TIDMFND 
 
Quarterly Report for the Period Ending December 31st 2008 
 
Highlights 
 
During the quarter, efforts were  focused on completion of the  Wetar 
Copper demonstration plant,  with all other  activities reduced to  a 
minimum expenditure basis to conserve funds. Delays in  commissioning 
of the Wetar plant,  mainly related to slow  logistics of the  remote 
project location, and  the weakness of  the Australian Dollar  during 
the period necessitated that Finders ("the Company") raise additional 
working capital which was achieved by means of convertible notes  and 
Directors loans. 
 
 
Wetar Copper Project 
 
 
  * Grade control and mining has commenced and is proceeding 
    according to plan. 
  * First heap completed with 21,000 tonnes, grading 2.9% Cu stacked 
    and under irrigation. 
  * The 5 tonnes per day SX-EW demonstration plant is mechanically 
    and electrically complete. 
 
            - Commissioning of SX and reagent additions ongoing. 
            - EW is  ready for powering up  under load with first  Cu 
plating to commence in the first week of February 
              2009. 
            - Heap showing excellent  percolation and strong  initial 
leaching of Cu, with off-flow solution up to 19g/l Cu 
 
 
*          The Feasibility Study for a full scale 20-25,000 tonnes 
  per annum plant has been revised to include 
             assessment of newly available second hand plant which 
gives scope for 
           - significant reductions of capital cost 
           - reduced lead times to full production 
 
Ojolali Gold-Silver Project 
 
*          Reduced activity to conserve funds. High grade silver 
  assays from channel samples strongly support the 
             concept of a zone of supergene enriched silver 
mineralization at the Tambang deposit. 
 
 
Corporate 
 
*          Robert Thomson accepts position on Finders Board as 
  Executive Director, Development 
*          Placement of 8,650,020 ordinary shares to raise 
  approximately AUD $5.4 million 
*          A Share Purchase Plan (SPP) raised AUD$163,000 leading to 
  the issue of 271,657 new shares 
 
 
Subsequent Events 
 
*          Successful fund-raising of up to US$1.5m by means of 
  convertible note with RCF 
 
Wetar Copper Project 
Finders Resources  Limited  93%  and  earning  through  expenditure, 
subject to audit 
 
Background Information 
As part of an ongoing  definitive feasibility study, a  demonstration 
SX-EW plant with 5  tonnes per day copper  cathode capacity is  being 
installed and is permitted to process 100,000 tonnes of ore from  the 
Kali Kuning deposit.  The Company is targeting commercial  production 
of 20-25,000  tonnes  per year  cathode  by early  2010,  subject  to 
schedules for engineering design work and project funding. 
 
Demonstration Plant 
The Company has made excellent progress during the Quarter. 
Open pit mining  of the  test pit  is ongoing  with daily  production 
around 1,250  tonnes  per day  from  a number  of  development  faces 
designed to provide mine feed which replicates the composition of ore 
types during  the  first  three  years  of  the  planned  full  scale 
operation.  Recent ROM ore has averaged over 4% Cu. 
 
Crushing and  stacking  rates  are regularly  exceeding  by  25%  the 
budgeted forecast of 100 tonnes per hour.  The first of three planned 
test heaps,  6.5m  high and  containing  21,000 tonnes  grading  2.9% 
copper, is stacked and under irrigation. Stacking of the second  test 
heap cell, to be 8m high, is underway. 
 
Mined grades, heap  percolation rates and  initial take-up of  copper 
into the leach solutions  are all in  line with predictions.   Copper 
grades in leach solution have reached 19 g/l Cu, but a more complete 
picture of leach  performance against model  predictions is  expected 
once recirculation of raffinate from the SX plant commences. 
 
Construction of the 5 tonnes per day Wetar Copper demonstration plant 
is now complete and wet testing of the SX circuit underway.   Initial 
plating of cathode is now expected during the first week of  February 
2009. The Company forecasts that  after an initial ramp-up period  of 
8-10 days, the plant would be able to sustain a nameplate capacity of 
5 tonnes copper cathode per day. 
 
Feasibility Study 
A number  of SX-EW  plants  have become  available for  purchase  and 
Finders is undertaking detailed assessment of two opportunities  with 
respect to use  of these  plants for the  planned expanded  20-25,000 
tonne cathode copper per year operations. 
 
In light of these opportunities,  the engineering and process  design 
work  for  a  new  plant  has  been  postponed  within  the   current 
feasibility study. 
 
However, on the basis  of work completed to  date, and using  current 
landed fuel prices  in Indonesia, the  estimated operating costs  for 
the full  scale plant  are  around US$0.70  per  lb Cu,  putting  the 
project on par  with the  average operating  cost per  lb for  copper 
producers globally.  The Directors believe the project remains robust 
even at current  depressed copper  prices and is  positioned to  take 
advantage of the future recovery of the global economy. 
 
Finders consider it is  prudent to finalise  the bankable study  when 
there is clarity on the SX-EW  plant purchase options (used or  new), 
and once operating data from the test heaps is sufficiently robust to 
ensure that the final  study has minimal  capital cost and  technical 
risk. 
 
Mining studies  are ongoing,  with a  site visit  by Australian  Mine 
Design  and  Development  Pty   Ltd  (AMDAD)  and  potential   mining 
contractors completed during the period. 
 
A revised  mining schedule  is being  designed on  the basis  of  new 
information from  the  revised resource  estimate  and  metallurgical 
modeling of ore types (see below) and earthworks requirements for the 
commercial scale leach pads. 
Environmental studies are  ongoing with  a first draft  of the  ANDAL 
document completed  subject  to revision  of  the mine  schedule  and 
layout options for the SX-EW plant. 
Resource Upgrade 
A new resource estimate has been independently estimated by Hellman & 
Schofield Pty  Ltd  and  reported  according to  the  JORC  Code  and 
Guidelines. The resource estimates (Table 1) for both the Kali Kuning 
and Lerokis massive sulphide deposits have been upgraded to +98% JORC 
Measured and Indicated categories.  This  is based on the results  of 
62 new diamond and reverse circulation drill holes. 
 
The combined resource estimate for Kali Kuning and Lerokis, at a 0.5% 
copper cutoff, of 9 Mt at 2.4% copper, or 218,000 tonnes of contained 
copper, represents  a  10%  reduction in  total  copper  compared  to 
previously announced estimates, due largely to the tighter control of 
the massive sulphide  boundaries from closer  spaced drilling at  the 
Lerokis deposit.  It is expected that almost all of the Measured  and 
Indicated Resources  will be  converted into  Ore Reserves  upon  the 
completion of further mine planning and feasibility work. 
 
Based on the new drilling  the Kali Kuning massive sulphide  resource 
has been re-classified into  three metallurgical sub-types,  Leached, 
Transition zone material and Primary massive sulphide, (Table 2). The 
Leached and Transition  types reflect incipient  in-situ leaching  of 
the massive sulphide unit by natural groundwater. The Transition zone 
material, although  of  lower  copper grade  than  the  main  Primary 
massive sulphide, (1.5% Cu vs 2.9%Cu) contains a higher proportion of 
readily leachable copper minerals  which translates to  significantly 
faster leach  rates  for  this  material,  as  described  below.  The 
Transition zone occurs at the highest levels of the deposit and  will 
comprise a major  proportion of  early mined  mineralization for  the 
expanded Wetar copper project. 
 
 
 
+--------------------------------------------------------------------+ 
|Table 1. Wetar project Resource Estimates      (Note:  Rounding     | 
|errors may cause inaccuracies in following tables)                  | 
|                                                                    | 
|                                                                    | 
|--------------------------------------------------------------------| 
|0.5% Cu  cut-off   |       |    |             |Attributable| 92.8%* | 
|grade              |       |    |             |            |        | 
|-------------------+-------+----+-------------+------------+--------| 
|        |Category  |Tonnes |Cu% |Cont. Cu (KT)| Tonnes (M) |Cont. Cu| 
|        |          |  (M)  |    |             |            |  (KT)  | 
|--------+----------+-------+----+-------------+------------+--------| 
|Kali    |Measured  |  5.2  |2.6 |     133     |    4.8     |  123   | 
|Kuning  |          |       |    |             |            |        | 
|--------+----------+-------+----+-------------+------------+--------| 
|        |Indicated |  0.9  |2.5 |     22      |    0.8     |   20   | 
|        |----------+-------+----+-------------+------------+--------| 
|        |Inferred  |  0.1  |1.8 |      2      |    0.1     |   2    | 
|        |----------+-------+----+-------------+------------+--------| 
|        |Total     |  6.1  |2.5 |     156     |    5.7     |  145   | 
|--------+----------+-------+----+-------------+------------+--------| 
|Lerokis |Measured  |  2.1  |2.4 |     51      |    1.9     |   47   | 
|--------+----------+-------+----+-------------+------------+--------| 
|        |Indicated |  0.5  |2.1 |     10      |    0.5     |   9    | 
|        |----------+-------+----+-------------+------------+--------| 
|        |Inferred  |  0.1  |1.4 |      2      |    0.1     |   2    | 
|        |----------+-------+----+-------------+------------+--------| 
|        |Total     |  2.7  |2.3 |     62      |    2.5     |   58   | 
|-------------------+-------+----+-------------+------------+--------| 
|Overall            |  8.8  |2.4 |     218     |    8.2     |  203   | 
+--------------------------------------------------------------------+ 
 
*Attributable:  ownership is based on estimates of project 
expenditure to end-November 2008 and is subject to final audit. 
 
 
+-------------------------------------------------------------------+ 
| Table 2. Breakdown of Kali Kuning by metallurgical zone           | 
|                                                                   | 
|-------------------------------------------------------------------| 
|                  |  Zone            | Tonnes (M) | Cu% | Cont. Cu | 
|                  |                  |            |     |   (KT)   | 
|------------------+------------------+------------+-----+----------| 
| Massive Sulphide | Leached Zone     |    0.1     | 0.7 |    1     | 
|------------------+------------------+------------+-----+----------| 
|  0.5% Cu         | Transition  Zone |    1.2     | 1.5 |    17    | 
| cut-off grade    |------------------+------------+-----+----------| 
|                  | Primary Zone     |    4.8     | 2.9 |   138    | 
|                  |------------------+------------+-----+----------| 
|                  | Total            |    6.1     | 2.5 |   156    | 
+-------------------------------------------------------------------+ 
 
 
An additional 700,000  t of  mineralized clay  altered tuff,  grading 
0.9% Cu, which forms the wallrock  to the massive sulphide, has  been 
excluded  from   the   resource  estimates   because   of   uncertain 
metallurgical response. 
 
Metallurgy 
Given the higher grade of the transitional mineralisation from recent 
drilling,  metallurgical  test  work   on  this  material  has   been 
instigated at site  with two new  column tests.  Though  still at  an 
early stage,  the results  are very  encouraging with  73-95%  copper 
recovery achieved  within  31 days,  subject  to final  mass  balance 
calculations.   These  results  are  significant  for  the  expansion 
project, since  the  SX-EW  plant  is  likely  to  achieve  nameplate 
capacity much  faster  than  previously  expected  due  to  the  fast 
leaching nature of the Transition mineralisation. 
 
The initial two 1.8m columns using  fresh ore material from the  Kali 
Kuning test pit confirm that copper recovery is faster and PLS grades 
higher with higher acid concentrations with 74 & 86% copper  recovery 
achieved within 131 days, subject to final mass balance calculations. 
 
The figure below shows  time-copper recovery curves  for a number  of 
column tests completed  under different conditions  for the two  main 
ore types, the primary (red) and the transitional (purple) zones  and 
a modelled recovery curve for 8m high heaps (orange). 
 
New Indonesian Mining Law 
The Company advises that it welcomes the new Indonesian mining  law. 
The Wetar project will the  first copper mining project in  Indonesia 
to produce  cathode metal  and,  as such,  is  aligned with  the  new 
obligation to process and purify mining products within the country. 
Our work to date under the KP title system in Indonesia had led us to 
develop a strong working relationship with the same local  government 
authorities who will administer the tenement system as required under 
the  new  law,  and  we  will  continue  to  benefit  from   existing 
relationships established with these agencies.  The basis of the  new 
tenement system has similar stages and approval mechanisms to the one 
we  currently  work  under.    Indonesian  Government  copper   metal 
royalties will apply to the Wetar project and these are currently 4%. 
 
Ojolali Project 
Finders Resources Limited 72% with option 
 
Background Information 
Finders believe  that the  Ojolali project  has strong  potential  to 
generate short-term cash flow by open pit CIL/CIP development of  the 
gold resource at the Jambi Oxide gold deposit (Table 3.) 
 
Table 3. Jambi Resource Estimates 
Cut     Indicated      Inferred         Total      Contained Attrib. 
off                                                            FND 
 Au   Mt   Au    Ag  Mt   Au   Ag   Mt   Au    Ag   Au koz   (72%) Au 
g/t        g/t  g/t      g/t  g/t        g/t  g/t              koz 
0.5  2.98  1.1  8.3  1.1 0.9  5.7  4.08 1.05  7.6     138       99 
1.0  1.13 1.74  8.5  0.3 1.6  6.7  1.43 1.71  8.1     79        57 
 
 
Finders has previously  announced Inferred Resources  at the  Tambang 
Prospect (7.9 Mt @ 167g/t Ag and 0.7 g/t Au at a 1 g/t Au  equivalent 
cut-off  using  drilling  data  from  a  previous  explorer).   Other 
prospects have outstanding potential for the discovery of  additional 
resources using  modern  geophysical  techniques  to  optimize  drill 
targeting. 
 
Recent Activities 
Activities during the  period have focused  on further evaluation  of 
prospect  areas  with  strongly   anomalous  soil  geochemistry   and 
extending the soil sampling program. 
 
During the  period a  further  9.5 line  km  of soil  traverses  were 
completed with follow-up trenching and channel sampling over 500m at 
25 locations. The main focus was assessment of the oxide potential of 
the Tambang vein system  and the zone of  5 sub-parallel vein  swarms 
(2-16m in width) at Way Neki,  the southern continuation of the  Batu 
Kuning prospect. 
 
The samples were  taken as part  of a systematic  program of  channel 
sampling from the oxidized near surface portion of the major  Tambang 
vein system (see  map).  This program  is aimed at  testing for  high 
grade supergene enriched silver values  at the base of oxidation  and 
preliminary  results  strongly  support  that  concept.  Assays  from 
additional channel samples are awaited. 
 
Preliminary results from Tambang are regarded by Finders as highly 
encouraging (Table 4). 
 
Table 4. Significant channel sample assays from Tambang 
 CTBG002    444159    9480615    2.0    0.5    315 
 CTBG003    444200    9480409    2.0    1.4    450 
 CTBG004    444203    9480349    2.0    0.5    109 
  CTBG22    443864    9480784    2.0    1.8    209 
 
 
Corporate 
 
Board Appointment 
Robert Thomson  accepted a  position on  the Finders  Board and  this 
appointment was made  effective on  6th Jan  2009. Rob's  appointment 
brings great experience in successful and timely project  development 
to the company for the forthcoming expansion of Wetar Copper to  full 
scale operations.  Rob was previously the Company's General  Manager, 
Development  and  has   the  prime   responsibility  for   successful 
completion of feasibility studies  and subsequent development of  the 
Company's Wetar copper project. Rob brings to the Finders  Management 
team a  strong track  record  of delivering  successful  construction 
projects in  challenging  south-east Asian  environments  notably  at 
Kingsgate's Chatree Gold  Mine in  Thailand and  Oxiana's Sepon  Gold 
Mine. 
 
Corporate Structure 
Allotment of shares for a placement approved by Finders  shareholders 
on 16 October  2008 was  completed on  23 October  2008. Gross  funds 
raised under the placement  totaled approximately A$5.4 million  from 
the issue of 8,650,020 new shares. 
 
The placement  consisted of  6,925,020 shares  issued at  A$0.60  per 
share through RFC Corporate Finance  Ltd and 1,725,000 shares  issued 
to parties in the UK at GBP0.28 per share through Finncap, Finders  AIM 
broker. 
In addition, on similar terms to the placement, the Company offered a 
Share Purchase Plan (SPP). Following closure of the SPP, 271,657 new 
shares were issued to raise approximately AUD$163,000. 
 
 
Table 5. Current Capital Structure 
Type of Security       Exercise Price Expiry Date   Number on Issue 
Fully Paid Ordinary 
Shares ("Shares") 
Shares on issue at 30                                     74,921,825 
September 2008 
New Shares Issued                                           8,650,020 
(Placement) 
New Shares Issued 
(SPP)                                             271,657 
New Shares Issued 
(Fee)                                             208,333 
Shares on Issue at 31                                     84, 051,835 
December 2008 
Unlisted Options 
                       A$0.50         March 20,             3,090,367 
                                      2009 
                       24p            March 22,             1,322,881 
                                      2009 
                       A$0.6875       June 13, 
                                      2010        500,000 
Total Unlisted Options                                      4,913,248 
on issue 
 
 
Cash Management 
 
The company was severely impacted  during the quarter by the  effects 
of  the  world  economic  crisis,  in  particular  the  fall  in  the 
Australian Dollar compared to the US$ and the Indonesian Rupiah. 
 
 
 
A delayed revenue stream (at lower than projected copper prices) also 
contributed to place pressure on  the company's cash resources.   The 
Board has responded to this situation with a number of initiatives to 
strengthen the Company's working capital position. 
 
1.       Arranging a placement of up to US$1.5 million in convertible 
notes to RCF (see subsequent events, below). 
2.       Suspending work on all non-essential programmes, with  total 
focus on completion of the WetarDemonstration 
          plant 
3.       Voluntary reductions in salary  by Directors and key  senior 
staff 
4.       Provision of loan funds to the company by certain  Directors 
of A$714,000 (see subsequent events, below) 
 
The company expects to generate cash flow from copper cathode sales 
from the end of February, 2009.  In addition, it has also arranged 
advance payment of up to A$1.5 million following commencement of 
production at Wetar under an agreement linked to a copper off-take 
contract. 
 
With the fall in the copper price, the Company's revenue projections 
for cathode sales in 2009 have been revised downwards; but, with 
estimated operating cost for the Wetar demonstration plant of around 
US$1/lb Cu, the Directors expect that the plant's operating margin 
will be comfortably positive on the basis of current average copper 
price estimates from a consensus of analysts (Bloomberg Jan 15: CY 
US$1.495/lb Cu). 
 
The Directors believe that with the planned expansion of the Wetar 
Copper Project by early 2010, the Company is placed well to benefit 
from positive changes in the commodity prices as the global economy 
recovers in future months. 
 
Subsequent Events 
On 16th January 2009,  Finders announced that it  has entered into  a 
Convertible  Note  Facility  Agreement  ("Facility")  with   Resource 
Capital Fund IV L.P. ("RCF").  Under the Facility, RCF has agreed  to 
provide the company with US$1.5 million, of which US$1.0 million will 
be made  available on  satisfaction  of certain  standard  conditions 
precedent with the balance to  be made available, subject to  further 
conditions precedent, on  or before  15 March  2009. The  convertible 
note has a  term of 3  years, is convertible  into Finders shares  at 
A$0.40 per share and interest at 12% per annum is payable quarterly. 
 
The  Company  has  also  entered  into  loan  agreements  with   four 
directors,  Messrs  Russell  Fountain,  Christopher  Farmer,   Robert 
Thomson and Stephen  de Belle  pursuant to which  the directors  have 
lent the Company a total of A$714,000. 
 
The mining exploration entity quarterly report (Appendix 5b) is 
appended. 
 
 
 
Chris Farmer 
 
Managing Director 
 
Further details for  all projects including  location maps,  tenement 
schedules and  technical descriptions  may be  found on  the  Finders 
website at www.findersresources.com 
 
 
 
For further information please contact 
 
Finders Resources Ltd: 
Russell         Executive Chairman          +61 2 9211 8299 
Fountain 
Chris Farmer    Managing Director           info@findersresources.com 
 
Financial PR: 
Doug Macdonald  Capital      Group      (in +61 424 255 959 
                Australia) 
Nick Elwes      College Hill (in the UK)    +44 20 7457 2020 
 
RFC Corporate Finance Ltd - Nomad: 
Rob Adamson     Managing Director           +61 2 9250 0000 
Stuart Laing    Executive Director          +61 8 9480 2500 
 
FinnCap -  Finders' Broker for the AIM market: 
Mathew Robinson Corporate Finance Director  +44 20 7600 1658 
Joe Lunn        Analyst                     +44 20 7600 1658 
 
 
Disclaimer 
 
The information in this report that relates mineral resource 
estimation is based on work completed by Dr Phillip Hellman who is a 
full time employee of Hellman and Schofield Pty Ltd and a Fellow of 
the Australian Institute of Geoscientists.  Dr Hellman has sufficient 
experience which is relevant to the style of mineralisation and type 
of deposit under consideration and to the activity which he is 
undertaking to qualify as a Competent Person as defined in the 2004 
Edition of the 'Australasian Code for Reporting of Exploration 
Results, Mineral Resources and Ore Reserves' and as a Qualified 
Person as defined in the AIM Rules. Dr Hellman consents to the 
inclusion in the report of the matters based on his information in 
the form and context in which it appears. Estimates for Kali Kuning 
are based on a data set from which some diamond drill holes have been 
excluded due to poor recovery of copper mineralisation as evidenced 
by neighbouring RC holes. 
 
Geological information in this announcement and comments relating  to 
exploration  potential  and  the  project  in  general  is  based  on 
information  compiled  by  Dr  Russell  Fountain,  who  also  accepts 
responsibility for  the data  on  which the  resource is  based.   Dr 
Fountain is a Director  of Finders and a  Fellow of the  Australasian 
Institute of  Geoscientists. Dr  Fountain has  sufficient  experience 
that is  relevant  to  the  styles of  mineralisation  and  types  of 
deposits  under  consideration  and  to  the  activity  that  he   is 
undertaking to qualify  as Competent  Person as defined  in the  JORC 
Code. He  consents  to the  inclusion  in this  announcement  of  the 
matters based on  his information in  the form and  context in  which 
they appear. All assaying of drill core samples was undertaken by the 
ITS laboratory in Jakarta. ITS is one of the world's largest  product 
and commodity  testing, inspection  and certification  organizations. 
The  Jakarta  laboratory  is  ISO  17025  accredited  and  employs  a 
Laboratory Information Management System (LIMS) for sample  tracking, 
quality control and reporting. 
 
Appendix 5B 
 
             Mining exploration entity quarterly report 
 
 
Name of entity 
FINDERS RESOURCES LIMITED 
 
 
 
ABN              Quarter ended ("current quarter") 
82 108 547 413           31 DECEMBER 2008 
 
 
 
Consolidated statement of cash flows 
 
 
                                                 Current Year to date 
Cash flows related to operating activities       quarter (.6.months) 
                                                 $A'000     $A'000 
1.1  Receipts from product sales and related 
     debtors 
     Payments for (a) exploration and evaluation  (49)      (320) 
1.2                       (b) development        (1,044)   (6,566) 
                          (c) production            -         - 
                          (d) administration      (539)    (1,614) 
1.3  Dividends received 
1.4  Interest and other items of a similar         11         51 
     nature received 
1.5  Interest and other costs of finance paid 
1.6  Income taxes paid 
1.7  Other (provide details if material) 
     Net Operating Cash Flows                    (1,621)   (8,449) 
 
     Cash flows related to investing activities 
     Payment for purchases of:          (a) 
     prospects                                    (325)     (325) 
1.8                                        (b)      -         - 
     equity investments                          (4,720)   (4,767) 
                                           (c) 
     other fixed assets 
     Proceeds from sale of:     (a) prospects 
                                           (b) 
1.9  equity investments 
                                           (c) 
     other fixed assets 
1.10 Loans to other entities 
1.11 Loans repaid by other entities 
1.12 Other (provide details if material) 
     Net investing cash flows                    (5,045)   (5,092) 
1.13 Total operating and investing cash flows    (6,666)   (13,541) 
     (carried forward) 
 
 
 
 
Appendix 5B 
Mining exploration entity quarterly report 
 
 
 
1.13 Total operating and investing cash          (6,666)     (13,541) 
     flows (brought  forward) 
 
     Cash flows related to financing 
     activities 
1.14 Proceeds from issues of shares,              5,357       5,357 
     options, etc. 
1.15 Proceeds from sale of forfeited shares 
1.16 Proceeds from borrowings                      429        1,711 
1.17 Repayment of borrowings                      (34)         (34) 
1.18 Dividends paid 
1.19 Other (provide details if material) 
 
     Net financing cash flows                     5,752       7,034 
 
     Net increase (decrease) in cash held         (914)      (6,507) 
 
1.20 Cash at beginning of quarter/year to          785        4,988 
     date 
1.21 Exchange rate adjustments to item 1.20        547        1,937 
1.22 Cash at end of quarter                        418         418 
 
Payments to directors of the entity and associates of the directors 
Payments to related entities of the entity and associates of the 
related entities 
 
                                                    Current quarter 
                                                        $A'000 
                      Aggregate amount of payments 
1.23                  to the parties included in          316 
                      item 1.2 
                      Aggregate amount of loans to 
1.24                  the parties included in item        NIL 
                      1.10 
1.25                  Explanation necessary for an understanding of 
                      the transactions 
                      Payments are for salaries, directors and 
                      consulting fees. 
 
Non-cash financing and investing activities 
 
2.1 Details of financing and investing transactions which have had a 
    material effect on consolidated assets and liabilities but did 
    not involve cash flows 
    Company issued 208,333 ordinary fully paid shares on 8 December 
    2008 for 60 cents each in payment of consulting fees. 
 
 
 
2.2 Details of outlays made by other entities to establish or 
    increase their share in projects in which the reporting entity 
    has an interest 
 
    NONE 
 
 
 
 
Appendix 5B 
Mining exploration entity quarterly report 
 
Financing facilities available 
Add notes as necessary for an understanding of the position. 
 
 
                                    Amount available Amount used 
                                         $A'000        $A'000 
3.1 Loan facilities (USD 5,000,000)      7,823          7,823 
3.2 Credit standby arrangements           NIL            NIL 
 
 
Estimated cash outflows for next quarter * 
 
                               $A'000 
 
4.1 Exploration and evaluation  170 
 
4.2 Development                3,500 
 
 
    Total                      3,670 
 
 
 
 
+-------------------------------------------------------------------+ 
|                                                                   | 
| Note:                                                             | 
|                                                                   | 
| On 16th January 2009 the Company announced a US$1.5m (A$2.25m)    | 
| convertible note facility and Directors loans totaling A$714,000. | 
|                                                                   | 
| The company expects to generate cashflow from copper cathode      | 
| sales from the end of February, 2009.  In addition, it has also   | 
| arranged advance payment of up to A$1.5 million following         | 
| commencement of production at Wetar under an agreement linked to  | 
| a copper off-take contract.                                       | 
|                                                                   | 
+-------------------------------------------------------------------+ 
 
 
Reconciliation of cash 
 
Reconciliation of cash at the end of the quarter (as Current Previous 
shown in the consolidated statement of cash flows)   quarter quarter 
to the related items in the accounts is as follows.  $A'000   $A'000 
5.1       Cash on hand and at bank                     418     785 
5.2       Deposits at call 
5.3       Bank overdraft 
5.4       Other (provide details) 
          Total: cash at end of quarter (item 1.22)    418     785 
 
 
 
Appendix 5B 
Mining exploration entity quarterly report 
 
Changes in interests in mining tenements 
 
 
                           Tenement  Nature of  Interest at Interest 
                           reference  interest   beginning  at end of 
                                     (note (2)) of quarter   quarter 
6.1 Interests in mining 
    tenements 
    relinquished, reduced     NIL                   NIL        NIL 
    or lapsed 
 
 
6.2 Interests in mining 
    tenements acquired or 
    increased                 NIL                   NIL        NIL 
 
 
 
 
Issued and quoted securities at end of current quarter 
Description includes rate of interest and any redemption or 
conversion rights together with prices and dates. 
 
 
                          Total      Number   Issue price Amount paid 
                          number     quoted       per       up per 
                                               security    security 
                                                (cents)     (cents) 
                                               (see note   (see note 
                                                  3)          3) 
7.1  Preference 
     +securities           N/A 
     (description) 
7.2  Changes during 
     quarter 
     (a)  Increases 
     through issues 
     (b)  Decreases        N/A 
     through returns of 
     capital, 
     buy-backs, 
     redemptions 
7.3  +Ordinary          84,051,835 83,870,017 
     securities 
7.4  Changes during 
     quarter 
     (a)  Increases     9,130,010  9,130,010    60cents     60cents 
     through issues        NIL        NIL 
     (b)  Decreases 
     through returns of 
     capital, buy-backs 
7.5  +Convertible debt 
     securities            N/A 
     (description) 
7.6  Changes during 
     quarter 
     (a)  Increases 
     through issues        N/A 
     (b)  Decreases 
     through securities 
     matured, converted 
7.7  Options                                   Exercise   Expiry date 
     (description and   3,090,367     NIL        price    20.03.2009 
     conversion factor) 1,322,881     NIL       50cents   22.03.2009 
                         500,000      NIL       24pence   13.06.2010 
                                              68.75cents 
7.8  Issued during         NIL        NIL 
     quarter 
7.9  Exercised during      NIL        NIL 
     quarter 
7.10 Expired during        NIL        NIL 
     quarter 
7.11 Debentures 
     (totals only) 
7.12 Unsecured notes 
     (totals only) 
 
 
 
 
Appendix 5B 
Mining exploration entity quarterly report 
 
Compliance statement 
 
1          This statement has been prepared under accounting policies 
which comply with accounting standards as defined in the Corporations 
Act or other standards acceptable to ASX (see note 4). 
 
2          This statement does  /does not* (delete  one) give a  true 
and fair view of the matters disclosed. 
 
 
 
Sign                          here: 
............................................................ 
Date: . 30th January 2009 
(Director) 
 
 
 
Print         name:                       ....Christopher         Ben 
Farmer........................... 
 
Notes 
 
1              The quarterly  report provides a  basis for  informing 
the market how  the entity's  activities have been  financed for  the 
past quarter and the effect on its cash position.  An entity  wanting 
to disclose additional information is encouraged to do so, in a  note 
or notes attached to this report. 
 
2              The "Nature of interest" (items 6.1 and 6.2)  includes 
options in respect of interests in mining tenements 
                acquired, exercised  or lapsed  during the  reporting 
period.  If the entity is involved in a joint venture 
               agreement  and there  are conditions  precedent  which 
will change its percentage interest in a mining 
               tenement, it should disclose the change of  percentage 
interest and conditions precedent in the list required 
               for items 6.1 and 6.2. 
 
3               Issued and  quoted securities   The issue  price  and 
amount paid up is not required in items 7.1 and 7.3 
                for fully paid securities. 
 
4              The  definitions in,  and  provisions of,  AASB  1022: 
Accounting for Extractive Industries and AASB 
                1026: Statement of Cash Flows apply to this report. 
 
5              Accounting Standards ASX will accept, for example, the 
use of International Accounting Standards for 
               foreign  entities.   If  the  standards  used  do  not 
address a topic, the Australian standard on that topic (if any) 
               must be complied with. 
 
Quarterly Report for the Period Ending December 31st 2008 
 
Highlights 
 
During the quarter, efforts were  focused on completion of the  Wetar 
Copper demonstration plant,  with all other  activities reduced to  a 
minimum expenditure basis to conserve funds. Delays in  commissioning 
of the Wetar plant,  mainly related to slow  logistics of the  remote 
project location, and  the weakness of  the Australian Dollar  during 
the period necessitated that Finders ("the Company") raise additional 
working capital which was achieved by means of convertible notes  and 
Directors loans. 
 
 
Wetar Copper Project 
 
 
  * Grade control and mining has commenced and is proceeding 
    according to plan. 
  * First heap completed with 21,000 tonnes, grading 2.9% Cu stacked 
    and under irrigation. 
  * The 5 tonnes per day SX-EW demonstration plant is mechanically 
    and electrically complete. 
 
           -  Commissioning of SX and reagent additions ongoing. 
           -  EW is  ready for powering up  under load with first  Cu 
plating to commence in the first week of February 
              2009. 
           - Heap showing  excellent percolation  and strong  initial 
leaching of Cu, with off-flow solution up to 19g/l Cu 
 
 
*          The Feasibility Study for a full scale 20-25,000 tonnes 
  per annum plant has been revised to include 
             assessment of newly available second hand plant which 
gives scope for 
              -  significant reductions of capital cost 
              -  reduced lead times to full production 
 
Ojolali Gold-Silver Project 
 
*          Reduced activity to conserve funds. High grade silver 
  assays from channel samples strongly support the 
             concept of a zone of supergene enriched silver 
mineralization at the Tambang deposit. 
 
 
Corporate 
 
*          Robert Thomson accepts position on Finders Board as 
  Executive Director, Development 
*          Placement of 8,650,020 ordinary shares to raise 
  approximately AUD $5.4 million 
*          A Share Purchase Plan (SPP) raised AUD$163,000 leading to 
  the issue of 271,657 new shares 
 
 
Subsequent Events 
 
*          Successful fund-raising of up to US$1.5m by means of 
  convertible note with RCF 
 
Wetar Copper Project 
Finders Resources  Limited  93%  and  earning  through  expenditure, 
subject to audit 
 
Background Information 
As part of an ongoing  definitive feasibility study, a  demonstration 
SX-EW plant with 5  tonnes per day copper  cathode capacity is  being 
installed and is permitted to process 100,000 tonnes of ore from  the 
Kali Kuning deposit.  The Company is targeting commercial  production 
of 20-25,000  tonnes  per year  cathode  by early  2010,  subject  to 
schedules for engineering design work and project funding. 
 
Demonstration Plant 
The Company has made excellent progress during the Quarter. 
Open pit mining  of the  test pit  is ongoing  with daily  production 
around 1,250  tonnes  per day  from  a number  of  development  faces 
designed to provide mine feed which replicates the composition of ore 
types during  the  first  three  years  of  the  planned  full  scale 
operation.  Recent ROM ore has averaged over 4% Cu. 
 
Crushing and  stacking  rates  are regularly  exceeding  by  25%  the 
budgeted forecast of 100 tonnes per hour.  The first of three planned 
test heaps,  6.5m  high and  containing  21,000 tonnes  grading  2.9% 
copper, is stacked and under irrigation. Stacking of the second  test 
heap cell, to be 8m high, is underway. 
 
Mined grades, heap  percolation rates and  initial take-up of  copper 
into the leach solutions  are all in  line with predictions.   Copper 
grades in leach solution have reached 19 g/l Cu, but a more complete 
picture of leach  performance against model  predictions is  expected 
once recirculation of raffinate from the SX plant commences. 
 
Construction of the 5 tonnes per day Wetar Copper demonstration plant 
is now complete and wet testing of the SX circuit underway.   Initial 
plating of cathode is now expected during the first week of  February 
2009. The Company forecasts that  after an initial ramp-up period  of 
8-10 days, the plant would be able to sustain a nameplate capacity of 
5 tonnes copper cathode per day. 
 
Feasibility Study 
A number  of SX-EW  plants  have become  available for  purchase  and 
Finders is undertaking detailed assessment of two opportunities  with 
respect to use  of these  plants for the  planned expanded  20-25,000 
tonne cathode copper per year operations. 
 
In light of these opportunities,  the engineering and process  design 
work  for  a  new  plant  has  been  postponed  within  the   current 
feasibility study. 
 
However, on the basis  of work completed to  date, and using  current 
landed fuel prices  in Indonesia, the  estimated operating costs  for 
the full  scale plant  are  around US$0.70  per  lb Cu,  putting  the 
project on par  with the  average operating  cost per  lb for  copper 
producers globally.  The Directors believe the project remains robust 
even at current  depressed copper  prices and is  positioned to  take 
advantage of the future recovery of the global economy. 
Finders consider it is  prudent to finalise  the bankable study  when 
there is clarity on the SX-EW  plant purchase options (used or  new), 
and once operating data from the test heaps is sufficiently robust to 
ensure that the final  study has minimal  capital cost and  technical 
risk. 
 
Mining studies  are ongoing,  with a  site visit  by Australian  Mine 
Design  and  Development  Pty   Ltd  (AMDAD)  and  potential   mining 
contractors completed during the period. 
 
A revised  mining schedule  is being  designed on  the basis  of  new 
information from  the  revised resource  estimate  and  metallurgical 
modeling of ore types (see below) and earthworks requirements for the 
commercial scale leach pads. 
Environmental studies are  ongoing with  a first draft  of the  ANDAL 
document completed  subject  to revision  of  the mine  schedule  and 
layout options for the SX-EW plant. 
 
Resource Upgrade 
A new resource estimate has been independently estimated by Hellman & 
Schofield Pty  Ltd  and  reported  according to  the  JORC  Code  and 
Guidelines. The resource estimates (Table 1) for both the Kali Kuning 
and Lerokis massive sulphide deposits have been upgraded to +98% JORC 
Measured and Indicated categories.  This  is based on the results  of 
62 new diamond and reverse circulation drill holes. 
 
The combined resource estimate for Kali Kuning and Lerokis, at a 0.5% 
copper cutoff, of 9 Mt at 2.4% copper, or 218,000 tonnes of contained 
copper, represents  a  10%  reduction in  total  copper  compared  to 
previously announced estimates, due largely to the tighter control of 
the massive sulphide  boundaries from closer  spaced drilling at  the 
Lerokis deposit.  It is expected that almost all of the Measured  and 
Indicated Resources  will be  converted into  Ore Reserves  upon  the 
completion of further mine planning and feasibility work. 
 
Based on the new drilling  the Kali Kuning massive sulphide  resource 
has been re-classified into  three metallurgical sub-types,  Leached, 
Transition zone material and Primary massive sulphide, (Table 2). The 
Leached and Transition  types reflect incipient  in-situ leaching  of 
the massive sulphide unit by natural groundwater. The Transition zone 
material, although  of  lower  copper grade  than  the  main  Primary 
massive sulphide, (1.5% Cu vs 2.9%Cu) contains a higher proportion of 
readily leachable copper minerals  which translates to  significantly 
faster leach  rates  for  this  material,  as  described  below.  The 
Transition zone occurs at the highest levels of the deposit and  will 
comprise a major  proportion of  early mined  mineralization for  the 
expanded Wetar copper project. 
 
 
 
+--------------------------------------------------------------------+ 
|Table 1. Wetar project Resource Estimates      (Note:  Rounding     | 
|errors may cause inaccuracies in following tables)                  | 
|                                                                    | 
|                                                                    | 
|--------------------------------------------------------------------| 
|0.5% Cu  cut-off   |       |    |             |Attributable| 92.8%* | 
|grade              |       |    |             |            |        | 
|-------------------+-------+----+-------------+------------+--------| 
|        |Category  |Tonnes |Cu% |Cont. Cu (KT)| Tonnes (M) |Cont. Cu| 
|        |          |  (M)  |    |             |            |  (KT)  | 
|--------+----------+-------+----+-------------+------------+--------| 
|Kali    |Measured  |  5.2  |2.6 |     133     |    4.8     |  123   | 
|Kuning  |          |       |    |             |            |        | 
|--------+----------+-------+----+-------------+------------+--------| 
|        |Indicated |  0.9  |2.5 |     22      |    0.8     |   20   | 
|        |----------+-------+----+-------------+------------+--------| 
|        |Inferred  |  0.1  |1.8 |      2      |    0.1     |   2    | 
|        |----------+-------+----+-------------+------------+--------| 
|        |Total     |  6.1  |2.5 |     156     |    5.7     |  145   | 
|--------+----------+-------+----+-------------+------------+--------| 
|Lerokis |Measured  |  2.1  |2.4 |     51      |    1.9     |   47   | 
|--------+----------+-------+----+-------------+------------+--------| 
|        |Indicated |  0.5  |2.1 |     10      |    0.5     |   9    | 
|        |----------+-------+----+-------------+------------+--------| 
|        |Inferred  |  0.1  |1.4 |      2      |    0.1     |   2    | 
|        |----------+-------+----+-------------+------------+--------| 
|        |Total     |  2.7  |2.3 |     62      |    2.5     |   58   | 
|-------------------+-------+----+-------------+------------+--------| 
|Overall            |  8.8  |2.4 |     218     |    8.2     |  203   | 
+--------------------------------------------------------------------+ 
 
*Attributable:  ownership is based on estimates of project 
expenditure to end-November 2008 and is subject to final audit. 
 
 
+-------------------------------------------------------------------+ 
| Table 2. Breakdown of Kali Kuning by metallurgical zone           | 
|                                                                   | 
|-------------------------------------------------------------------| 
|                  |  Zone            | Tonnes (M) | Cu% | Cont. Cu | 
|                  |                  |            |     |   (KT)   | 
|------------------+------------------+------------+-----+----------| 
| Massive Sulphide | Leached Zone     |    0.1     | 0.7 |    1     | 
|------------------+------------------+------------+-----+----------| 
|  0.5% Cu         | Transition  Zone |    1.2     | 1.5 |    17    | 
| cut-off grade    |------------------+------------+-----+----------| 
|                  | Primary Zone     |    4.8     | 2.9 |   138    | 
|                  |------------------+------------+-----+----------| 
|                  | Total            |    6.1     | 2.5 |   156    | 
+-------------------------------------------------------------------+ 
 
 
An additional 700,000  t of  mineralized clay  altered tuff,  grading 
0.9% Cu, which forms the wallrock  to the massive sulphide, has  been 
excluded  from   the   resource  estimates   because   of   uncertain 
metallurgical response. 
 
Metallurgy 
Given the higher grade of the transitional mineralisation from recent 
drilling,  metallurgical  test  work   on  this  material  has   been 
instigated at site  with two new  column tests.  Though  still at  an 
early stage,  the results  are very  encouraging with  73-95%  copper 
recovery achieved  within  31 days,  subject  to final  mass  balance 
calculations.   These  results  are  significant  for  the  expansion 
project, since  the  SX-EW  plant  is  likely  to  achieve  nameplate 
capacity much  faster  than  previously  expected  due  to  the  fast 
leaching nature of the Transition mineralisation. 
The initial two 1.8m columns using  fresh ore material from the  Kali 
Kuning test pit confirm that copper recovery is faster and PLS grades 
higher with higher acid concentrations with 74 & 86% copper  recovery 
achieved within 131 days, subject to final mass balance calculations. 
 
The figure below shows  time-copper recovery curves  for a number  of 
column tests completed  under different conditions  for the two  main 
ore types, the primary (red) and the transitional (purple) zones  and 
a modelled recovery curve for 8m high heaps (orange). 
 
New Indonesian Mining Law 
The Company advises that it welcomes the new Indonesian mining  law. 
The Wetar project will the  first copper mining project in  Indonesia 
to produce  cathode metal  and,  as such,  is  aligned with  the  new 
obligation to process and purify mining products within the country. 
Our work to date under the KP title system in Indonesia had led us to 
develop a strong working relationship with the same local  government 
authorities who will administer the tenement system as required under 
the  new  law,  and  we  will  continue  to  benefit  from   existing 
relationships established with these agencies.  The basis of the  new 
tenement system has similar stages and approval mechanisms to the one 
we  currently  work  under.    Indonesian  Government  copper   metal 
royalties will apply to the Wetar project and these are currently 4%. 
 
Ojolali Project 
Finders Resources Limited 72% with option 
 
Background Information 
Finders believe  that the  Ojolali project  has strong  potential  to 
generate short-term cash flow by open pit CIL/CIP development of  the 
gold resource at the Jambi Oxide gold deposit (Table 3.) 
 
Table 3. Jambi Resource Estimates 
Cut     Indicated      Inferred         Total      Contained Attrib. 
off                                                            FND 
 Au   Mt   Au    Ag  Mt   Au   Ag   Mt   Au    Ag   Au koz   (72%) Au 
g/t        g/t  g/t      g/t  g/t        g/t  g/t              koz 
0.5  2.98  1.1  8.3  1.1 0.9  5.7  4.08 1.05  7.6     138       99 
1.0  1.13 1.74  8.5  0.3 1.6  6.7  1.43 1.71  8.1     79        57 
 
Finders has previously  announced Inferred Resources  at the  Tambang 
Prospect (7.9 Mt @ 167g/t Ag and 0.7 g/t Au at a 1 g/t Au  equivalent 
cut-off  using  drilling  data  from  a  previous  explorer).   Other 
prospects have outstanding potential for the discovery of  additional 
resources using  modern  geophysical  techniques  to  optimize  drill 
targeting. 
 
Recent Activities 
Activities during the  period have focused  on further evaluation  of 
prospect  areas  with  strongly   anomalous  soil  geochemistry   and 
extending the soil sampling program. 
 
During the  period a  further  9.5 line  km  of soil  traverses  were 
completed with follow-up trenching and channel sampling over 500m at 
25 locations. The main focus was assessment of the oxide potential of 
the Tambang vein system  and the zone of  5 sub-parallel vein  swarms 
(2-16m in width) at Way Neki,  the southern continuation of the  Batu 
Kuning prospect. 
 
The samples were  taken as part  of a systematic  program of  channel 
sampling from the oxidized near surface portion of the major  Tambang 
vein system (see  map).  This program  is aimed at  testing for  high 
grade supergene enriched silver values  at the base of oxidation  and 
preliminary  results  strongly  support  that  concept.  Assays  from 
additional channel samples are awaited. 
 
Preliminary results from Tambang are regarded by Finders as highly 
encouraging (Table 4). 
 
Table 4. Significant channel sample assays from Tambang 
 CTBG002    444159    9480615    2.0    0.5    315 
 CTBG003    444200    9480409    2.0    1.4    450 
 CTBG004    444203    9480349    2.0    0.5    109 
  CTBG22    443864    9480784    2.0    1.8    209 
 
 
Corporate 
 
Board Appointment 
Robert Thomson  accepted a  position on  the Finders  Board and  this 
appointment was made  effective on  6th Jan  2009. Rob's  appointment 
brings great experience in successful and timely project  development 
to the company for the forthcoming expansion of Wetar Copper to  full 
scale operations.  Rob was previously the Company's General  Manager, 
Development  and  has   the  prime   responsibility  for   successful 
completion of feasibility studies  and subsequent development of  the 
Company's Wetar copper project. Rob brings to the Finders  Management 
team a  strong track  record  of delivering  successful  construction 
projects in  challenging  south-east Asian  environments  notably  at 
Kingsgate's Chatree Gold  Mine in  Thailand and  Oxiana's Sepon  Gold 
Mine. 
 
Corporate Structure 
Allotment of shares for a placement approved by Finders  shareholders 
on 16 October  2008 was  completed on  23 October  2008. Gross  funds 
raised under the placement  totaled approximately A$5.4 million  from 
the issue of 8,650,020 new shares. 
 
The placement  consisted of  6,925,020 shares  issued at  A$0.60  per 
share through RFC Corporate Finance  Ltd and 1,725,000 shares  issued 
to parties in the UK at GBP0.28 per share through Finncap, Finders  AIM 
broker. 
In addition, on similar terms to the placement, the Company offered a 
Share Purchase Plan (SPP). Following closure of the SPP, 271,657 new 
shares were issued to raise approximately AUD$163,000. 
 
 
Table 5. Current Capital Structure 
Type of Security       Exercise Price Expiry Date   Number on Issue 
Fully Paid Ordinary 
Shares ("Shares") 
Shares on issue at 30                                     74,921,825 
September 2008 
New Shares Issued                                           8,650,020 
(Placement) 
New Shares Issued 
(SPP)                                             271,657 
New Shares Issued 
(Fee)                                             208,333 
Shares on Issue at 31                                     84, 051,835 
December 2008 
Unlisted Options 
                       A$0.50         March 20,             3,090,367 
                                      2009 
                       24p            March 22,             1,322,881 
                                      2009 
                       A$0.6875       June 13, 
                                      2010        500,000 
Total Unlisted Options                                      4,913,248 
on issue 
 
 
Cash Management 
 
The company was severely impacted  during the quarter by the  effects 
of  the  world  economic  crisis,  in  particular  the  fall  in  the 
Australian Dollar compared to the US$ and the Indonesian Rupiah. 
 
 
 
A delayed revenue stream (at lower than projected copper prices) also 
contributed to place pressure on  the company's cash resources.   The 
Board has responded to this situation with a number of initiatives to 
strengthen the Company's working capital position. 
 
1.       Arranging a placement of up to US$1.5 million in convertible 
notes to RCF (see subsequent events, below). 
2.       Suspending work on all non-essential programmes, with  total 
focus on completion of the Wetar 
          Demonstration plant 
3.       Voluntary reductions in salary  by Directors and key  senior 
staff 
4.       Provision of loan funds to the company by certain  Directors 
of A$714,000 (see subsequent events, below) 
 
The company expects to generate cash flow from copper cathode sales 
from the end of February, 2009.  In addition, it has also arranged 
advance payment of up to A$1.5 million following commencement of 
production at Wetar under an agreement linked to a copper off-take 
contract. 
 
With the fall in the copper price, the Company's revenue projections 
for cathode sales in 2009 have been revised downwards; but, with 
estimated operating cost for the Wetar demonstration plant of around 
US$1/lb Cu, the Directors expect that the plant's operating margin 
will be comfortably positive on the basis of current average copper 
price estimates from a consensus of analysts (Bloomberg Jan 15: CY 
US$1.495/lb Cu). 
 
The Directors believe that with the planned expansion of the Wetar 
Copper Project by early 2010, the Company is placed well to benefit 
from positive changes in the commodity prices as the global economy 
recovers in future months. 
 
Subsequent Events 
On 16th January 2009,  Finders announced that it  has entered into  a 
Convertible  Note  Facility  Agreement  ("Facility")  with   Resource 
Capital Fund IV L.P. ("RCF").  Under the Facility, RCF has agreed  to 
provide the company with US$1.5 million, of which US$1.0 million will 
be made  available on  satisfaction  of certain  standard  conditions 
precedent with the balance to  be made available, subject to  further 
conditions precedent, on  or before  15 March  2009. The  convertible 
note has a  term of 3  years, is convertible  into Finders shares  at 
A$0.40 per share and interest at 12% per annum is payable quarterly. 
 
The  Company  has  also  entered  into  loan  agreements  with   four 
directors,  Messrs  Russell  Fountain,  Christopher  Farmer,   Robert 
Thomson and Stephen  de Belle  pursuant to which  the directors  have 
lent the Company a total of A$714,000. 
 
The mining exploration entity quarterly report (Appendix 5b) is 
appended. 
 
 
 
Chris Farmer 
 
Managing Director 
 
Further details for  all projects including  location maps,  tenement 
schedules and  technical descriptions  may be  found on  the  Finders 
website at www.findersresources.com 
 
 
 
For further information please contact 
 
Finders Resources Ltd: 
Russell         Executive Chairman          +61 2 9211 8299 
Fountain 
Chris Farmer    Managing Director           info@findersresources.com 
 
Financial PR: 
Doug Macdonald  Capital      Group      (in +61 424 255 959 
                Australia) 
Nick Elwes      College Hill (in the UK)    +44 20 7457 2020 
 
RFC Corporate Finance Ltd - Nomad: 
Rob Adamson     Managing Director           +61 2 9250 0000 
Stuart Laing    Executive Director          +61 8 9480 2500 
 
FinnCap -  Finders' Broker for the AIM market: 
Mathew Robinson Corporate Finance Director  +44 20 7600 1658 
Joe Lunn        Analyst                     +44 20 7600 1658 
 
 
Disclaimer 
 
The information in this report that relates mineral resource 
estimation is based on work completed by Dr Phillip Hellman who is a 
full time employee of Hellman and Schofield Pty Ltd and a Fellow of 
the Australian Institute of Geoscientists.  Dr Hellman has sufficient 
experience which is relevant to the style of mineralisation and type 
of deposit under consideration and to the activity which he is 
undertaking to qualify as a Competent Person as defined in the 2004 
Edition of the 'Australasian Code for Reporting of Exploration 
Results, Mineral Resources and Ore Reserves' and as a Qualified 
Person as defined in the AIM Rules. Dr Hellman consents to the 
inclusion in the report of the matters based on his information in 
the form and context in which it appears. Estimates for Kali Kuning 
are based on a data set from which some diamond drill holes have been 
excluded due to poor recovery of copper mineralisation as evidenced 
by neighbouring RC holes. 
 
Geological information in this announcement and comments relating  to 
exploration  potential  and  the  project  in  general  is  based  on 
information  compiled  by  Dr  Russell  Fountain,  who  also  accepts 
responsibility for  the data  on  which the  resource is  based.   Dr 
Fountain is a Director  of Finders and a  Fellow of the  Australasian 
Institute of  Geoscientists. Dr  Fountain has  sufficient  experience 
that is  relevant  to  the  styles of  mineralisation  and  types  of 
deposits  under  consideration  and  to  the  activity  that  he   is 
undertaking to qualify  as Competent  Person as defined  in the  JORC 
Code. He  consents  to the  inclusion  in this  announcement  of  the 
matters based on  his information in  the form and  context in  which 
they appear. All assaying of drill core samples was undertaken by the 
ITS laboratory in Jakarta. ITS is one of the world's largest  product 
and commodity  testing, inspection  and certification  organizations. 
The  Jakarta  laboratory  is  ISO  17025  accredited  and  employs  a 
Laboratory Information Management System (LIMS) for sample  tracking, 
quality control and reporting. 
 
Appendix 5B 
 
             Mining exploration entity quarterly report 
 
 
Name of entity 
FINDERS RESOURCES LIMITED 
 
 
 
ABN              Quarter ended ("current quarter") 
82 108 547 413           31 DECEMBER 2008 
 
 
 
Consolidated statement of cash flows 
 
 
                                                 Current Year to date 
Cash flows related to operating activities       quarter (.6.months) 
                                                 $A'000     $A'000 
1.1  Receipts from product sales and related 
     debtors 
     Payments for (a) exploration and evaluation  (49)      (320) 
1.2                       (b) development        (1,044)   (6,566) 
                          (c) production            -         - 
                          (d) administration      (539)    (1,614) 
1.3  Dividends received 
1.4  Interest and other items of a similar         11         51 
     nature received 
1.5  Interest and other costs of finance paid 
1.6  Income taxes paid 
1.7  Other (provide details if material) 
     Net Operating Cash Flows                    (1,621)   (8,449) 
 
     Cash flows related to investing activities 
     Payment for purchases of:          (a) 
     prospects                                    (325)     (325) 
1.8                                        (b)      -         - 
     equity investments                          (4,720)   (4,767) 
                                           (c) 
     other fixed assets 
     Proceeds from sale of:     (a) prospects 
                                           (b) 
1.9  equity investments 
                                           (c) 
     other fixed assets 
1.10 Loans to other entities 
1.11 Loans repaid by other entities 
1.12 Other (provide details if material) 
     Net investing cash flows                    (5,045)   (5,092) 
1.13 Total operating and investing cash flows    (6,666)   (13,541) 
     (carried forward) 
 
 
 
 
Appendix 5B 
Mining exploration entity quarterly report 
 
 
 
1.13 Total operating and investing cash          (6,666)     (13,541) 
     flows (brought  forward) 
 
     Cash flows related to financing 
     activities 
1.14 Proceeds from issues of shares,              5,357       5,357 
     options, etc. 
1.15 Proceeds from sale of forfeited shares 
1.16 Proceeds from borrowings                      429        1,711 
1.17 Repayment of borrowings                      (34)         (34) 
1.18 Dividends paid 
1.19 Other (provide details if material) 
 
     Net financing cash flows                     5,752       7,034 
 
     Net increase (decrease) in cash held         (914)      (6,507) 
 
1.20 Cash at beginning of quarter/year to          785        4,988 
     date 
1.21 Exchange rate adjustments to item 1.20        547        1,937 
1.22 Cash at end of quarter                        418         418 
 
Payments to directors of the entity and associates of the directors 
Payments to related entities of the entity and associates of the 
related entities 
 
                                                    Current quarter 
                                                        $A'000 
                      Aggregate amount of payments 
1.23                  to the parties included in          316 
                      item 1.2 
                      Aggregate amount of loans to 
1.24                  the parties included in item        NIL 
                      1.10 
1.25                  Explanation necessary for an understanding of 
                      the transactions 
                      Payments are for salaries, directors and 
                      consulting fees. 
 
Non-cash financing and investing activities 
 
2.1 Details of financing and investing transactions which have had a 
    material effect on consolidated assets and liabilities but did 
    not involve cash flows 
    Company issued 208,333 ordinary fully paid shares on 8 December 
    2008 for 60 cents each in payment of consulting fees. 
 
 
 
2.2 Details of outlays made by other entities to establish or 
    increase their share in projects in which the reporting entity 
    has an interest 
 
    NONE 
 
 
 
 
Appendix 5B 
Mining exploration entity quarterly report 
 
Financing facilities available 
Add notes as necessary for an understanding of the position. 
 
 
                                    Amount available Amount used 
                                         $A'000        $A'000 
3.1 Loan facilities (USD 5,000,000)      7,823          7,823 
3.2 Credit standby arrangements           NIL            NIL 
 
 
Estimated cash outflows for next quarter * 
 
                               $A'000 
 
4.1 Exploration and evaluation  170 
 
4.2 Development                3,500 
 
 
    Total                      3,670 
 
 
 
 
+-------------------------------------------------------------------+ 
|                                                                   | 
| Note:                                                             | 
|                                                                   | 
| On 16th January 2009 the Company announced a US$1.5m (A$2.25m)    | 
| convertible note facility and Directors loans totaling A$714,000. | 
|                                                                   | 
| The company expects to generate cashflow from copper cathode      | 
| sales from the end of February, 2009.  In addition, it has also   | 
| arranged advance payment of up to A$1.5 million following         | 
| commencement of production at Wetar under an agreement linked to  | 
| a copper off-take contract.                                       | 
|                                                                   | 
+-------------------------------------------------------------------+ 
 
 
Reconciliation of cash 
 
Reconciliation of cash at the end of the quarter (as Current Previous 
shown in the consolidated statement of cash flows)   quarter quarter 
to the related items in the accounts is as follows.  $A'000   $A'000 
5.1       Cash on hand and at bank                     418     785 
5.2       Deposits at call 
5.3       Bank overdraft 
5.4       Other (provide details) 
          Total: cash at end of quarter (item 1.22)    418     785 
 
 
 
Appendix 5B 
Mining exploration entity quarterly report 
 
Changes in interests in mining tenements 
 
 
                           Tenement  Nature of  Interest at Interest 
                           reference  interest   beginning  at end of 
                                     (note (2)) of quarter   quarter 
6.1 Interests in mining 
    tenements 
    relinquished, reduced     NIL                   NIL        NIL 
    or lapsed 
 
 
6.2 Interests in mining 
    tenements acquired or 
    increased                 NIL                   NIL        NIL 
 
 
 
 
Issued and quoted securities at end of current quarter 
Description includes rate of interest and any redemption or 
conversion rights together with prices and dates. 
 
 
                          Total      Number   Issue price Amount paid 
                          number     quoted       per       up per 
                                               security    security 
                                                (cents)     (cents) 
                                               (see note   (see note 
                                                  3)          3) 
7.1  Preference 
     +securities           N/A 
     (description) 
7.2  Changes during 
     quarter 
     (a)  Increases 
     through issues 
     (b)  Decreases        N/A 
     through returns of 
     capital, 
     buy-backs, 
     redemptions 
7.3  +Ordinary          84,051,835 83,870,017 
     securities 
7.4  Changes during 
     quarter 
     (a)  Increases     9,130,010  9,130,010    60cents     60cents 
     through issues        NIL        NIL 
     (b)  Decreases 
     through returns of 
     capital, buy-backs 
7.5  +Convertible debt 
     securities            N/A 
     (description) 
7.6  Changes during 
     quarter 
     (a)  Increases 
     through issues        N/A 
     (b)  Decreases 
     through securities 
     matured, converted 
7.7  Options                                   Exercise   Expiry date 
     (description and   3,090,367     NIL        price    20.03.2009 
     conversion factor) 1,322,881     NIL       50cents   22.03.2009 
                         500,000      NIL       24pence   13.06.2010 
                                              68.75cents 
7.8  Issued during         NIL        NIL 
     quarter 
7.9  Exercised during      NIL        NIL 
     quarter 
7.10 Expired during        NIL        NIL 
     quarter 
7.11 Debentures 
     (totals only) 
7.12 Unsecured notes 
     (totals only) 
 
 
 
 
Appendix 5B 
Mining exploration entity quarterly report 
 
Compliance statement 
 
1          This statement has been prepared under accounting policies 
which comply with accounting standards as defined in the Corporations 
Act or other standards acceptable to ASX (see note 4). 
 
2          This statement does  /does not* (delete  one) give a  true 
and fair view of the matters disclosed. 
 
 
 
Sign                          here: 
............................................................ 
Date: . 30th January 2009 
(Director) 
 
 
 
Print         name:                       ....Christopher         Ben 
Farmer........................... 
 
Notes 
 
1              The quarterly  report provides a  basis for  informing 
the market how  the entity's  activities have been  financed for  the 
past quarter and the effect on its cash position.  An entity  wanting 
to disclose additional information is encouraged to do so, in a  note 
or notes attached to this report. 
 
2              The "Nature of interest" (items 6.1 and 6.2)  includes 
options  in  respect  of  interests  in  mining  tenements  acquired, 
exercised or lapsed during  the reporting period.   If the entity  is 
involved in  a  joint  venture agreement  and  there  are  conditions 
precedent which  will  change its  percentage  interest in  a  mining 
tenement, it should  disclose the change  of percentage interest  and 
conditions precedent in the list required for items 6.1 and 6.2. 
 
3               Issued and  quoted securities   The issue  price  and 
amount paid up is not  required in items 7.1  and 7.3 for fully  paid 
securities. 
 
4              The  definitions in,  and  provisions of,  AASB  1022: 
Accounting for Extractive Industries and AASB 1026: Statement of Cash 
Flows apply to this report. 
 
5              Accounting Standards ASX will accept, for example, the 
use of International Accounting  Standards for foreign entities.   If 
the standards used do not address a topic, the Australian standard on 
that topic (if any) must be complied with. 
 
=--END OF MESSAGE--- 
 
 
 
 
This announcement was originally distributed by Hugin. The issuer is 
solely responsible for the content of this announcement. 
 

Finders Resources (LSE:FND)
Historical Stock Chart
From Dec 2024 to Jan 2025 Click Here for more Finders Resources Charts.
Finders Resources (LSE:FND)
Historical Stock Chart
From Jan 2024 to Jan 2025 Click Here for more Finders Resources Charts.