TIDMALBA

RNS Number : 5953F

Alba Mineral Resources PLC

19 July 2021

Click on or paste the following link into your website browser to view the associated PDF document (including maps and images):

http://www.rns-pdf.londonstockexchange.com/rns/5953F_1-2021-7-18.pdf

Alba Mineral Resources plc

("Alba" or the "Company")

Clogau-St David's Gold Mine Update

Phase 2 Surface Drilling Completed

Alba Mineral Resources plc (AIM: ALBA) is pleased to provide an update on its ongoing activities at the Clogau-St David's Gold Mine ("Clogau" or the "Mine").

Key Points

Phase 2 Surface Drilling Completed

-- Ten holes drilled for 1,475.6 m. All holes to date have intersected the Main Lode Extension.

-- JW008 intercepted the best developed example of the Main Lode extension including an intercept of 3.40 m from 49.90 m.

-- Galena has been identified in this intercept, an indicator mineral for gold-bearing veins and previously associated with high gold grades.

-- Main Lode Extension now projected to have strike length of 585 m and a depth extent of 63 m below surface.

-- Targets below Grandfathers and 7-10 Lodes also successfully intersected, with the Grandfathers Extension now being projected to measure approximately 57.6m and the 7-10 Extension 30m.

Phase 2 Underground Drilling

-- Three underground holes drilled, two successfully intersecting the Main Lode Extension north of the Llechfraith adit.

Dewatering Llechfraith Shaft

   --      Permit applications progressing well. 

Mine Development

-- Next steps will be to undertake technical and engineering studies to assess the optimal means to access the gold targets defined by Alba's drilling.

Alba's Executive Chairman, George Frangeskides, commented:

"The key objective of this second phase of surface drilling at Clogau-St David's was to prove up the continuity of the Main Lode Extension we had identified during the drilling at the end of last year. We have now delivered emphatically on that aim, by intersecting the Main Lode Extension on every one of the 10 holes we have drilled in this phase. We are now projecting the Main Lode Extension to have a strike extent of 585 m and a depth extent of up to 63 m. This is shaping up to be a significant target."

"As we approach the end of this phase of drilling, we will be focusing next on a detailed technical and engineering evaluation of the most efficient access routes to the key gold targets we have identified through our drilling, namely the Llechfraith Lode, Main Lode Extension, Grandfathers Extension and 7-10 Extension."

Completion of Phase 2 Surface Drilling

The Phase 2 Surface Drilling Programme at Clogau-St David's, which commenced in April 2021, has now been completed. A total of ten holes have been drilled for a total of 1,475.6 metres.

The Phase 2 programme was designed to confirm the continuity of the westerly, potential 550-metre extension of the Clogau Main Lode (the "Main Lode Extension") which Alba identified during its October 2020 underground drilling. The significance of such a discovery is that the Main Lode is the source of most historic production at the Mine. If the continuity of the Main Lode Extension could be confirmed, this would become a primary zone for underground development and extraction.

All holes have successfully intersected the Main Lode Extension. As seen in Figure 1 (in the PDF version of this RNS), the Main Lode Extension is now projected to have a strike extent of 585 metres, and a depth extent of 63 metres below surface at its widest point.

In relation to the other zones targeted during this Phase 2 drilling, namely the depth extensions to the Grandfathers Lode ("Grandfathers Extension") and to the 7-10 Lode ("7-10 Extension"), holes JW001 and JW006 both intersected the Grandfathers Lode below the Llechfraith Level. It should also be noted that the bulk sampling from Grandfathers returned the highest value concentrates with values up to 461 g/t. Holes JW002 (2.0m at 171m) and JW010 (4.5m at 119m) intersected thick quartz veining below the 7-10 Lode. These intersections are considered to represent extensions of the Grandfathers and 7-10 Lodes systems and thus justify further exploration. Both existing Lodes are significant targets, with Grandfathers measuring approximately 80m on strike and 7-10 approximately 90m (see Figure 1 in the PDF version of this RNS). The drilling beneath these Lodes has now confirmed continuity of these Lodes below the existing Llechfraith level, some 57.6m beneath Grandfathers, and some 30m beneath 7-10.

For illustration, the intercepts from JW001-4 can be seen in Figure 2 (in the PDF version of this RNS).

One of the most recently drilled holes, JW008, was drilled to intercept the lode in between JW002 and JW003 in the eastern portion of the drilling programme. JW008 intercepted the best developed example of the Main Lode extension at approximately 10 m west of the intersection in JW002, which is also relatively well developed in terms of thickness. Preliminary observations indicate an intercept of 3.40 m from 49.90 m in JW008, which is preceded by a 0.80 m intercept at 49.00 m downhole (see Figure 4 in the PDF version of this RNS).

Galena has been identified in the intercept in JW008. This is an indicator mineral for gold-bearing veins and in the past has been associated with high gold grades in the John Hughes lode, an offshoot from the Main Lode/Jack Williams target structure.

JW009 was drilled on the same azimuth but at a slightly steeper angle to try and ascertain

whether this thick intercept marked the development of a previously unidentified payshoot. JW009 did intersect the lode, which was similar in size to the intercept in JW002. Initial core observations show a 0.60 m intercept from 109.70 m and a second 0.70 m from 111.40 m. This may suggest that the thickest section of the lode (i.e. the intercept in JW008) plunges to the south-west within the main vein structure itself, a phenomenon which has been historically observed elsewhere at Clogau.

JW010 was drilled slightly to the west of JW008 and was completed at 123.60 m. This final hole intercepted a relatively diffuse example of the Main Lode extension with stringer zones at 36 and 48 m. This clearly indicates that the potential payshoot identified in JW008 pinches to the west before the intersection of JW010, whilst remaining open east of JW002 in which there is still notable mineralisation (see Figure 2 in the PDF version of this RNS). Prior to completing JW010, the hole encountered further diffuse stringers over 4-5 m from 119.00 m. These are thought to show a branch of the 7-10 Lode which has seen minor trial development on the Llechfraith Level.

Alba's technical team will now concentrate on integrating the results of Phase 2 into the Company's geological model for Clogau-St David's, as well as cutting and assaying the core for gold content.

Table 1: Phase 2 Surface Drilling: Key Structural Intercepts

 
  Hole     Azimuth    Dip    Length        Lode Classification          Structural Intercepts 
                               (m) 
                                         Structure       Lode Name       Depth      Thickness 
                                                                                       (m) 
          --------  ------  -------  ----------------                 ----------  ------------ 
  GMOW_                                                  Main Lode 
  JW001     177.5    -42.9   240.30     Quartz Vein       Extension      33.78        0.98 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                                          Unnamed 
                                        Quartz Vein         Lode        164.20        0.52 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                                          Unnamed 
                                        Quartz Vein         Lode        168.60        0.75 
                                     ----------------  -------------  ----------  ------------ 
                                      Quartz Stringer 
                                          Network       Grandfathers    187.60        0.95 
                                     ----------------  -------------  ----------  ------------ 
                                      Quartz Stringer     Unnamed 
                                          Network           Lode        190.00        8.00 
                                     ----------------  -------------  ----------  ------------ 
                                                          Unnamed 
                                        Quartz Vein         Lode        202.00        2.00 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                                         Main Lode 
  GMOW_                                                   Extension 
  JW002      120      -45    204.30     Quartz Vein       offshoot       94.32        0.24 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                                         Main Lode 
                                        Quartz Vein       Extension      94.87        0.95 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                      Quartz Stringer 
                                          Network        7-10 Lode      171.00        2.00 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
  GMOW_                                                  Main Lode 
  JW003     143.6    -55.2   115.00     Quartz Vein       Extension      89.36        0.81 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                                         Main Lode 
                                                          Extension 
                                        Quartz Vein       offshoot       90.34        0.17 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
  GMOW_                                                  Main Lode 
  JW004     165.2     -46    205.40     Quartz Vein       Extension      35.08        0.93 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
  GMOW_                                                  Main Lode 
  JW005     166.1    -55.4   108.00     Quartz Vein       Extension      87.50        0.65 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
  GMOW_                                                  Main Lode 
  JW006     154.2    -44.1   189.00     Quartz Vein       Extension      38.00        0.05 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                      Quartz Stringer 
                                          Network       Grandfathers    121.00        0.30 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
  GMOW_                                                  Main Lode 
  JW007      154      -55    94.00      Quartz Vein       Extension      79.40        0.30 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                      Quartz Stringer     Unnamed 
                                          Network           Lode         92.00        0.75 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                                         Main Lode 
  GMOW_                                                   Extension 
  JW008      130      -45    69.00      Quartz Vein       offshoot       48.20        0.25 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                                         Main Lode 
                                                          Extension 
                                        Quartz Vein       offshoot       49.00        0.80 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                                         Main Lode 
                                        Quartz Vein       Extension      49.90        3.40 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                                         Main Lode 
  GMOW_                                                   Extension 
  JW009      130      -55    127.00     Quartz Vein       offshoot      109.70        0.60 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                                         Main Lode 
                                        Quartz Vein       Extension     111.40        0.70 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
  GMOW_                               Quartz Stringer    Main Lode 
  JW010      120      -45    123.60       Network         Extension      36.10        0.20 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
                                      Quartz Stringer    7-10 Lode 
                                          Network          branch       119.00        4.50 
          --------  ------  -------  ----------------  -------------  ----------  ------------ 
 

Update on Phase 2 Underground Drilling

To date, three drill holes have been completed in the Phase 2 Underground Drilling Programme.

Drill holes UG002 and UG003 were drilled in a northerly direction, and both intercepted the Main Lode extension, adding critical data on how this structure behaves in 3D. The drill trace for UG002 is shown in Figure 3 (in the PDF version of this RNS).

Both holes show relatively diffuse mineralisation, with the target structure presenting as two intercepts (0.18 m @ 86.08 m and 0.24 m @ 87.36 m) in UG002. In UG003 the first indications of the Lode system occur at 87.70 m (0.20 m thick), however the hole was deepened and encountered further mineralisation at 106.90 m with a prominent stringer zone at 108.90m for 0.40 m with the last intercept (0.10 m thick) in this zone finishing at 109.58 m. This indicates that there has been a split in the Main Lode extension into two branches which remains to be defined by UG004 and UG005 from the current drill pad.

Drill hole UG001 was targeted to the south of the Llechfraith workings in order to intercept potential target structures for future drilling programmes, and despite intercepting a 0.99 m thick mineralised zone from 42.24 m (analogous to the Canol Vein System from the Phase 1 Surface Drilling Programme), technical difficulties meant that the hole could not reach far enough to intercept a possible extension of the Sill Vein System. The drill trace for UG001 is shown in Figure 3 (in the PDF version of this RNS). Alba is confident that the additional holes planned to the south from the remaining two drill pads will be able to intersect this target and provide further critical data for Alba's geological model.

The underground drilling programme is currently paused but expected to resume again in due course. A further update will be provided on completion of the programme.

Table 2: Phase 2 Underground Drilling: Key Structural Intercepts

 
  Hole     Azimuth   Dip    Length       Lode Classification         Structural Intercepts 
                              (m) 
                                        Structure      Lode Name      Depth      Thickness 
                                                                                    (m) 
          --------  -----  -------  ----------------               ----------  ------------ 
  GMOW_                                                 Unnamed 
  UG001     127.3    -7.0   142.00     Quartz Vein        Lode        42.24        0.99 
          --------  -----  -------  ----------------  -----------  ----------  ------------ 
  GMOW_                                                Main Lode 
  UG002     350.0    -10    93.60      Quartz Vein      Extension     86.08        0.18 
          --------  -----  -------  ----------------  -----------  ----------  ------------ 
                                     Quartz Stringer   Main Lode 
                                         Network        Extension     87.36        0.24 
          --------  -----  -------  ----------------  -----------  ----------  ------------ 
  GMOW_                              Quartz Stringer   Main Lode 
  UG003      0.0     -7.0   114.00       Network        Extension     87.70        0.20 
          --------  -----  -------  ----------------  -----------  ----------  ------------ 
                                                       Main Lode 
                                       Quartz Vein      Extension    106.90        0.25 
          --------  -----  -------  ----------------  -----------  ----------  ------------ 
                                     Quartz Stringer   Main Lode 
                                         Network        Extension    108.90        0.40 
                                    ----------------  -----------  ----------  ------------ 
                                                       Main Lode 
                                       Quartz Vein      Extension    109.58        0.10 
          --------  -----  -------  ----------------  -----------  ----------  ------------ 
 

Dewatering of Llechfraith Shaft

As previously advised, Alba has applied to the competent regulator, Natural Resources Wales, for permission to divert the drainage water from the current Llechfraith drainage adit and to dewater the lower workings in the Llechfraith Shaft, in order to undertake underground drilling and bulk sampling directly from that zone.

Two permits have been applied for, a Transfer Permit which allows for the dewatering of the Llechfraith Shaft and the water to be transferred to a water treatment plant which will be established at the mine site, and a Discharge Permit which allows for the water to be discharged into a water course. All pumped water will be treated with flocculant and passed through a clarifier to remove any silt. Samples of the treated water will be sent for laboratory analysis throughout the dewatering process.

Alba is confident that the application process for the Discharge and Transfer Permits will be concluded shortly and the permits issued. As and when the permits are issued, it is expected that the dewatering of the Llechfraith Shaft will take around two weeks, after which Alba's technical team will be able to access the lower levels and assess the exposed lode. After dewatering, and while this exploration work is being undertaken, a constant discharge will be maintained in order to ensure dry workings.

By way of a recap, the Company regards the Llechfraith Lode, incorporating the Llechfraith Shaft, as a key target for future mining operations, not least given the positive results of the Phase 1 Surface Drilling Programme (see the Company's RNSs of 2 and 12 March 2021). At its deepest point, the Phase 1 drilling intersected the Llechfraith Lode structure 122 metres below the existing Llechfraith mine workings. Alba's initial geological modelling indicates that the total tonnage estimation for this newly identified lode structure is between 24,000 to 27,000 tonnes in the Lower Lode alone.

Next Steps

As we approach the end of this phase of drilling, the Company will be moving into a detailed evaluation of the optimal means to access the key target zones which have been identified from the completed drilling phases, in particular the Llechfraith Lode, Main Lode Extension, Grandfathers Extension and 7-10 Extension. This evaluation will be undertaken by Alba's technical team, headed by Senior Geologist and COO Mark Austin, with specialist input from Alba's preferred mining, geotechnical and confined space engineering contractors.

This announcement contains inside information for the purposes of the UK Market Abuse Regulation and the Directors of the Company are responsible for the release of this announcement.

Glossary

7-10 Lode: The 7-10 Lode is a parallel vein structure to the Main Lode, lying some 30-40m to the south of the Main Lode. The whole of the Llechfraith Level is developed on the 7-10 Lode.

Borehole or

   drillhole:        A hole drilled into bedrock using a diamond-coated bit to return core samples. 

Grandfathers: Grandfathers or Grandfathers Lode is a pay-shoot within the 7-10 Lode.

Jack Williams: The Jack Williams Stope is the most westerly mined portion of the Main Lode on the Ty'n-y-Cornel Level.

Intercept: A section of core in which a target lithology, structure or significant assay result has been identified.

Main Lode: The main quartz vein structure along which the majority of historic mining took place at Clogau-St David's. The Main Lode was mined from the Jack Williams Stope for approximately 300m eastwards to the Bryntirion Fault, on the other side of which it was mined over a strike of at least 150m at the St David's Mine.

Mineralisation: Any single mineral or combination of minerals occurring in a mass, or deposit, of economic interest. The term is intended to cover all forms in which mineralisation might occur, whether by class of deposit, mode of occurrence, genesis or composition.

Quartz vein: A sheet-like body consisting predominantly of the mineral quartz, which is known to host gold mineralisation in the Dolgellau Gold Belt.

   Stope:          A mined-out area along a lode structure from which ore has been extracted. 

Forward Looking Statements

This announcement contains forward-looking statements relating to expected or anticipated future events and anticipated results that are forward-looking in nature and, as a result, are subject to certain risks and uncertainties, such as general economic, market and business conditions, competition for qualified staff, the regulatory process and actions, technical issues, new legislation, uncertainties resulting from potential delays or changes in plans, uncertainties resulting from working in a new political jurisdiction, uncertainties regarding the results of exploration, uncertainties regarding the timing and granting of prospecting rights, uncertainties regarding the timing and granting of regulatory and other third party consents and approvals, uncertainties regarding the Company's or any third party's ability to execute and implement future plans, and the occurrence of unexpected events.

Without prejudice to the generality of the foregoing, uncertainties also exist in connection with the ongoing Coronavirus (COVID-19) pandemic which may result in further lockdown measures and restrictions being imposed by Governments and other competent regulatory bodies and agencies from time to time in response to the pandemic, which measures and restrictions may prevent or inhibit the Company from executing its work activities according to the timelines set out in this announcement or indeed from executing its work activities at all. The Coronavirus (COVID-19) pandemic may also affect the Company's ability to execute its work activities due to personnel and contractors testing positive for COVID-19 or otherwise being required to self-isolate from time to time.

Actual results achieved may vary from the information provided herein as a result of numerous known and unknown risks and uncertainties and other factors.

Competent Person Declaration

The information in this release that relates to Exploration Results has been reviewed by Mr Mark Austin. Mr Austin is a member of SACNASP (Reg. No. 400235/06), Fellow of The Geological Society and Fellow of the Geological Society of South Africa. He has a B.Sc. Honours in Geology with 38 years' experience.

Mark Austin has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration targets, Exploration Results, Mineral Resources and Ore Reserves', also known as the JORC Code. The JORC code is a national reporting organisation that is aligned with CRIRSCO. Mr Austin consents to the inclusion in the announcement of the matters based on his information in the form and context in which they appear.

For further information, please contact:

 
 Alba Mineral Resources plc 
  George Frangeskides, Executive Chairman    +44 20 3950 0725 
 
 Cairn Financial Advisers LLP (Nomad) 
  James Caithie / Liam Murray                +44 20 7213 0880 
 
 ETX Capital (Broker) 
  Thomas Smith                               +44 20 7392 1494 
 
 
 

Alba's Project and Investment Portfolio

 
 Project (commodity)            Location     Ownership 
 Mining Projects 
 Amitsoq (graphite)             Greenland    90% 
                               -----------  ---------- 
 Clogau (gold)                  Wales        90% 
                               -----------  ---------- 
 Gwynfynydd (gold)              Wales        100% 
                               -----------  ---------- 
 Inglefield (copper, cobalt, 
  gold)                         Greenland    100% 
                               -----------  ---------- 
 Limerick (zinc-lead)           Ireland      100% 
                               -----------  ---------- 
 Melville Bay (iron ore)        Greenland    51% 
                               -----------  ---------- 
 TBS (ilmenite)                 Greenland    100% 
                               -----------  ---------- 
 Oil & Gas Investments 
 Horse Hill (oil)               England      11.765% 
                               -----------  ---------- 
 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

DRLDDGDRLXBDGBI

(END) Dow Jones Newswires

July 19, 2021 02:00 ET (06:00 GMT)

Alba Mineral Resources (LSE:ALBA)
Historical Stock Chart
From Mar 2024 to Apr 2024 Click Here for more Alba Mineral Resources Charts.
Alba Mineral Resources (LSE:ALBA)
Historical Stock Chart
From Apr 2023 to Apr 2024 Click Here for more Alba Mineral Resources Charts.