Resource has been estimated using 5.0 m x 5.0 m x 5.0 m (x, y, z) blocks;

3. The estimate was constrained to the mineralised zone using wireframe solid models;

4. The wireframes were sub-domained to isolate the strongly mineralised main zone from the gold mineralisation in the main structural corridor;

5. Grade estimates were based on 1.5 m composited assay data;

6. The Mineral Resource estimate has been reported to 0.21 g/t cut-off grade; and

7. The Mineral Resource estimate is based on 100% of the Project. Çiftay, the Company's construction and equity partner, may earn into the project over time.

Tulkubash Ore Reserve Estimate

 
       Category          Quantity   Grade    Content 
                           (Mt)      (g/t)    (koz) 
======================  =========  =======  ======== 
  Proven Ore Reserve 
                        =========  =======  ======== 
 Probable Ore Reserve      20.9      0.85      571 
                        =========  =======  ======== 
 Combined Ore Reserve      20.9      0.85      571 
======================  =========  =======  ======== 
 

Notes

1. Any apparent computational errors are due to rounding and are not considered significant.

2. Ore Reserves are reported with appropriate modifying factors of mining dilution (8%) and mining recovery (97.5%);

3. The Ore Reserve is defined using a 0.17 g/t recovered Au cutoff, the equivalent of a 0.23 g/t marginal cutoff.

4. Ore Reserves are reported at the head grade delivered to the leach pad;

5. The Ore Reserves are stated at a price of USD1,450/tr oz as at 2020 EOY;

6. Although stated separately, the Mineral Resources are inclusive of Ore Reserves;

7. No Inferred Mineral Resources have been included in the Ore Reserve estimate; and

8. The Mineral Resource estimate is based on 100% of the Project. Çiftay, the Company's construction and equity partner, may earn into the project over time.

 
 Enquiries 
 
                                         +44 (0)20 7499 
 Chaarat Gold Holdings Limited            2612 
 Artem Volynets (CEO)                    info@chaarat.com 
 
 Canaccord Genuity Limited (NOMAD and    + 44 (0)20 7523 
  Joint Broker)                           8000 
 Henry Fitzgerald-O'Connor 
 James Asensio 
 
                                         +44 (0)20 7220 
 finnCap Limited (Joint Broker)           0500 
 Christopher Raggett 
 
 Panmure Gordon (UK) Limited (Joint      +44 (0)20 7886 
  Broker)                                 2500 
 John Prior 
  Hugh Rich 
 

Competent Person Statement

 
 Company            Responsibility 
 LogiProc           Overall project management; 
                     mineral processing and metallurgical 
                     testing; recovery methods; 
                     project infrastructure; capital 
                     cost estimate, economic analysis, 
                     operating cost estimate, project 
                     execution plan. 
 Viktor Usenko      Geological block model and 
  Evgeny Fomichev    associated data integrity. 
 Peter Carter       Mining method review; and 
                     ore reserve statement. Competent 
                     person for ore reserves and 
                     Mining Engineering. 
 WAI                Environmental studies, permitting, 
                     and social or community impact; 
                     geochemistry; hydrology; hydrogeology. 
 Ausenco            Heap leach facility design. 
 

The 2020 Mineral Resource Estimate was produced by Victor Usenko, Principal Geologist, MAIG, Director of the Department of Solid Metals at the Institute of Geotechnologies Moscow ("IGT") who has more than 13 years of experience in resource geology and Evgeny Fomichev, Principal Geologist, MAIG, head of the geological department at IGT who has more than 10 years of experience in resource geology. Both are competent persons as defined by the JORC code.

The statement of Ore Reserves has been reported in accordance with the classification criteria of the JORC Code, 2012 and is 100% attributable to Chaarat and prepared by Mr Peter C Carter, an independent consulting mining engineer, based on a review of work performed by Chaarat Gold technical staff. Mr Carter is a member of the Association of Professional Engineers and Geoscientists of British Columbia and is qualified as a Competent Person under the JORC Code, 2012. Mr. Carter has over 30 years' experience in mine engineering, operations, and management. He has completed assignments in North America, Asia, and Africa with a focus on open pit mining and significant exposure to heap leach operations.

The competent persons consent to the inclusion in this announcement of the matters based on this information in the form and context in which it appears.

About Chaarat

Chaarat is a gold mining company which owns the Kapan operating mine in Armenia as well as the Tulkubash and Kyzyltash Gold Projects in the Kyrgyz Republic. The Company has a clear strategy to build a leading emerging markets gold company with an initial focus on the former Soviet Union through organic growth and selective M&A.

Chaarat is engaged in active community engagement programmes to optimise the value of the Chaarat investment proposition.

Chaarat aims to create value for its shareholders, employees and communities from its high-quality gold and mineral deposits by building relationships based on trust and operating to the best environmental, social and employment standards. Further information is available at www.chaarat.com/ .

Appendix - JORC Table

Section 3. Estimation and Reporting of Mineral Resources

 
 Criteria         JORC Code explanation                                         Commentary 
===============  ============================================================  ================================================================ 
 Database 
 integrity          *    Measures taken to ensure that data has not been          *    Databases are compiled directly by the operator on 
                         corrupted by, for example, transcription or keying            site. All drilling data is securely stored in Excel 
                         errors, between its initial collection and its use            spreadsheets. The database is backed up by Chaarat 
                         for Mineral Resource estimation purposes.                     off- and on site. 
 
 
                    *    Data validation procedures used.                         *    Assay data was cut and pasted into the database from 
                                                                                       electronic versions of the laboratory reports. 
 
 
                                                                                  *    The drill hole database used for Mineral Resource 
                                                                                       estimation has been internally validated and 
                                                                                       externally audited, by Gustavson and Associates 
                                                                                       (2014), by GeoSystems International (GSI, 2018) and 
                                                                                       by Sound Mining (2019). 
 
 
                                                                                  *    The databases have been additional checked for logic 
                                                                                       errors using Micromine inbuilt routines. 
 
 
                                                                                  *    All drilling data is securely stored in Excel 
                                                                                       spreadsheets. The database is backed up by Chaarat 
                                                                                       off- and on site. 
                 ------------------------------------------------------------  ---------------------------------------------------------------- 
 Site visits 
                    *    Comment on any site visits undertaken by the             *    The Competent Person visited Chaarat from August 25th 
                         Competent Person and the outcome of those visits.             through August 28th, 2014, again from August 30th 
                                                                                       through September 3rd, 2017, and again from August 
                                                                                       7th through August 13th, 2018. 
                    *    If no site visits have been undertaken indicate why 
                         this is the case. 
===============  ============================================================  ================================================================ 
 Geological 
 interpretation    *    Confidence in (or conversely, the uncertainty of) the     *    Mineralization and associated hydrothermal alteration 
                        geological interpretation of the mineral deposit.              at Chaarat are genetically associated with igneous 
                                                                                       intrusive rocks along a system of regional-scale, 
                                                                                       dextral, oblique-slip faults. 
                   *    Nature of the data used and of any assumptions made. 
 
                                                                                  *    At this stage of knowledge, the geological 
                   *    The effect, if any, of alternative interpretations on          interpretation of the mineralized zones is deemed to 
                        Mineral Resource estimation.                                   be reliable. 
 
 
                   *    The use of geology in guiding and controlling Mineral     *    The interpretation was based only on the actual data 
                        Resource estimation.                                           for drill holes, underground adits, trenches and 
                                                                                       roads. 
 
                   *    The factors affecting continuity both of grade and 
                        geology.                                                  *    Conclusions on geological/structural environment of 
                                                                                       the deposit based on previous works carried out 
                                                                                       within Tulkubash and observations made in 2018 by IGT 
                                                                                       Chief Geologist Andrey Chitalin. Structural control 
                                                                                       of mineralization is the main factor for the 
                                                                                       Tulkubash deposit. All other factors were checked 
                                                                                       (lithology, alteration etc.) in an initial IGT report 
                                                                                       (2018). Pre- or syn-mineralization stage predefined 
                                                                                       the shape of the deposit within the right strike-slip 
                                                                                       fault conditions with extension (transtension). 
                                                                                       Sinistral strike-slip fault is the 
                                                                                       post-mineralization stage. This structural assumption 
                                                                                       predefined the style of interpretation of the deposit 
                                                                                       as linear extended mineralized zones. 
 
 
                                                                                  *    Overall, there is good level of confidence in the 
                                                                                       geological continuity although small scale variation 
                                                                                       in grade means that high confidence in grade 
                                                                                       continuity is limited to those areas drilled at a 
                                                                                       closer spacing ( .APPROX. 20m). 
 
 
                                                                                  *    Based on visual and statistical analysis of gold 
                                                                                       grade distribution, high-grade and low-grade domains 
                                                                                       were identified. Mineralized zones (high grade 
                                                                                       domains) were interpreted on cross-section using 0.7 
                                                                                       g/t cut-off grade. Interpretation was carrying out as 
                                                                                       mineralized zones so internal dilution included where 
                                                                                       appropriate to get better thickness variability. 
                                                                                       Low-grade domain was interpreted using 0.2 g/t gold 
                                                                                       grade which is close to tailings grades. Low-grade 
                                                                                       domain interpretation was carrying out according to 
                                                                                       the high-grade domain interpretation and in a view of 
                                                                                       structural model of the deposit. 
 
 
                                                                                  *    No alternative interpretation is considered or 
                                                                                       assumed at this stage. 
                 ------------------------------------------------------------  ---------------------------------------------------------------- 
 Dimensions 
                   *    The extent and variability of the Mineral Resource        *    The Mineral Resource extends 4,800 m along strike, 
                        expressed as length (along strike or otherwise), plan          maximum plan width of 500 m and a maximum depth below 
                        width, and depth below surface to the upper and lower          surface of 300 m. 
                        limits of the Mineral Resource. 
===============  ============================================================  ================================================================ 
 Estimation and 
 modelling         *    The nature and appropriateness of the estimation          *    The Mineral Resource was estimated into a block model 
 techniques             technique(s) applied and key assumptions, including            using ordinary kriging for Au. Ag were also estimated 
                        treatment of extreme grade values, domaining,                  but not reported as Resource. 
                        interpolation parameters and maximum distance of 
                        extrapolation from data points. If a computer 
                        assisted estimation method was chosen include a           *    The block model is prepared in Micromine software. 
                        description of computer software and parameters used. 
 
                                                                                  *    Block model with parent block size of 5 x 5 x 5 m 
                   *    The availability of check estimates, previous                  were generated within the wireframe domains models as 
                        estimates and/or mine production records and whether           it is considered to best reflect gold distribution 
                        the Mineral Resource estimate takes appropriate                and similar to the considered SMU. Minimum subcelling 
                        account of such data.                                          was 1m. IGT subsequently checked how block size 
                                                                                       affects resource estimation including comparison with 
                                                                                       a 10 m SMU block model. 
                   *    The assumptions made regarding recovery of 
                        by-products. 
                                                                                  *    Grade estimates were based on 1.5 m composited assay 
                                                                                       data. 
                   *    Estimation of deleterious elements or other non-grade 
                        variables of economic significance (e.g., sulphur for 
                        acid mine drainage characterisation).                     *    Ellipse based on geostatistics initially. Meanwhile, 
                                                                                       dynamic anisotropy was used during the interpolation. 
                                                                                       Some subdomains were determined, and different 
                   *    In the case of block model interpolation, the block            ellipse orientation applied. Constant parameters for 
                        size in relation to the average sample spacing and             Ellipse were 40.6 x 18.5 x 27.1 m, 4 sectors. 
                        the search employed. 
 
                                                                                  *    The block model was generated in 6 runs using the 
                   *    Any assumptions behind modelling of selective mining           different interpolation parameters (min drill holes, 
                        units.                                                         min points, max points/sector, radius factor). 
 
 
                   *    Any assumptions about correlation between variables.      *    Block model was checked visually from section to 
                                                                                       section, on plan and grade distribution in block 
                                                                                       model match assays results. 
                   *    Description of how the geological interpretation was 
                        used to control the resource estimates. 
                                                                                  *    No assumptions have been made regarding the recovery 
                                                                                       of any by-products. 
                   *    Discussion of basis for using or not using grade 
                        cutting or capping. 
                                                                                  *    No estimation of deleterious components was carried 
                                                                                       out. 
                   *    The process of validation, the checking process used, 
                        the comparison of model data to drill hole data, and 
                        use of reconciliation data if available.                  *    Domains were generated following visual and 
                                                                                       statistical analysis of gold 
                                                                                       mineralisation/distribution. Consequently, a low- and 
                                                                                       high-grade domain was generated based on a 0.2 and 
                                                                                       0.7 g/t Au cut-off. 
 
 
                                                                                  *    Log probability plots were analysed for each domain 
                                                                                       (and sub-domain) to review and support the 
                                                                                       requirement of top cuts. Top cuts were then applied 
                                                                                       on a domain basis. 
 
 
                                                                                  *    Comparison to previous estimates is not considered 
                                                                                       relevant due to an increase in the available data and 
                                                                                       amendments to the interpretation and mineralised 
                                                                                       domains, as well as technical and economic parameters 
                                                                                       applied. The previous mineral resource is summarised 
                                                                                       in the main body of the report. The current mineral 
                                                                                       resource is considered to be more robust and better 
                                                                                       reflect the mineral resources of the Tulkubash 
                                                                                       deposit. 
                 ------------------------------------------------------------  ---------------------------------------------------------------- 
 Moisture 
                    *    Whether the tonnages are estimated on a dry basis or    *    All Mineral Resource tonnages are estimated and 
                         with natural moisture, and the method of                     reported on a dry basis. 
                         determination of the moisture content. 
===============  ============================================================  ================================================================ 
 Cut-off 
 parameters         *    The basis of the adopted cut-off grade(s) or quality     *    Mineral Resources have been reported at cut-off grade 
                         parameters applied.                                           of 0.21 g/t Au . Cut-off grade determined using 
                                                                                       appropriate economic and technical parameters for 
                                                                                       open pit mining operations. 
                 ------------------------------------------------------------  ---------------------------------------------------------------- 
 Mining factors 
 or assumptions    *    Assumptions made regarding possible mining methods,       *    Mining would be through conventional open pit 
                        minimum mining dimensions and internal (or, if                 methods. 
                        applicable, external) mining dilution. It is always 
                        necessary as part of the process of determining 
                        reasonable prospects for eventual economic extraction     *    The Company believes there are no mining factors 
                        to consider potential mining methods, but the                  which affect the assumption that deposit has 
                        assumptions made regarding mining methods and                  reasonable prospects for eventual economic mining. 
                        parameters when estimating Mineral Resources may not 
                        always be rigorous. Where this is the case, this 
                        should be reported with an explanation of the basis       *    In order to adhere to the guidelines of the JORC Code 
                        of the mining assumptions made.                                (2012) that a Mineral Resource should display 
                                                                                       reasonable prospects for eventual economic assessment 
                                                                                       IGT has constrained the Mineral Resource to that 
                                                                                       portion of the deposit which falls within a 
                                                                                       conceptual open pit which is based on reasonably 
                                                                                       assumed economic and mining parameters. 
 
 
                                                                                  *    The key parameters used in the pit optimisation are 
                                                                                       shown in the below: 
 
 
 
                                                                                 Au price of US$ 1,800/oz 
                                                                                 Au recovery of 73.3% 
                                                                                 Mining of US$ 1.89/t mined 
                                                                                 Extra Ore Mining of US$ 0.84/t ore 
                                                                                 Processing of US$ 4.25/t ore 
                                                                                 Stacking of US$ 0.54/t ore 
                                                                                 Owner's Mining Cost of US$ 0.34/t ore 
                                                                                 G&A cost of US$ 1.27/t ore 
                                                                                 Discount Rate of 5.0% 
===============  ============================================================  ================================================================ 
 Metallurgical 
 factors or        *    The basis for assumptions or predictions regarding        *    Metallurgical parameters have been taken from the 
 assumptions            metallurgical amenability. It is always necessary as           metallurgical tests and metallurgical test work 
                        part of the process of determining reasonable                  results support the recovery. 
                        prospects for eventual economic extraction to 
                        consider potential metallurgical methods, but the 
                        assumptions regarding metallurgical treatment 
                        processes and parameters made when reporting Mineral 
                        Resources may not always be rigorous. Where this is 
                        the case, this should be reported with an explanation 
                        of the basis of the metallurgical assumptions made. 
                 ------------------------------------------------------------  ---------------------------------------------------------------- 
 Environmental 
 factors or        *    Assumptions made regarding possible waste and process     *    There are not considered to be any environmental 
 assumptions            residue disposal options. It is always necessary as            factors likely to affect the assumption that the 
                        part of the process of determining reasonable                  deposit has reasonable prospects for eventual 
                        prospects for eventual economic extraction to                  economic extraction. 
                        consider the potential environmental impacts of the 
                        mining and processing operation. While at this stage 
                        the determination of potential environmental impacts, 
                        particularly for a greenfields project, may not 
                        always be well advanced, the status of early 
                        consideration of these potential environmental 
                        impacts should be reported. Where these aspects have 
                        not been considered this should be reported with an 
                        explanation of the environmental assumptions made. 
===============  ============================================================  ================================================================ 
 Bulk density 
                   *    Whether assumed or determined. If assumed, the basis          *    Dry bulk density is measured using a paraffin-coated 
                        for the assumptions. If determined, the method used,               immersion (Archimedes) method to evaluate the 
                        whether wet or dry, the frequency of the measurements              specific gravity (SG). 
                  , 
                        the nature, size, and representativeness of the 
                        samples.                                                      *    Density (SG) values have been estimated and included 
                                                                                           in the block model. 
 
                   *    The bulk density for bulk material must have been 
                        measured by methods that adequately account for void          *    The density estimate was based upon 1,420 dry 
                        spaces (vugs, porosity, etc), moisture and                         specific gravity determinations, completed by 
                        differences between rock and alteration zones within               Chaarat. 
                        the deposit. 
 
 
                   *    Discuss assumptions for bulk density estimates used 
                        in the evaluation process of the different materials. 
                 ------------------------------------------------------------  ---------------------------------------------------------------- 
 Classification 
                   *    The basis for the classification of the Mineral            *    Classification of Mineral Resources is based upon a 
                        Resources into varying confidence categories.                   review of geological continuity and complexity, 
                                                                                        quality of supporting data, spatial grade continuity 
                                                                                        and quality of block model. 
                   *    Whether appropriate account has been taken of all 
                        relevant factors (i.e., relative confidence in 
                        tonnage/grade estimations, reliability of input data,      *    Mineral resource classification was made manually 
                        confidence in continuity of geology and metal values,           from section to section. 
                        quality, quantity, and distribution of the data). 
 
                                                                                   *    Following criteria have been took in account during 
                   *    Whether the result appropriately reflects the                   resource classification: 
                        Competent Person's view of the deposit. 
 
                                                                                   *    Variography results (40m is the regular distance 
                                                                                        along strike for Indicated resources). 
 
 
                                                                                   *    Grade/thickness variability and continuity. 
 
 
                                                                                   *    Drill hole spacing. 
 
 
                                                                                   *    Confirmation of grades on surface (trenches/roads). 
 
 
                                                                                   *    Total depth of mineral resource classification was 
                                                                                        defined (for Inferred resources up to 80m along 
                                                                                        strike and along dip). 
 
 
                                                                                   *    The model has been classified into the categories of 
                                                                                        Indicated and Inferred. IGT assumes that measured 
                                                                                        mineral resources could not be classified for 
                                                                                        Tulkubash deposit due to a lot of exploration issues 
                                                                                        within the main zone of the deposit. 
 
 
                                                                                   *    The results of the validation of the block model 
                                                                                        shows acceptable correlation of the input data to the 
                                                                                        estimated grades. 
 
 
                                                                                   *    The Competent Person is confident that all relevant 
                                                                                        factors have been considered and the results reflect 
                                                                                        his views. 
===============  ============================================================  ================================================================ 
 Audits or 
 reviews            *    The results of any audits or reviews of Mineral          *    External reviews of Mineral Resource were performed 
                         Resource estimates.                                           by Wardell Armstrong International (WAI) and by 
                                                                                       Roscoe Postle Associates Inc. (RPA). 
 
 
                                                                                  *    An external peer reviews by independent third parties 
                                                                                       revealed no material concerns. 
                 ------------------------------------------------------------  ---------------------------------------------------------------- 
 Discussion of 
 relative          *    Where appropriate a statement of the relative             *    The Mineral Resource estimate is appropriate for the 
 accuracy/              accuracy and confidence level in the Mineral Resource          style of mineralization and available data. IGT 
 confidence             estimate using an approach or procedure deemed                 considers that the current drill hole spacing is 
                        appropriate by the Competent Person. For example, the          sufficient to demonstrate geological continuity of 
                        application of statistical or geostatistical                   the main geological structures hosting the 
                        procedures to quantify the relative accuracy of the            mineralization. 
                        resource within stated confidence limits, or, if such 
                        an approach is not deemed appropriate, a qualitative 
                        discussion of the factors that could affect the           *    Accuracy of the Mineral Resource estimate is 
                        relative accuracy and confidence of the estimate.              represented in the model classification. 
 
 
                   *    The statement should specify whether it relates to        *    The Mineral Resource relates to global estimates. 
                        global or local estimates, and, if local, state the 
                        relevant tonnages, which should be relevant to 
                        technical and economic evaluation. Documentation          *    The application of top-cuts and compositing in the 
                        should include assumptions made and the procedures             Mineral Resource estimation are considered 
                        used.                                                          appropriate at this stage of development. Any 
                                                                                       additional sampling works, however, may necessitate a 
                                                                                       revision of the top-cuts used. 
                   *    These statements of relative accuracy and confidence 
                        of the estimate should be compared with production 
                        data, where available.                                    *    The Mineral Resource estimation methodology used is 
                                                                                       deemed appropriate based upon validation of the model 
                                                                                       using visual, statistical, and graphical checks. The 
                                                                                       use of alternative methods is likely to yield only 
                                                                                       minor changes to the global Mineral Resource 
                                                                                       estimate. 
 
 
                                                                                  *    The mineralization domains have been adhered to 
                                                                                       through the geostatistical and grade estimation works, 
                                                                                       and the spatial distribution of grade in the final 
                                                                                       Mineral Resource model is representative of the 
                                                                                       sample data. 
                 ------------------------------------------------------------  ---------------------------------------------------------------- 
 

Section 4

 
 Criteria                    JORC Code explanation                               Commentary 
 Site Visits 
                    *    Comment on any site visit undertaken by the Competent     *    Peter C. Carter is qualified as a CP under JORC code 
                         Person and the outcome of those visits                         (2012) 
 
 
                                                                                   *    As a previous member of Chaarat staff, Mr. Carter has 
                                                                                        visited the site on numerous occasions in 2018 and 
                                                                                        2019 
 
 
                                                                                   *    There have been no material changes to the project 
                                                                                        site with respect to Ore Reserves since Mr. Carter's 
                                                                                        last site visit 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Study Status 
                    *    The type and level of study undertaken to enable the      *    The basis for the conversion of the Mineral Resource 
                         Mineral Resource to be converted to Ore Reserves               to an Ore Reserve is the 2019 Updated Feasibility 
                                                                                        Study completed by LogiProc PLC and Sound Mining Inc. 
                                                                                        of Johannesburg. 
                    *    The code requires that a study, at least to 
                         Pre-feasibility Study level has been undertaken to 
                         convert Mineral Resources to Ore Reserves. Such           *    The study represents a Class 3 estimate of the 
                         studies will have been carried out and will have               project value with an accuracy of -10% to +15%. 
                         determined a mine plan that is technically achievable 
                         and economically viable, and that material Modifying 
                         Factors have been considered.                             *    The study determined the project to be both 
                                                                                        technically and economically viable. 
 
 
                                                                                   *    Modifying Factors have been considered in the 
                                                                                        conversion of the Mineral Resource to an Ore Reserve 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Cutoff Grade 
                    *    Nature of cutoff grade                                    *    A cutoff grade for recovered Au was employed due to 
                                                                                        the variable recovery in the geo-metallurgical model. 
 
 
                                                                                   *    The cutoff grade parameters are based on those from 
                                                                                        the 2019 FS with mining and refining costs updated 
 
 
                                                                                   *    Recovered Au cutoff = 0.17 g/t Au 
 
 
                                                                                   *    True marginal cutoff = 0.24 g/t Au at 74% recovery 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Parameters used to calculate cutoff grade                 *    Owner's Mining = 0.34 $/t ore 
 
 
                                                                                   *    Ore Haul = 0.72 $/t ore 
 
 
                                                                                   *    Process = 4.80 $/t ore 
 
 
                                                                                   *    G&A = 1.25 $/t ore 
 
 
                                                                                   *    Refining = 9.78 $/oz 
 
 
                                                                                   *    Gold Price = 1,450 $/oz Au 
 
 
                                                                                   *    Royalty = 12% 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Mining Factors 
 or Assumptions     *    The methods and assumptions used as reported in the       *    Mineral Resource model used a parent block size of 5 
                         PFS or FS to convert the Mineral Resource to an Ore            m x 5 m x 5 m which respects the selective mining 
                         Reserve.                                                       unit 
 
 
                                                                                   *    Pit optimization conducted with Whittle 4X 
 
 
                                                                                   *    Mining costs were $2.55/t ore and $1.83/t waste 
 
 
                                                                                   *    Other parameters as per cutoff grade calculation and 
                                                                                        recommended pit slopes 
 
 
                                                                                   *    Shells optimized for $1,000-$1800/oz Au 
 
 
                                                                                   *    $1,450/oz shell selected as basis for pit design 
 
 
                                                                                   *    Manual design process using GEMS software used to 
                                                                                        generate minable pit design 
 
 
                                                                                   *    Ore Reserve inside manual design within 5% of the 
                                                                                        minable resource within optimized shell 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Use of Inferred Mineral Resources                         *    Inferred Mineral Resources were not permitted to 
                                                                                        influence the pit optimization and were treated as 
                                                                                        waste during mine design and reserve calculation 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Dilution and Mining Recovery                              *    0.5 m "dilution skin" modelled around ore 
 
 
                                                                                   *    Average dilution 8.6% at 
 
 
                                                                                   *    Dilution grade high due to presence of Inferred 
                                                                                        resources adjacent to ore zones 
 
 
                                                                                   *    Mining losses estimated at 2.5% resulting in 97.5% 
                                                                                        ore recovery 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Geotechnical                                              *    Pit slopes based on slope design study by WAI in 2017 
 
 
                                                                                   *    IRAs of 51o and 58o 
 
 
                                                                                   *    Overall slopes of 40-50o 
 
 
                                                                                   *    5 m benches; 8 m berms; 20 m highwalls 
 
 
                                                                                   *    Design criteria extrapolated to Mid Zone as those 
                                                                                        areas host only 8% of the reserve 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Adjusted Reserve                                          *    19.7 Mt ore grading 0.86 g/t Au containing 546 Koz Au 
 
 
                                                                                   *    52.7 Mt associated waste 
 
 
                                                                                   *    2.7:1 strip ratio 
 
 
                                                                                   *    72.4 Mt total material 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Open Pit Description                                      *    3 pits arranged along 2 km of strike 
 
 
                                                                                   *    Main Zone (MZ) Pit; 1 large pit; contains 94% of the 
                                                                                        reserve 
 
 
                                                                                   *    Mid Zone; 2 small pits; 6% of reserve 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Mining Plan 
                    *    Mining Approach                                           *    Contract mining 
 
 
                                                                                   *    Contracting reduces capital costs and training burden 
 
 
                                                                                   *    Contractor experienced in western-style open pit gold 
                                                                                        mining 
 
 
                                                                                   *    Contractor has similar culture and language as local 
                                                                                        workforce 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Mining Method                                             *    Conventional drill-blast, truck-shovel open pit 
                                                                                        mining method 
 
 
                                                                                   *    Small equipment able to provide production capacity, 
                                                                                        selectivity, and flexibility in restricted working 
                                                                                        areas 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Mine Production Plan                                      *    5.4 years of mining including 1.1 years of 
                                                                                        pre-stripping 
 
 
                                                                                   *    350 days of operation per year 
 
 
                                                                                   *    Average mining rate, 40,000 tpd over LOM 
 
 
                                                                                   *    Peak mining rate, 55,000 tpd, 2023-2024 
 
 
                                                                                   *    Average strip ratio during operating period, 2.2:1 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Ore Control                                               *    Blasthole cuttings tested for g/t Au, % Total Sulphur, 
                                                                                        CN solubility 
 
 
                                                                                   *    Geologists log cuttings for degree of oxidation 
 
 
                                                                                   *    Ore and waste blocks flagged by surveyors for 
                                                                                        excavation 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                       *    Mine Water Management                                  *    Groundwater inflows of 4-6 m3/hr anticipated 
 
 
                                                                                   *    Inflows to be collected in sumps and pumped to a 
                                                                                        holding pond 
 
 
                                                                                   *    Runoff will be diverted around the open pits by 
                                                                                        ditches 
 
 
                                                                                   *    Collected water used for dust suppression or treated 
                                                                                        and released 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Slope Stability                                           *    Pre-shear and buffer blasting to protect pit walls 
 
 
                                                                                   *    Walls to be cleaned with by excavators with hydraulic 
                                                                                        hammers 
 
 
                                                                                   *    Visual inspections and survey employed to monitor 
                                                                                        movement 
 
 
                                                                                   *    Mapping of structural features to optimize design 
                                                                                        safety 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Mining Equipment                                          *    5 x 5 m3 excavator + 1 x 5 m3 FEL 
 
 
                                                                                   *    6 x crawler-type, 125 mm, blasthole drills 
 
 
                                                                                   *    55 x highway-type, 30t haul trucks 
 
 
                                                                                   *    Peak truck requirements, 80 units in 2023 
 
 
                                                                                   *    40-50 t bulldozers and 200 HP graders in support 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Mine 
 Infrastructure     *    Dumps & Stockpiles                                        *    Main waste dump 
 
 
                                                                                   *    4 Mt of waste used to backfill pits in 2026 
 
 
                                                                                   *    Ore SP 500 kt capacity located near Sandalash River 
                                                                                        bridge 
 
 
                                                                                   *    All stockpiled ore processed by end of LOM 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Mine Roads                                                *    Dual access to MZ Pit 
 
 
                                                                                   *    6.5 Km Ore Haul Road from Sandalash River bridge to 
                                                                                        ROM Pad 
 
 
                                                                                   *    All haul roads 15 m wide for 2-way traffic; maximum 
                                                                                        grade 10% 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Mine Facilities                                           *    Maintenance Workshop 
 
 
                                                                                   *    Magazine 
 
 
                                                                                   *    AN Storage 
 
 
                                                                                   *    Fuel Farm 
 
 
                                                                                   *    Offices & communications 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Metallurgical 
  Factors or        *    Proposed metallurgical process and flowsheet              *    Heap leach (HL) processing selected 
  assumptions 
 
                                                                                   *    3-stage crushing of ore to P100 12 mm 
 
 
                                                                                   *    Crushed ore stacked by trucks in 7 m lifts on 
                                                                                        valley-fill leach pad 
 
 
                                                                                   *    Au adsorbed onto activated carbon from PLS in CIC 
                                                                                        circuit 
 
 
                                                                                   *    Loaded carbon stripped in AARL-type elution circuit 
 
 
                                                                                   *    Electrowinning and smelting on site produce dore for 
                                                                                        shipment 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Appropriateness of process to the style of                *    About 70% of the Au is readily CN soluble 
                         mineralization 
 
                                                                                   *    Host rock fractures easily to produce 12 mm crush 
 
 
                                                                                   *    No agglomeration at crush sizes > 6 mm 
 
 
                                                                                   *    Lowest capital and operating costs for treating low 
                                                                                        grade, oxidized ore 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Is the metallurgical process well-tested or novel in      *    Process is robust and widely used 
                         nature? 
 
                                                                                   *    Practical for cold-weather conditions 
 
 
                                                                                   *    Heap leaching proven globally over last 40 years 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Nature of metallurgical test work                         *    Process scoping test work conducted by Mintek, SGS, 
                                                                                        RDI, BGRIMM, and Hazen 
 
 
                                                                                   *    HL test programs by WAI (2017), MLI (2018), SAEL 
                                                                                        (2019) 
 
 
                                                                                   *    HL testing included bottle roll (BR), column leach 
                                                                                        (CL), load-permeability, and agglomeration test work 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                      *    Amount and representativeness of metallurgical test     *    93 composite samples tested in all three programs 
                           work 
 
                                                                                   *    78 BR and 11 CL tests produced results representing 
                                                                                        potential leach feed 
 
 
                                                                                   *    75% of samples from Main Zone, 25% from Mid Zone and 
                                                                                        potential East Zone 
 
 
                                                                                   *    Results indicate BR good proxy HL recovery 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Nature of metallurgical domaining                         *    Sulphide and oxide domains defined 
 
 
                                                                                   *    Three oxidation states established 
 
 
                                                                                   *    BR and CL results matched to each ox state 
 
 
                                                                                   *    IDW2 used to estimate recovery for individual blocks 
                                                                                        in oxide domain 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Metallurgical recovery factors applied                    *    Recoveries derived from geo-metallurgical model 
 
 
                                                                                   *    Overall recovery for the Ore Reserve 74% 
 
 
                                                                                   *    Average recovery in Main Zone 73%, Mid Zone 78% 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Assumptions or allowances for deleterious elements        *    Ore is associated with arsenic and antimony 
 
 
                                                                                   *    Neither element is present in amounts which affect 
                                                                                        the selected process or create environmental issues 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Existence of bulk sample or pilot scale test work and     *    No bulk samples or pilot scale test work has been 
                         the degree to which such samples are considered                conducted 
                         representative 
 
                                                                                   *    The samples tested are representative of the 
                                                                                        variability of leach feed across the entire known 
                                                                                        deposit 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    For minerals that are defined by specification, has       *    The Ore Reserve is not defined by a specification 
                         the ore reserve estimate been based on the 
                         appropriate mineralogy to meet the specification? 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Environmental 
                    *    The status of studies of potential environmental          *    ESIA completed by WAI in 2018 
                         impacts of the mining and processing operations. 
 
                                                                                   *    Kyrgyz EIA (OVOS) completed in 2015 
 
 
                                                                                   *    OVOS being updated in support of project permitting 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Details of waste rock characterization                    *    NAG testing in 2020 on 110 samples distributed 
                                                                                        throughout deposit 
 
 
                                                                                   *    Average NAG pH 5-6 indicating little or no acid 
                                                                                        generating potential 
 
 
                                                                                   *    Complimentary ABA testing underway 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Consideration of potential sites and status of design     *    Project site terrain is extremely rugged and 
                         options considered                                             constrained 
 
 
                                                                                   *    Only location able to accommodate the heap leach pad 
                                                                                        and process facility was the selected Dry Valley site 
 
 
                                                                                   *    Dry Valley enables a valley-fill leach pad design 
                                                                                        suited for cold weather operation 
 
 
                                                                                   *    Detailed engineering is in progress 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Status of approvals for process residue storage and       *    Dry Valley location for the heap leach pad is 
                         waste dumps                                                    approved 
 
 
                                                                                   *    MZ waste dump in the Irisai Valley is approved 
 
 
                                                                                   *    Permitting process for various aspects of the process 
                                                                                        facility is ongoing 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Infrastructure 
                    *    Existence of appropriate infrastructure                   *    New site access road completed 
 
 
                                                                                   *    Exploration/Pioneer camps established 
 
 
                                                                                   *    Permanent camp under construction 
 
 
                                                                                   *    All other infrastructure to be provided during 
                                                                                        construction 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Availability of land for development                      *    Chaarat has been granted surface rights for the land 
                                                                                        required to develop the project 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Power                                                     *    A 4.5 MW diesel-fired power plant will supply the 
                                                                                        site with electricity 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Water                                                     *    Process water and raw water will be sourced from 
                                                                                        boreholes located near the plant and camp 
                                                                                        respectively 
 
 
                                                                                   *    Raw water at the camp and ADR plant will be treated 
                                                                                        to generate potable water 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Transportation                                            *    All personnel, goods, and materials will be 
                                                                                        transported to and from site via road 
 
 
                                                                                   *    Bulk materials and equipment will arrive by rail in 
                                                                                        Bishkek, 750 km from site, finishing the journey by 
                                                                                        truck 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Labour                                                    *    The project workforce is estimated at 720 
 
 
                                                                                   *    On a 15-15 continuous shift schedule, half the 
                                                                                        workforce will be on site at any given time 
 
 
                                                                                   *    80% of the workforce is expected to be national with 
                                                                                        a target of 30% coming from local villages 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Accommodation                                             *    The workforce will be housed on site in a 360-man 
                                                                                        permanent camp 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Ease with which infrastructure can be provided            *    All infrastructure will be installed during the 
                                                                                        construction period 
 
 
                                                                                   *    The construction period 18-months but some works are 
                                                                                        seasonally dependent 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Costs 
                    *    Derivation and assumptions regarding capital costs        *    Capital costs adjusted from 2019 FS Update LOM 
                                                                                        estimate to $125 M 
 
 
                                                                                   *    Initial capital = $109 M 
 
 
                                                                                   *    Deferred and Closure costs = $16 M 
 
 
                                                                                   *    Contingency was applied at 10% 
 
 
                                                                                   *    The estimate has an accuracy of -10% to +15% under 
                                                                                        the AACE cost classification system 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Methodology used to estimate operating costs              *    Mining cost from quote by the Contractor based on the 
                                                                                        detailed mine plan 
 
 
                                                                                   *    Process, Owner Mining, and G&A were developed from 
                                                                                        first principles based on detailed operating plans 
 
 
                                                                                   *    All other are based on the 2019 FS Update 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Allowances made for deleterious elements                  *    Project does not incur any added cost due to 
                                                                                        deleterious elements 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Source of exchange rates used in the study                *    Exchange rates for Roubles, Som, and Euros to USD 
                                                                                        were as per prevailing rates in H1 2019 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Derivation of transportation charges                      *    Transportation costs were included in the price of 
                                                                                        all goods and materials 
 
 
                                                                                   *    Cost of shipping was based on estimates a specialist 
                                                                                        logistics service provider in the region 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Basis for forecasting refining charges                    *    Refining charges were based on advice from the Kyrgyz 
                                                                                        gold refinery at Kara-Balta 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Allowances for royalties, both government and private     *    Kyrgyzstan has a sliding scale royalty system pegged 
                                                                                        to gold price 
 
 
                                                                                   *    At a gold price of $1,450/oz Au the royalty payable 
                                                                                        is 12% 
 
 
                                                                                   *    No private royalty payable on the project 
 
 
                                                                                   *    Royalties are applied in lieu of corporate tax in 
                                                                                        Kyrgyzstan 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Revenue 
 Factors            *    Head grade and recovery                                   *    Average head grade 0.86 g/t Au from the block model 
 
 
                                                                                   *    Average Au recovery 74% from geo-metallurgical model 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Metal price                                               *    Average gold price $1,450/oz Au over LOM 
 
 
                                                                                   *    Forecast from BoA/Merrill Lynch 
 
 
                                                                                   *    Conservative compared to World Bank Q2 2020 forecast 
 
 
                                                                                   *    By-product silver priced at $17.50/oz 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Exchange rates                                            *    Exchange rates are based on actuals from H1 2019 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Transportation and treatment charges                      *    Refining and transport costs from Kyrgyz national 
                                                                                        gold refinery at Kara-Balta and a bonded carrier 
                                                                                        respectively 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Refining penalties                                        *    No penalties payable on Tulkubash dore 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Net Smelter Returns                                       *    Dore, 45% Au and 55% Ag, payable 99.5% and 85% 
                                                                                        respectively 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Market 
 Assessment         *    The demand, supply, and stock situation for the           *    All producers of precious metals in Kyrgyzstan are 
                         commodity, consumption trends and factors likely to            obliged to offer their output for sale to the 
                         affect supply and demand in the future                         National Bank of the Kyrgyz Republic (NBKR) at world 
                                                                                        spot prices 
 
 
                                                                                   *    If NBKR declines to purchase metals offered, the 
                                                                                        producer is free to directly sell on world markets 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
                                                                                 *    Not applicable 
                    *    A customer/competitor analysis along with 
                         identification of likely market windows for the 
                         product 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Price and volume forecasts and the basis of these         *    The forecast gold price averages $1,450/oz over LOM 
                         forecasts 
 
                                                                                   *    The project will produce approximately 96 Koz 
                                                                                        annually over 4 years of full operation 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
                                                                                 *    Not applicable 
                    *    For industrial minerals, the customer specification, 
                         testing, and acceptance requirements prior to a 
                         supply contract 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Economic 
                    *    Production Plan                                           *    Operations will mine 19.7 Mt ore grading 0.86 g/t Au 
                                                                                        and 52.7 Mt associated waste over 5.4-year period 
 
 
                                                                                   *    Project will recover 401 Koz primary Au and 515 Koz 
                                                                                        by-product Ag over a 4.9-year LOM 
 
 
                                                                                   *    LOM includes 6 months of residual production while 
                                                                                        rinsing the heap 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Capital Costs                                             *    2019 FS LOM capital of $127 M adjusted to $125 M 
 
 
                                                                                   *    Initial CAPEX decreased $2 M for 2019 sunk costs 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Operating Costs                                           *    Mining, Contract = $2.07/t mined 
 
 
                                                                                   *    Mining, Owner = $0.34/t ore 
 
 
                                                                                   *    Process = $4.77/t ore 
 
 
                                                                                   *    G&A = $1.25/t ore 
 
 
                                                                                   *    All costs applicable to the 4.3-year full production 
                                                                                        period 
 
 
                                                                                   *    Some LOM production costs occur prior to First Gold 
                                                                                        and therefore are accounted for in CAPEX 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Financial Considerations                                  *    Royalty applied at 12% in lieu of tax 
 
 
                                                                                   *    Base Case discount rate = 5% 
 
 
                                                                                   *    Project value calculated from Jan 1, 2020 
 
 
                                                                                   *    Model is unleveraged, assumes 100% equity 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Cost Exclusions                                           *    Inflation 
 
 
                                                                                   *    Engineering 
 
 
                                                                                   *    Permitting 
 
 
                                                                                   *    Exploration 
 
 
                                                                                   *    Interest and financing charges 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Economic Performance                                      *    After-tax NPV discounted at 5% = $85 M 
 
 
                                                                                   *    After-tax IRR = 27% 
 
 
                                                                                   *    Simple Payback = 2.6 years 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Comparison to 2019 FS                                     *    21% increase in NPV at $1,450/oz Au 
 
 
                                                                                   *    13% decrease in NPV at $1,300/oz Au 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Sensitivity Analysis                                        *    Project NPV declines to $69 M and $55 M at discount 
                                                                                          rates of 7.5% and 10% respectively 
 
 
                                                                                     *    Changes of 1% in CAPEX and OPEX result in $1 M and $2 
                                                                                          M changes in NPV, respectively 
 
 
                                                                                     *    1% changes in gold price result in $3-$4 M changes in 
                                                                                          NPV 
 
 
                                                                                     *    Project is breakeven is at a gold price of about 
                                                                                          $1,090/oz Au 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Social 
                    *    Status of agreements with key stakeholders and            *    Chaarat has a standing agreement to fund annual 
                         matters leading to social license to operate                   "social package" for Chatkal as per Kyrgyz 
                                                                                        legislation 
 
 
                                                                                   *    Chaarat has committed to hiring quotas from local 
                                                                                        villages 
 
 
                                                                                   *    Chaarat has promoted the development of local 
                                                                                        business, education, and social events 
 
 
                                                                                   *    Chaarat maintains a program of engagement with the 
                                                                                        local government and population 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Other 
                    *    Naturally Occurring Risks                                 *    The project is subject to risks from geohazards, 
                                                                                        seismicity, and extreme weather 
 
 
                                                                                   *    The project design has been developed to mitigate, 
                                                                                        control, or manage these risks 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Legal Agreements                                          *    Chaarat has partnered with its Mining Contractor, 
                                                                                        Ç iftay Insaat 
 
 
                                                                                   *    Ç iftay has taken a 12% stake in the project 
                                                                                        worth $31 M 
 
 
                                                                                   *    Ç iftay will perform construction earthworks, 
                                                                                        mining, ore stacking, and operate the Permanent Camp 
                                                                                        under a variety of separate contracts 
 
 
                                                                                   *    Chaarat has identified Aggreko to potentially supply 
                                                                                        power under a rental agreement 
 
 
                                                                                   *    Aggreko will install and operate the power plant at 
                                                                                        an estimated cost of $0.197/kwHr 
 
 
                                                                                   *    Chaarat will conclude long-term contracts to ensure 
                                                                                        an adequate supply of fuel and sodium cyanide 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Permitting                                                *    Chaarat holds a mining license for the operating area, 
                                                                                        700 ha, and an exploration license for the 
                                                                                        surrounding 6,770 ha 
 
 
                                                                                   *    Surface rights have been secured for all land 
                                                                                        required to develop the project 
 
 
                                                                                   *    Permitting process is actively working to acquire all 
                                                                                        permits and approvals required for construction and 
                                                                                        operation 
 
 
                                                                                   *    Resolution of the dispute regarding the Besh-Aral 
                                                                                        protected area is in progress 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Ore Reserve 
 Classification     *    Basis for classifying the ore reserve into various        *    Drillhole data density 
                         confidence categories 
 
                                                                                   *    Search for Probable reserves 40 m 
 
 
                                                                                   *    Grade/thickness variability 
 
 
                                                                                   *    Continuity along strike 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Do the results reflect the CP's view of the deposit?      *    Yes. The absence of Measured resources precludes 
                                                                                        declaring Proven reserves 
 
 
                                                                                   *    The Probable reserves are based on accepted standards 
                                                                                        for similar deposits and appropriately reflect the 
                                                                                        quality of the geologic, technical, and economic 
                                                                                        factors used to define them 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    What proportion of Probable Ore Reserves have been        *    None, there are no Measured resources 
                         derived from Measured Mineral Resources? 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Audits or 
  Reviews           *    Results of any audits or reviews of the Ore Reserve       *    No external audits or reviews have been completed on 
                         estimate                                                       the new Ore Reserve 
 
 
                                                                                   *    External reviews of the underlying resource have been 
                                                                                        conducted by SLR Consulting and WAI 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 Discussion 
  of relative       *    Qualitative discussion of the factors that would          *    Mineral Resource Estimate based on an additional 
  accuracy               affect the accuracy and confidence of the estimate             20,000 m of drilling 
  /confidence 
 
                    *    State whether the accuracy/confidence refers to the       *    More rigorous resource classification criteria make 
                         global or a local Ore Reserve estimate                         the Ore Reserve estimate more conservative than 
                                                                                        previous estimates 
 
 
                                                                                   *    Mineral Resource Estimate reviewed by external 
                                                                                        parties with no fatal flaws found 
 
 
                                                                                   *    Accuracy and confidence refer to the global Ore 
                                                                                        Reserve estimate 
 
 
                                                                                   *    Project design is flexible enough to accommodate 
                                                                                        local variations in presentation of tonnage and grade 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 
                    *    Modifying Factors which may affect the                    *    The mining plan employs a conventional approach with 
                         accuracy/confidence of the Ore Reserve estimate                reasonable mining rates. 
 
 
                                                                                   *    Some geotechnical and hydrogeological factors need 
                                                                                        further definition, however, this will not affect the 
                                                                                        accuracy of the Ore Reserve estimate 
 
 
                                                                                   *    The process technology is proven based on a 
                                                                                        comprehensive recovery estimate 
 
 
                                                                                   *    CAPEX and OPEX estimates are FS-level 
 
 
                                                                                   *    The project can manage variations in metal and 
                                                                                        commodity prices of 10-20% 
 
 
                                                                                   *    The project is subject to political and regulatory 
                                                                                        risks whose management is consistent with the 
                                                                                        accuracy of the Ore Reserve estimate 
 
 
                                                                                   *    Natural risks such as geohazards and seismicity have 
                                                                                        been considered in the project design 
                 -------------------------------------------------------------  --------------------------------------------------------------- 
 

Glossary of Technical Terms

   "Ag"                                chemical symbol for silver 
 
 "Au"                   chemical symbol for gold 
 
  "AuEq"                 the value of a tonne of mineralised material 
                         calculated by summing the value of each contained 
                         payable metal and expressing it as an equivalent 
                         gold content at a given set of metals prices 
 "cut off"              the lowest grade value that is included in a 
                         Resource statement. It must comply with JORC 
                         requirement 19: "reasonable prospects for eventual 
                         economic extraction" the lowest grade, or quality, 
                         of mineralised material that qualifies as economically 
                         mineable and available in a given deposit. It 
                         may be defined on the basis of economic evaluation, 
                         or on physical or chemical attributes that define 
                         an acceptable product specification 
 ESIA                   Environmental & Social Impact Assessment 
 
 "g/t"                  grammes per tonne, equivalent to parts per million 
 "Inferred Resource"    that part of a Mineral Resource for which tonnage, 
                         grade and mineral content can be estimated with 
                         a low level of confidence. It is inferred from 
                         geological evidence and assumed but not verified 
                         geological and/or grade continuity. It is based 
                         on information gathered through appropriate techniques 
                         from locations such as outcrops, trenches, pits, 
                         workings, and drill holes which may be limited 
                         or of uncertain quality and reliability 
 "Indicated Resource"   that part of a Mineral Resource for which tonnage, 
                         densities, shape, physical characteristics, grade, 
                         and mineral content can be estimated with a reasonable 
                         level of confidence. It is based on exploration, 
                         sampling and testing information gathered through 
                         appropriate techniques from locations such as 
                         outcrops, trenches, pits, workings, and drill 
                         holes. The locations are too widely or inappropriately 
                         spaced to confirm geological and/or grade continuity 
                         but are spaced closely enough for continuity 
                         to be assumed 
 "JORC"                 The Australasian Joint Ore Reserves Committee 
                         Code for Reporting of Exploration Results, Mineral 
                         Resources and Ore Reserves 2012 (the "JORC Code" 
                         or "the Code"). The Code sets out minimum standards, 
                         recommendations and guidelines for Public Reporting 
                         in Australasia of Exploration Results, Mineral 
                         Resources and Ore Reserves 
 "koz"                  thousand troy ounces of gold 
 "Measured Resource"    that part of a Mineral Resource for which tonnage, 
                         densities, shape, physical characteristics, grade, 
                         and mineral content can be estimated with a high 
                         level of confidence. It is based on detailed 
                         and reliable exploration, sampling and testing 
                         information gathered through appropriate techniques 
                         from locations such as outcrops, trenches, pits, 
                         workings, and drill holes. The locations are 
                         spaced closely enough to confirm geological and 
                         grade continuity 
 "Mineral Resource"     a concentration or occurrence of material of 
                         intrinsic economic interest in or on the Earth's 
                         crust in such form, quality, and quantity that 
                         there are reasonable prospects for eventual economic 
                         extraction. The location, quantity, grade, geological 
                         characteristics, and continuity of a Mineral 
                         Resource are known, estimated, or interpreted 
                         from specific geological evidence and knowledge. 
                         Mineral Resources are sub-divided, in order of 
                         increasing geological confidence, into Inferred, 
                         Indicated and Measured categories when reporting 
                         under JORC 
 "Mt"                   million tonnes 
 "oz"                   troy ounce (= 31.103477 grammes) 
 
  "Probable Reserve"     the part of Indicated and in some cases Measured 
                         Resource that can be mined at a profit. It includes 
                         diluting materials and allowances for losses 
  "Proven Reserve"       that may occur during mining. 
 
                         the part of Indicated Measured Resource that 
                         can be mined at a profit. It includes diluting 
                         materials and allowances for losses that may 
                         occur during mining. 
 "Reserve"              the part of a Measured and/or Indicated Mineral 
                         Resource that can be mined at a profit. Reserves 
                         are subdivided in order of increasing confidence 
                         into Probable and Proven categories when reporting 
                         under JORC. 
 "t"                    tonne (= 1 million grammes) 
 
 WAI                    Wardell Armstrong International 
 

ENDS

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

UPDKZLFLFELZBBB

(END) Dow Jones Newswires

May 25, 2021 02:00 ET (06:00 GMT)

Chaarat Gold (LSE:CGH)
Historical Stock Chart
From Mar 2024 to Apr 2024 Click Here for more Chaarat Gold Charts.
Chaarat Gold (LSE:CGH)
Historical Stock Chart
From Apr 2023 to Apr 2024 Click Here for more Chaarat Gold Charts.