Cadence Minerals
Plc
("Cadence Minerals",
"Cadence", or "the Company")
Amapá Iron Ore Project
Licensing on Schedule. Project Financing Discussions
Advancing.
Cadence Minerals (AIM: KDNC) is
pleased to report the progress of the environmental licensing and
the testing of the 67% 'Green Iron' processing flow sheet at the
Amapá Iron Ore Project.
Highlights:
· Installation Licences for the Amapá mine and railway remain on
schedule to be granted this year.
· The license application for the port was submitted in
September and is also scheduled for a grant this year.
· The test work for sixty-seven per cent
(67%) iron flow sheet is due for completion in the fourth quarter
of this year.
· The Project is actively discussing the equity portion of
project financing to complement the existing debt financing
MOU.
Kiran Morzaria, the CEO of
Cadence, commented, "It's great to see the
continued progress at Amapá. The Project has consistently delivered
all the required environmental studies and applications either on
time or ahead of schedule. Based on the positive feedback from the
local government, we understand that all necessary permits will be
granted before the year's end. Additionally, we are actively
advancing the development of a 67% "green iron" product and
securing equity financing for the Project."
Licensing
As announced in September 2023
(News
Release Here), the Amapá Project
has agreed with the Amapá State Environmental Agency ("SEMA") to an
expedited environmental licensing process, given the Project was
previously operating and had been granted all required
licenses.
The Amapá Project owns the required
Mining Concessions; however, it must obtain a Mine Extraction and
Processing Permit ("Mining Permit") to begin operation. To obtain
this permit, the Amapá Project must obtain an Installation License
("LI") to begin construction and, when constructed, an Operational
License ("LO"). An LI and LO are also required to construct and
operate the railway and port.
In April 2023, the Amapá Project
submitted the required environmental studies and applications for
the Amapá mine and railway. This application was in the form of the
Environmental Control Plan, "PCA" (Plano de Controle Ambiental),
and an Environmental Control Report, "RCA" (Relatório de Controle
Ambiental).
In early September, the Amapá
Project submitted the required environmental studies and
application for the LI grant for iron ore port. This
application was submitted after those for the mine and railway as
SEMA required an extended environmental study. Nevertheless, the
application was submitted on schedule.
Our joint venture has continued
engaging with SEMA and other relevant authorities, who have
indicated that the LI for the rail and mine remain on schedule for
the grant this year. Given the impact that the railway's restart
will make on local communities, the installation license for the
railway is anticipated to have some conditions precedent. This is
expected in any project of this nature. The Amapá project
management team always anticipated this as part of the required
licensing requirements to redevelop the Amapá Iron Ore
project.
Our understanding from SEMA is that,
based on the current timeline, all the LIs will be granted by the
end of 2024.
67% 'Green Iron'
Flowsheet
The testing of the 67% processing
route is continuing. The Amapá Project originally produced three
products: 58%, 62%, and 65% iron ore concentrate. The 2023
pre-feasibility improved this product mix, with only a 62% and 65%
produce mix being envisaged. The current flowsheet aims to produce
one hundred per cent 67% iron ore concentrate, which has both a
premium in price and is anticipated to be a growth market in the
iron ore concentrate as it represents the feedstock to DRI
furnaces. These furnaces enable the
decarbonising of the steel industry by replacing blast
furnaces.
The main variances in the proposed
67% flow sheet involve:
· Removing the jigging circuit, with the iron being recovered
via the grinding, magnetic, and flotation circuits. This will
improve the iron recovery rate.
· Replacing hydrocyclone desliming with thickeners, improving
classification efficiency and lowering power
consumption.
· The
67% flow sheet will remove the 62% product stream, eliminating the
spiral circuit. This will shorten the process flow and reduce power
consumption.
· Adding
a flowsheet to improve iron concentrates from 65.4% to 67% via
regrinding the material from the magnetic separator, meaning finer
particles can be further liberated, improving iron concentrate
grade to 67%.
· Replacement of all slurry, water, and reagent pumps involved
in the beneficiation process.
· A
concentrate slurry pipeline and filtrate water return pipeline
system will be built to replace truck transportation.
· The
particle size of the concentrate after the tower mills is too fine
to be filtered by the existing vacuum disc filters. Therefore,
horizontal press filters are required to ensure the moisture
content of the filter cake is no larger than 8%.
· A
train loading system will be built in the train loading
area.
A summary of the new flow sheet is
available
here.
The main metallurgical test work
being carried out includes raw ore liberation testing, desliming
testing, magnetic separation testing, floatation testing, grinding
work index testing, concentrate tailings thickening testing and
tailings filtration testing. We expect this work to be completed in
the fourth quarter of this year.
Project Financing
In October 2023
(News
Release Here), our joint venture
company and DEV Mineração S.A. ("DEV") entered into a memorandum of
understanding ("MOU"). The MOU is in place to secure the required
project debt financing for the construction and re-development of
the Amapá Project.
To complement the project debt
financing, our joint venture is actively engaging with several
potential financing partners to provide the equity portion of the
funding at the project level.
About the Amapá Project and
Cadence Ownership
The Amapá Project is a brownfield
integrated iron ore project in the Amapá State of Brazil. It has
Mineral Resources of 276 million tonnes (Mt) at 38.33% Iron (Fe)
and Ore Reserves of 196 Mt at 39.34%. The Project consists of the
mine, processing plant, wholly owned port and a 194km railway, all
operated by PBA.
As of August 31st, 2024, Cadence's
total investment in the Amapá million was approximately US$14.2
million, and its equity stake in the project stands at 34.5%, an
increase of approximately US$0.57 million since 30 June
2024
For further information
contact:
|
|
Cadence Minerals plc
|
+44
(0) 20 3582 6636
|
Andrew Suckling
|
|
Kiran Morzaria
|
|
|
|
Zeus
Capital Limited (NOMAD & Broker)
|
+44
(0) 20 3829 5000
|
James Joyce
|
|
Darshan Patel
Isaac Hooper
|
|
|
|
Fortified Securities - Joint Broker
|
+44
(0) 20 3411 7773
|
Guy Wheatley
|
|
|
|
Brand Communications
|
+44
(0) 7976 431608
|
Public & Investor
Relations
|
|
Alan Green
|
|
Qualified Person
Kiran Morzaria B.Eng. (ACSM), MBA,
has reviewed and approved the information contained in this
announcement. Kiran holds a Bachelor of Engineering (Industrial
Geology) from the Camborne School of Mines and an MBA (Finance)
from CASS Business School.
Cautionary and
Forward-Looking Statements
Certain statements in this
announcement are or may be considered forward-looking.
Forward-looking statements are identified by their use of terms and
phrases such as "believe", "could", "should", "envisage",
"estimate", "intend", "may", "plan", "will", or the negative of
those variations or comparable expressions
including references to assumptions. These forward-looking
statements are not based on historical facts but rather on the
Directors' current expectations and assumptions regarding the
company's future growth results of operations
performance, future
capital, and other expenditures (including the
amount, nature, and sources of funding thereof) competitive
advantages business prospects and opportunities. Such
forward-looking statements reflect the Directors' current beliefs
and assumptions and are based on information currently available to
the Directors. Many factors could cause actual results to
differ materially from the results discussed in the forward-looking
statements, including risks associated with vulnerability to
general economic and business conditions, competition,
environmental and other regulatory changes actions by governmental
authorities, the availability of capital markets reliance on
crucial personnel uninsured and underinsured losses and other
factors many of which are beyond the control of the company.
Although any forward-looking statements contained in this
announcement are based upon what the Directors believe to be
reasonable assumptions. The company cannot assure investors that
results will be consistent with such forward-looking
statements.
The company deems the information contained within this
announcement to constitute Inside Information as stipulated under
the Market Abuse Regulation (E.U.) No. 596/2014, as it forms part
of U.K. domestic law under the European Union (Withdrawal) Act
2018, as amended. Upon the publication of this announcement via a
regulatory information service, this information is considered to
be in the public domain.