Corcel PLC Wowo Gap -- Receipt of Gap Analysis Report (2421O)
June 09 2022 - 1:02AM
UK Regulatory
TIDMCRCL
RNS Number : 2421O
Corcel PLC
09 June 2022
Corcel PLC
("Corcel" or the "Company")
Wowo Gap - Receipt of Gap Analysis Report
09 June 2022
Corcel, the natural resource exploration and development company
with interests in battery metals and flexible energy generation and
storage, announces receipt of its externally commissioned Gap
Analysis Report conducted on the Company's Wowo Gap nickel/cobalt
project, where the Company retains a 100% interest.
Highlights:
o A detailed Gap Analysis report for the Wowo Gap Project has
been completed externally, including a comprehensive review of
legacy data and proposals for areas of future emphasis in
preparation for an eventual Mining Lease application
o Key findings, other than the need to continue to mature the
project technically, include the requirement to update offtake
assumptions given recent positive structural changes in Nickel
prices and the proposed broadening of focus to include multiple
development concepts including both a DSO alongside HPAL (High
Pressure Acid Leach) and DNi (Direct Nickel) processing options
Gap Analysis:
AMC Consultants Pty Ltd ("AMC") were contracted, as part of the
Company's preparation work for a Mining Lease application, to
prepare a Gap Analysis of the Wowo Gap lateritic nickel/cobalt
project in Papua New Guinea ("PNG"). This work builds on the
historic 2010 feasibility study and the 2016 direct shipping ore
("DSO") study conducted by the previous owners of the project. The
focus of the study was to provide a clear understanding of the
additional data and work required to make an eventual formal
application for the Mining Lease, including a bankable feasibility
study ("BFS") acceptable for project financing purposes.
Key Findings:
Geology:
o In general AMC considers the deposit geology to be well
understood however some additional resource definition work
suggested to define mineralization boundaries and the extent of the
deposit
o Some portion of the resource may need to be upgraded to the
JORC Measured classification in order complete a full BFS
Offtake:
o Requirement to update previous 2010 and 2016 views on market
demand, quality, and expected Nickel prices, particularly given
recent strong structural changes in Nickel prices
Geotechnical:
o Requirement to plan for expected very wet conditions at the
minesite including surface drainage, stability of excavation and
landform walls and trafficability across benches and haul roads
Operations and Infrastructure:
o Currently envisaged operations are considered reasonable and
consistent with others in the region (including the Ramu nickel
mine- using hydraulic excavators and articulated dump trucks).
Further work limited to finalising routine additional
documentation, economic assessment and engineering work
o Ore likely to be stockpiled at the mine to be dried and later
sent to the coast for export through a barge loading facility at
Collingwood Bay hence key infrastructure spread across minesite,
local village and barge loading facility
Mine Planning:
o Some early work on mine planning completed by the previous
owners but additional work, including ore loss and dilution models,
cut-off grade analysis and the determination of economic pit limits
now required
Environmental:
o Requirement to prepare detailed risk mapping including risk
mitigation measures and associated implications.
o Requirements to understanding project hydrology including peak
flows and flood mapping alongside relevant average recurrence
intervals for the predicted mine-life with a view to right sizing
required development infrastructure
o Greatest risk which requires mitigation is expected to be
water quality downstream of project and potential contamination
from run-off, leachate and spills
Economic Assessment:
o Building on previous work additional analysis of expected
operating and capital costs will be developed
Development Concept :
o Wowo Gap was originally developed in 2010 as a 1.5Mtpa (dry)
open pit mine with on-site processing using HPAL technology. In
2016 a further study was undertaken examining a 2Mtpa DSO nickel
laterite operation. Based on the results of the AMC report Corcel
intends to conduct a Pre-Feasibility Study ("PFS") examining
multiple development concepts including both a DSO operation
alongside a HPAL or Direct Nickel operation.
The Company will update the market as it continues its technical
work to advance the Wowo Gap project.
For further information, please contact:
Scott Kaintz 020 7747 9960 Corcel Plc CEO
James Joyce / Andrew de Andrade 0207 220 1666 WH Ireland Ltd
NOMAD & Broker
Simon Woods 0207 3900 230 Vigo Communications IR
The information contained within this announcement is deemed to
constitute inside information as stipulated under the retained EU
law version of the Market Abuse Regulation (EU) No. 596/2014 (the
"UK MAR") which is part of UK law by virtue of the European Union
(Withdrawal) Act 2018. The information is disclosed in accordance
with the Company's obligations under Article 17 of the UK MAR. Upon
the publication of this announcement, this inside information is
now considered to be in the public domain.
This information is provided by RNS, the news service of the
London Stock Exchange. RNS is approved by the Financial Conduct
Authority to act as a Primary Information Provider in the United
Kingdom. Terms and conditions relating to the use and distribution
of this information may apply. For further information, please
contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms
and conditions, to analyse how you engage with the information
contained in this communication, and to share such analysis on an
anonymised basis with others as part of our commercial services.
For further information about how RNS and the London Stock Exchange
use the personal data you provide us, please see our Privacy
Policy.
END
MSCUWAURUUUNRUR
(END) Dow Jones Newswires
June 09, 2022 02:02 ET (06:02 GMT)
Regency Mines (LSE:RGM)
Historical Stock Chart
From Dec 2024 to Jan 2025
Regency Mines (LSE:RGM)
Historical Stock Chart
From Jan 2024 to Jan 2025