Victoria Gold Corp. (TSX-VGCX) (“Victoria” or the “Company”)
provides an update on the management of the heap leach facility
(“HLF”) incident that occurred at the Eagle Gold Mine on June 24,
2024 (see Company news releases dated June 24, 2024, July 4, 2024,
and July 12, 2024).
Safety
Victoria’s focus continues to be on the safety
of its employees and mitigation of harm to the environment. As
previously reported, the Company has and will continue to liaise
with the Government of Yukon, the First Nation of Nacho Nyak Dun
(“FNNND”), the Village of Mayo, the Yukon Workers’ Safety and
Compensation Board and other regulatory authorities.
Each activity occurring on site where workers
could potentially be exposed to risks related to the HLF incident
undergoes a rigorous Job Hazard Analysis to ensure employees are
working in a safe manner and under safe conditions. This includes
designation of certain areas of the site as Restricted Zones
pending the outcome of more detailed independent third-party
geotechnical and related reviews. The Company has conducted a
seismic survey, the results from which will aid in the assessment
of the integrity of the HLF embankment. The Company has also
established additional geotechnical monitoring initiatives. There
has been no significant material movement on the HLF since the
initial HLF incident.
Water Sampling
Victoria is actively sampling water daily from
multiple sample locations at the Eagle Mine. Several of these
sample locations are located downstream from the location of the
HLF incident. As previously disclosed in Victoria’s news release
dated July 12, 2024, the Company has detected trace amounts of
cyanide in Haggart Creek downstream of the HLF incident. The
majority of samples tested by the Company downstream of the HLF
have not detected any cyanide. The Company has detected minor
amounts of WAD cyanide in 7 of 134 samples collected as of July 23,
2024 downstream of the HLF incident in Haggart Creek. These results
range from concentrations of 5.2 to 9.3 parts per billion WAD
cyanide. The Company’s Downstream Water Quality Objectives pursuant
to its Water Use License for cyanide are 5 parts per billion WAD
cyanide.
For context, the Guidelines for Canadian
Drinking Water Quality1 establish a maximum acceptable
concentration (MAC) of 200 parts per billion free cyanide.
WAD cyanide includes the toxicologically
important forms of cyanide, including free cyanide and moderately
and weakly complexed metal-cyanides. Total cyanide includes free
cyanide, WAD cyanide, and relatively non-toxic iron-cyanide
complexes.
Water Management
Since the HLF incident, as previously disclosed,
within hours of the HLF incident a pumping system was established
to return contact water to lined containment ponds. The Company is
also collecting and storing groundwater in lined containment
ponds.
In addition, in order to further manage contact
water at the Eagle Gold Mine, the Company is completing the
expedited construction of additional lined water storage on site.
This additional storage will supplement pre-existing lined water
storage capacity at Eagle.
The Company, in consultation with independent
third-party experts, has evaluated a number of water management
strategies to minimize environmental impacts, with the safety of
employees as a foremost priority. The Company and its third-party
experts have determined that a modest irrigation strategy to the
areas of the HLF that were not impacted by the HLF incident is a
safe water management plan which will allow time for the Company to
augment water treatment and discharge capacity at site and will
avoid direct discharge of untreated water to the environment.
Water Treatment
In order to establish capacity to safely
discharge water in compliance with its Water Use License, the
Company has augmented its water treatment capacity on site. This
includes the modification of piping, the addition of tankage and
the procurement and installation of a Reverse Osmosis (“RO”) plant
which will be used as a final stage of water treatment.
The existing infrastructure within the Mine
Water Treatment Plant has been modified to allow inclusion of a
breakpoint alkaline chlorination process for cyanide destruction
and metals precipitation. This process utilizes sodium hypochlorite
to oxidize cyanide with the resulting ammonia byproduct oxidized by
chlorine to nitrogen gas.
The Company has successfully commissioned its
augmented water treatment capacity and anticipates the commencement
of treated water discharge in the coming days.
Root Cause Analysis
Investigations are underway to determine the
cause of the incident. The Company has engaged with its engineer of
record for the HLF and has retained multiple independent industry
leading experts to conduct a Root Cause Analysis. In addition, the
Company is cooperating with third-party technical experts retained
by the Yukon Government and the FNNND.
Production operations remain suspended and may
not restart without authorization from the Yukon Director of
Mineral Resources. Victoria will continue to work to minimize
impacts to the environment, with the safety of employees as a
foremost priority. There can be no assurance that the Company will
receive authorizations necessary to restart production, or that the
Company will have the financial resources necessary to repair
damage to equipment and facilities or remediate impacts caused by
the incident or restart production. The Company will provide
further updates in due course.
References:
1 -
https://www.canada.ca/en/health-canada/services/environmental-workplace-health/reports-publications/water-quality/guidelines-canadian-drinking-water-quality-summary-table.htmlAnd:https://www.canada.ca/en/health-canada/services/publications/healthy-living/guidelines-canadian-drinking-water-quality-guideline-technical-document-cyanide.htm
Qualified PersonThe technical
content of this news release has been reviewed and approved by Paul
D. Gray, P.Geo., who is a “Qualified Person” as defined in National
Instrument 43-101 - Standards of Disclosure for Mineral
Projects.
About the Dublin Gulch
PropertyVictoria Gold's 100%-owned Dublin Gulch gold
property (the “Property”) is situated in central Yukon Territory,
Canada, approximately 375 kilometers north of the capital city of
Whitehorse, and approximately 85 kilometers from the town of Mayo.
The Property is accessible by road year round, and is located
within Yukon Energy's electrical grid.
The Property covers an area of approximately 555
square kilometers, and is the site of the Company's Eagle and Olive
Gold Deposits. As at December 31, 2023, and adjusting for mining
depletion through this date, the Eagle and Olive Deposits include
Proven and Probable Reserves of 2.3 million ounces of gold from 114
million tonnes of ore with a grade of 0.63 grams of gold per tonne.
As at December 31, 2023, and adjusting for mining depletion through
this date, the Mineral Resource for the Eagle and Olive Gold
Deposits are estimated to host 234 million tonnes averaging 0.59
grams of gold per tonne, containing 4.4 million ounces of gold in
the "Measured and Indicated" category, inclusive of Proven and
Probable Reserves, and a further 36 million tonnes averaging 0.63
grams of gold per tonne, containing 0.7 million ounces of gold in
the "Inferred" category.
Cautionary Language and Forward-Looking
StatementsThis press release includes certain statements
that may be deemed "forward-looking statements". Except for
statements of historical fact relating to Victoria, information
contained herein constitutes forward-looking information, including
any information related to and the HLF incident, health, safety and
environmental impact matters relating to the HLF incident, the
results of Victoria’s engagement efforts with the Government of
Yukon and applicable regulatory authorities, as well as the FNNND,
the results of the ongoing investigation into the causes of the
failure at the heap leach facility, plans for remediating the
impact of the HLF incident and other related matters.
Forward-looking information is characterized by words such as
“plan”, “expect”, “budget”, “target”, “project”, “intend”,
“believe”, “anticipate”, “estimate” and other similar words, or
statements that certain events or conditions “may”, “will”, “could”
or “should” occur, and includes any guidance and forecasts set out
herein (including, but not limited to, production and operational
guidance of the Corporation). In order to give such forward-looking
information, the Corporation has made certain assumptions about its
business, operations, activities relating to the HLF incident, the
economy and the mineral exploration industry in general. In this
respect, the Corporation has assumed that production at the Eagle
Gold Mine will remain suspended indefinitely pending the results of
the investigation into the causes of the failure at the heap leach
facility and the successful conclusion of ongoing engagement and
discussions with the Government of Yukon, the FNNND and the
Corporation’s other stakeholders, no unusual geological or further
technical problems occur, no material adverse change in the price
of gold occurs and no further significant events occur outside of
the Corporation's normal course of business. Forward-looking
information is based on the opinions, assumptions and estimates of
management considered reasonable at the date the statements are
made, and are inherently subject to a variety of risks and
uncertainties and other known and unknown factors that could cause
actual events or results to differ materially from those described
in, or implied by, the forward-looking information. These factors
include the impact of the HLF incident on the Corporation’s
business and financial condition, risks related to liquidity and
credit availability resulting from the indefinite suspension of
production at the Eagle Gold Mine, the values of assets and
liabilities based on projected future conditions, potential
resumption of metals production, fluctuating metal prices, currency
exchange rates, estimated ore grades, possible variations in ore
grade or recovery rates, changes in economic model as a result of
unanticipated costs associated with the HLF incident, changes in
accounting policies, changes in Victoria's corporate resources,
changes in project parameters as plans continue to be refined,
changes in development and production time frames, the possibility
of cost overruns or further unanticipated costs and expenses,
uncertainty of mineral reserve and mineral resource estimates,
higher prices for fuel, steel, power, labour and other consumables
contributing to higher costs and general risks of the mining
industry, further failures of plant, equipment or processes to
operate as anticipated, final pricing for metal sales,
unanticipated results of future studies, seasonality and
unanticipated weather changes, costs and timing of the development
of new deposits, success of exploration activities, requirements
for additional capital, permitting time lines, government
regulation of mining operations, environmental risks, unanticipated
reclamation expenses, title disputes or claims, limitations on
insurance coverage and timing and possible outcomes of pending
litigation and labour disputes, risks related to remote operations
and the availability of adequate infrastructure, fluctuations in
price and availability of energy and other inputs necessary for
mining operations. Although Victoria has attempted to identify
important factors that could cause actual actions, events or
results to differ materially from those described in, or implied
by, the forward-looking information, there may be other factors
that cause actions, events or results not to be anticipated,
estimated or intended. There can be no assurance that
forward-looking information will prove to be accurate, as actual
results and future events could differ materially from those
anticipated in such statements. The reader is cautioned not to
place undue reliance on forward-looking information. The
forward-looking information contained herein is presented for the
purpose of assisting investors in understanding Victoria's expected
financial and operational performance and Victoria's plans and
objectives and may not be appropriate for other purposes. All
forward-looking information contained herein is given as of the
date hereof, as the case may be, and is based upon the opinions and
estimates of management and information available to management of
the Corporation as at the date hereof. The Corporation undertakes
no obligation to update or revise the forward-looking information
contained herein and the documents incorporated by reference
herein, whether as a result of new information, future events or
otherwise, except as required by applicable laws.
For Further Information
Contact:John McConnellPresident & CEOVictoria Gold
CorpTel: 604-696-6605ceo@vgcx.com
Victoria Gold (TSX:VGCX)
Historical Stock Chart
From Oct 2024 to Nov 2024
Victoria Gold (TSX:VGCX)
Historical Stock Chart
From Nov 2023 to Nov 2024