21 March
2024
Centamin plc
("Centamin" or "the
Company")
(LSE:CEY, TSX:CEE)
Full year 2023 results
Audited results
for the twelve months ended 31 December
2023
MARTIN HORGAN, CEO, commented: "2023 is the third
consecutive year that we have safely delivered on our production
guidance, reflecting the operational improvements and flexibility
from our three-year reinvestment plan. Despite ongoing local
inflationary pressures, we reduced our AISC by $194/oz versus 2022,
beating the lower end of our guidance range. With the reinvestment
programme ending in 2024, Sukari has been repositioned towards
consistently delivering 500,000 ounces per annum over the
long-term, with further growth and cost saving opportunities
identified.
Looking ahead to 2024, the grid connection project will
continue our recent success in taking costs out of the business
whilst delivering into our near-term decarbonisation targets of
reducing our scope 1 and 2 emissions by 30% by 2030. We will
continue to advance the organic growth opportunities within our
portfolio of assets by aggressively following up on the recent
exploration success with our Eastern Desert Exploration
drilling programme
("EDX") and
proceed towards
an investment
decision at Doropo in Cote d'Ivoire following the publication of
the DFS later this year."
HIGHLIGHTS
●
|
9.5 million hours worked at the Sukari Gold Mine ("Sukari")
with zero lost time injuries ("LTI"). The Group lost time injury frequency rate ("LTIFR") of 0.08
was an 83% improvement on the 3-year trailing average. Total
recordable injury frequency rate ("TRIFR") of 2.83, a 24%
improvement on the 3-year trailing average.
|
●
|
Scope 1 and 2 Greenhouse Gas Emissions "GHG" reduced by 7%
since 2021 base year, driven primarily by the 21.5 million litre
reduction in diesel consumption during the first full year of solar power
generation.
|
●
|
Gold production of 450,058 ounces ("oz"), a 2% increase on 2022, delivered in line with 2023
guidance.
|
●
|
All-in sustaining costs ("AISC") of US$1,205/oz
sold, a 14% improvement on 2022,
beating 2023 guidance.
|
●
|
Increased adjusted EBITDA by 25% to US$398 million, at a 45% margin, up from 40% in
2022.
|
●
|
Annual capital expenditure ("capex") of US$204 million below
guidance of US$272 million: due to
cost savings, lower capitalisation of costs and changes to
equipment rebuild schedules.
|
●
|
Sukari cash contribution of US$121m, including US$45 million in cost recovery and US$112 million
of profit share, net of US$36 million capex funded from corporate.
Government profit share and royalties totalled US$139
million.
|
●
|
Group free cash flow of US$49
million, up from -US$18 million in
2022.
|
●
|
Robust balance sheet with
cash and liquid assets of US$153 million, as at 31 December 2023,
and total liquidity of US$303 million including the undrawn US$150
million sustainability-linked revolving credit facility.
|
●
|
Final dividend of 2.0 US cents per
share, equating to US$23 million,
subject to approval at the annual general meeting on 21 May 2024.
Total dividend for full year 2023 of 4.0 US cents per share or
US$46 million.
|
GROUP FINANCIAL SUMMARY
|
FY 2023
|
FY
2022(2)
|
% Δ
|
H2-2023
|
H1-2023
|
Gold sold (oz)
|
456,625
|
438,638
|
4%
|
237,271
|
219,354
|
Cash costs (US$/oz
produced)
|
875
|
913
|
-4%
|
901
|
849
|
AISC (US$/oz sold)
|
1,205
|
1,399
|
-14%
|
1,184
|
1,228
|
Realised gold price
(US$/oz)
|
1,948
|
1,794
|
9%
|
1,963
|
1,936
|
Revenue (US$000)
|
891,262
|
788,424
|
13%
|
465,650
|
425,612
|
Adjusted EBITDA
(US$000)
|
398,175
|
319,015
|
25%
|
205,250
|
192,925
|
Profit before tax
(US$000)
|
195,140
|
171,001
|
14%
|
80,336
|
114,804
|
Profit after tax attrib. to the
parent (US$000) (1)
|
92,284
|
72,490
|
27%
|
34,916
|
57,368
|
Basic EPS (US cents)
(1)
|
7.97
|
6.29
|
27%
|
3.02
|
4.96
|
Gross capex (US$'000)
|
204,111
|
283,543
|
-28%
|
95,850
|
108,261
|
Operating cash
flow(US$'000)(2)
|
353,600
|
292,524
|
21%
|
181,834
|
171,767
|
Adjusted free cash flow(US$'000)
(2)
|
48,995
|
-17,551
|
379%
|
29,633
|
19,362
|
1. The profit after tax
attributable to the parent and the Basic EPS for H1 2023 was
updated after the reconciliation of the profit attributable to the
Non-Controlling Interest (due to EMRA) for both H1 2023 and H2 2023
was completed at year end.
2. The comparatives in the
Consolidated Statement of Cash Flows for the year ended 31 December
2022 have been restated to reflect an increase of cash generated
from operating activities of $2.5m, interest paid of $1.9m and a
reduction of the effect of foreign exchange rate changes of $0.6m,
resulting in the net restatement of the Operating cash flow and the
adjusted free cash flow figures by an increase of
US$0.6m
2024 OUTLOOK
Guidance unchanged
●
|
Gold production guidance range of
470,000 to 500,000 oz per annum with a minor weighting towards
H2
|
●
|
Cost guidance:
|
|
○
|
Cash cost guidance range of
US$700-850/oz produced
|
|
○
|
AISC guidance range of
US$1,200-1,350/oz sold
|
|
○
|
Guidance reflects a range of
diesel prices from 75-90 US cents per litre
|
●
|
Adjusted capex guidance is $215m,
including:
|
|
○
|
US$112m of sustaining
capex
|
|
○
|
US$103m of non-sustaining capex,
of which US$58m is allocated to growth projects that are funded
from Centamin treasury under the Sukari Concession Agreement and
cost recovered over three years
|
|
○
|
Adjusted capex excludes US$91m of
sustaining deferred stripping reclassified from operating
costs
|
|
|
| |
2024 KEY MILESTONES
●
|
Doropo Project, Cote d'Ivoire,
completed DFS (mid-2024)
|
●
|
Accelerated waste-stripping
programme completion (mid-2024)
|
●
|
EDX exploration update (H2
2024)
|
●
|
Sukari 50MW grid connection
project construction (H2 2024)
|
●
|
Completion of Solar Expansion
Study (H2 2024)
|
WEBCAST PRESENTATION
The Company will host a webcast
presentation today, Thursday 21 March, at 08.30 GMT, to discuss the
results with investors and analysts, followed by an opportunity to
ask questions. Please find below the required participation
details. A recording will be made available on the Company
website.
To join the webcast:
https://www.lsegissuerservices.com/spark/Centamin/events/0995e3c5-b8c1-46ed-ac98-de2fa708e250
Please allow a few minutes to
register.
PRINT-FRIENDLY VERSION of the
results: www.centamin.com/investors/results-reports/
About Centamin
Centamin is an established gold
producer, with premium listings on the London Stock Exchange and
Toronto Stock Exchange. The Company's flagship asset is the Sukari
Gold Mine ("Sukari"), Egypt's largest and first modern gold mine,
as well as one of the world's largest producing mines. Since
production began in 2009 Sukari has produced 5.7 million ounces of
gold, and today has a projected mine life to 2034.
Through its large portfolio of
exploration assets in Egypt and Côte d'Ivoire, Centamin is
advancing an active pipeline of future growth prospects, including
the Doropo project in Côte d'Ivoire, and over 3,000km2
of highly prospective exploration ground in Egypt's Arabian Nubian
Shield.
Centamin practices responsible
mining activities, recognising its responsibility to deliver
operational and financial performance and create lasting mutual
benefit for all stakeholders through good corporate
citizenship.
FOR MORE INFORMATION please
visit the website www.centamin.com
or contact:
ENDNOTES
Guidance
The Company actively monitors the
global geopolitical uncertainties and macroeconomics, such as
global inflation, and guidance may be impacted if the supply chain,
workforce or operation are disrupted.
Financials
Full year financial data points
included within this report are audited.
Non-GAAP measures
This statement includes certain
financial performance measures which are not GAAP measures as
defined under International Financial Reporting Standards (IFRS).
These include EBITDA and adjusted EBITDA, Cash costs of production,
AISC, Cash and liquid assets, Free cash flow and adjusted Free cash
flow. Management believes these measures provide valuable
additional information for users of the financial statements to
understand the underlying trading performance. An explanation of
the measures used along with reconciliation to the nearest IFRS
measures is provided in the Financial Review.
Profit after tax attributable to the parent
Centamin profit after the profit
share split with the Arab Republic of Egypt.
Royalties
Royalties are accrued and paid six
months in arrears.
Cash and liquid assets
Cash and liquid assets include
cash, bullion on hand and gold sales receivables and financial
assets at fair value through profit or loss.
Movements in inventory
Movement in inventory on ounces
produced is the movement in mining stockpiles and ore in circuit
while the movement in inventory on ounces sold is the net movement
in mining stockpiles, ore in circuit and gold in safe
inventory.
Gold produced
Gold produced is gold poured and
does not include gold-in-circuit at period end.
Dividend
All dividends are subject to final
Board approval and final dividends are subject to shareholder
approval at the Company's annual general meeting.
Forward-looking Statements
This announcement (including
information incorporated by reference) contains "forward-looking
statements" and "forward-looking information" under applicable
securities laws (collectively, "forward-looking statements"),
including statements with respect to future financial or operating
performance. Such statements include "future-oriented financial
information" or "financial outlook" with respect to prospective
financial performance, financial position, EBITDA, cash flows and
other financial metrics that are based on assumptions about future
economic conditions and courses of action. Generally, these
forward-looking statements can be identified by the use of
forward-looking terminology such as "believes", "expects",
"expected", "budgeted", "forecasts" and "anticipates" and include
production outlook, operating schedules, production profiles,
expansion and expansion plans, efficiency gains, production and
cost guidance, capital expenditure outlook, exploration spend and
other mine plans. Although Centamin believes that the expectations
reflected in such forward-looking statements are reasonable,
Centamin can give no assurance that such expectations will prove to
be correct. Forward-looking statements are prospective in nature
and are not based on historical facts, but rather on current
expectations and projections of the management of Centamin about
future events and are therefore subject to known and unknown risks
and uncertainties which could cause actual results to differ
materially from the future results expressed or implied by the
forward-looking statements. In addition, there are a number of
factors that could cause actual results, performance, achievements
or developments to differ materially from those expressed or
implied by such forward-looking statements; the risks and
uncertainties associated with direct or indirect impacts of
COVID-19 or other pandemic, general business, economic,
competitive, political and social uncertainties; the results of
exploration activities and feasibility studies; assumptions in
economic evaluations which prove to be inaccurate; currency
fluctuations; changes in project parameters; future prices of gold
and other metals; possible variations of ore grade or recovery
rates; accidents, labour disputes and other risks of the mining
industry; climatic conditions; political instability; decisions and
regulatory changes enacted by governmental authorities; delays in
obtaining approvals or financing or completing development or
construction activities; and discovery of archaeological ruins.
Financial outlook and future-ordinated financial information
contained in this news release is based on assumptions about future
events, including economic conditions and proposed courses of
action, based on management's assessment of the relevant
information currently available. Readers are cautioned that any
such financial outlook or future-ordinated financial information
contained or referenced herein may not be appropriate and should
not be used for purposes other than those for which it is disclosed
herein. The Company and its management believe that the prospective
financial information has been prepared on a reasonable basis,
reflecting management's best estimates and judgments at the date
hereof, and represent, to the best of management's knowledge and
opinion, the Company's expected course of action. However, because
this information is highly subjective, it should not be relied on
as necessarily indicative of future results. There can be no
assurance that forward-looking statements will prove to be
accurate, as actual results and future events could differ
materially from those anticipated in such information or
statements, particularly in light of the current economic climate
and the significant volatility, the risks and uncertainties
associated with the direct and indirect impacts of COVID-19.
Forward-looking statements contained herein are made as of the date
of this announcement and the Company disclaims any obligation to
update any forward-looking statement, whether as a result of new
information, future events or results or otherwise. Accordingly,
readers should not place undue reliance on forward-looking
statements.
LEI: 213800PDI9G7OUKLPV84
Company No: 109180
CEO Statement
I am pleased to report that 2023
was the third consecutive year of delivery into our production
guidance while beating our all-in sustaining cost and capex
forecasts. Our focus on operation delivery, alongside a strong gold
price environment enabled the Company to generate robust cash
flows, supporting the continued investment in our operations
without the need to draw down on our sustainability-linked
loan.
2023 was the last full-year of our
operational reset plan as we unlock the full potential of the
Company's portfolio, at the Sukari mine we have focused on the
optimisation of the operations and we published a new Life of Mine
Plan. The plan maximises the production opportunity and returns the
mine to a 500,000 ounce annual production run rate in the long-term
while simultaneously focussing on cost and operational efficiencies
that will position the mine in the lower half of the industry cost
curve and, when combined with the increased gold production,
deliver a sustainable improvement in cashflows.
Alongside Sukari, we have made
encouraging progress across our EDX portfolio with the
identification of potential satellite feed targets in close
proximity to the Sukari mine, whilst in Côte d'Ivoire, we have
delivered a Pre-Feasibility Study for our Doropo
project.
Having delivered on our
commitments during 2023, we enter 2024 with confidence and the
potential to realise further opportunity across our portfolio,
supported by a strong balance sheet. With the investment in
resetting our operations now pivoting to investment in growth we
believe we are at an inflection point that will soon see us
rewarded for the multi-year investment programme, with stronger
free cash flow enabling us to deliver that growth while maintaining
our track record of dividend payments.
EGYPT
It was a challenging year within
the broader North Africa and Middle East region as a result of
multiple conflicts across the region alongside the ongoing impact
of the global inflationary environment. Despite these challenges,
the Company was well positioned to navigate the operating
environment with limited impact on our business. We believe that
the risk management processes developed through COVID-19 have
enabled the Company to continue to better identify and therefore
mitigate risks. For example, to minimise disruption to
operations the Sukari mine carries higher levels of inventory which
are sourced from a more diversified supply chain, helping to
minimise any potential interruption to our business in 2023.
We continue to monitor the state of the broader Egyptian economy as
it navigates short term pressures and note that as a "Dollar
functional business" Centamin has been largely insulated from many
of these pressures.
We recognise the importance of the
Sukari Gold Mine and our exploration blocks to our host nation,
Egypt. Through Royalties and profit share payments we have returned
US$139m to the government in 2023 while indirectly contributing
US$686m through employment and local procurement. The Sukari mine
is an important employer within Egypt with over 4,400 jobs at the
mine site through direct and contractor
employment.
Given mining's current and
potential contribution to the broader Egyptian economy, I am
pleased to note that the modernisation of the Egyptian mining
industry continued during 2023, with an in-principle agreement
around the terms of a new Model Mining Exploitation Agreement
(MMEA) with EMRA and the Ministry of Petroleum & Natural
Resources. The successful completion of two years of negotiation
between an industry group and the government lays the foundation
for a balanced economic outcome between state and industry that
sits within a robust development framework that is in-line with
international practices. The new MMEA unlocks untapped potential of
the Arabian Nubian Shield in Egypt and we have been able to
leverage off our previous success at Sukari to be one of the first
movers in Egypt's Eastern Desert and despite only starting drilling
in 2023, we have already enjoyed drilling success which we will
build on in 2024.
Sukari Gold Mine
We view safety performance as a
good proxy for management capability - 2023 saw continued
improvement with only a single LTI recorded within the period and
an improvement across LTIRF and TRIFR metrics relative to the three
year trailing average. Following an ISO audit we are pleased to
have been certified for ISO 45001 Occupational Health and Safety
management systems, giving external validation to the strength of
our safety systems and processes and external validation of the
work completed by the team at Sukari over the last few
years.
Our work on sustainability
continued with a focus on defining and delivering our
decarbonisation roadmap, staffing across gender diversification,
training and management promotion. We also developed a roadmap
for Global Industry Standard on Tailings
Management ("GISTM") conformance with the Engineer of
Record (Epoch) to manage our tailings facilities - targeting
conformance by 2025 for SGM across the TSFs we operate.
This year was the first full year
that Sukari benefited from the cost savings and decarbonisation
impact of the 30MWAC solar plant commissioned in 2022. The facility achieved
design specifications in terms of reduction in diesel consumption
and hence carbon abatement and it is pleasing to see that we are
already delivering into our carbon reduction targets. Given
the success of this facility we are assessing the solar expansion
project which would provide further cost and decarbonisation
benefits by generating all our power requirements from full solar
power during daylight hours. In parallel our grid connection
project offers further carbon abatement and significant cost
benefits following the planned implementation in 2025 with the aim
of displacing diesel completely from power generation at Sukari on
a combined basis.
2023 saw the publication of the
updated Life of Mine Plan ("LoM plan") which confirms Sukari's
status as a Tier 1 asset based on the forecast production and cost
profile over the next decade of operations. We have demonstrated a
fully engineered plan that sees production return to 500,000 ounces
per year, costs in the lower half of the industry cost curve and a
mine life in excess of ten years. The plan is centred around the
lowering of operating risk through the use of improved data and
technical understanding, underpinning a more robust planning
process that incorporates operational contingency to address
unforeseen issues that arise from time to time.
Despite the excellent progress
already made, we are continually searching for continuous
improvement opportunities. We have already identified areas to
refine and improve this plan. During 2024 we will continue to
investigate these opportunities and seek further opportunity for
growth and optimisation.
In addition to articulating our
long term vision for the Sukari mine, we also maintained our focus
on delivery into guidance. Our production was in the lower
end of the guidance range which given the unscheduled, preventative
maintenance completed in the milling circuit during the third
quarter was pleasing and highlighted the contingency in the
operating plan. The focus on cost control and prudent
budgeting continued through 2023, enabling us to beat the all-in
sustaining cost guidance while we further improved cash flow
through capex savings associated with a change in our rebuild
strategy alongside some deferrals on project spend.
Since 2020 we have placed a
significant focus on our geological understanding of our assets and
2023 saw continued progress delivering Resource and Reserve growth
at the operation, driven by underground exploration success and a
redesign of the open pit and underground mining areas in the new
LoM Plan.
Operationally, the open pit
performed well with the planned waste movement being achieved while
the team mined 44% more ore compared to 2022 due to mining in the
northerly stage 7 area of the pit which saw significant waste to
ore conversion resulting from a lack of drill coverage due to steep
terrain - it is not anticipated that this will continue into 2024
or beyond. The underground achieved the targeted volume
growth with one million tonnes of ore hauled to surface by our
mining fleet, up from 625,000 tonnes in 2020 when underground
mining was carried out by a contractor. We remain on track to
achieve 1.4Mt per annum by 2026 as per the new LoM plan. Despite
the unscheduled mill maintenance issue, the processing facility
achieved 12Mt milled with metallurgical recoveries at the top end
of the targeted performance range which was an excellent
outcome.
In respect of our tailings
facilities, further progress was made with our work to bring
Centamin in line with the requirements of the GISTM and we have
developed a roadmap of work streams that will see the company
conforming by end-2025 - our facilities are in a good position at
this time and the work being completed at Sukari will ensure we
continue to work in line with international standards around
tailings facilities.
On the workforce front, we
continued to make good progress around our gender diversity targets
and as 2023 saw a further increase in female employment at the
Sukari mine - this initiative is a key priority for the Company and
performance in this area is embedded in both our corporate lending
facility and management performance metrics relating to
remuneration. While gender diversification lends itself to
new employees, it has not come at the cost of our existing
workforce - our Employee Development Pathway training programme
continued to make good progress since commencement in 2021 and last
year we introduced the Leadership Development Pathway focussing on
the identification and development of talented individuals and
providing a framework for them to reach their full
potential.
Looking forward to 2024, we expect
to see continued Resource and Reserve development resulting from
our focused geological exploration efforts, maintain our upward
trajectory in regards to production growth and retain a focus on
cost control to drive improved cash flow through delivering such
outcomes as the grid connection and potential solar
expansion.
Eastern Desert Exploration ("EDX")
It was a landmark year for our
Egyptian exploration activities outside of the Sukari Mining
Concession. In 2020, with the launch of Egypt's EDX bid round
and vision for a new modern mining industry, Centamin applied for a
number of exploration licences across the Eastern Desert - both
adjacent to the Sukari mine and more remote from the
operations. Since being successfully awarded approximately
3,000km2 of ground, Centamin has embarked on both field
work to generate drill targets while simultaneously working with
the government of Egypt and an industry group to finalise the terms
of the new model mining exploitation agreement (MMEA).
In mid-2023, negotiations between
government and industry were concluded to set out the final terms
of a comprehensive legal and fiscal framework applicable to any
future discovery in the EDX blocks that compliments the agreed
exploration terms finalised in 2021. Following agreement of the
terms, the MMEA will be submitted to Parliament for approval as a
special law. The MMEA terms represent a balanced and equitable
outcome for stakeholders (government / industry / local
communities) while providing a robust legal framework in line with
the internationally accepted standards required by the industry for
the long-term investment horizons associated with mining
projects. It also places Egypt in a competitive position
compared to other mining jurisdictions as it seeks to unlock its
untapped geological potential.
In parallel with the negotiation
process, Centamin continued exploration field work across our
portfolio with an initial focus on the areas immediately adjacent
to the Sukari mine.
During 2022 and the first half of
2023, a series of drill targets in the Nugrus Block were identified
by our team with some eight zones of interest all within 30km of
Sukari. H2 2023 saw the mobilisation of an RC rig to undertake an
initial 16,216 meter scout drilling campaign across these targets.
The results were released in early 2024 showing promise at two of
the eight targets - Little Sukari and Um Majal - where potentially
commercial zones of mineralisation were identified.
In parallel, soil sampling was
completed across the Um Rus block some 50km north of Sukari with
the aim of testing geological structures for potential gold
mineralisation that could be developed into drill targets.
Late in the year field work commenced at the Nadj block, some 100km
north of Sukari with the timing aimed at seeking to work in the
cooler winter and spring months ahead of the
summer.
2024 will see an aggressive follow
up to the success seen in Nugrus at Little Sukari and Um Majal.
Further mapping, IP surveys and an extended drilling campaign are
planned to further define the potential of both targets. Work will
continue at Um Rus and Nadj blocks with the potential to generate
drill targets that can be tested in late 2024 and into 2025,
subject to successful outcomes.
CÔTE D'IVOIRE
Doropo
Good progress was achieved across
our Côte d'Ivoire portfolio with a specific focus on the
advancement of the Doropo project in northern Côte d'Ivoire.
The Pre-Feasibility Study ("PFS") demonstrated a viable project
with an attractive scale of gold production at a competitive cost
profile in line with capital cost intensity as seen across the
region. Based on the PFS outcomes the project currently meets
Centamin's hurdles for scale, quality and financial metrics which
supported the decision to commence a full Feasibility Study and
associated ESIA for Doropo which will be completed in
mid-2024.
The development plan is
technically simple in terms of robust geology, supporting
relatively shallow open pit mining across multiple sites which feed
into an industry standard process facility - the main challenge
with the project relates to its interaction with and impacts on
local communities during the construction and operation
phases.
As such, a significant effort has
been completed in respect of mapping and understanding the baseline
social and environmental setting of the project area and
importantly ensuring that this data is utilised in the project
design phase to minimise impacts on local communities by following
a hierarchy of: Avoid / Minimise / Mitigate / Compensate. This has
led to changes in project design to accommodate this strategy and
ultimately deliver a more robust outcome for all
stakeholders.
The delivery of the Doropo PFS has
enabled Centamin to publish our first non-Sukari reserve and has
been one of the key drivers of the Company exceeding its stated aim
of growing the Group Reserves by more than 3Moz over the three
years from 2021 to 2023, having now delivered 3.5Moz of Reserve
growth.
Building on the success of the
PFS, the Company launched the Definitive Feasibility Study ("DFS")
and associated ESIA in mid-2023 with aim of submitting a mining
licence application in mid-2024. In parallel, we have started to
assess the funding options for the construction phase of Doropo
with the aim of reaching a final investment decision point in late
2024 with a fully funded construction package in place alongside
the requisite in-country permits required to enable the Board to
make an informed decision on the construction phase.
2024 OUTLOOK
In 2024 we look to continue our
track record of delivery and building on the platform for growth
that has been established by the reinvestment programme at Sukari.
We are forecasting increased production of 470,000 to 500,000
ounces and are targeting all-in sustaining costs of US$1,200-1,350
per ounce sold.
This year capex at Sukari will be
US$215m, plus US$91m of sustaining deferred stripping reclassified
from operating costs. This includes the final phase of contracted
waste-stripping programme which is expected to be completed during
the middle of the year. Other investments include the grid power
connection project, fleet expansion and underground expansion which
will combine to support long-term production rates of around
500,000 ounces per year and improved margins.
We will follow up on our initial
success at EDX to assess the potential for satellite feed to be
trucked to the Sukari mine and complete the Doropo Definitive
Feasibility Study. In respect of Government interaction we will
look to finalise the MMEA signature and have this ratified by
Parliament and progress the work on our 15 year Tax Exemption
Renewal for Sukari to take effect from March 2025.
After a successful year of
excellent progress across our portfolio, I would like to thank all
our stakeholders who have made this progress possible. From the
dedication and hard work of our workforce across our portfolio,
through to our host governments and local stakeholders, it is their
support and engagement that has enabled us to continue the journey
at Centamin across 2023 and set us up for further success into 2024
and beyond.
Martin Horgan
Chief Executive Officer
FINANCIAL REVIEW
The last three years have been
about delivering the bold capital reinvestment plans required to
sustain our business and drive both higher production and improved
margins for the next decade and beyond. We exit this
reinvestment period with a much improved business which is well set
for the future.
The significance of having a tier
one asset is evident when faced with economic challenges. Inflation
was the one common threat that had an impact across the whole
industry in 2023. Despite these pricing pressures and persisting
global supply-side issues, our focus was firmly on what we could
control. We did this through rigorous planning and disciplined
execution on plans, and supported by a robust risk and opportunity
assessment to ensure we were always striving to improve.
FINANCIAL PERFORMANCE
Centamin delivered a resilient
financial performance that was in line with our expectations and
guidance for the year. The Company's strong operational performance
throughout the year was supported by the healthy gold price
environment, which remained robust in 2023.
The Group's results are
significantly affected by movements in the gold price, input costs,
particularly in consumables and fuel, and to a lesser degree
foreign exchange rates. All of which are external factors of which
we need to minimise the impact. We have protected our exposure to
the gold price through the gold price protection programme from
July 2023 through to June 2024 (240,000 ounces at a $1,900 gold
price per ounce) to match the remaining significant capital
investment period which ends in H1 2024.
Revenues increased year-on-year by
13% to US$891 million, generated from annual gold sales of
456,625 ounces, up 4%,
at an average realised price of US$1,948 per ounce, up 9%
year-on-year. A total of 6,915 ounces of unsold gold bullion was
held onsite at year end, due to the timing of gold shipments across
the year end.
Adjusted EBITDA increased by 25%
to US$398 million, at a 45% EBITDA margin, principally driven
by;
●
|
a 2% increase in gold production,
as scheduled, at an average realised gold price that was 9% higher
as compared to last year;
|
●
|
cost of sales (excluding the
effect of depreciation and amortisation) remaining flat year on
year which was due to a 5% decrease in the combined open pit and
underground material mined at a slightly higher cost per tonne,
part of this cost has been capitalised to mining properties as a
waste stripping asset.
|
Profit before tax increased by 14%
to US$195 million, due to;
●
|
a 13% increase in revenue of
US$103 million as compared to 2022, in line with both increased
gold sales and gold prices,
|
●
|
a 10% increase in cost of sales
driven by a marginal change in mine production costs, however a 25%
movement of mining inventory (decrease) against a 35% movement
depreciation and amortisation costs (increase), accounts for the
net change,
|
●
|
a 240% increase in interest income
due to higher interest rates on amounts placed in interest bearing
deposit products in 2023 as compared to deposit yields in
2022,
|
●
|
a 12% decrease in other income,
mainly driven by foreign exchange movements during the
year,
|
●
|
a 40% increase in other operating
costs of US$20 million mainly due to a non-cash US$4 million
inventory write off, a US$3 million increase in royalties (due to
the higher gold sales) and an US$9 million non-cash loss on asset
disposals.
The Group implemented a new
enterprise resource planning (ERP) software system, SAP (S4 HANA)
during the year. As part of the implementation and migration from
the legacy system, an extensive review process of the fixed assets
was performed as part of the fixed asset register and operational
records clean up. Consequently, assets that were identified as not
being in use and/or had been previously replaced by other assets
(e.g. mobile equipment rebuilds) had their carrying values
derecognised from the statement of financial position resulting in
a US$9 million loss on asset disposals.
|
●
|
a 6% increase in greenfield
exploration and evaluation expenditure.
|
As expected, and in line with our
three-year reinvestment plans, Centamin's cash flows and earnings
were positively impacted in 2023 by higher gold production and
sales, offset by higher costs.
Cashflows
Operational cash flow increased by
21% to US$354 million. Cash flows from investing activities were
impacted mainly by gross capital expenditure of US$204 million,
predominantly invested in sustaining the long-term production from
Sukari.
During 2023 each partner received
profit share distributions of US$112 million (2022: US$36 million
(EMRA) and US$46 million (Centamin).
In addition to the profit share
distributions, Centamin also received cost recovery payments
totalling US$45 million from SGM.
Centamin financed growth projects
of US$36 million into Sukari, spent US$31 million in greenfield
exploration related costs, advancing of our organic growth pipeline
at our exploration projects Doropo, EDX and ABC, plus paid for our
corporate activities.
COST MANAGEMENT
Our approach to forecasting and
stringent cost management meant we were able to counter some of the
global inflationary cost pressures last year and delivered costs
either below or as stated in our guidance (albeit that the ounce
profile was at the lower end of the range).
Continued good progress was made
during the year on the cost savings programme. At 31 December 2023
we had extracted US$185 million of sustainable cost savings from
the business over the period of the programme. We remain motivated
to find further opportunities, initiatives
included the solar plant, light weight truck trays, re-ripping of
dump leach material and appointment of a new underground drilling
contractor.
The most significant future
opportunity remains the national grid power tie
in. The tender for connection to the national grid was successfully
completed, and the Sukari leadership is busy drafting a definitive
agreement with the winning bidder, with an estimated energisation
date at the beginning of 2025.
Programme 2020 -2023
|
31 Dec
2023
|
Cost savings achieved per
year
|
US$'000
|
2020
|
44,000
|
2021
|
28,870
|
2022
|
43,273
|
2023
|
68,777
|
Cumulative total cost savings since
start of initiative
|
184,920
|
Cash costs of production were
US$875 per ounce produced, down 4%, reflecting a 5% decrease in
total open pit material mined tonnes, and a 2% decrease in tonnes
processed, offset by a 36% year on year increase in total
underground mined tonnes and a 2% increase in gold ounces
produced.
AISC was US$1,205 per ounce sold,
down 14%, mainly due to a 63% decrease in other sustaining capital
expenditure, partially offset by a 12% increase in royalties on
gold sales paid to the Egyptian government, a 36% increase in
corporate administration costs which was driven by a number of one
off projects. This was also complemented by a 4% increase in gold
ounces sold (which was as scheduled and in line with
guidance).
FUEL PRICES
Major macroeconomic and
geopolitical events influenced the oil price throughout 2023 with
rising interest rates and the risks of recessions weighing on oil
price demand outlooks.
Oil price is the most
significant commodity assumption materially
affecting the cost base of our business. The average price realised for the 2023 year was US$0.80 per
litre which was below actual spend and what we had budgeted for and
resulted in savings of US$15m despite using 2.3 million litres more
than budgeted (actual fuel used in 2023 was 165m litres) with
majority being used in the underground operations due to increased
activity.
Total diesel consumption across the Sukari operation
in 2024 is
expected to be 160m litres equating to
US$145 million at US$0.90/litre. The solar plant performance has resulted in a
significant reduction in diesel
consumption compared to historical averages, while
the mining contractor's
diesel consumption is reduced by 50% as the waste mining contract comes to an end by June 2024.
Further fuel savings are expected
beyond 2024 with the Grid Connection Project and solar expansion
opportunities. Refer to our Decarbonisation Roadmap for more
information on the initiatives underway to fully displace the use
of diesel oil for power generation at Sukari.
IMPACT OF FOREX
Some of Egypt's more long-standing
challenges have intersected with multiple global shocks causing a
foreign exchange crisis, historic inflation, and pressures to
worsen the already-stretched fiscal and external
accounts.
While triggered by the global
polycrisis, the rising macroeconomic imbalances in Egypt reflect
pre-existing domestic challenges, including the sluggish non-oil
exports and FDI, constrained private sector activity and
job-creation, as well as the elevated and rising government debt.
Egypt's overall macroeconomic environment during FY2023/24 is
expected to be undermined by the concurrent global shocks and
domestic macroeconomic imbalances and regional instability, before
starting to improve over the medium-term as the country continues
to push ahead with stabilisation and structural reforms.
The three pillars of Egypt's path
forward focus on foreign exchange management, inflation targeting
at the central bank, and private sector development / State Owned
Enterprises ("SOE") reform. There remain notable opportunities for
Egypt to attract foreign capital and investment which will drive
much-needed sustainable inflows for a medium-term solution to the
current economic imbalances. A significant step forward was made on
the reform programme when the Egyptian Pound ("EGP") was free
floated on 6 March 2024.
Our business is primarily USD
denominated so largely protected against the EGP devaluation, but
local supply chain costs and availability of goods becomes
challenging. The workforce in Egypt were awarded two sets of
increases during 2023 with a 15% increase in January 2023 and a
further 30% increase in October 2023. We continue to focus on and
manage these challenges as a business to ensure that our EGP
component cost base remains well managed (circa 15% of the Group
spend) and anticipate that while inflation remains a challenge in
the short term, expect it to settle over the longer
term.
CAPITALISATION OF OPEN PIT
WASTE-STRIPPING
The largest investment in 2023 was
on the accelerated waste-stripping (deferred waste-stripping) which
added US$90 million to our balance sheet, US$89 million was
included in non-sustaining capital expenditure and related
specifically to the work done by the waste-mining contractor, with
the balance of US$1 million allocated to sustaining capital
expenditure, which was waste material mined by the Centamin fleet
above the life of mine strip ratio. Some deferred waste-stripping
has already been amortised in the year based on ore extracted from
the areas mined.
Refer to note 2.10 to the
financial statements for further information.
STRONG BALANCE SHEET
Centamin closed the 2023 financial
year with cash and liquid assets of US$153 million.
As announced on 22 December 2022,
we secured the first piece of corporate debt and on 13 March 2023,
all conditions precedent were met regarding the US$150 million
sustainably linked revolving credit facility ("RCF"), significantly
increasing the Company's financial flexibility to fund growth
projects across the portfolio. Initially, the focus will be Sukari.
Under the terms of our Concession Agreement growth capital invested
and funded by Centamin, is recovered over three years, making these
investments ideally suited for the structure of the RCF. Due to the
strong operational performance supported by the gold price we were
able to manage our investments without drawing on the RCF facility
during 2023.
APPROACH TO CAPITAL
ALLOCATION
Capital allocation continues to be
disciplined and closely qualified against value creation. The
Company continues to exercise a balanced approach to responsibly
maximising operating cash flow generation, reinvesting for future
growth and prioritising sustainable shareholder returns. The
Company's liquidity and strength of the balance sheet is
fundamental to the longevity of the business and is a key
consideration when assessing capital allocation.
Centamin has an active growth
pipeline through results-driven exploration and continually
assesses inorganic growth opportunities. Our organic projects are
self-funded but before capital is allocated, they are routinely
ranked based on results against our development criteria and
prospective returns.
In 2023, a key focus was on
improving operational efficiencies to achieve consistent
operational performance with US$88 million spent on sustaining
capital expenditure and US$116 million on non-sustaining, or
'growth' capital expenditure.
Impressive progress was made on
project delivery as we achieved several further important
milestones, most notable the successful implementation of the SAP
(S4 HANA) ERP system which will greatly assist in centralising our
accounting and internal control systems across the Group and will
enable faster and more efficient reporting.
ACCELERATING BUSINESS TRANSFORMATION:
2023 has been pivotal in our
ongoing digital transformation journey, marking a significant step
in enhancing operational efficiency and financial oversight across
our Group.
The successful implementation of
SAP across our key operational areas -finance, procurement, human
resources, and maintenance, marks a transformative step in our
commitment to operational efficiencies, financial excellence and
strategic growth.
Enhanced Financial Oversight
Integrating SAP's financial
management solutions has started and will continue to evolve and
transform our approach to fiscal operations, centralising financial
activities across all our entities, enabling real-time, integrated
financial reporting and providing greater transparency and control.
This streamlined financial consolidation will facilitate strategic
decision-making, particularly in cost management, and is a good
foundation for robust financial governance.
Revitalising Procurement and Supply Chain
Management
SAP's advanced procurement
solutions are expected to significantly enhance our procurement and
supply chain management processes. This will lead to increased time
and cost efficiencies and strengthened supplier relationships,
further bolstering our supply chain resilience and strategic
purchasing capabilities.
Human Resources
The SAP suite has brought a new
dimension to our human resources management. By automating and
streamlining HR processes, we will enhance employee engagement and
efficiency, whilst aligning our workforce strategy with our broader
business objectives.
Transforming Maintenance Operations
A notable addition to our SAP
integration is through our maintenance teams. The SAP Maintenance
module
will
improve how we manage and optimise our maintenance activities. This
integration ensures more efficient scheduling, tracking, and
execution of maintenance tasks, and is expected to significantly
reduce downtime and increase operational reliability. The enhanced
visibility and control over maintenance operations will improve
asset longevity and contribute to overall operational cost
savings.
Future Proofing our Business
The strategic implementation of
SAP solutions across our diverse operational areas signifies our
commitment to leveraging technology for sustainable and scalable
growth. This comprehensive digital transformation enhances our
day-to-day operations, long-term strategic planning and execution
capabilities.
As we move forward, the SAP
implementation will continue to support the redefinition of our
business processes and will be instrumental in driving our success
whilst maintaining our commitment to excellence within our
sector.
2023 DIVIDEND
Stakeholder, and specifically
shareholder returns, are central to our Company strategy. We have
built a ten-year track record of returning cash to shareholders,
based on our policy linked to free cash flow generation before
growth investment. Our dividend policy makes firm commitments on
capital allocation, meaning shareholder interests are always at the
centre of what we do.
Consistent with the Company's
commitment to returning cash to shareholders, and recognising 2023
as the final full year of reset of Sukari, the Board proposes a
2023 final dividend, for the year ended 31 December 2023 of 2.0 US
cents per share (circa.US$23 million), bringing the proposed total
dividend for 2023 to 4 US cents per share (circa.US$46
million):
●
|
Interim 2023 dividend paid: 2.0 US
cents per share
|
●
|
Final 2023 dividend proposed: 2.0
US cents per share
|
The final 2023 dividend is subject
to shareholder approval at the AGM on 21 May 2024 and following
approval would be paid on 19 June 2024.
MANAGING OUR RISKS AND
OPPORTUNITIES
In an unpredictable world, due to
increasing macroeconomic and geopolitical pressures, you can see
below in the Principal Risks and Uncertainties some of the main
areas we consider to enable more effective decision making that
supports the delivery of our objectives and improves our
performance as a responsible mining company.
OUTLOOK
We are fully focused on managing
the bottom line of the business so that we can maximise the value
at Sukari and deliver growth and diversification combined with
sustainable stakeholder returns.
We have budgeted for similar costs
in 2024 as 2023, accounting for rising input costs, driven by
higher consumer price inflation within our operating countries,
supply chain pressures on fuel, consumables and shipping costs and
tighter labour markets. We have prudently decided not to budget any
offsetting impacts of our ongoing cost-savings and improving
operating efficiencies and productivity gains until we have a
better sense of the longer-term inflationary
environment.
Ross Jerrard
Chief Financial Officer
PRIMARY STATEMENTS
HIGHLIGHTS
|
Year ended 31 December 2023
US$'000
|
Year ended 31 December 2022
US$'000
|
Revenue
|
891,262
|
788,424
|
Revenue from gold and silver sales
for the year increased by 13% year-on-year to US$891 million (2022:
US$788 million) with the year-on-year average realised gold price
also increasing by 9% to US$1,948 per ounce sold (2022: US$1,794
per ounce sold) complimented by a 4% increase in gold ounces sold
of 456,625 ounces (2022: 438,638 ounces).
|
Year ended 31 December 2023
US$'000
|
Year ended 31 December 2022
US$'000
|
Cost of sales
|
(596,836)
|
(544,075)
|
Cost of sales represents the cost
of mining, processing, refining, transport, site administration,
depreciation, amortisation and movement in production inventories.
Cost of sales is up 10% year-on-year to US$597 million, mainly as a
result of:
●
|
35% increase (US$51 million) in
depreciation and amortisation charge which increased from US$146
million to US$197 million (+ve), primarily due to the following
drivers:
|
|
₋
|
increase in the depreciation and
amortisation base from new fixed assets capitalised during the year
in addition to increased charges due to additional volumes moved;
and importantly
|
|
₋
|
SAP (S4 HANA) was implemented
during the year, an extensive review process of the fixed asset
components and useful lives was performed as part of the
implementation and migration from the legacy system to the new SAP
fixed asset register, this accelerated the depreciation of some
assets resulting in a higher depreciation charge in the year as
asset categories were depreciated at a much more granular component
level.
|
|
Year ended 31 December 2023
US$'000
|
Year ended 31 December 2022
US$'000
|
Dividend paid ₋ non-controlling interest in
SGM
|
(112,000)
|
(35,492)
|
The profit share payments during
the year are reconciled against SGM's audited financial statements.
Any variation between payments made during the year (which are
based on the Company's estimates) and the audited financial
statements, may result in a balance due and payable to EMRA or
advances to be offset against future distributions. SGM's 30 June
2023 financial statements have been audited and signed
off.
Refer to note 1.2.1.2 in the notes
for details of the treatment and disclosure of the EMRA profit
share.
CAPITAL EXPENDITURE
The following table provides a
breakdown of the total capital expenditure of the Group:
|
Year ended
31 December 2023
US$'000
|
Year ended
31 December 2022
US$'000
|
Underground exploration
|
9,225
|
8,636
|
Underground mine
development
|
32,350
|
32,107
|
Other sustaining capital
expenditure
|
46,241
|
124,162
|
Total sustaining capital
expenditure
|
87,816
|
164,905
|
Non-sustaining exploration
expenditure
|
2,947
|
3,539
|
Other non-sustaining capital
expenditure(1)
|
113,348
|
115,099
|
Total gross capital
expenditure
|
204,111
|
283,543
|
Less:
|
|
|
Sustaining element of waste
stripping capitalised(2)
|
(843)
|
(51,527)
|
Capitalised Right of Use
Assets
|
(1,216)
|
(7,746)
|
Adjusted capital expenditure
(after reclassification)
|
202,052
|
224,270
|
(1) Non-sustaining capital
expenditure included further spend on the solar plant, underground
paste-fill plant and the Capital Waste Stripping. Non-sustaining
costs are primarily those costs incurred at 'new operations' and
costs related to 'major projects at existing operations' that will
materially benefit the operation.
(2) Reclassified from
operating expenditure.
EXPLORATION EXPENDITURE
The following table provides a
breakdown of the total exploration expenditure of the
Group:
|
Year ended
31 December 2023
US$'000
|
Year ended
31 December 2022
US$'000
|
Greenfield exploration
|
|
|
Burkina Faso
|
869
|
2,928
|
Côte d'Ivoire
|
25,226
|
25,120
|
Egypt - Eastern Desert
exploration
|
5,558
|
1,675
|
Total greenfield exploration
expenditure
|
31,653
|
29,723
|
Brownfield exploration
|
|
|
Sukari Tenement
|
12,172
|
12,175
|
Total brownfield exploration
expenditure
|
12,172
|
12,175
|
Total exploration
expenditure
|
43,825
|
41,898
|
Exploration and evaluation
expenditure comprises expenditure incurred for exploration
activities primarily in Côte d'Ivoire and in the new Egypt
greenfield permit areas. Greenfield exploration and evaluation
costs (excluding Burkina Faso) increased by US$2 million or 6% as
more exploration and evaluation work specifically drilling and
assaying at the two Côte d'Ivoire sites was done in 2023 as
compared to 2022 as well as the expansion of exploration work in
the Eastern Desert Exploration area under the new Egypt permit
areas. The brownfield capitalised exploration costs on the Sukari
Mining Concession area remained flat year on year.
The spend in Burkina Faso was on
key services, wind down procedures and other regulatory obligations
to formally exit the country. The process to formally exit and
wind-up the in country incorporated entities is at an advanced
stage.
SUBSEQUENT EVENTS
As referred to in note 5.3 of the
Group Consolidated Financial Statements, subsequent to the year
end, the Board proposed a final dividend for 2023 of 2.0 US cents
per share. Subject to shareholder approval at the Annual General
Meeting on 21 May 2024, the final dividend will be paid on 19 June
2024 to shareholders on record date of 31 May 2024.
Other than as noted above, there
were no other significant events occurring after the reporting date
requiring disclosure in the financial statements.
NON‑GAAP FINANCIAL
MEASURES
1) EBITDA and adjusted
EBITDA
EBITDA is a non‑GAAP financial
measure, which excludes the following from profit before
tax:
●
|
Finance costs
|
●
|
Finance income
|
●
|
Depreciation and
amortisation
|
Management considers EBITDA a
valuable indicator of the Group's ability to generate liquidity by
producing operating cash flows to fund working capital needs and
capital expenditures. EBITDA is also frequently used by investors
and analysts for valuation purposes whereby EBITDA is multiplied by
a factor or 'EBITDA multiple' that is based on an observed or
inferred relationship between EBITDA and market values to determine
a company's approximate total enterprise value. EBITDA is intended
to provide additional information to investors and analysts and
does not have any standardised definition under IFRS and should not
be considered in isolation or as a substitute for measures of
performance prepared under IFRS.
EBITDA excludes the impact of
depreciation and amortisation, income from financing activities and
taxes, and therefore is not necessarily indicative of operating
profit or cash flow from operations as determined under IFRS. Other
companies may also calculate EBITDA differently. The following
table provides a reconciliation of EBITDA to profit for the year
before tax.
Adjusted EBITDA removes the effect
of transactions that are not core to the Group's main operations,
like adjustments made to normalise earnings, for example fair value
movements on derivative financial instruments, profit on financial
assets at fair value through profit or loss, impairments of
property, plant and equipment, non-current mining stockpiles and
exploration and evaluation assets.
Reconciliation of profit before
tax to EBITDA and adjusted EBITDA:
|
31 December 2023
US$'000
|
31 December 2022
US$'000
|
Profit for the year before
tax
|
195,140
|
171,001
|
Finance income
|
(4,127)
|
(1,214)
|
Finance costs
|
3,526
|
2,459
|
Depreciation and
amortisation
|
198,127
|
146,769
|
EBITDA
|
392,666
|
319,015
|
Add back:
|
|
|
Net fair value loss on derivative
financial instruments
|
5,509
|
-
|
Adjusted EBITDA
|
398,175
|
319,015
|
2) Cash cost of production per
ounce produced and sold and all-in sustaining costs ("AISC") per
ounce sold calculation
Cash cost of production and AISC
are non-GAAP financial measures. Cash cost of production per ounce
is a measure of the average cost of producing an ounce of gold,
calculated by dividing the operating costs in a period by the total
gold production over the same period. Operating costs represent
total operating costs less sustaining administrative expenses,
royalties, depreciation and amortisation. Management uses this
measure internally to better assess performance trends for the
Company as a whole. Management considers that, in addition to
conventional measures prepared in accordance with GAAP, certain
investors use such non-GAAP information to evaluate the Company's
performance and ability to generate cash flow. Management considers
that these measures provide an alternative reflection of the
Group's performance for the current year and are an alternative
indication of its expected performance in future periods. Cash cost
of production is intended to provide additional information, does
not have any standardised meaning prescribed by GAAP and should not
be considered in isolation or as a substitute for measures of
performance prepared in accordance with GAAP. This measure is not
necessarily indicative of operating profit or cash flow from
operations as determined under GAAP. Other companies may calculate
these measures differently.
During June 2013 the World Gold
Council ("WGC"), an industry body, published a Guidance Note on the
'all in sustaining costs' metric, which gold mining companies can
use to supplement their overall non-GAAP disclosure. AISC is an
extension of the existing 'cash cost' metric and incorporates all
costs related to sustaining production and in particular
recognising the sustaining capital expenditure associated with
developing and maintaining gold mines. In addition, this metric
includes the cost associated with developing and maintaining gold
mines. This metric also includes the cost associated with corporate
office structures that support these operations, the community and
rehabilitation costs attendant with responsible mining and any
exploration and evaluation costs associated with sustaining current
operations. AISC US$/oz is arrived at by dividing the dollar value
of the sum of these cost metrics, by the ounces of gold sold (as
compared to using ounces produced which is used in the cash cost of
production calculation).
On 14 November 2018 the World Gold
Council published an updated Guidance Note on 'all-in sustaining
costs' and 'all-in costs' metrics. Per their press release it was
expected that companies would choose to use the updated guidance
from 1 January 2019 or on commencement of their financial year if
later. The Group has applied the updated guidance from
1 January 2019 with no impact on our results or
comparatives.
Reconciliation of cash cost of
production per ounce produced:
|
|
31 December 2023
|
31 December 2022
|
Mine production costs (note
2.3)
|
US$'000
|
412,827
|
408,543
|
Less: Refinery and
transport
|
US$'000
|
(1,871)
|
(2,324)
|
Movement of
inventory(1)
|
US$'000
|
(17,133)
|
(3,673)
|
Cash cost of production - gold
produced
|
US$'000
|
393,823
|
402,546
|
Gold produced - total
(oz.)
|
oz
|
450,058
|
440,974
|
Cash cost of production per ounce
produced
|
US$/oz
|
875
|
913
|
|
|
|
| |
(1) The movement
in inventory on ounces produced is only the net movement in mining
stockpiles and ore in circuit while the movement in ounces sold is
the net movement in mining stockpiles, ore in circuit and gold in
safe inventory.
A reconciliation has been included
below to show the cash cost of production metric should gold sold
ounces be used as a denominator.
Reconciliation of cash cost of
production per ounce sold:
|
|
31 December 2023
|
31 December 2022
|
Mine production costs (note
2.3)
|
US$'000
|
412,827
|
408,543
|
Royalties
|
US$'000
|
26,682
|
23,842
|
Movement of
inventory(1)
|
US$'000
|
(9,536)
|
(6,789)
|
Cash cost of production - gold
sold
|
US$'000
|
429,973
|
425,596
|
Gold sold - total (oz.)
|
oz
|
456,625
|
438,638
|
Cash cost of production per ounce
sold
|
US$/oz
|
942
|
970
|
|
|
31
December 2023(1)
|
31
December 2022(1)
|
Movement in inventory
|
|
|
|
Movement in inventory - cash
(above)
|
US$'000
|
(9,536)
|
(6,789)
|
Effect of depreciation and
amortisation - non-cash
|
US$'000
|
22,855
|
17,448
|
Movement in inventory - cash &
non-cash (note 2.3)
|
US$'000
|
13,319
|
10,659
|
|
|
|
| |
(1) The movement in
inventory on ounces produced is only net the movement in mining
stockpiles and ore in circuit while the movement in ounces sold is
the net movement in mining stockpiles, ore in circuit and gold in
safe inventory.
Reconciliation of AISC per ounce
sold:
|
|
31 December 2023
|
31 December 2022
|
Mine production costs (note
2.3)
|
US$'000
|
412,827
|
408,543
|
Movement in inventory
|
US$'000
|
(9,536)
|
(6,789)
|
Royalties (note 2.3)
|
US$'000
|
26,682
|
23,842
|
Corporate administration
costs
|
US$'000
|
33,110
|
24,282
|
Rehabilitation provision interest
expense - unwinding of discount
|
US$'000
|
1,333
|
588
|
Sustaining underground development
and exploration
|
US$'000
|
41,575
|
40,743
|
Other sustaining capital
expenditure
|
US$'000
|
46,241
|
124,162
|
By‑product credit
|
US$'000
|
(1,878)
|
(1,503)
|
All‑in sustaining
costs(1)
|
US$'000
|
550,354
|
613,868
|
Gold sold - total (oz.)
|
oz
|
456,625
|
438,638
|
AISC per ounce sold
|
US$/oz
|
1,205
|
1,399
|
|
|
|
| |
(1) Includes
refinery and transport.
(3)
Cash and cash equivalents, bullion on hand, gold and silver sales
debtor and financial assets at fair value through profit or
loss
Cash and cash equivalents, bullion
on hand, gold and silver sales debtor is a non-GAAP financial
measure of the available cash and liquid assets at a point in time.
Management uses this measure internally to better assess
performance trends for the Company as a whole. Management considers
that, in addition to conventional measures prepared in accordance
with GAAP, certain investors use such non-GAAP information to
evaluate the Company's performance and ability to generate cash
flow and the measure is intended to provide additional
information.
This non-GAAP measure does not
have any standardised meaning prescribed by GAAP and should not be
considered in isolation or as a substitute for measures of
performance prepared in accordance with GAAP. This measure is not
necessarily indicative of cash and cash equivalents as determined
under GAAP and other companies may calculate it
differently.
Reconciliation to cash and cash
equivalents, bullion on hand, gold and silver sales debtor and
financial assets
at fair value through profit or
loss:
|
31 December 2023
US$'000
|
31 December 2022
US$'000
|
Cash and cash equivalents (note
2.17(a))
|
93,322
|
102,373
|
Bullion on hand (valued at the
year-end spot price)
|
14,261
|
24,440
|
Gold and silver sales debtor (note
2.8)
|
44,917
|
29,832
|
Derivative financial
instruments
|
654
|
-
|
Cash and cash equivalents, bullion
on hand, gold and silver sales
debtor
and financial assets at fair value through profit or
loss
|
153,154
|
156,645
|
The majority of funds have been
invested in international rolling short-term interest money market
deposits.
(4)
Free cash flow and adjusted free cash flow
Free cash flow is a non-GAAP
financial measure. Free cash flow is a measure of the available
cash after distributions to the Non-Controlling Interest ("NCI") in
SGM, being EMRA, that the Group has at its disposal to use for
capital reinvestment and to distribute to shareholders of the
parent. Free cash flow is intended to provide additional
information, does not have any standardised meaning prescribed by
GAAP and should not be considered in isolation or as a substitute
for measures of performance prepared in accordance with GAAP. This
measure is not necessarily indicative of operating profit or cash
flow from operations as determined under GAAP and other companies
may calculate this measure differently.
|
31 December 2023
US$'000
|
31 December 2022
US$'000(1)
|
Net cash generated from operating
activities
|
353,600
|
292,524
|
Less:
|
|
|
Net cash used in investing
activities
|
(198,768)
|
(274,583)
|
Dividend paid - non-controlling
interest in SGM
|
(112,000)
|
(35,492)
|
Free cash flow
|
42,832
|
(17,551)
|
Add back:
|
|
|
Transactions completed through
specific available cash resources(2)
|
6,163
|
-
|
Adjusted free cash flow
|
48,995
|
(17,551)
|
(1) The
comparatives in the Consolidated Statement of Cash Flows for the
year ended 31 December 2022 have been restated to reflect an
increase of cash generated from operating activities of $2.5m,
interest paid of $1.9m and a reduction of the effect of foreign
exchange rate changes of $0.6m.
(2) Adjustments
made to free cash flow, for example the cost of the put options
under the gold price protection programme, acquisitions and
disposals of financial assets at fair value through profit or loss,
which are completed through specific allocated available cash
reserves.
CORPORATE GOVERNACE UPDATE
The Board understands the benefits
of refreshing its composition, committee structures as well as
planning for future succession. The changes to the committee
structures illustrate the Company's commitment to continue to
evolve and strengthen our governance model.
BOARD APPOINTMENTS, RETIREMENT AND COMMITTEE
RESTRUCTURING
The following disclosures are made
in accordance with LR 9.6.11:
●
|
Dr Ibrahim Fawzy, Non-Executive
Director, will not stand for re-election at the upcoming AGM in
2024 and will therefore retire from the Board effective from the
close of the AGM on 21 May 2024.
|
●
|
Following the appointment of Iman
Naguib on 10 January 2024 as a Non-Executive Director, Iman will
join the Remuneration Committee as a member in addition to being a
member of the Audit & Risk Committee,
|
●
|
Following the appointment of Hoda
Mansour on 10 January 2024 as a Non-Executive Director, Hoda will
join the Audit and Risk Committee as a member in addition to being
a member of the Sustainability Committee.
|
●
|
Hennie Faul will step down as a
member of the Audit and Risk Committee but will continue as Chair
of the Technical Committee and as a member of the Nomination
Committee and Sustainability Committee.
|
Committee membership following the
AGM:
At the recommendation of the
Nomination Committee, the Centamin Board has approved the following
planned Committee membership to take effect following the AGM on 21
May 2024:
|
|
Audit &
Risk
|
Remuneration
|
Nomination
|
Sustainability
|
Technical
|
Jim Rutherford
|
NEC
|
|
Member
|
Chair
|
|
|
Dr Sally Eyre
|
SID
|
|
Chair
|
Member
|
|
Member
|
Mark Bankes
|
NED
|
|
|
Member
|
|
Member
|
Marna Cloete
|
NED
|
Chair
|
Member
|
|
Member
|
|
Dr Catharine Farrow
|
NED
|
Member
|
|
|
Chair
|
Member
|
Hennie Faul
|
NED
|
|
|
Member
|
Member
|
Chair
|
Hoda Mansour
|
NED
|
Member
|
|
|
Member
|
|
Iman Naguib
|
NED
|
Member
|
Member
|
|
|
|
Following the AGM on 21 May 2024,
the Board will be made up of the Chair, Senior Independent Director
plus six Non-Executive Directors and two Executive
Directors.
PRINCIPAL RISKS AND UNCERTAINTIES
PRINCIPAL RISKS
For the current reporting period
we have identified 16 principal risks and 3 emerging risks, which
means there is no change from the 2022 Annual Report. Further
detail on the Principal Risks which could affect Centamin are shown
below with a description of the nature of the risk, mitigation
measures and ongoing strategy to manage the risk.
Principal Risk
|
Nature of Risk
|
Mitigation Measures
|
Ongoing Strategy
|
GEOPOLITICAL
|
Future political, security and
social changes in the countries in which we operate may impact on
the Group.
The future investment framework,
stability and business conditions in our operating locations could
change with governments adopting different laws, regulations and
policies that may impact on the ownership, development and
operation of our mineral resources projects. The Company continues
to adapt to the changing regional security in our development and
exploration projects in Côte d'Ivoire. Outside of our host
countries we are monitoring the ongoing conflicts in the Ukraine,
Gaza and the Red Sea to ensure we can mitigate where possible the
potential wider impact of this on the Company.
|
Government policies have developed
over the past years in host countries to incentivise foreign direct
investment and the development of local mining industries. Centamin
deploys a proactive approach to government and stakeholder liaison
and actively monitors - on an ongoing basis - legal, fiscal,
regulatory and political developments in its host
countries.
The terms of the Sukari Concession
Agreement, (including the applicable tax regime and rights of
tenure), were issued and ratified under special Law No. 222 of 1994
and can, therefore, only be amended by the passing of a further
law. We continue to closely monitor the situation through our own
security, local and national government contacts, national security
and external advisors.
|
To maintain a detailed and up to
date understanding of the investment framework and operating
conditions as well as a constructive relationship with all
concerned stakeholders including host governments and local
partners, such as EMRA.
The Company undertakes to abide by
the spirit and letter of the Concession Agreement as well as local
laws/regulations in Egypt including around the areas of exploration
and furthermore where our development and exploration activities
are taking place in Côte d'Ivoire.
|
LEGAL AND REGULATORY COMPLIANCE
|
The Group's structure includes
mining exploitation and exploration licences in Egypt and Côte
d'Ivoire held through companies in Australia, Jersey and the United
Kingdom. As a result, the Group is subject to various legal and
regulatory requirements across all jurisdictions, including cross
jurisdictional taxation, related party transactions, antibribery
and corruption.
Ongoing legal, fiscal and regulatory
changes may impact project permitting, tenure, taxation, exchange
rates, environmental protection, labour relations, and the ability
to repatriate income and capital. These measures may also impact
the ability to import key supplies, export gold production and
repatriate revenues.
|
Centamin deploys a proactive
approach to government and stakeholder liaison and actively
monitors - on an ongoing basis - legal, fiscal, regulatory and
political developments in its host countries.
In Egypt we have the Sukari
Concession Agreement which was passed as a law and can only be
amended by means of another law amending this law, so we have the
right to export gold, repatriation of funds, the Tax Exemption and
further considerations.
The Group engages with the relevant
regulatory authorities. In addition, on an ongoing basis, the Group
seeks appropriate advice to ensure compliance with all relevant
regulation and legislation. Examples would be the global tax
strategy in place which ensures all taxes are paid at an
operational level and further tax requirements are met through the
holding structure in addition to added protection afforded by
double tax and bilateral investment treaties in Australia and the
United Kingdom. Further to this the negotiation of the Mining Model
Exploitation Agreement (MMEA) provides a new legal and fiscal
framework for any new EDX commercial discoveries. Appropriate
monitoring procedures are in place, and we ensure that we manage
legal and regulatory compliance where
required.
|
The Company seeks to ensure that it
complies with all relevant regulation and legislation including its
environmental and operational commitments set out in the relevant
permits/authorisations and local
laws/regulations.
|
LITIGATION
|
Centamin's ability to operate and conduct its business may be
adversely affected by current and any future dispute resolution
and/or litigation proceedings. Centamin was party to a single legal
action in Egypt. The details of this litigation, which relates to
the Sukari Concession Agreement, are given on our website in the
update issued on the 29 November 2023. This challenge to the Sukari
Concession Agreement could have affected the Company's ability to
operate the mine.
|
In order
to mitigate this risk Centamin had (a) retained reputable legal
advisers and continues to actively pursue its legal rights with
respect to this case; and (b) maintained regular contact with its
Egyptian legal advisers who actively monitored developments in both
court and local media for signs of any legislative or similar
developments that related to this litigation or which may have
otherwise threatened its operations, finances or
prospects.
The
potential for serious impact was further mitigated by:
• Centamin's adherence to local
laws and agreements; the Egyptian government's continued support on
the constitutionality of Law No. 32 of 2014, which restricts the
ability of third parties to challenge contractual agreements
between the Egyptian government and investors such as Centamin; the
investment protections and dispute resolution provisions set out in
the Sukari Concession Agreement and the bilateral investment treaty
between Australia (PGM's place of incorporation) and the Arab
Republic of Egypt
• On 14 of January 2023 there was a
ruling by the Egyptian Supreme Constitutional Court which held that
Law No. 32 of 2014 was constitutional. This was upheld in the final
judgement by the Egyptian Supreme Administrative Court setting
aside the 2011 third party challenge to the validity of the Sukari
Gold Mine exploitation licence issued under the Sukari Concession
Agreement. Further detail is given on our website in the update
issued on the 29 November 2023.
|
To
minimise exposure to litigation and reduce the impact of actions by
complying with all relevant laws and regulations and to defend
and/or bring any actions necessary to protect the Company's assets,
rights and reputation.
|
GLOBAL MACROECONOMIC DEVELOPMENTS
|
Economies across the world
negatively impacted by COVID-19 have been further impacted by
ongoing conflicts in the Ukraine, Gaza and the Red Sea plus wider
macroeconomic developments globally. From 2021 we saw increases in
operating costs and greater inflationary pressures, together with a
shortage of critical consumables and equipment. We expect this
uncertainty to continue in 2024. This situation could create an
adverse impact on our operations, costs, sales and
profits.
|
We monitor price movements and
market dynamics using primarily third-party analysis and forecasts
in order to support our financial projections and cash management
strategies. Prices will continue to influence budget considerations
in areas such as development, exploration and the timing of certain
capital expenditures. We focus on cost efficiencies and capital
discipline to deliver competitive all-in sustaining
cost.
The Group must continue with the
disciplined approach to managing operating costs, continual
investigation and implementation of cost saving opportunities to
counter inflation and improve margins. Further to this we have
established increased levels of stores and inventory which will be
maintained in the short to medium term to reduce uncertainty
alongside continual engagement with our partners to assist with
support of managing our supplies in a timely
manner.
|
We will continue to allow for
financial flexibility when budgeting and forecasting using a
measured approach to the potential fluctuations in gold price,
inflationary pressures and the increasing costs across our capital
expenditure and operational needs. Initiatives to manage these
external pressures include the RCF, Gold Price Protection
Programme, the solar plant, Grid Connection Project and potential
solar plant extension at Sukari.
|
GOLD PRICE
|
The extent of the Company's
financial performance is due in part to the price of gold, over
which the Company has no influence. Revenues from gold sales are in
US dollars and Centamin has exposure to costs in other currencies
including Egyptian pounds, Australian dollars and
sterling.
Centamin manages its exposure to
gold price by keeping operating costs as low as possible, has in
place the Gold Price Protection Programme and continues to consider
other options where these would be viewed as beneficial for our
commitment to stakeholder returns.
|
The Group continues to be exposed to
the gold price; however, in 2023 we introduced the Gold Price
Protection Programme and the cash costs of the Sukari Gold Mine
remain within our budget, which is conservatively based on the
long-term gold price as modelled by external advisors. This often
means we can take advantage of any changes in the gold price,
alongside retaining an element of downside protection, which have
been positive over the course of 2023 with a realised average price
of $1,948.
|
We will continue to allow for
financial flexibility when budgeting and forecasting using a
measured approach to the potential fluctuations in gold price. This
includes ensuring that we can manage within the boundaries and
margins that the price of gold and the impacts to our cost base
allow.
|
CAPITAL ALLOCATION AND LIQUIDITY
|
Centamin targets a capital
structure to provide sufficient liquidity and financial flexibility
to meet the Company's current and future financial commitments,
while balancing that with sustainable stakeholder
returns.
The capital requirements to
develop Sukari, to deliver key projects, which in 2024 is a focus
on the potential development of Doropo, future gold prices and
operating costs are all factors which need to be considered
alongside the external pressures, as highlighted in the Global
Macroeconomic Developments risk.
|
We monitor price movements and
market dynamics using primarily third-party analysis and forecasts
in order to support our financial projections and cash management
strategies. Prices will continue to influence budget considerations
in areas such as exploration and the timing of certain capital
expenditures. We focus on cost efficiencies and capital discipline
to deliver competitive all-in sustaining cost. Additional
optionality could be generated through the use or extension of the
RCF.
The Group must continue with the
disciplined approach to managing operating costs, continual
investigation and implementation of cost saving opportunities to
counter inflation and improve margins with recent examples
including delivery of the solar plant, competitive tendering on
operational contracts and the project allowing for connection to
the grid due to start in 2024. Further options being considered
include a solar plant extension, underground operational expansion
and proactive management of the supply chain to meet our
operational needs.
We have a robust investment approval
process involving the management and the Board as
required.
|
We will continue to allow for
financial flexibility when budgeting and forecasting using a
measured approach to the potential fluctuations in gold price,
inflationary pressures and the increasing costs across our capital
expenditure and operational needs. This includes ensuring that we
can manage within the boundaries and margins that the impacts to
our cost base allow.
Distribution of free cash flow to
stakeholders will continue to be managed in a balanced and
sustainable manner that allows for both growth and
returns.
|
DIVERSIFICATION
|
Sukari currently constitutes
Centamin's main mineral resource providing production and revenue.
We recognise until further production growth beyond the core Sukari
asset is identified there is the challenge of
diversification.
|
Sukari has a number of measures to
increase operational and financial resilience including, two
distinct ore sources (open pit and underground), the processing
plant has two separate circuits and there are two separate power
stations. These factors and the investment in opening up multiple
mining areas during 2021-23 results in improved operational
flexibility. The commissioning of the Solar Farm, the project
allowing for connection to the grid and further opportunities to
reduce operating costs all act to improve margins at Sukari, and
therefore strengthen the Group's balance
sheet.
The Group's organic growth
opportunities progressed in 2023 with the delivery of a positive
update on the pre-feasibility study for Doropo, with additional
updates on the EISA and DFS planned for mid-2024. We also started
fieldwork on the highly prospective Eastern Desert exploration
ground in Egypt with an update available on our website dated the 9
January 2024 on the encouraging maiden EDX drill
results.
Our existing assets offer
longevity and organic growth which stands to deliver
diversification over time. Outside of this, where opportunities
would provide the correct asset quality and meet returns criteria,
we would also consider further expansion to the portfolio through
acquisitions.
|
We are therefore actively looking
to diversify the portfolio at all development stages. From the
earliest stage targeting exploration ground which could build our
long-term development programme, to considering the acquisition of
production and development assets. These opportunities are subject
to strict investment criteria and a robust investment approval
process involving the Management Team and the Board, as
required.
The exploration projects across
the business provide a well-balanced project pipeline, with
potential to add incremental shareholder value by increasing
production. Further information will be provided through 2024 in
updates on the development and exploration activities including the
release of the latest position for Doropo.
|
CONCESSION GOVERNANCE AND MANAGEMENT
|
SGM is 50:50 jointly owned by PGM
(the Company's wholly owned subsidiary who operate Sukari) and
EMRA, with equal board representation from both parties. The board
of SGM operates by way of simple majority. Further to this with the
award of the EDX concession areas we need to adhere with the agreed
terms.
Should a dispute arise, or decision
making become deadlocked which cannot otherwise be amicably
resolved then time-consuming and costly arbitration or other
dispute resolution proceedings may need to be
initiated.
|
It is of key importance for
Centamin to maintain a healthy and transparent working relationship
with its 50% partner, EMRA, through adherence to the Sukari
Concession Agreement. With the onset of profit sharing, the proper
application of the cost recovery, net profit share payment
provisions and SGM protocols under the Concession Agreement, has
become a key priority.
It is a key focus to maintain good
working relations with EMRA, other relevant ministries and the
wider government to ensure successful operation of the Sukari Gold
Mine including our appointment of external PR consultants. The
Group has regular meetings with officials from EMRA and invests
time in liaising with the relevant ministry and other governmental
representatives. This investment is shown by the wider commitment
to Egypt through the EDX Exploration investment.
|
A key objective of the Company is
to maintain its licence to operate in its host countries. In Egypt,
this is achieved through active and ongoing co-operation, regular
meetings and correspondence with EMRA and the Ministry of Petroleum
& Natural Resources, as well as making sure that the terms and
conditions of the Concession Agreement and applicable laws are
complied with as well as the terms of the EDX concessions. Ongoing
monitoring and review of this is key and is an activity which we
will continue to give the required focus to. A key focus in 2024
will be the engagement with EMRA and the Government on the Tax
Exemption Renewal for the Sukari Concession.
|
LICENCE TO OPERATE
|
Centamin is committed to building
and operating our mines in a safe and responsible manner. To do
this, we seek to build trust-based partnerships with host
governments and local communities to protect our licence to operate
and ability to grow. We should only advance our business interests
where this protects people, fosters socio-economic development and
safeguards the environment, and leaves a positive legacy for our
host communities.
|
Ensure that we act in an ethical,
responsible and transparent manner. This includes establishing
clear performance standards that meet both industry good practice
and local expectations within our areas of
operation.
Confirming compliance with
applicable regulatory requirements by maintaining an up-to-date
compliance register for each asset and routinely review our
performance against these commitments and
obligations.
Sustain broad-based support to our
investment plans through informed consultation and participation
with stakeholders.
Establish baseline environmental
and social conditions that provide a robust science-based
assessment of risks and impacts at the earliest stage in the
project cycle.
The government in Côte d'Ivoire
have recognised the Doropo Project as a strategic priority for the
country, we will ensure we continue to engage with the appointed
Technical Committee on the progress of the EIS and
DFS.
|
Acting in an ethical, responsible
and transparent manner is fundamental to realising the significant
business benefits gained from building trusted and constructive
relationships with all our stakeholders, and to maintaining our
socio-political licence to operate.
We will continue to reinforce our
sustainability performance framework - policies, standards, and
management assurance - to support growth.
Further information is shown in our
2023 Sustainability Report.
|
PEOPLE
(Attract, develop and retain skilled people)
|
Our accomplishments as a Company
rely on our ability to attract, develop and retain talented people
as they are the foundation of our business.
It is imperative that we support
our people to develop a shared understanding of the critical
behaviours and skills required for successful performance and
provide them with the opportunity to progress to more senior
positions within the Company. Otherwise, we face the risk of
elevated rates of turnover and knowledge
loss.
Valuing diversity and promoting
inclusion is an ethical imperative for a sustainable
business.
|
The Company will provide
professional and personal development opportunities that empower
employees to fulfil their potential and operate at a proficient
level, including succession planning.
All employees participate in an
annual performance appraisal and objective setting process that
defines their expectations and the support required for further
development.
We ensure that we raise workplace
awareness of our organisational Values and the critical behaviours
required for successful performance.
We provide visible leadership to
improve diversity and inclusion in the workplace supported by
target setting to increase female representation.
|
Reinforce awareness of our Code of
Conduct, sustain training and professional development programmes
and reinforce leadership to overcome barriers to diversity and
inclusion.
|
STAKEHOLDER ENVIRONMENTAL AND SOCIAL
EXPECTATIONS
|
Elevated expectations on
sustainability, including stakeholder scrutiny, third-party
assurance, reporting and disclosure, regulatory requirements and
application of good industry practice.
Recent high-profile external
events have put a spotlight on the need for increased levels of
corporate accountability on matters including tailings management,
climate change, biodiversity, water management, responsible supply
chains, diversity and inclusion.
|
The Company will engage with
industry groups, investors and regulators to understand their
expectations.
We have established clear
performance standards that meet both industry good practice and
local expectations within our areas of operation. Key industry
standards include the RGMPs, GISTM, TCFD and the emergence of the
Integrated Reporting Framework (IFRS).
We have defined environmental and
social objectives and set targets to drive continuous improvement.
We measure, evaluate, report and disclose on our sustainability
performance.
We shall continue to build the
capacity of our asset-level HSES specialist teams to meet our
performance standards including the development of operational
management systems aligned to ISO standards.
|
Ensuring we continue to monitor
the emergence of new industry standards and their application to
Centamin's business. Reinforce our Sustainability Performance
Framework - policies, standards and management assurance - and its
integration into asset-level management systems and
practice.
Continue to build the capacity and
awareness of our asset-level teams to integrate environmental and
social risks and opportunities into operational
activities.
Further information is shown in
our 2023 Sustainability
Report.
|
Decarbonisation
|
We recognise transition to a net
zero carbon economy is expected to profoundly affect our business
model over the medium and/or long term due to factors including:
capital investment and access to new technology, the pricing of
carbon emissions; availability and costing of commodities and
consumables; changing market and investor
sentiment.
The most significant opportunity
for decarbonisation is the ability to reduce and potentially remove
fossil fuel-generated electricity from gold mining's sources of
power.
|
We will focus on execution of our
2030 Decarbonisation Roadmap to reduce emissions, from the existing
business, by 30% versus a 2021 base-year. This target is
underpinned by: (i) a 50MWAC connection to the national
grid and (ii) a 15MWAC expansion of the existing solar
PV plant.
The Company continues to
investigate other carbon abatement opportunities including
electrification of our mining fleet and energy efficiency
programmes.
We have completed scenario
analysis of climate-related transition risks and opportunities over
the long term and assess the impact of these risks on business
strategy. We will systematically review our climate-related
transition risks and opportunities on an annual basis, including
application to growth projects.
|
Continued execution of our 2030
Decarbonisation Roadmap including assessing other carbon abatement
opportunities to a higher level of detail.
Integration of the results of the
scenario analysis for climate-related transition risks into our
business model and life of mine planning as
appropriate.
Further information on our Climate
Change Governance, Strategy, Risks, Metrics and Targets are given
in our 2030 Decarbonisation
Roadmap.
|
SAFETY, HEALTH AND WELLBEING
|
It is an inherent risk in our
industry that incidents due to unsafe acts or conditions, or the
failure of our equipment or infrastructure could lead to injuries
or fatalities. Remote and rostered work also has potential to
impact the mental health and wellbeing of our
workers.
Our workforce faces potential risks
from hazards such as fire, explosion and electrocution, as well as
risks specific to the mine site and development project. These
include potential slope failures or collapse in the underground,
mobile plant collisions and incidents involving hazardous
materials. Continuing focus on the risks associated with mining
companies' tailings facilities also means we continue to monitor
this risk, completing regular internal and external technical
reviews.
|
Protecting the safety, health and
wellbeing of employees, contractors, local communities and other
stakeholders is a fundamental responsibility for Centamin. We seek
continuous improvement of our safety and health management system
and practices including assurance processes, with particular focus
on the early identification of risks and the prevention of
incidents.
We have defined our OHS objectives
and set targets to drive continuous improvement. These are
supported by a process to measure, evaluate, report and disclose on
our safety performance.
We have continued to reinforce our
critical risk and control standards, review and test our crisis
management plan, and enhanced employee benefits including delivery
of a Health & Wellbeing plan. We continue to build the
awareness and capacity of senior management teams to operationalise
our critical risks standards. Our OHS management system at Sukari
is now certified to ISO 45001.
|
Ensuring the safety, health and
wellbeing of our workforce is directly aligned with our first
Value, to Protect,
and is a moral imperative. This
requires a focus on zero harm whilst constituting a direct
investment in the
productivity of the business and
the physical integrity of our operations.
A safe and healthy workforce
translates into an engaged, motivated and productive workforce that
mitigates operational stoppages, and reduces potential incidents or
harm. We will ensure we sustain visible leadership in the
achievement of a zero-harm workplace. Further information in relation to our commitments and
standards to Safety, Health and Wellbeing is given in the 2023
Sustainability Report.
|
EXPLORATION AND PROJECT DEVELOPMENT
|
Exploration activities by their
very nature are highly speculative with an inherent degree of risk.
Centamin strives to make new discoveries, growth and value-creation
opportunities through our exploration
programme.
Whilst Egypt continues to
represent a significant opportunity through brownfield and
greenfield exploration around the Sukari Concession and highly
prospective ground in Egypt's Eastern Desert, we also recognise our
potential growth projects in Côte d'Ivoire.
|
Before undertaking any exploration
activities a risk-based approach is undertaken to filter projects
considering a number of factors.
There is a structured approach
established with the exploration team who undertake systematic work
programmes which reduce the risk and gradually increase the
certainty of exploration discoveries that allows a focussed
spending strategy. This is supported by independent advice and an
investment in technology.
2023 delivered a positive update
on the finalisation of the pre-feasibility study for Doropo with
additional updates on the EISA and DFS planned for mid-2024, we
started fieldwork on the highly prospective and underexplored
ground in Egypt with an update available on our website dated the 9
January 2024. During 2023 we invested a total of US$31M in
greenfield exploration and development activities, with further
expenditure on brownfield exploration provided in the Financial
Review. An initial US$9M is budgeted for exploration expenditure at
EDX and US$14M on project development at Doropo in
2024.
|
Ensuring we have an effective and
efficient exploration and development programme to meet our
strategic targets, long-term production and reserves goals. During
the first half of 2024, we will release the results of the maiden
drilling campaign across our Egyptian exploration portfolio and
will also aim to publish the updated reserve numbers for
Doropo.
|
MAXIMISING OUR GEOLOGICAL POTENTIAL
|
Geological uncertainty is an
inherent risk which all mining companies
face.
Understanding of the geology and
associated grade distribution can be influenced by a number of
factors which can impact the size, orientation and shape of the ore
and the potential grade expected by the mining
operations.
As these estimations are used to
inform our operations and the wider business strategy we need to
ensure that we can make this process as accurate as
possible.
|
The Mineral Resource Management
team is focused on developing the geological and structural
framework in which mineralisation is hosted. This has brought
about a clear understanding of the structural and lithological
controls on mineralisation and the development of a predictive
model which is being used to expand the Mineral Resource and
Reserve base for the company.
Orebody stewardship ensures
geology and the geologist are at the forefront of all mining and
extraction process decision-making. This has allowed improved
long and short-term planning, timing of grade control, material
movement, blending and processing requirements to maximise return
on investment. A specific example would be the change in drilling
strategy for 2024, with a focus on grade control and infill
drilling to support short- and medium-term operational planning as
well as the introduction of underground RC grade control
drilling.
Detail on increases in the Group
Resource and Reserves was issued on the 24 January 2024.
|
To achieve an accurate estimation
based on geology, that informs improved mine planning and
operations to deliver results. This will be supported by the
near-term roadmap to 475 - 500koz pa and updated Life of Mine Plan
for Sukari issued in 2023 including average guidance issued to
2034.
|
OPERATIONAL PERFORMANCE AND PLANNING
|
By their nature, mineral resources
and reserves are estimates based on a range of assumptions,
including geological, metallurgical, technical and economic
factors. Other variables include expected costs, inflation rates,
gold price, grade downgrades and production
outputs.
Unplanned operational stoppages
can impact our production. An inability to shift the volumes of
waste required, drops in our operational capacity in mining,
contractor management, supply chain disruption or ground stability
are examples of potential risks.
Accurate and complete planning is
pivotal to informing production estimates, grade quality and
provide greater clarity to corporate/operational decision making.
We then need to deliver against our targets by analysis of our data
to inform the right decisions.
|
Over 2021 and 2022 the Company
focused on improving mining flexibility, delivering growth and
building consistency alongside other improvements.
During 2023 we extended our track
record of meeting production guidance to a third year, commissioned
the underground paste plant, updated the market on the new Life of
Mine (LOM) Plan, issued estimated average guidance until 2034,
continued with accelerated waste-stripping due to complete in
mid-2024, started the grid connection project and provided a Group
Resource & Reserve update. We also had a change in drilling
strategy, to further reinforce operational delivery in the near
term.
The LOM should deliver increased
gold production, lower operational costs, reduce operational risk
and significantly reduce carbon emissions. Further details can be
found in the announcements we have made to the market and most
recently in the Q4 report on the 18 January
2024.
|
To achieve reliable and consistent
production, whilst optimising the potential of the operation. The
Company provides timely and accurate information to the market on
production levels and forecasts. The mining sector continues to
face operating cost inflation, including labour costs, energy costs
and the natural impact of ore-grade deterioration over time which
we are looking to manage where possible.
In order to deliver our growth
strategy and to maintain and improve our competitive position, the
Group must continue with the disciplined approach to managing
operating costs, continual investigation and implementation of cost
saving opportunities and maintain consistent operational
delivery
|
EMERGING RISKS
Emerging risks are defined as
circumstances or trends that could significantly impact the
Company's financial strength, competitive position or reputation
within the next three years or over a longer term. Emerging risks
may prove difficult to quantify as they are often influenced by
external factors and difficult to predict. Emerging risks are
considered as part of the Company's strategic discussions through
all levels of the Group.
Cyber security
|
Cybersecurity risks, such as data
breaches, cyber-attacks, phishing, and compliance challenges, pose
significant threats to our operational integrity. These require
proactive and flexible risk management strategies. These risks can
cause disruptions to our data and systems, undermining their
security and integrity. This can potentially lead to operational
difficulties and a decrease in stakeholder confidence. The Company
is committed to increasing its investment in cybersecurity. This
involves strengthening our resilience and advancing our technology
infrastructure through a comprehensive digital transformation
initiative, ensuring robust defence against emerging
threats.
|
Infectious Disease
|
Potential of a regional/global
outbreak of a new disease bringing medical, economic and social
challenges. We continue to recognise the potential impacts of a
global pandemic similar to COVID-19 as a threat bringing potential
risks to our people and business. Learning from COVID-19 and other
infectious disease management, we developed a dynamic action plan
to safeguard the health of our people and minimise any business
impact. This will continue to adapt and evolve to ensure we are in
the best place to manage and respond as required, during 2023 we
have continued to manage the ongoing macroeconomic and supply chain
shocks with minimal impact to the business.
|
Climate Change
|
Understanding of the Physical and
Transition risks associated with Climate Change and the required
adaptation to these are given in greater detail in the 2023
Sustainability Report. At an emerging risk level, our operations
and projects are expected to face physical risks in the medium to
longer term alongside the wider systemic challenges within our
countries of operation and globally. Risks associated with the
global transition to a low carbon economy to reduce global warming
could also affect the economic performance of the company. We have
undertaken modelling of the potential physical and transition risks
to the Sukari asset, and when practical will do for our other
projects, to ensure that we can respond accordingly. Financial
modelling of key transition related risks and opportunities under a
'Net Zero by 2050' climate scenario assessed Centamin to remain
financially viable over the Life of Mine.
|
CONSOLIDATED STATEMENT OF CHANGES
IN EQUITY
for the year ended 31 December
2023
|
Note
|
Issued
capital
US$'000
|
Share option
reserve
US$'000
|
Accumulated
profits
US$'000
|
Total
US$'000
|
Non-controlling
interests
US$'000
|
Total
equity
US$'000
|
Balance as at 1 January
2023
|
|
670,994
|
6,082
|
641,794
|
1,318,870
|
22,537
|
1,341,407
|
Profit for the year after
tax
|
|
−
|
−
|
92,284
|
92,284
|
102,601
|
194,885
|
Total comprehensive income for
the year
|
|
−
|
−
|
92,284
|
92,284
|
102,601
|
194,885
|
Own shares acquired
|
2.15
|
(245)
|
−
|
−
|
(245)
|
−
|
(245)
|
Net recognition of share-based
payments
|
2.16
|
−
|
−
|
−
|
6,725
|
−
|
6,725
|
Transfer of share-based
payments
|
2.16
|
2,683
|
(2,683)
|
−
|
−
|
−
|
−
|
Dividend paid - non-controlling
interest in SGM
|
2.5
|
−
|
−
|
−
|
−
|
(112,000)
|
(112,000)
|
Dividend paid - owners of the
parent
|
|
−
|
−
|
(52,166)
|
(52,166)
|
−
|
(52,166)
|
Balance as at 31 December
2023
|
|
673,432
|
10,124
|
681,912
|
1,365,468
|
13,138
|
1,378,606
|
|
Note
|
Issued
capital
US$'000
|
Share option
reserve
US$'000
|
Accumulated
profits
US$'000
|
Total
US$'000
|
Non-controlling
interests
US$'000
|
Total
equity
US$'000
|
Balance as at 1 January
2022
|
|
669,531
|
4,975
|
655,508
|
1,330,014
|
(40,256)
|
1,289,758
|
Profit for the year after
tax
|
|
−
|
−
|
72,490
|
72,490
|
98,285
|
170,775
|
Total comprehensive income for
the year
|
|
−
|
−
|
72,490
|
72,490
|
98,285
|
170,775
|
Net recognition of share-based
payments
|
2.16
|
−
|
2,570
|
−
|
2,570
|
−
|
2,570
|
Transfer of share-based
payments
|
2.16
|
1,463
|
(1,463)
|
−
|
−
|
−
|
−
|
Dividend paid - non-controlling
interest in SGM
|
2.5
|
−
|
−
|
−
|
−
|
(35,492)
|
(35,492)
|
Dividend paid - owners of the
parent
|
|
−
|
−
|
(86,204)
|
(86,204)
|
−
|
(86,204)
|
Balance as at 31 December
2022
|
|
670,994
|
6,082
|
641,794
|
1,318,870
|
22,537
|
1,341,407
|
The above audited consolidated
statement of changes in equity should be read in conjunction with
the accompanying notes.
CONSOLIDATED STATEMENT OF CASH
FLOWS
for the year ended 31 December
2023
|
Note
|
31 December 2023
US$'000
|
31
December 2022*
US$'000 (restated)
|
Cash flows from operating
activities
|
|
|
|
Cash generated from operating
activities
|
2.17(b)
|
356,195
|
294,625
|
Income tax paid
|
|
(402)
|
(230)
|
Interest paid
|
|
(2,193)
|
(1,871)
|
Net cash generated from operating
activities
|
|
353,600
|
292,524
|
Cash flows from investing
activities
|
|
|
|
Acquisition of property, plant,
and equipment
|
|
(190,723)
|
(263,622)
|
Brownfield exploration and
evaluation expenditure
|
|
(12,172)
|
(12,175)
|
Finance income
|
2.3
|
4,127
|
1,214
|
Net cash used in investing
activities
|
|
(198,768)
|
(274,583)
|
Cash flows from financing
activities
|
|
|
|
Cash element of share-based
payments
|
|
(583)
|
(523)
|
Own shares acquired
|
|
(245)
|
−
|
Dividend paid - non-controlling
interest in SGM
|
2.5
|
(112,000)
|
(35,492)
|
Dividend paid - owners of the
parent
|
3.2.2
|
(52,166)
|
(86,204)
|
Net cash used in financing
activities
|
|
(164,994)
|
(122,219)
|
Net decrease in cash and cash
equivalents
|
|
(10,163)
|
(104,278)
|
Cash and cash equivalents at the
beginning of the year
|
|
102,373
|
207,821
|
Effect of foreign exchange rate
changes on cash and cash equivalents
|
|
1,112
|
(1,170)
|
Cash and cash equivalents at the
end of the year
|
2.17(a)
|
93,322
|
102,373
|
* The comparatives in the
Consolidated Statement of Cash Flows for the year ended 31 December
2022 have been restated to reflect an increase of cash generated
from operating activities of $2.5m, interest paid of $1.9m and a
reduction of the effect of foreign exchange rate changes of
$0.6m.
The above audited consolidated
statement of cash flows should be read in conjunction with the
accompanying notes.
NOTES TO THE CONSOLIDATED
FINANCIAL STATEMENTS
for the year ended 31 December
2023
BASIS OF PREPARATION
These financial statements are
denominated in US dollars ("US$"), which is the presentation
currency of Centamin plc. All companies in the Group use the US$ as
their functional currency. All financial statements presented in
US$ have been rounded to the nearest thousand dollars, unless
otherwise stated.
These consolidated financial
statements have been prepared in accordance with the International
Financial Reporting Standards ("IFRS") as adopted by the European
Union ("EU") and interpretations issued from time to time by the
IFRS Interpretations Committee ("IFRS IC") and which are mandatory
for reporting as at 31 December 2023 and the Companies (Jersey) Law
1991. The Group has not early adopted any other amendments,
standards or interpretations that have been issued but are not yet
mandatory or effective.
The consolidated financial
statements have been prepared on a going concern basis and under
the historical cost convention, as modified by financial assets and
financial liabilities (including derivative) instruments which are
measured at fair value.
The consolidated financial
statements for the year ended 31 December 2023 were authorised by
the Board of Directors of the Company for issue on 21 March
2024.
Going concern
The Directors have assessed the
going concern status of the Group, considering the period to 31
December 2025.
Management prepares consolidated
group budgets for each upcoming financial period, the 2024 budget
model has been used as the base case for the going concern
analysis. Management also prepares a financial model over the life
of mine which covers a period of twelve years and this model has
been used as the base case for the viability assessment for the
years beyond the going concern assessment period. Further detailed
analyses and forecasts are then applied to the base case models to
assess the economic impact of various downside scenarios from a
going concern and viability perspective.
The Group continues to benefit
from a strong balance sheet with a large cash balance and no debt.
At 31 December 2023 the Group had cash and cash equivalents of
US$93 million. As part of assessing the Group's ability to continue
as a going concern, management performed various downside stress
testing scenarios to assess the impact on liquidity headroom. The
scenarios were considered without applying any mitigating actions
over the assessment period, as well as assuming that the US$150
million revolving credit facility which was available as of 13
March 2023, will not be drawn down. An example of mitigating
actions would involve assessing capital expenditures and focussing
on critical items only. The assessment covers a period of 24 months
from 1 January 2024 and therefore 21 months from the date of
signing the consolidated financial statements.
Key assumptions underpinning the
base case forecast include:
●
|
A consistently applied fuel price
of US$0.90/litre;
|
●
|
A consistently applied processing
plant recovery rate of 88.4%
|
●
|
A consistently applied gold price
of US$1,900/oz.; and
|
●
|
Production volumes and grades in
line with 2024 guidance and in-line with the 2025
forecast.
|
Management considered the
potential impact of climate-related physical and transition risks
including modelling potential carbon pricing scenarios, in the
context of the disclosures included in the Strategic Report. Based
on this current assessment modelling plausible scenarios,
climate-related risks are not assessed to have a material financial
impact on the going concern assessment.
The base case and downside
scenarios for the going concern assessment are as
follows:
●
|
Base case: 2024 budget/24-month
forward plan run against opening cash balance at 1 January
2024;
|
●
|
Gold price reduced to US$1,600 per
ounce consistently applied through the assessment
period;
|
●
|
Fuel price increase to
US$1.25/litre;
|
●
|
Open pit ore mined reduction by
10%;
|
●
|
Open pit ore mined grade reduction
by 15%;
|
●
|
Underground ore mined reduction by
10%;
|
●
|
Underground ore mined grade
reduction by 15%;
|
●
|
Processing capacity reduction by
20%; and
|
●
|
Processing plant recovery rate
reduction to 85.0%.
|
In all the above scenarios,
liquidity was maintained throughout the going concern period. We
also note that a scenario run with a combination of all the above
factors consistently applied for a full 24-month period would still
maintain liquidity after mitigating measures within management's
control are applied.
The sensitivities applied were
informed by internal and external data sources, were identified as
scenarios that could have the most significant impact on the
Group's available liquidity and are the primary drivers of the
Group's profitability.
The ability of the Company to
continue as a going concern is contingent on the ongoing viability
of the Group, principally the Sukari operations. The Group meets
its day-to-day working capital requirements through its available
cash balances. The Group continues to closely monitor its major
cost drivers e.g., fuel and other key consumables and reagents as
well as key operational KPIs that may have an impact on going
concern and take mitigating actions where necessary. The Group
continues to benefit from a strong ungeared balance sheet and a
gold price protection programme with put option contracts in place
until 30 June 2024, refer to note 2.4. The Group also has US$150
million of liquidity through the undrawn RCF which can be accessed
at any time.
The Group's forecasts and
projections, taking account of reasonably possible changes in
performance, show that the Group should be able to operate within
the level of its available cash balances and will have adequate
resources to continue in operational existence throughout the
assessment period and that currently there are no material
uncertainties regarding going concern.
Therefore, having assessed the
Group's principal risks, a detailed cash flow forecast prepared by
management and the various downside scenarios outlined above, the
Directors considered it appropriate to adopt the going concern
basis of accounting in preparing its consolidated financial
statements for the year ended 31 December 2023, which contemplate
the realisation of assets and settlement of liabilities during the
normal course of operations.
Accounting policies
This note provides a list of the
other potentially material accounting policies adopted in the
preparation of these consolidated financial statements to the
extent that they have not already been disclosed above. These
policies have been consistently applied to all the years presented,
unless otherwise stated.
1. Current reporting period
amendments
1.1 Changes in policies and
estimates
Certain new accounting standards,
amendments to accounting standards and interpretations have been
published that are not mandatory for 31 December 2023 reporting
periods and have not been early adopted by the Group.
New or amended accounting
standards
a. Adoption of new accounting
standards
The following accounting
standards, amendments and interpretations became effective in the
current year:
●
|
IFRS 17, Insurance
Contracts
|
●
|
Deferred Tax related to Assets and
Liabilities arising from a Single Transaction (Amendments to IAS
12)
|
●
|
Disclosure of Accounting Policies
- Amendments to IAS 1 and IFRS Practice Statement 2
|
●
|
Definition of Accounting Estimates
- Amendments to IAS 8
|
●
|
International Tax Reform - Pillar
Two Model Rules (Amendments to IAS 12)
|
The application of these standards
and interpretations effective for the first time in the current
year has had no significant impact on the amounts reported in these
financial statements.
b. Accounting standards issued but not yet
effective
At the date of authorisation of
these financial statements, the following standards and
interpretations, which have not been applied in these financial
statements, were in issue but not yet effective. It is expected
that where applicable, these standards and amendments will be
adopted on each respective effective date. None of these standards
are expected to have a significant impact on the
Group.
Amendments to IFRSs
|
Effective date
|
Lease Liability in a Sale and
Leaseback
(Amendments to IFRS 16)
|
Annual periods beginning on or
after January 1, 2024
|
Classification of Liabilities as
Current or Non-Current
(Amendments to IAS 1)
|
Annual periods beginning on or
after January 1, 2024
|
Non-current Liabilities with
Covenants
(Amendments to IAS 1)
|
Annual periods beginning on or
after January 1, 2024
|
Supplier Finance
Arrangements
(Amendments to IAS 7 and IFRS
7)
|
Annual periods beginning on or
after January 1, 2024
|
Lack of Exchangeability
(Amendments to IAS 21)
|
Annual periods beginning on or
after January 1, 2025
|
1.2 Critical judgements and
estimates in applying the entity's accounting policies
The following are the critical
judgements and estimates that management has made in the process of
applying the Group's accounting policies and that have the most
significant effect on the amounts recognised in the financial
statements. Management has discussed its critical accounting
judgements and estimates and associated disclosures with the
Company's Audit and Risk Committee.
The critical accounting judgements
are as follows:
1.2.1 JUDGEMENT:
CONTROL
1.2.1.1 Judgement: Accounting treatment of the
Sukari Gold Mining Company ("SGM")
Pharaoh Gold Mines NL ("PGM") (the
holder of an Egyptian branch) and EMRA are 50:50 partners in SGM.
However, SGM is fully consolidated within the Group as if it were a
subsidiary due to it being a controlled entity, reflecting the
substance and economic reality of the Concession Agreement ("CA")
(see note 4.1 to the financial statements).
IFRS 10 Consolidated financial statements defines control as
encompassing three distinct principles, which, if present, identify
the existence of control by an investor over an investee, hence
forming a parent-subsidiary relationship. The principles
are:
−
|
power over the
investee;
|
−
|
exposure, or rights, to variable
returns from its involvement with the investee; and
|
−
|
the ability to use its power over
the investee to affect the amount of the investor's
returns.
|
An investor has power over an
investee when the investor has existing rights that give it the
current ability to direct the relevant activities (i.e., the
activities that significantly affect the investee's
returns).
The Company's control of SGM,
through PGM
PGM is a 100% owned subsidiary of
the Company. The Company, through PGM, has the right to appoint or
remove the managing director of SGM under the terms of the CA and
in doing so controls the activities in relation to the operation of
SGM that most significantly affect the returns of SGM. These are
all illustrated in the sections that follow:
a) The duties of PGM
●
|
PGM controls the appointment of the
General Manager ("GM") at the Sukari Gold Mine;
|
●
|
By controlling the appointment of
the GM and directing their activities, the GM will make all
day-to-day decisions to allow the mine to operate in a manner that
aligns with the Company's objectives which involve:
|
−
|
preparing SGM's work programmes
through determination of the daily and longer-term mine plans, the
budgets covering the operations to be carried out throughout the
life of the mine ("LOM") and approval of the same;
|
−
|
managing capital expenditure,
procurement, cost control and treasury;
|
−
|
conducting exploration,
development, production, and marketing operations;
|
−
|
co-ordinating SGM operations and
activities, including its dealings with all contractors and
subcontractors;
|
−
|
bearing ultimate responsibility
for all costs and expenses required in carrying out any and all
operations under the CA;
|
−
|
funding the operations of SGM and
recovering costs and expenses throughout the LOM (i.e.,
exploration, development, and production phases);
|
−
|
funding additional exploration and
expansion programmes within the mine during the production
phase;
|
−
|
taking custody of SGM's stock and
management of its funds;
|
−
|
selling and shipping of all gold
and associated metals produced; and
|
−
|
entering into and managing gold
sales or hedging contracts and forward sale agreements
|
|
| |
b) The duties of EMRA
EMRA must, under the terms of the
CA, provide the required approvals to allow the mine to
operate.
c) The duties, role, and function
of the board of SGM:
The board of SGM has six board
members:
−
|
three of whom are appointed by the
Company, through PGM; and
|
−
|
three of whom are appointed by
EMRA:
|
−
|
the executive chairman, as one of
the three EMRA appointed board members, is a representative of EMRA
and is appointed by the Egyptian Ministry of Finance.
|
The board of SGM convenes twice a
year to:
−
|
facilitate a forum for sharing
information between the owners of SGM;
|
−
|
provide a mechanism to scrutinise
the timing and amounts of expenses; rather than as a
decision-making body over SGM's most significant relevant
activities;
|
−
|
consider, review, and approve all
the following in relation to SGM:
|
−
|
the budget;
|
−
|
the annual financial
statements;
|
−
|
the cost recovery position;
and
|
−
|
other compliance
matters.
|
The board of SGM is not allowed to
unreasonably withhold approval of any of the above.
If there is a disputed matter or
deadlock position at an SGM board level, it is resolved as
follows:
−
|
through open discussion at board
level;
|
−
|
the executive chairman does not
have a veto or casting vote;
|
−
|
where matters cannot be agreed
upon, an ad-hoc committee is appointed with each party having equal
representation. This committee will then recommend an appropriate
course of action to the board with the best interest of all
shareholders in mind; and
|
−
|
should the board still not agree
on a course of action, there is a provision for final and binding
arbitration
|
The board of SGM cannot appoint or
remove the GM, this right belongs solely to the Company, through
PGM, under the terms of the CA;
EMRA and/or the Egyptian
government have no downside risk in their share of SGM. If SGM were
to become loss making or insolvent, these costs are absorbed in
their entirety by the Company, through PGM,
in accordance with the CA.
The Company, through PGM, is
therefore exposed to the variable returns of SGM, has the ability
to affect the amount of those returns, has power over SGM through
its ability to direct its relevant activities and therefore meets
all the criteria of control to consolidate SGM's results within the
Group to reflect the substance and economic reality of the
CA.
As the Company, through PGM, is
determined to be the controlling party, it should consolidate
SGM, and should apply consolidation procedures, combining
balance sheet and profit and loss items line by line as well
as applying the rest of the consolidation procedures set out
in IFRS 10 App B para B86. The Group therefore prepares
consolidated financial statements on this basis.
1.2.1.2 Judgement: Treatment and disclosure
of EMRA profit share
EMRA holds 50% of the shares in
the Group controlled entity, SGM, which are not attributable to the
Company, and it is entitled to receive net proceeds from the
operations of SGM on a residual basis in accordance with their
specified shareholding per the CA (this distribution is in
accordance with the profit share mechanism and not as a consequence
of accumulated profits as defined by accounting standards).
Therefore, the Group recognises a Non-Controlling Interest ("NCI")
in SGM to represent EMRA's participation.
In terms of the CA, the NCI's
rights to any profit share payments (dividend distributions) is
only triggered after the cost recovery of all amounts invested (or
spent during operations) during the exploration, construction and
development stages have been repaid to PGM. The profit share
mechanism was only triggered in November 2016 (after all amounts
due to be cost recovered were complete). Until that time the NCI
had no rights to claim any distribution of accumulated profits or
profit share.
It is important to note that the
availability of cash in SGM for distribution to its shareholders as
profit share is under the control of the Company, through PGM, by
the decisions made on SGM's strategic direction and day-to-day
operational requirements of running the mine. This is regarded as
discretionary and exposes the Company to variable
returns.
Distributions to shareholders in
SGM:
once all expenditure requirements,
including current cost recovery payments due, have been met, excess
cash reserves, if any, are distributed to both SGM
shareholders:
−
|
distributions are always made
simultaneously to both shareholders;
|
−
|
the split of the distribution is
in accordance with the ratchet mechanism (i.e. the standard profit
share ratios of 60/40 (first two years from 1 July 2016),
55/45 (second two years from 1 July 2018) and 50/50 (from 1 July
2020) to PGM and EMRA respectively) as governed by the CA;
but:
|
−
|
distributions are not mandatory,
they are entirely discretionary and are only done if there are
excess funds;
|
−
|
distributions are paid in advance
on a weekly or fortnightly basis by mutual agreement between
shareholders;
|
at the end of the SGM reporting
period, final profits are determined, externally audited, and then
approved by the SGM board:
−
|
final profit distributions become
payable within 60 days of the financial year end, SGM is unable to
avoid payment at this point and the amount payable is recorded as
equity attributable to the NCI until paid;
|
the CA is merely a shareholder
agreement specifying how and when profits from SGM will be
distributed to shareholders and is typical of a minority
shareholder protection mechanism
The Group should attribute the
profit or loss for the year after tax and each component of
other comprehensive income for the year to the owners of the parent
and to the NCI in SGM. The entity shall also attribute total
comprehensive income for the year to the owners of the parent and
to NCI even if this results in the NCI having a deficit balance
(IFRS 10 App B para B94). The CA only contemplates the distribution
of profit to shareholders.
The NCI would only have a
deficit balance where advance distributions paid during the year
have exceeded final distributions payable after the year-end
financial statements have been prepared and audited. This deficit
would be entirely funded by the Company, through PGM, and would
first be redeemed from future excess cash before regular
distributions to both parties resume. SGM has no claw back
provision for advance profits paid to the NCI. We note that
annual dividend payments, after approval of audited financial
statements, is a standard feature of transactions with an NCI and
that such payments are not normally treated as non‑discretionary
payments triggering a liability in the consolidated statement
of financial position of the parent.
Any losses generated by SGM will
be entirely funded by the Company, through PGM, but attributed to
both shareholders. These losses will first be recovered before
further profit share distributions commence.
In the Group statement of
financial position, all the accumulated profits of SGM are
attributable to the Company as EMRA have already received their
share through the advance profit distribution payments made,
therefore NCI is usually disclosed in the financial statements as
nil unless there is an outstanding distribution payable to, or
deficit due from EMRA due to timing differences of the cash
sweep.
SGM and Centamin have
non-coterminous year ends and the audit of the profit share and
cost recovery mechanism and numbers is performed by EMRA for each
half year period ended 30 June and 31 December. There are inherent
uncertainties that may arise in the determination of amounts due to
EMRA from profit share and therefore, in some periods, additional
amounts than would have been paid to EMRA may become due and
payable, creating additional liabilities. The process may also
determine that more profit share than was due to EMRA was paid in
which case this will create a receivable from EMRA which will be
offset against future profit share amounts. Please refer to note
2.5 for further information.
1.2.2 JUDGEMENT: IMPAIRMENT
TRIGGER ASSESSMENT - SUKARI
IFRS requires management to test
for impairment if events or changes in circumstances indicate
that the carrying amount of a finite life asset may not be
recoverable. Considering the requirements of IAS 36 Impairment of
Assets an impairment trigger assessment has
been performed.
Group operating assets
As part of the impairment trigger
assessment, management has also considered movements in the key
assumptions which have historically been used in impairment
assessments and is satisfied that there have not been any changes
that would constitute an impairment trigger.
These include changes
to:
−
|
forecast gold prices, considering
current and historical prices, price trends and related
factors;
|
−
|
discount rates;
|
−
|
operating performance which
includes production and sales volumes;
|
−
|
exploration potential and reserves
and resources report;
|
−
|
operating costs, taking into
consideration the impact of the solar plant on those costs and
emissions targets;
|
−
|
recovery rates; and significant
changes to the mine plan with an impact on the mine's cost of
mineral extraction
|
−
|
share price; sustained decline in
share price which is not consistent with industry peers.
|
Management has considered a number
of factors as listed above when concluding on whether an impairment
trigger existed as at 31 December 2023. Notwithstanding the fact
that the carrying value of the Group's net assets exceeded its
market capitalisation at some points during 2023, management noted
that both the fall in the share price at those points and the
general movement in the Company's share price was consistent with
an industry-wide trend, and that there have not been significant
Group specific operational issues at any of its locations in the
year that may have a bearing on the share price
movement.
The Group achieved its annual
production guidance, with costs in line with forecasts.
On review, management concluded
that there were no impairment triggers affecting the Group's fixed
assets as at 31 December 2023.
Consideration of climate change risks
In preparing the financial
statements, the Directors have considered the potential impact of
climate-related physical and transitional risks for the Group's
operating assets, in the context of the TCFD disclosures. The
Directors recognise that climate-related risks have the potential
to impact the carrying value of assets through their effect on
future cash flow projections and impairments on the useful life of
assets. The financial statements also consider the opportunities
arising from our transition to a low carbon future and achievement
of our target for reducing Greenhouse Gas "GHG"
emissions.
In particular, the Directors have
applied qualitative and quantitative methods to stress test the
financial and strategic viability of the business for various
climate scenarios (including 'Net Zero by 2050'), to the likely
impact of climate-related transitional and physical risks in
respect of the following areas:
●
|
Cash flow forecasts considering
carbon, diesel and utility pricing increases on operating and
procurement costs;
|
●
|
Effects on property, plant and
equipment, arising from acute extreme weather events and chronic
shifts in climate patterns including precipitation, temperature and
sea-level rise;
|
●
|
Capital expenditure over the
short, medium and long term, arising from the adoption/deployment
of low carbon technology; and
|
●
|
Going concern and viability of the
Group to decreases in gold price arising from market and investor
uncertainty.
|
The Directors have made judgements
and assumptions using available internal and external information
to assess the impact of climate-related risks on the future cash
flows and operations of the business and are aware of the
uncertainty around how climate-related transition risks will affect
global and national economies over the medium and longer term, and
more specifically: gold price, carbon pricing, other regulatory
mechanisms and the availability of low carbon technology of
relevance to our operations.
In the case of climate-related
transition risks under a Net Zero by 2050 scenario, preliminary
modelling indicated that the introduction of carbon pricing on our
Scope 1 and 2 GHG emissions in Egypt and domestic supply chain
predicted that it could have an impact on the Group during the
Sukari Life of Mine, however this is still being assessed. A
review of the regulatory landscape relevant to
our assets noted that Egypt does not have any carbon mechanisms in place and
there is no indication of when one may be implemented. As a
consequence, carbon pricing is not expected to have a material
impact on the carrying values of assets or liability of the Group
in the short term. If we conservatively
assume that Egypt was to start developing ambitious (i.e. 'Net Zero
by 2050') climate policies over the short term, these are not
predicted to impact the business until the medium term and beyond.
We will regularly review the development of climate policy and the
timing of its potential impact on the business.
In the case of gold price, the
nature and extent of impact arising from climate-related risk is
uncertain taking into consideration the role of gold in low-carbon
technologies, gold as a traditional investment asset or downstream
consumption patterns. We have been unable to reference any credible
data sources of gold price for future climate scenarios and
therefore have not performed a quantitative assessment of
climate-related impacts. Separately the impact of fluctuations in
gold to the business is assessed in note 3.1.1(d).
Under the scope of our existing
target for GHG emissions reductions, capital expenditure related to
the adoption/deployment of low carbon technology
is assessed to be financially material in the
short term, however the technology is commercially available and
the expenditure is value accretive in the medium term and beyond.
At Sukari, our planned extension to the solar plant and grid
connection are forecast to provide a positive return on investment
within the life of the asset.
We have assessed the physical
risks to our operations under future emissions scenarios. Our
business was assessed to be resilient to physical risks for the
near-term predictions indicating that adaptation specifically to
mitigate the effects of climate change is not required for the
operational life of Sukari. The useful life of the Sukari asset is
not expected to be reduced by climate-related physical
risks.
The Group will monitor and
routinely test climate-related risk against judgements and
estimates made in preparation of the Group's financial statements.
Climate-related transitional and physical risks as well as carbon
pricing is not expected to have a material impact on the carrying
values of assets or liability of the Group during the Sukari Life
of Mine and there is no expectation that climate change will impact
any of the useful economic lives of the Sukari fixed
assets.
The Group's critical estimates and
assumptions are as follows:
1.2.3 ESTIMATE: MINERAL RESERVE
AND RESOURCE STATEMENT IMPACT ON ORE RESERVES
Ore reserves and mineral resource
estimates are estimates of the amount of ore that can be
economically and legally extracted from the Group's mining
properties. The Group's Mineral Reserve and Resource statement for
SGM with an effective date of 30 June 2023 is contained in the
supplementary section of the 2023 Annual Report. The information on
the Mineral Resources and Reserves statement was prepared by
Qualified Persons as defined by the National Instrument 43-101 of
the Canadian Securities Administrators.
There are numerous uncertainties
inherent in estimating Mineral Resources and Mineral Reserves.
Assumptions that are valid at the time of estimation may change
significantly when new information becomes available. Estimates of
recoverable quantities of reserves include assumptions on commodity
prices, exchange rates, discount rates and production costs for
future cash flows. It also involves assessment and judgement of
complex geological models. The economic, geological, and technical
factors used to estimate ore reserves may change from period to
period.
Ore reserves are integral to the
recognised amounts of depreciation and amortisation and the
valuation of inventory because of the unit of production ("UOP")
amortisation method. Therefore, changes to ore reserves may impact
the Group's reported financial position and results in the
following way:
●
|
The carrying value of mine
development properties, which incorporates the rehabilitation
obligation assets may be affected due to changes in estimated
future cash flows. The recoverable amount of mine development
properties is directly linked to the quantities of the economically
recoverable reserves of the mine and therefore with other factors
held constant, a significant decrease in the reserves might result
in an impairment loss on the asset and have a negative impact on
the carrying values;
|
●
|
Capitalised stripping costs
recognised in the statement of financial position, as either part
of mine development properties or inventory or charged to profit or
loss, may change due to changes in stripping ratios;
|
●
|
Depreciation and amortisation
charges in the statement of profit or loss and other comprehensive
income may change where such charges are determined using the UOP,
or where the useful life of the related assets change. The Group's
mine development properties asset category, incorporating the
deferred stripping asset and rehabilitation obligation assets is
amortised using the UOP method; and
|
●
|
Provisions for rehabilitation and
environmental provisions may change where reserve estimate changes
affect expectations about when such activities will occur and the
associated cost of these activities.
|
Production forecasts from the
underground mine at Sukari are partly based on estimates regarding
future resource and reserve growth. It should be specifically noted
that the potential quantity and grade from the Sukari underground
mine is conceptual in nature and that it is uncertain if
exploration will result in further targets being delineated as a
mineral resource. Please refer to the Mineral Reserve and Resource
statement impact on ore reserves sensitivity, note
3.1.1(h).
1.2.4 ESTIMATE: RESTORATION AND
REHABILITATION PROVISION
Management performed a
reassessment of the restoration and rehabilitation plan for Sukari
to determine the Company's obligation as at 31 December 2023. This
follows an extensive review process of the plan and provision in
the prior year's assessment which involved an external third party
to verify the assumptions and methodology used in the restoration
and rehabilitation plan. On the financial side, the restoration and
rehabilitation plan and provision assessment resulted in an
increase of the provision by US$1.3 million (2022: US$ 5.8 million
decrease) to US$40 million as at 31 December 2023, see note
2.14.
The marginal US$1.3 million
increase in the provision from the December 2023 reassessment,
other than the unwinding of interest was due to a number of factors
and assumptions affecting the inputs to the model e.g. a small
increase in the inflation rate to 2.40% in 2023 from 2.37% in 2022
and an increase in the undiscounted provision amount by US$6.2
million, partially offset by the increase in the discount rate from
3.63% in 2022 to 4.01% in 2023. The undiscounted cost base for
various components of the expected rehabilitation activities also
increased by a net amount of US$6.2 million. The key drivers for
the cost base increase were mainly due to the following
changes:
●
|
Waste Rock Dumps
− a US$1.3 million
increase ( 2022: Nil) in the rehabilitation cost of the surface
area requiring regrading of slopes and batters;
|
●
|
Mine services area
− a US$1.4 million
increase (2022: Nil), in the costs related to the dismantling,
grading of surfaces and restoration of contours within the mine
services area;
|
●
|
North and West Dump Leach
− a US$0.9 million
increase (2022: US$0.4 million increase) in the cost of loading and
hauling waste rock to create a cover over the tailings
surface;
|
●
|
TSF2 − a US$2.1 million increase (US$ 3
million decrease) in the cost of loading and hauling and spreading
the waste rock over the tailings surface and regrading of
embankments. Increase was mainly due to a revision of the unit cost
of the closure activities; and
|
●
|
US$0.8 million increase (2022:
US$1.5 million increase) in cost of mine closure planning and
design related work.
|
Estimates in the process include
the unit costs used in calculating the provision e.g., ripping and
grading, hauling and application, regrading slopes, construction of
bunds and demolition of buildings and certain fixed costs,
including labour and dismantling of equipment. Management has
assessed the compliance costs relating to Global Industry Standard
on Tailings Management ("GISTM") and this was concluded to be
immaterial.
For rehabilitation activities
measured in tonnes, the unit costs range between US$0.30/t to
US$0.77/t and for those measured in cubic metres and for surface
areas measured in metres, the unit cost used are as
follows:
●
|
Load and haul waste rock by mass
(average haul distance of 2km)
|
US$0.30/t
|
●
|
Load and haul waste rock by mass
(average haul distance of 6km)
|
US$0.75/t
|
●
|
Load and haul waste rock by volume
(average haul distance of 2km)
|
US$0.64/m3
|
●
|
Spread waste rock to create
cover
|
US$2.70/m3
|
●
|
Load and haul demolition waste for
on-site landfill
|
US$1.92/m3
|
●
|
Demolish concrete foundations
(medium reinforced)
|
US$53.00/m3
|
●
|
Regrade slopes and
batters
|
US$1.35/m2
|
●
|
Rip and grade compacted
surfaces
|
US$0.71/m2
|
●
|
Demolish buildings (mix of
prefabricated, steel and blockwork)
|
US$8.00/m2
|
The range of the estimated unit
costs as outlined above is primarily driven by the level of the
work required for each work area requiring restoration and
rehabilitation activity, the extent of the mine areas and/or
infrastructure or equipment requiring such work as well as the
expected mix of the resources to execute the activities i.e.,
either internally sourced, contracted third party, other specialist
resource or a combination of the three.
Sukari has a life of mine which
runs through to 2034 and while generally the majority of
restoration and rehabilitation work will be undertaken when the
economically viable resources of the mine are depleted at the end
of the life of mine, the actual estimated timing of cash outflows
for the restoration and rehabilitation work may be different and,
in some cases, significantly different due to various factors,
including the discovery of more resources that increase the
quantities of economically recoverable resources and therefore,
extend the life of mine. The ore reserves available for economic
extraction, the extent of the area they are located and the
timeframe within which they are reasonably expected to be depleted
and consequently for rehabilitation activities to commence
therefore, have a significant impact on the estimation process of
the restoration and rehabilitation provision amount.
Some of the unit rates have
changed from prior year, with a few of them having only a marginal
change and there are also other unit rates with no movement from
prior year. As the rehabilitation and restoration work will be done
in-country, management has considered the year-on-year inflation in
Egypt and particularly the devaluation of the Egyptian currency,
EGP against the USD in the year over the last two years and
concluded that maintaining the unit rates largely within the same
range as the prior year would be reasonable in the estimation
process for the current year provision.
Management has performed
sensitivity analyses of reasonably possible changes in the
significant assumptions which are primarily the unit costs of the
rehabilitation activities above as well as the discount and
inflation rates.
The sensitivity results below are
based on illustrative percentage changes, however the estimates may
vary by greater amounts. The provision for restoration and
rehabilitation may also change where reserve estimate changes
affect expectations about when such activities will occur and
therefore the associated cost of these activities.
The reported provision and
corresponding asset amount would change as shown below should there
be a change in the estimated unit cost rates, discount rates and
inflation rate assumptions on the basis that all the other factors
that can potentially change remain constant:
●
|
A 10% increase in these estimated
unit and fixed costs elements would result in a US$3.3 million
increase (2022:US$3.1 million) in the provision and corresponding
asset amounts, while a 10% decrease would result in a US$3.3
million decrease (2022:US$3.1 million).
|
●
|
A 10% increase in the discount
rate would result in a US$1.8 million decrease (2022: US$1.4
million) in the provision and corresponding asset amounts, while a
10% decrease would result in a US$1.9 million increase (2022:
US$1.4 million).
|
●
|
A 10% increase in the inflation
rate would result in a US$1.1 million increase (2022: US$0.9
million) in the provision and corresponding asset amounts, while a
10% decrease would result in a US$1.1 million decrease (2022:
US$0.9 million).
|
The above scenarios resulted in
increases of the restoration and rehabilitation provision ranging
from US$1.1 million (2022: US$0.7 million) to US$3.3 million (2022:
US$3.1 million) and decreases of the similar ranges. All the
scenarios would have an insignificant effect on the consolidated
statement of comprehensive income, through immaterial movements in
the interest cost on the liability and reduced rehabilitation asset
amortisation charge. Refer to note 2.14 for additional information
on the restoration and rehabilitation provision
movements.
The sensitivities analysed above
reflect reasonably possible changes in the provisions in response
to changes in the underlying assumptions.
1.3 OTHER SIGNIFICANT ACCOUNTING
POLICIES
1.3.1 PRINCIPLES OF
CONSOLIDATION
The consolidated financial
statements are prepared by combining the financial statements of
all the entities that comprise the consolidated group, being the
Company (the parent entity) and its subsidiaries. Subsidiaries are
all entities over which the Group has control, as defined in IFRS
10 Consolidated financial statements.
Consistent accounting policies are employed in the preparation and
presentation of the consolidated financial statements.
The consolidated financial
statements include the information and results of each subsidiary
and controlled entity from the date on which the Company obtains
control and until such time as the Company ceases to control such
entities. The Group controls an entity when the Group is exposed
to, or has rights to, variable returns from its involvement with
the entity and has the ability to affect those returns through its
power over the entity.
In preparing the consolidated
financial statements, all intercompany balances and transactions,
and unrealised profits arising within the consolidated group, are
eliminated in full.
2. How numbers are
calculated
2.1 Segment reporting
The Group is engaged in the
business of exploration for and mining of precious metals, which
represents three operating segments, two in the business of
exploration and one in the mining of precious metals. The Board is
the Group's chief operating decision-maker within the meaning of
IFRS 8 Operating segments. Management has
determined the operating segments based on the information reviewed
by the Board for the purposes of allocating resources and assessing
performance. Operating segments are reported in a manner consistent
with the internal reporting provided to the chief operating
decision-maker. The chief operating decision-maker, who is
responsible for allocating resources and assessing performance of
the operating segments, has been identified as the Board of
Directors.
The Board considers the business
from a geographic perspective and a mining of precious metals
versus exploration for precious metals perspective. Geographically,
management considers separately the performance in Egypt, Burkina
Faso, Côte d'Ivoire and Corporate (which includes Jersey, United
Kingdom, and Australia). From a mining of precious metals versus
exploration for precious metals perspective, management separately
considers the Egyptian mining of precious metals from the Egyptian
and Côte d'Ivoire exploration for precious metals in these
geographies. The Egyptian mining operations derive revenue from the
sale of gold while Côte d'Ivoire and the new Egyptian entities are
currently only engaged in precious metal exploration and do not
produce any revenue.
The Board assesses the performance
of the operating segments based on profits and expenditure incurred
as well as exploration expenditure in each region. Egypt is the
only operating segment with one of its entities, SGM, mining
precious metals and therefore has revenue and cost of sales whilst
the remaining operating segments do not. All operating segments are
reviewed by the Board as presented and are key to the monitoring of
ongoing performance and assessing plans of the Company.
The Burkina Faso incorporated
legal entities are currently at an advanced stage of being formally
wound-up and costs incurred in the year relate to various aspects
of that process. Costs incurred up to the time the Burkina Faso
entities' wind-up process is formally concluded will continue to be
disclosed within exploration costs and under Burkina Faso in the
segment reporting disclosures.
NON-CURRENT ASSETS, INCLUDING
FINANCIAL INSTRUMENTS BY COUNTRY:
31 December 2023
|
Total
US$'000
|
Egypt
US$'000
|
Burkina Faso
US$'000
|
Côte d'Ivoire
US$'000
|
Corporate
US$'000
|
Non-current assets (excl.
financial assets)
|
1,211,949
|
1,210,391
|
−
|
537
|
1,021
|
Non-current assets (financial
instruments)
|
1,014
|
927
|
2
|
85
|
−
|
Total non-current
assets
|
1,212,963
|
1,211,318
|
2
|
622
|
1,021
|
31 December 2022
|
Total
US$'000
|
Egypt
US$'000
|
Burkina Faso
US$'000
|
Côte d'Ivoire
US$'000
|
Corporate
US$'000
|
Non-current assets (excl.
financial assets)
|
1,206,231
|
1,204,956
|
−
|
826
|
449
|
Non-current assets (financial
instruments)
|
1,372
|
1,270
|
20
|
82
|
−
|
Total non-current
assets
|
1,207,603
|
1,206,226
|
20
|
908
|
449
|
Additions to non-current assets
mainly relate to Egypt and are disclosed in note 2.10.
STATEMENT OF FINANCIAL POSTION BY
OPERATING SEGMENT:
31 December 2023
|
Total
US$'000
|
Egypt Mining
US$'000
|
Egypt Exploration
US$'000
|
Burkina Faso
US$'000
|
Côte d'Ivoire
US$'000
|
Corporate
US$'000
|
Total assets
|
1,523,243
|
1,434,074
|
4,391
|
30
|
6,149
|
78,600
|
Total liabilities
|
(144,637)
|
(133,177)
|
(787)
|
−
|
(2,596)
|
(8,077)
|
Net assets
|
1,378,606
|
1,300,897
|
3,604
|
30
|
3,553
|
70,523
|
31 December 2022
|
Total
US$'000
|
Egypt Mining
US$'000
|
Egypt Exploration
US$'000
|
Burkina Faso
US$'000
|
Côte d'Ivoire
US$'000
|
Corporate
US$'000
|
Total assets
|
1,493,533
|
1,413,266
|
4,057
|
40
|
4,074
|
72,096
|
Total liabilities
|
(152,126)
|
(142,556)
|
(533)
|
(470)
|
(3,421)
|
(5,146)
|
Net
assets/(liabilities)
|
1,341,407
|
1,270,710
|
3,524
|
(430)
|
653
|
66,950
|
STATEMENT OF COMPREHENSIVE INCOME
BY OPERATING SEGMENT:
For the year ended 31 December 2023
|
Total
US$'000
|
Egypt Mining
US$'000
|
Egypt Exploration
US$'000
|
Burkina Faso
US$'000
|
Côte d'Ivoire
US$'000
|
Corporate
US$'000
|
Revenue
|
891,262
|
891,262
|
−
|
−
|
−
|
−
|
Cost of sales
|
(596,836)
|
(596,836)
|
−
|
−
|
−
|
−
|
Gross profit
|
294,426
|
294,426
|
−
|
−
|
−
|
−
|
Exploration and evaluation
costs
|
(31,653)
|
−
|
−
|
(869)
|
(25,226)
|
−
|
Other operating
costs(1)
|
(68,542)
|
(39,069)
|
(377)
|
1,221
|
(127)
|
(30,190)
|
Other income
|
5,817
|
6,058
|
99
|
102
|
1,686
|
(2,128)
|
Finance income
|
4,127
|
1,475
|
−
|
−
|
−
|
2,652
|
Finance costs
|
(3,526)
|
(1,681)
|
(42)
|
2
|
(75)
|
(1,730)
|
Net fair value loss on
derivatives
|
(5,509)
|
−
|
−
|
−
|
−
|
(5,509)
|
Profit/(loss) for the year before
tax
|
195,140
|
261,209
|
(5,878)
|
456
|
(23,742)
|
(36,905)
|
Tax
|
(255)
|
(220)
|
−
|
−
|
(21)
|
(14)
|
Profit/(loss) for the year after
tax
|
194,885
|
260,989
|
(5,878)
|
456
|
(23,763)
|
(36,919)
|
Profit/(loss) for the year after
tax attributable to:
|
|
|
|
|
|
|
- the owners of the
parent(2)
|
92,284
|
158,388
|
(5,878)
|
456
|
(23,763)
|
(36,919)
|
- non-controlling
interest in SGM(2)
|
102,601
|
102,601
|
−
|
−
|
−
|
−
|
(1) The US$1.2m
gain in the Burkina Faso segment relates to intercompany loans due
to Centamin West Africa Holdings Limited (included as an expense
within the Corporate segment) that were written off in the year.
These amounts are fully eliminated on consolidation, therefore do
not impact the overall Group results.
(2) Please note
that the cost recovery model on which profit share is based under
the Concession Agreement is different to the accounting results
presented above due to various adjustments and as such the share of
profit disclosed above is not reflective of the 55%:45% split that
was in place from 1 July 2018 to 30 June 2020 and 50%:50% split
from 1 July 2020 onwards that occurs in practice, refer to the
statement of cash flows by operating segment below for further
information.
For the year ended 31 December 2022
|
Total
US$'000
|
Egypt Mining
US$'000
|
Egypt Exploration
US$'000
|
Burkina Faso
US$'000
|
Côte d'Ivoire
US$'000
|
Corporate
US$'000
|
Revenue
|
788,424
|
788,424
|
−
|
−
|
−
|
−
|
Cost of sales
|
(544,075)
|
(544,075)
|
−
|
−
|
−
|
−
|
Gross profit
|
244,349
|
244,349
|
−
|
−
|
−
|
−
|
Exploration and evaluation
costs
|
(29,723)
|
−
|
(1,675)
|
(2,928)
|
(25,120)
|
−
|
Other operating costs
|
(49,003)
|
(27,299)
|
(116)
|
(506)
|
(326)
|
(20,756)
|
Other income
|
6,623
|
8,039
|
196
|
(168)
|
(666)
|
(778)
|
Finance income
|
1,214
|
99
|
−
|
−
|
−
|
1,115
|
Finance costs(1)
|
(2,459)
|
(1,098)
|
(19)
|
(2)
|
(58)
|
(1,282)
|
Impairment of intra-group
loans
|
−
|
−
|
−
|
140,623
|
−
|
(140,623)
|
Profit/(loss) for the year before
tax
|
171,001
|
224,090
|
(1,614)
|
137,019
|
(26,170)
|
(162,324)
|
Tax
|
(226)
|
(226)
|
−
|
−
|
−
|
−
|
Profit/(loss) for the year after
tax
|
170,775
|
223,864
|
(1,614)
|
137,019
|
(26,170)
|
(162,324)
|
Profit/(loss) for the year after
tax attributable to:
|
|
|
|
|
|
|
− the
owners of the parent(1)
|
72,490
|
125,579
|
(1,614)
|
137,019
|
(26,170)
|
(162,324)
|
− non-controlling interest in SGM(1)
|
98,285
|
98,285
|
−
|
−
|
−
|
−
|
(1) Please note that the
cost recovery model on which profit share is based under the
Concession Agreement is different to the accounting results
presented above due to various adjustments and as such the
share of profit disclosed above is not reflective of the 55%:45%
split that was in place from 1 July 2018 to 30 June 2020 and
50%:50% split from the 1 July 2020 onwards that occurs in practice,
refer to the statement of cash flows by operating segment below for
further information.
STATEMENT OF CASH FLOWS BY
OPERATING SEGMENT:
For the year ended 31 December 2023
|
Total
US$'000
|
Egypt Mining
US$'000
|
Egypt Exploration
US$'000
|
Burkina Faso
US$'000
|
Côte d'Ivoire
US$'000
|
Corporate
US$'000
|
Statement of cash flows
|
|
|
|
|
|
|
Net cash generated from/(used in)
operating activities
|
353,600
|
419,210
|
(395)
|
54
|
(1,384)
|
(63,885)
|
Net cash (used in)/generated from
investing activities
|
(198,768)
|
(200,631)
|
(512)
|
−
|
(276)
|
2,651
|
Net cash used in financing
activities
|
(164,994)
|
(232,994)
|
−
|
−
|
−
|
68,000
|
Own shares acquired
|
(245)
|
−
|
−
|
−
|
−
|
(245)
|
Cash component of share-based
payments
|
(583)
|
−
|
−
|
−
|
−
|
(583)
|
Dividend paid − non-controlling interest in
SGM
|
(112,000)
|
(112,000)
|
−
|
−
|
−
|
−
|
Dividend paid − intercompany
|
−
|
(120,994)
|
−
|
−
|
−
|
120,994
|
Dividend paid − owners of the parent
|
(52,166)
|
−
|
−
|
−
|
−
|
(52,166)
|
Net increase/(decrease) in cash
and cash equivalents
|
(10,163)
|
(14,416)
|
(907)
|
54
|
(1,660)
|
6,766
|
Cash and cash equivalents at the
beginning of the year
|
102,373
|
27,373
|
1,971
|
1
|
1,422
|
71,606
|
Effect of foreign exchange rate
changes
|
1,112
|
729
|
100
|
(25)
|
1,782
|
(1,474)
|
Cash and cash equivalents at the
end of the year
|
93,322
|
13,686
|
1,164
|
30
|
1,544
|
76,898
|
For the year ended 31 December 2022
|
Total
US$'000
(restated)
|
Egypt
Mining(1)
US$'000
|
Egypt Exploration
US$'000
|
Burkina Faso
US$'000
|
Côte d'Ivoire
US$'000
|
Corporate(1)
US$'000
|
Statement of cash flows
|
|
|
|
|
|
|
Net cash generated from/(used in)
operating activities
|
292,524
|
321,542
|
1,912
|
(2,644)
|
1,673
|
(29,959)
|
Net cash (used in)/generated from
investing activities
|
(274,583)
|
(274,120)
|
(976)
|
−
|
(595)
|
1,108
|
Net cash used in financing
activities
|
(122,219)
|
(35,492)
|
−
|
−
|
−
|
(86,727)
|
Cash element of share-based
payments
|
(523)
|
−
|
−
|
−
|
−
|
(523)
|
Dividend paid − non-controlling interest
in SGM
|
(35,492)
|
(35,492)
|
−
|
−
|
−
|
−
|
Dividend paid − owners of the parent
|
(86,204)
|
−
|
−
|
−
|
−
|
(86,204)
|
Net (decrease)/increase in cash
and cash equivalents
|
(104,278)
|
11,930
|
936
|
(2,644)
|
1,078
|
(115,578)
|
Cash and cash equivalents at the
beginning of the year
|
(207,821)
|
13,609
|
935
|
5
|
859
|
192,413
|
Effect of foreign exchange rate
changes
|
(1,170)
|
1,834
|
100
|
2,640
|
(515)
|
(5,229)
|
Cash and cash equivalents at the
end of the year
|
102,373
|
27,373
|
1,971
|
1
|
1,422
|
71,606
|
1)
The comparatives in the Consolidated Statement of Cash Flows for
the year ended 31 December 2022 have been restated to reflect an
increase of cash generated from operating activities of $2.5m,
interest paid of $1.9m and a reduction of the effect of foreign
exchange rate changes of $0.6m.
2.2 Revenue
An analysis of the Group's revenue
for the year, is as follows:
|
For the year ended
31
December 2023
US$'000
|
For the year ended
31
December 2022
US$'000
|
Gold sales
|
889,384
|
786,921
|
Silver sales
|
1,878
|
1,503
|
|
891,262
|
788,424
|
All gold and silver sales up to 30
June 2023 were made to a single customer in North America, Asahi
Refining Canada Ltd ("Asahi"). Asahi's contract expired on 30 June
2023 and effective 1 July 2023, all gold and silver sales were made
to another single customer in Switzerland, MKS PAMP SA
("MKS").
ACCOUNTING POLICY:
REVENUE
Revenue is measured at the fair
value of the consideration received or receivable for goods in the
normal course of business.
Sale of goods
Under IFRS 15, revenue from the
sale of mineral production is recognised when the Group has passed
control of the mineral production to the buyer (the performance
obligation), it is probable that economic benefits associated with
the transaction will flow to the Group, the sales price can be
measured reliably, and the Group has no significant continuing
involvement and the costs incurred or to be incurred in respect of
the transaction can be measured reliably.
Up to 30 June 2023, with the Asahi
contract, the performance obligation was satisfied when the doré
bars were packaged and collected by the approved carrier with the
appropriate required documentation at the gold room and the
approved carrier accepted control of the shipment by signature.
After receipt of the shipment at the refinery, 98% of the amounts
due are paid within five working days, with the balance being paid
within four working days thereafter. Effective 1 July 2023, a new
contract was signed with MKS and based on management's assessment
of the contract, SGM's performance obligations for the
determination of timing of revenue recognition have not changed,
and revenue continues to be recognised on satisfaction of the
performance obligations as outlined above.
Where an adjustment to the sales
price based on a survey of the mineral production by the buyer (for
instance an assay for gold content) is done, recognition of the
revenue from the sale of mineral production is based on the
most recently determined estimate of product
specifications.
Royalty
The Arab Republic of Egypt ("ARE")
is entitled to a royalty of 3% of net sales revenue (revenue net of
freight and refining costs) as defined from the sale of gold and
associated minerals from SGM. This royalty is calculated and
recognised on receipt of the final certificate of analysis document
received from the refinery. Due to its nature, this royalty is not
recognised in cost of sales but rather in other operating
costs.
2.3 Profit before tax
Profit for the year before tax has
been arrived at after crediting/(charging) the following
gains/(losses) and income/(expenses):
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Other income
|
|
|
Net foreign exchange
gains
|
5,641
|
6,559
|
Other income
|
176
|
64
|
|
5,817
|
6,623
|
Finance cost - net
|
|
|
Finance income
|
4,127
|
1,214
|
Finance costs
|
(3,526)
|
(2,459)
|
|
601
|
(1,245)
|
Net fair value loss on derivative
financial instruments
|
(5,509)
|
−
|
Expenses
|
|
|
Cost of sales*
|
|
|
Mine production costs
|
(412,827)
|
(408,543)
|
Movement in inventory
|
13,319
|
10,659
|
Depreciation and
amortisation
|
(197,328)
|
(146,191)
|
|
(596,836)
|
(544,075)
|
Other operating costs
|
|
|
Corporate compliance
|
(3,961)
|
(2,869)
|
Fees payable to the external
auditors
6.5
|
(1,080)
|
(895)
|
Corporate consultants
fees
|
(4,301)
|
(2,697)
|
Salaries and wages
|
(12,434)
|
(11,979)
|
Other administration
expenses
|
(4,026)
|
(3,272)
|
Employee equity settled
share-based payments
|
(7,308)
|
(2,570)
|
Corporate costs
(sub-total)
|
(33,110)
|
(24,282)
|
Other provisions
|
1,182
|
1,180
|
Inventory written-off
|
(3,721)
|
(1)
|
Net movement on provision for
stock obsolescence
|
4,004
|
(579)
|
Other non-corporate operating
expenses
|
(10,215)
|
(1,479)
|
Royalty - attributable to the ARE
government
|
(26,682)
|
(23,842)
|
Other operating costs
(total)
|
(68,542)
|
(49,003)
|
* Inventories recognised as an
expense in the Consolidated Statement of Comprehensive Income
during the year ended 31 December 2023 amounted to US$ 597 million
(2022: US$544 million) and these were included in 'cost of
sales'.
ACCOUNTING POLICY: FINANCE INCOME,
OTHER INCOME AND FOREIGN CURRENCIES
FINANCE INCOME
Finance income is accrued on a
time basis, by reference to the principal outstanding and at the
effective interest rate applicable, which is the rate that
discounts estimated future cash receipts through the expected life
of the financial asset to that asset's net carrying
amount.
Finance income is generated mainly
from treasury activities (e.g., income on surplus funds invested
for the short term) and therefore is separately disclosed outside
of the Group's operating profit in the consolidated statement of
comprehensive income and disclosed as a separate line under
investing activities in the consolidated statement of cash
flows.
FOREIGN CURRENCIES
The individual financial
statements of each Group entity are presented in its functional
currency being the currency of the primary economic environment in
which the entity operates. For the purpose of the consolidated
financial statements, the results and financial position of each
entity are expressed in US dollars, which is the functional
currency of all companies in the Group and the presentation
currency for the consolidated financial statements.
In preparing the financial
statements of the individual entities, transactions in currencies
other than the entity's functional currency are recorded at the
rates of exchange prevailing on the dates of the transactions. At
each reporting date, monetary items denominated in foreign
currencies are retranslated at the rates prevailing at the
reporting date. Non-monetary items carried at fair value that are
denominated in foreign currencies are retranslated at the rates
prevailing on the date when the fair value was
determined.
Non-monetary items that are
measured in terms of historical cost in a foreign currency are not
retranslated. Exchange differences are recognised in profit or loss
in the period in which they arise.
ACCOUNTING POLICY: FINANCE
COSTS
FINANCE COSTS
Finance costs for the Group will
normally include:
●
|
Costs that are 'borrowing costs
for the purposes of IAS 23 Borrowing Costs:
|
|
−
|
interest expense calculated using
the effective interest rate method as described in IFRS 9
Financial Instruments;
|
|
−
|
interest in respect of lease
liabilities; and
|
|
−
|
exchange differences arising from
foreign currency borrowings to the extent that they are regarded as
an adjustment to interest costs.
|
●
|
the unwinding of the effect of
discounting provisions.
|
Borrowing and finance costs which
are generally incurred in the Group's ordinary activities are
recognised in the statement of profit or loss and other
comprehensive income in the period in which they are incurred, and
the Group would also include foreign exchange differences on
directly attributable borrowings as borrowing costs capable of
capitalisation to the extent that they represented an adjustment to
interest costs. These finance costs are separately disclosed in the
consolidated statement of comprehensive income as required by
IAS 1 Presentation of Financial
Statements and disclosed under operating activities
in the consolidated statement of cash flows.
Even though exploration and
evaluation assets can be qualifying assets, they generally do not
meet the 'probable economic benefits' test therefore any related
borrowing costs incurred during this phase are generally recognised
in the statement of profit or loss and other comprehensive income
in the period in which they are incurred.
ACCOUNTING POLICY: EMPLOYEE BENEFITS
EMPLOYEE BENEFITS
Salary costs are absorbed within
cost of sales and other operating costs. Short term employee
benefits are recognised when an employee has rendered service to
the Group in the accounting period, and bonus plans are recognised
when the Group has a present legal or constructive obligation as a
result of past events and the obligation can be reliably
measured.
2.4 DERIVATIVE FINANCIAL
INSTRUMENTS
On 14 June 2023, the Company
entered into put option contracts whereby it purchased a series of
gold put option contracts (the "commodity contracts"). A total of
US$2.5 million, was paid to BMO, the counterparty as a premium on
entering into six put option contracts for a total of 120,000
ounces representing, 20,000 ounces for each month beginning 1 July
2023 to 31 December 2023 at a strike price of US$1,900/oz as part
of the Gold Price Protection Programme. As part of the same
programme, on 20 July 2023, the Company entered into a second
series of six put option contracts for a total of 120,000 ounces
representing, 20,000 ounces for each month beginning 1 January 2024
to 30 June 2024 at a strike price of US$1,900/oz and a total of
US$3.6 million, was paid to HSBC, the counterparty as a premium on
entering into the contracts. By entering into these contracts, the
Company was able to ensure it can reasonably protect the Group's
cash flows by initiating a gold price protection program for the
contracted ounces at these prices over the six-month period to year
end.
The details of the commodity
contracts opened and expired during the year and those outstanding
as at 31 December 2023, are as follows:
Commodity
contract
Type purchased
|
Quantity (1)
(Oz)
|
Contract
Term
|
Strike price per Oz
(1)(2)
$US
|
Premium
Paid
$US'000
|
Mark-to-Market
(MtM)
$US'000
|
Unrealised loss
recognised
(Open
Contracts)
$US'000
|
Realised
loss
recognised
(Settled
Contracts)
$US'000
|
Gold put options
|
120,000
|
1 Jul
23 to 31 Dec 23
|
1,900
|
2,538
|
−
|
−
|
(2,538)
|
Gold put option
|
20,000
|
1 Jan
24 to 31 Jan 24
|
1,900
|
604
|
−
|
(604)
|
−
|
Gold put option
|
20,000
|
1 Feb
24 to 29 Feb 24
|
1,900
|
604
|
22
|
(582)
|
−
|
Gold put option
|
20,000
|
1 Mar
24 to 31 Mar 24
|
1,900
|
604
|
76
|
(528)
|
−
|
Gold put option
|
20,000
|
1 Apr
24 to 30 Apr 24
|
1,900
|
604
|
123
|
(481)
|
−
|
Gold put option
|
20,000
|
1 May
24 to 31 May 24
|
1,900
|
604
|
185
|
(419)
|
−
|
Gold put option
|
20,000
|
1 Jun
24 to 30 Jun 24
|
1,900
|
604
|
248
|
(357)
|
−
|
Total
|
240,000
|
|
|
6,162
|
654
|
(2,971)
|
(2,538)
|
1.
Quantities and strike prices do not fluctuate by month within each
calendar year
2.
Contracts are exercisable based on the average
price for the month being below the strike price of the
put
The resulting fair values of the
outstanding commodity contracts at 31 December 2023 as shown in the
table above, have been recognised, in derivative financial
instruments on the consolidated statement of financial position.
These derivative financial instruments were not designated as
hedges by the Company and are marked-to-market at the end of each
reporting period with the mark-to-market adjustment recorded in the
consolidated profit or loss.
The commodity contracts are
marked-to-market using a valuation model which uses quoted
observable inputs and are classified as Level 2 in the fair value
hierarchy. During the year ended 31 December 2023, a total of
US$5.5m, made up of US$2.5m realised fair value loss and US$3.0m
unrealised fair value loss on the put options was recognised in the
consolidated profit or loss.
2.5 Non-controlling interest in
SGM
EMRA is a 50% shareholder in SGM
and is entitled to a share of 50% of SGM's net production surplus
which can be defined as 'revenue less payment of the fixed royalty
to the ARE and recoverable costs'.
Earnings attributable to the
non-controlling interest in SGM (i.e., EMRA) are pursuant to the
provisions of the CA and are recognised as profit attributable to
the non-controlling interest in SGM in the attribution of profit
section of the statement of comprehensive income of the Group. The
profit share payments during the year will be reconciled against
SGM's audited financial statements. SGM's financial statements for
the year ended 30 June 2023 have been audited and signed off at the
date of this report.
Certain terms of the CA and
amounts in the cost recovery model may also vary depending on
interpretation and management and the Board making various
judgements and estimates that can affect the amounts recognised in
the financial statements.
(A) STATEMENT OF COMPREHENSIVE
INCOME AND STATEMENT OF FINANCIAL POSITION IMPACT
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Statement of comprehensive
income
|
|
|
Profit for the year after tax
attributable to the non-controlling interest in SGM(1)
|
102,601
|
98,285
|
Statement of financial
position
|
|
|
Total equity attributable to
non-controlling interest in SGM(1)
(opening)
|
22,537
|
(40,256)
|
Profit for the year after tax
attributable to the non-controlling interest in SGM(1)
|
102,601
|
98,285
|
Dividend paid - non-controlling
interest in SGM
|
(112,000)
|
(35,492)
|
Total equity attributable to
non-controlling interest in SGM(1)
(closing)
|
13,138
|
22,537
|
(1) Profit share commenced
during the third quarter of 2016. The first two years was a 60:40
split of net production surplus to PGM and EMRA respectively. From
1 July 2018 this changed to a 55:45 split for the next two-year
period until 30 June 2020, after which all net production surpluses
have been split 50:50.
Any variation between payments
made during the year (which are based on the Company's estimates)
and the SGM audited financial statements, may result in a balance
due and payable to EMRA or advances to be offset against future
distributions and included within the non-controlling interest in
SGM balance on the statement of financial position and statement of
changes in equity.
(b) Statement of cash flows
impact
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Statement of cash flows
|
|
|
Dividend paid - non-controlling interest in SGM(1)
|
(112,000)
|
(35,492)
|
(1) Profit share commenced
during the third quarter of 2016. The first two years was a 60:40
split of net production surplus to PGM and EMRA respectively. From
1 July 2018 this changed to a 55:45 split for the next two-year
period until 30 June 2020, after which all net production surpluses
will be split 50:50.
EMRA and PGM benefit from advance
distributions of profit share which are made on a weekly or
fortnightly basis and proportionately in accordance with the terms
of the CA. Future distributions will consider ongoing cash flows,
historical costs that are still to be recovered and any future
capital expenditure. All profit share payments will be reconciled
against SGM's audited June financial statements for current and
future periods.
2.6 Tax
The Group operates in several
countries and, accordingly, it is subject to the various tax
regimes applicable in such countries. From time to time the Group
is subject to changes in tax laws and/or a review of its related
tax regime and filings. Disputes can arise with the tax authorities
over the interpretation or application of applicable tax laws,
regulations and/or rules to the Group's business. If the Group is
unable to resolve any of these matters favourably, there may be an
adverse impact on the Group's financial performance, cash flows or
results of operations. If management's estimate of the future
resolution of these matters' changes, the Group will recognise the
effects of the changes in its consolidated financial statements in
the period that such changes occur.
Tax exemptions
In Egypt, Pharaoh Gold Mines NL
("PGM") has entered into a Concession Agreement ("CA") with EMRA
and the Government of Egypt represented by the Ministry of
Petroleum & Natural Resources. The CA was issued under special
law no. 222 of 1994. Under the CA, income generated by SGM's
activities is granted a tax exemption (as described below) from all
taxes imposed in Egypt (as at the date of the CA and any new taxes
imposed under a different name since such date), other than the
fixed 3% royalty attributable to the Egyptian government, rental
income on property and interest income on cash and cash
equivalents. PGM and SGM have further tax
exemptions for the duration of the CA from certain other
taxes.
The CA grants certain tax
exemptions, including the following:
●
|
Article III(e) of the CA provides
for a 15-year exemption from any taxes imposed by the Egyptian
government on the revenues generated from SGM for the period 10
March 2010 (being the date of commencement of commercial
production) to 9 March 2025. SGM will in due course have to file an
application with the Ministry of Petroleum & Natural Resources
to extend the tax-free period for a further 15 years to 9 March
2040. ("Tax Exemption Renewal") Under the CA, EMRA is obliged to support the application for the Tax
Exemption Renewal so long as (i) there is no tax dispute with
Government at SGM level or its equity holders (PGM & EMRA) and
(ii) exploration activities in the licence areas have
been planned and agreed by all parties. Preparatory works have
already commenced on the application for the Tax Exemption Renewal
and the Group intends for SGM to submit the application in the near
future but no later than Q3 2024.
If granted, the extension should be on the same
terms (as it is an extension).
Albeit there is no guarantee that the
Government will agree to grant the
renewal or on the
same basis, the Group believes that
all requisite requirements are and will have been
complied with for such renewal. Should the Tax Exemption renewal
not be granted, then SGM will be subject to previously exempted
taxes, such as, for example, the prevailing 22.5% corporate income
tax rate applicable in Egypt.
|
●
|
Article XI of the CA provides for
PGM and SGM to be exempt for the duration of the CA from custom
taxes and duties with respect to the importation of machinery,
equipment and consumable items required for the purpose of
exploration and mining activities at SGM. The exemption shall only
apply if there is no local substitution with the same or similar
quality to the imported machinery, equipment, or consumables. Such
exemption will also be granted if the local substitution is more
than 10% more expensive than the imported machinery, equipment, or
consumables after the addition of the insurance and transportation
costs. To this end, PGM's contractors and subcontractors are -
under the same provision - also entitled to import machinery,
equipment, and consumable items under the 'Temporary Release
System' which provides exemption from Egyptian customs
duty.
|
●
|
Under Article XIX of the CA, PGM,
EMRA and SGM and their respective buyers will for the duration of
the CA be exempt from any duties or taxes on the export of gold and
associated minerals produced from SGM. PGM is at all times free to
transfer in US$ or other freely convertible foreign currency, any
cash of PGM representing its share of net proceeds and recovery of
costs, without any Egyptian government limitation, tax or
duty.
|
●
|
Under Article VIII of the CA legal
title of all operating assets of PGM will pass to EMRA when cost
recovery is completed at the end of the life of mine. PGM is
exempted from all custom, duties, excise, stamps and sale taxes on
the transfer of such assets to EMRA. The right of use of all fixed
and movable assets, however, remains with PGM and
SGM.
|
RELEVANCE OF TAX CONSOLIDATION TO
THE CONSOLIDATED ENTITY
In Australia, Centamin Egypt
Limited and Pharaoh Gold Mines NL, both wholly owned Australian
resident entities within the Group, have elected to form a
tax-consolidated group from 1 July 2003 and therefore are treated
as a single entity for Australian income tax purposes. The
head entity within the tax-consolidated group is Centamin Egypt
Limited. Pharaoh Gold Mines NL, which has a registered Egyptian
branch, benefits from the 'branch profits exemption' whereby
foreign branch income will generally not be subject to Australian
income tax. Ampella Mining Limited (in Liquidation) is a single
entity for Australian income tax purposes.
NATURE OF TAX FUNDING ARRANGEMENTS
AND TAX-SHARING AGREEMENTS
Entities within the Australian
tax-consolidated group have entered into a tax funding arrangement
and a tax-sharing agreement with the head entity. Under the terms
of the tax-funding agreement, Centamin Egypt Limited and each of
the entities in the tax-consolidated group have agreed to pay a
tax-equivalent payment to or from the head entity, based on the
current tax liability or current tax asset of the entity. Such
amounts are reflected in amounts receivable from or payable to
other entities in the tax‑consolidated group.
The tax-sharing agreement entered
between members of the tax-consolidated group provides for the
determination of the allocation of income tax liabilities between
the entities should the head entity default on its tax payment
obligations. No amounts have been recognised in the financial
statements in respect of this agreement as payment of any amounts
under the tax-sharing agreement is considered
remote.
Tax recognised in profit is
summarised as follows:
TAX EXPENSE
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Current tax
|
|
|
Current tax expense in respect of
the current year
|
(255)
|
(226)
|
Deferred tax
|
−
|
−
|
Total tax expense
|
(255)
|
(226)
|
The tax expense for the year can
be reconciled to the profit per the consolidated statement of
comprehensive income as follows:
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Profit for the year before
tax
|
195,140
|
171,001
|
Tax expense calculated at
0%(1) (2022: 0%)(1)
of profit for the year before tax
|
−
|
−
|
Tax effect of:
|
|
|
Other
|
(255)
|
(226)
|
Tax expense
|
(255)
|
(226)
|
(1) The tax rate used in the
above reconciliation is the corporate tax rate of 0% payable by
Jersey corporate entities under the Jersey tax law (2022: 0%).
There has been no change in the underlying corporate tax rates when
compared with the previous financial period.
Tax recognised in the balance
sheet is summarised as follows:
|
For the year ended
31
December 2023
US$'000
|
For the year ended
31
December 2022
US$'000
|
Current tax liabilities
|
102
|
249
|
Global implementation of OECD Pillar Two model
rules
In December 2021, the Organisation
for Economic Co-operation and Development ("OECD") published Tax
Challenges Arising from the Digitalisation of the Economy - Global
Anti-Base Erosion Model Rules (Pillar Two): Inclusive Framework on
BEPS, hereafter referred to as the 'OECD Pillar Two model rules' or
'the rules'. The rules are designed to ensure that large
multinational enterprises within the scope of the rules pay a
minimum level of tax on the income arising in a specific period in
each jurisdiction where they operate. In general, the rules apply a
system of top-up taxes that brings the total amount of taxes paid
on an entity's excess profit in a jurisdiction up to the minimum
rate of 15%.
The rules need to be passed into
national legislation based on each country's approach. The Pillar
Two legislation has not yet been enacted in Jersey, however, the
treasury minister of Jersey, the Company's country of
incorporation, announced the intentions in relation to Pillar Two
implementation, they intend to implement an Income Inclusion Rule
("IIR") and domestic minimum tax from 2025, while continuing to
monitor global implementation. The rules will impact current income
tax when the legislation comes into effect.
When enacted, applying the OECD
Pillar Two model rules and determining their impact on the Group's
financial statements is complex and poses a number of practical
challenges. However, since the Pillar Two legislation was not
effective at the reporting date, the Group has no related current
tax exposure.
The Group could be in scope of the
OECD Pillar Two model rules from 2025 onwards in either Jersey or
Australia based on current forecasts of revenue and is currently in
the process of performing an assessment of the potential impact of
this on the Group. The Group currently has an effective tax rate of
approximately 0%, albeit it makes substantial profit share payments
to EMRA, an Egyptian government body, refer to note 2.5 for further
information on the profit attributable to the NCI. There is
uncertainty around how the OECD Pillar Two model rules will be
applied to the Group, and the position is currently being worked
through with the relevant tax advisors.
ACCOUNTING POLICY:
TAXATION
Income tax expense comprises
current and deferred tax. It is recognised in profit or loss except
to the extent that it relates to a business combination, or items
recognised directly in equity or in OCI.
CURRENT TAX
The tax currently payable is based
on taxable profit for the period. Taxable profit differs from
profit as reported in the consolidated statement of comprehensive
income because of items of income or expense that are taxable or
deductible in other periods and items that are never taxable or
deductible. The Group's liability for current tax is calculated
using tax rates that have been enacted or substantively enacted by
the end of the reporting period.
DEFERRED TAX
Deferred tax is recognised on
temporary differences between the carrying amounts of assets and
liabilities in the financial statements and the corresponding tax
bases used in the computation of taxable profit. Deferred tax
liabilities are generally recognised for all taxable temporary
differences. Deferred tax assets are generally recognised for all
deductible temporary differences to the extent that it is probable
that taxable profits will be available against which those
deductible temporary differences can be utilised. Such deferred tax
assets and liabilities are not recognised if the temporary
difference arises from goodwill or from the initial recognition
(other than in a business combination) of other assets and
liabilities in a transaction that affects neither the taxable
profit nor the accounting profit.
2.7 FINANCIAL
INSTRUMENTS
INTEREST BEARING LOANS AND
BORROWINGS
US$150 million Revolving Credit Facility
("RCF")
On 22 December 2022, the Company
entered into an agreement for a US$150 million RCF with a syndicate
of four banks: Bank of Montreal (London Branch), HSBC Bank plc, ING
Bank N.V. (Amsterdam Branch) and Nedbank Limited (London
Branch).
As at 31 December 2023, there were
no drawdowns on the facility and therefore no interest expense on
borrowings was recognised in the period, however, in accordance
with the RCF, commitment fees are charged on the US$150 million
undrawn commitment and the total commitment fees charged on this
undrawn commitment during the year ended 31 December 2023 was
US$1.6 million (2022: US$ Nil)and this was recognised in the
consolidated statements of comprehensive income in period. The
commitment fee is charged and paid on a quarterly basis at an
annual rate of 1.4%.
The terms of the facility imposes
certain financial covenants on the Company in respect of each
Relevant Period that has an outstanding borrowing as outlined below
i.e., the Company shall ensure that:
a) Interest Cover: Interest Cover in respect of any
Relevant Period shall not be less than the ratio of 4:1;
b) Leverage: Leverage in respect of any Relevant Period
shall not exceed the ratio of 3:1;
c) Liquidity: Liquidity shall at all times exceed
US$50,000,000; and
d) Reserve
Tail: at each Scheduled Reserves Assessment Date, the
Reserve Tail Ratio is not less than thirty per cent.
As at 31 December 2023, although
there was no drawdown on the facility, the Company was in full
compliance with all the requirements and obligations in respect of
financial covenants and financial conditions as stipulated in the
agreement.
The Relevant Period is defined as
each period of twelve months ending on or about the last day of the
Financial Year and each period of twelve months ending on or about
the last day of each Financial Quarter.
ACCOUNTING POLICY: FINANCIAL
INSTRUMENTS
FINANCIAL LIABILITIES AND
EQUITY
Debt and equity instruments are
classified as either financial liabilities or as equity in
accordance with the substance of the contractual arrangement as
defined below. Financial liabilities are recognised in the Group's
balance sheet when the Group becomes a party to the contractual
provisions of the instrument.
OTHER FINANCIAL
LIABILITIES
Other financial liabilities,
including borrowings, are initially measured at fair value, net of
transaction costs and are subsequently measured at amortised cost
using the effective interest method, with interest expense
recognised on an effective yield basis.
DERECOGNITION OF FINANCIAL
LIABILITIES
The Group derecognises financial
liabilities when, and only when, the Group's obligations are
discharged, cancelled or they expire.
FINANCIAL ASSETS
CLASSIFICATION
The Group classifies its financial
assets in the following measurement categories:
●
|
those to be measured subsequently
at fair value (either through OCI or through profit or loss);
and
|
●
|
those to be measured at amortised
cost.
|
The classification depends on the
entity's business model for managing the financial assets and the
contractual terms of the cash flows.
For assets measured at fair value,
gains and losses will either be recorded in profit or loss or OCI.
For investments in equity instruments that are not held for
trading, this will depend on whether the Group has made an
irrevocable election at the time of initial recognition to account
for the equity investment at Fair Value through other Comprehensive
Income ("FVOCI").
RECOGNITION AND
DERECOGNITION
Purchases and sales of financial
assets are recognised on trade date, being the date on which the
Group commits to purchase or sell the asset.
Financial assets are derecognised
when the rights to receive cash flows from the financial assets
have expired or have been transferred and the Group has transferred
substantially all the risks and rewards of ownership. If the Group
neither transfers nor retains substantially all the risks and
rewards of ownership and continues to control the transferred
asset, the Group recognises its retained interest in the asset and
an associated liability for amounts it may have to pay. If the
Group retains substantially all the risks and rewards of ownership
of a transferred financial asset, it continues to recognise the
financial asset and also recognises a collateralised borrowing for
the proceeds received.
MEASUREMENT
At initial recognition, the Group
measures a financial asset at its fair value plus, in the case of a
financial asset not at Fair Value through Profit or Loss ("FVPL"),
transaction costs that are directly attributable to the acquisition
of the financial asset and trade receivables are initially
recognised at transaction price unless they have a significant
financing component. Transaction costs of financial assets carried
at FVPL are expensed in profit or loss. Financial assets with
embedded derivatives are considered in their entirety when
determining whether their cash flows are solely payment of
principal and interest.
Subsequent to initial recognition,
investments in subsidiaries are measured at cost in the Company's
financial statements. The classification depends on the nature and
purpose of the financial assets and is determined at the time of
initial recognition.
EFFECTIVE INTEREST
METHOD
The effective interest method is a
method of calculating the amortised cost of a financial asset and
of allocating interest income over the relevant period. The
effective interest rate is the rate that exactly discounts
estimated future cash receipts through the expected life of the
financial asset, or, where appropriate, a shorter period, to the
net carrying amount on initial recognition.
FINANCIAL ASSETS AT AMORTISED
COST
The Group classifies its financial
assets as at amortised cost only if both of the following criteria
are met:
●
|
the asset is held within a
business model whose objective is to collect the contractual cash
flows; and
|
●
|
the contractual terms give rise to
cash flows that are solely payments of principal and
interest.
|
This category of financial assets
is measured at amortised cost using the effective interest rate
method less impairment. Interest is recognised by applying the
effective interest rate except for short-term receivables when the
recognition of interest would be immaterial.
IMPAIRMENT OF FINANCIAL
ASSETS
Financial assets, other than those
at fair value through profit or loss, are assessed for indicators
of impairment at each reporting date. In accordance with paragraph
5.5.1 of IFRS 9 Financial Instruments,
with respect to recognition of expected credit losses, a loss
allowance shall be recognised for expected credit losses on a
financial asset that is measured in accordance with paragraphs
4.1.2 or 4.1.2A, a lease receivable, a contract asset or a loan
commitment and a financial guarantee contract to which the
impairment requirements apply in accordance with paragraphs 2.1(g),
4.2.1(c) or 4.2.1(d).
The objective of the impairment
requirements is to recognise lifetime expected credit losses for
which there have been significant increase in credit risk since
initial recognition, whether assessed on an individual or
collective basis, considering all reasonable and supportable
information, including that which is forward-looking.
At each reporting date, the Group
assesses whether financial assets carried at amortised cost are
credit impaired. A financial asset is credit-impaired when one or
more events that have a detrimental impact on the estimated future
cash flows of the financial asset have occurred.
The carrying amount of the
financial asset is reduced by the impairment loss directly for all
financial assets through the use of an allowance account, with a
simplified approach for trade receivables. When a trade receivable
is uncollectible, it is written off against the allowance account.
Subsequent recoveries of amounts previously written off are
credited against the allowance account. Changes in the carrying
amount of the allowance account are recognised in profit or
loss.
With the exception of financial
assets at fair value through other comprehensive income equity
instruments, if, in a subsequent period, the amount of the
impairment loss decreases and the decrease can be related
objectively to an event occurring after the impairment was
recognised, the previously recognised impairment loss is reversed
through profit or loss to the extent the carrying amount of the
investment at the date the impairment is reversed does not exceed
what the amortised cost would have been had the impairment not been
recognised.
2.8 Trade and other
receivables
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Non-current
|
|
|
Other receivables
− deposits
|
1,014
|
1,372
|
Current
|
|
|
Gold and silver sales
debtor
|
44,917
|
29,832
|
Other receivables
|
4,526
|
5,796
|
|
49,443
|
35,628
|
Trade and other receivables are
classified as financial assets subsequently measured at amortised
cost.
All gold and silver sales during
the first half of the year were made to a single customer in North
America, Asahi Refining Canada Ltd, and there is no recognised
receivable balance from this customer as at year end. In the second
half of the year, all gold and silver sales were made to a single
customer in Switzerland, MKS PAMP SA, and there were no receivables
past due from this customer.
The average age of the total
receivables is 20 days (2022: 16 days) while that of gold and
silver sales only which make up the significant part of the debtors
is an average of 9 days (2022: 9 days), see not 2.2 above and
expected credit losses ("ECL") are considered immaterial and
therefore, no ECL have been recognised in these financial
statements. No interest is charged on the receivables. Of the trade
receivables balance, the gold and silver sales debtor is all
receivable from MKS PAMP SA. The amount due has been received in
full after year end. Other receivables represent GST and VAT owing
from various jurisdictions in which the Group operates.
The Directors consider that the
carrying amount of trade and other receivables is approximately
equal to their fair value, therefore no expected credit loss is
recognised within this note, see note 3.1.1 for the risk assessment
related to trade receivables.
2.9 Prepayments
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Current
|
|
|
Prepayments (1)
|
17,404
|
13,864
|
|
17,404
|
13,864
|
(1) The prepayments balance
above mainly consists of warehouse inventories paid for in
advance.
2.10 Property, plant, and
equipment
|
Office equipment
US$'000
|
Buildings
US$'000
|
Plant and equipment
US$'000
|
Mining
equipment
US$'000
|
Mine
development
properties
US$'000
|
Capital
work in
progress
US$'000
|
Total
US$'000
|
Year ended 31 December 2023
cost
|
|
|
|
|
|
|
|
Balance at 1 January
2023
|
8,151
|
21,701
|
635,376
|
383,521
|
1,009,754
|
78,804
|
2,137,307
|
Additions
|
76
|
290
|
44
|
402
|
−
|
189,911
|
190,723
|
Additions: IFRS 16 right of use
assets
|
−
|
1,150
|
66
|
−
|
−
|
−
|
1,216
|
Increase in rehabilitation
asset
|
−
|
−
|
−
|
−
|
1,310
|
−
|
1,310
|
Transfers from capital work in
progress
|
890
|
3,216
|
74,033
|
29,233
|
123,599
|
(230,971)
|
−
|
Transfers from exploration and
evaluation asset
|
−
|
−
|
−
|
−
|
12,172
|
−
|
12,172
|
Transfers between
categories
|
515
|
31,782
|
(26,266)
|
(6,031)
|
−
|
−
|
−
|
Disposals
|
(1,464)
|
(52)
|
(9,373)
|
(87,350)
|
−
|
−
|
(98,239)
|
Disposals: IFRS 16 right of use
assets
|
−
|
(1,311)
|
(279)
|
−
|
−
|
−
|
(1,590)
|
Balance at 31 December
2023
|
8,168
|
56,776
|
673,601
|
319,775
|
1,146,835
|
37,744
|
2,242,899
|
Accumulated depreciation and
amortisation
|
|
|
|
|
|
|
|
Balance at 1 January
2023
|
(6,634)
|
(3,573)
|
(308,034)
|
(288,521)
|
(443,896)
|
−
|
(1,050,658)
|
Depreciation and
amortisation
|
(1,387)
|
(3,001)
|
(63,511)
|
(43,986)
|
(86,242)
|
−
|
(198,127)
|
Transfers between
categories
|
(522)
|
(19,412)
|
15,589
|
4,345
|
−
|
−
|
−
|
Disposals
|
1,467
|
1,018
|
9,620
|
77,800
|
−
|
−
|
89,905
|
Balance at 31 December
2023
|
(7,076)
|
(24,968)
|
(346,336)
|
(250,362)
|
(530,138)
|
−
|
(1,158,880)
|
Year ended 31 December 2022
cost
|
|
|
|
|
|
|
|
Balance at 1 January
2022
|
9,243
|
13,823
|
625,077
|
359,467
|
816,224
|
85,003
|
1,908,837
|
Additions
|
127
|
1,041
|
526
|
281
|
−
|
261,647
|
263,622
|
Additions: IFRS 16 right of use
assets
|
−
|
2,342
|
1,399
|
4,005
|
−
|
−
|
7,746
|
Decrease in rehabilitation
asset
|
−
|
−
|
−
|
−
|
(5,839)
|
−
|
(5,839)
|
Transfers from capital work in
progress
|
508
|
6,587
|
10,808
|
63,201
|
186,742
|
(267,846)
|
−
|
Transfers from exploration and
evaluation asset
|
−
|
−
|
−
|
−
|
12,627
|
−
|
12,627
|
Disposals
|
(1,727)
|
(1,019)
|
(2,434)
|
(43,294)
|
−
|
−
|
(48,474)
|
Disposals: IFRS 16 right of use
assets
|
−
|
(1,073)
|
−
|
(139)
|
−
|
−
|
(1,212)
|
Balance at 31 December
2023
|
8,151
|
21,701
|
635,376
|
383,521
|
1,009,754
|
78,804
|
2,137,307
|
Accumulated depreciation and
amortisation
|
|
|
|
|
|
|
|
Balance at 1 January
2022
|
(7,543)
|
(3,026)
|
(275,640)
|
(288,323)
|
(378,088)
|
−
|
(952,620)
|
Depreciation and
amortisation
|
(818)
|
(2,221)
|
(34,467)
|
(43,455)
|
(65,808)
|
−
|
(146,769)
|
Disposals
|
1,727
|
1,674
|
2,073
|
43,257
|
−
|
−
|
48,731
|
Balance at 31 December
2022
|
(6,634)
|
(3,573)
|
(308,034)
|
(288,521)
|
(443,896)
|
−
|
(1,050,658)
|
Net book value
|
|
|
|
|
|
|
|
As at 31 December 2023
|
1,092
|
31,808
|
327,265
|
69,413
|
616,697
|
37,744
|
1,084,019
|
As at 31 December 2022
|
1,517
|
18,128
|
327,342
|
95,000
|
565,858
|
78,804
|
1,086,649
|
Included within the depreciation
charge in relation to depreciation of ROU assets is US$1.0 million
within the buildings asset class (2022: US$1 million), US$0.3
million within plant and equipment (2022: US$0.3 million) and
US$0.8 million related to mining equipment (2022: US$ 0.9
million).
The net book value of the assets
in the note above includes the following amounts relating to ROU
assets on leases; US$2.1 million (2022: US$1.8 million) within
buildings, US$0.9 million (2022: US$1.1 million) within plant and
equipment and US$2.4 million (2021: US$3.2 million) within mining
equipment.
An impairment trigger assessment
was performed in 2023 on all Cash Generating Units ("CGUs")
including the Sukari Mine, refer to note 1.2.2 above, however no
impairment triggers on property, plant and equipment were
identified in the assessment.
Deferred stripping assets of US$90
million (2022: $141 million) were recognised in the year ended 31
December 2023 and have been included within mine development
properties. An amortisation charge of US$35 million (2022: US$26
million) has been recognised in the year relating to the deferred
stripping assets.
Assets that have been cost
recovered under the terms of the Concession Agreement ("CA") in
Egypt are included on the statement of financial position under
property, plant and equipment as the Company will use them until
the expiration of the CA.
None of the Group's property,
plant and equipment items is pledged as security and the Group had
US$54 million capital expenditure commitments as at 31 December
2023 (2022: US$19 million).
The Group implemented a new
enterprise resource planning (ERP) software system, SAP (S4 HANA)
during the year. As part of the implementation and migration from
the legacy system, an extensive review process of the fixed assets
was performed as part of the fixed asset register and operational
record clean up and consequently assets that were identified as not
being in use and/or had been previously replaced by other assets
(e.g. mobile equipment rebuilds) had their carrying values
derecognised from the statement of financial position. The fixed
assets derecognised as part of this process, which are included
within disposals in the above table, had a total cost of US$61
million, accumulated depreciation of US$53 million and a carrying
value of US$8 million which was recognised as a loss in the profit
or loss statement within the other operating costs line. In
addition, where assets were identified as being classified in
incorrect asset categories, reclassification adjustments were made
to correct this in the current year, see the PPE note above. The
Directors have concluded that these adjustments are qualitatively
immaterial to these financial statements given the small proportion
of the overall property, plant and equipment balance impacted, and
the quantum of the impact in the profit or loss
statement.
ACCOUNTING POLICY: PROPERTY, PLANT
AND EQUIPMENT ("PPE")
PPE is stated at cost less
accumulated depreciation and impairment. PPE includes capitalised
development expenditure. Cost includes expenditure that is
directly attributable to the acquisition of the item and the
estimated cost of abandonment. In the event that settlement of
all or part of the purchase consideration is deferred, cost is
determined by discounting the amounts payable in the future to
their present value as at the date of acquisition. Subsequent costs
are included in the asset's carrying amount or recognised as a
separate asset, as appropriate, only when it is probable that
future economic benefits associated with the item will flow to the
Group and the cost of the item can be measured reliably. The
carrying amount of the replaced part is derecognised.
All other repairs and maintenance are charged to the income
statement during the financial year in which they are incurred.
The cost of PPE includes the estimated restoration costs
associated with the asset.
Depreciation is charged on PPE,
except for capital work in progress. Depreciation is calculated on
a straight-line basis so as to write off the net cost or other
revalued amount of each asset over its expected useful life to its
estimated residual value. Depreciation on capital work in progress
commences on commissioning of the asset and transfer to the
relevant PPE category.
The estimated useful lives,
residual values and depreciation method are reviewed at the end of
each annual financial year, with the effect of any changes
recognised on a prospective basis. The following estimated useful
lives are used in the calculation of straight-line basis
depreciation:
Plant and equipment:
|
2−20 years
|
Office equipment:
|
3−7 years
|
Mining equipment:
|
2−13 years
|
Buildings:
|
4−20 years
|
Where the assets relate to an
active mine site, the shorter of the above periods or remaining
life of mine are used.
Freehold land is not depreciated,
and all other depreciable assets are depreciated over their useful
life or the life of mine whichever is shorter.
The gain or loss arising on the
disposal or scrappage of an asset is determined as the difference
between the sales proceeds and the carrying amount of the asset and
is recognised in other income or operating expenses.
RIGHT OF USE ASSETS
Right-of-use assets are measured
at cost comprising the following:
●
|
the amount of the initial
measurement of lease liability.
|
●
|
any lease payments made at or
before the commencement date less any lease incentives
received.
|
●
|
any initial direct
costs.
|
●
|
restoration costs
|
Right-of-use assets are generally
depreciated over the shorter of the asset's useful life and the
lease term on a straight-line basis. If the Group is reasonably
certain to exercise a purchase option, the right-of-use asset is
depreciated over the underlying asset's useful life.
MINE DEVELOPMENT
PROPERTIES
Where mining of a mineral reserve
has commenced, the accumulated costs are transferred from
exploration and evaluation assets to mine development
properties.
Amortisation is first charged to
new mine development ventures from the date of first commercial
production. Amortisation of mine properties is on a unit of
production basis resulting in an amortisation charge proportional
to the depletion of the proven and probable ore reserves. The unit
of production is on an ore tonne depleted basis for open pit mining
property assets and an ounce depleted basis for underground mining
property assets.
Capitalised underground
development costs incurred to enable access to specific ore blocks
or areas of the underground mine, and which only provide an
economic benefit over the period of mining that ore block or area,
are depreciated on a unit of production basis, whereby the
denominator is estimated ounces of gold in proven and probable
reserves within that ore block or area where it is considered
probable that those reserves will be extracted
economically.
IFRIC 20 'STRIPPING COSTS IN THE
PRODUCTION PHASE OF A SURFACE MINE'
IFRIC 20 provides clarity on how
to account for and measure the removal of mine waste materials
which provide access to mineral ore deposits. Within Sukari's open
pit operations, removal of mine overburden or waste material is
routinely necessary to gain access to mineral ore deposits and this
waste removal activity is known as 'stripping'. There can be two
benefits accruing to the entity from the stripping
activity:
●
|
usable ore that can be used to
produce inventory; and
|
●
|
improved access to further
quantities of material that will be mined in future
periods.
|
The costs of stripping activity
are required to be accounted for in accordance with the principles
of IAS 2 Inventories to the extent that
the benefit from the stripping activity is realised in the form of
inventory produced. The costs of stripping activity which provides
a benefit in the form of improved access to ore is recognised as a
non-current 'stripping activity asset' where the following criteria
are met:
●
|
it is probable that the future
economic benefit (improved access to the ore body) associated with
the stripping activity will flow to the entity;
|
●
|
the entity can identify the
component of the ore body for which access has been improved;
and
|
●
|
the costs relating to the
stripping activity associated with that component can be measured
reliably.
|
When the costs of the stripping
activity asset and the inventory produced are not separately
identifiable, production stripping costs are allocated between the
inventory produced and the stripping asset by using an allocation
basis that is based on a relevant production measure. A stripping
activity asset is accounted for as an addition to, or as an
enhancement of, an existing asset and classified as tangible or
intangible according to the nature of the existing asset of which
it forms part.
A deferred stripping asset is
initially measured at cost and subsequently carried at cost or its
revalued amount less depreciation or amortisation and impairment
losses. A stripping asset is depreciated or amortised on a
systematic basis, over the expected useful life of the identified
component of the ore body that becomes more accessible as a result
of the stripping activity. The stripping activity asset is
depreciated using a unit of production method based on the total
ounces to be produced for the component over the life of the
component of the ore body.
Capitalised deferred stripping
costs are included in 'Mine Development Properties', within
property, plant, and equipment. These form part of the total
investment in the relevant cash generating unit, which is reviewed
for impairment if events or a change in circumstances indicate that
the carrying value may not be recoverable. Amortisation of deferred
stripping costs is included in cost of sales.
The stripping costs associated
with the current period operations are expensed during that period
and any stripping activity cost associated with producing future
benefit is deferred on the balance sheet and amortised over the
period that the benefit is received i.e., is classified as capital
expenditure, creating a Deferred Stripping asset.
The pit components are the
separate stages of the open pit mine. For each component, the
stripping ratio is determined, and costs are capitalised if the
stripping ratio in the year for that component is greater than the
overall LOM stripping ratio for that component. Based on the
calculations performed the amount capitalised to the balance sheet
for 2023 is US$90 million (2022: US$141 million).
Impairment of assets (other than
exploration and evaluation and financial assets)
At each reporting date, the Group
reviews the carrying amounts of its tangible and intangible assets
to determine whether there is any indication that those assets have
suffered an impairment loss. If such an indication exists, the
recoverable amount of the asset is estimated to determine the
extent of the impairment loss (if any). For the purposes of
assessing impairment, assets are grouped at the lowest levels for
which they potentially generate largely independent cash inflows
(cash generating units).
Recoverable amount is the higher
of fair value loss costs to sell and value in use. In assessing
value in use, the estimated future cash flows are discounted to
their present value using a pre-tax discount rate that reflects
current market assessment of the time value of money and the risks
specific to the asset for which the estimates of future flows have
not been adjusted.
If the recoverable amount of a
cash generating unit ("CGU") is estimated to be less than its
carrying amount, the carrying amount of the CGU is reduced to its
recoverable amount. Where an impairment loss subsequently reverses,
the carrying amount of the cash generating unit is increased to the
revised estimate of its recoverable amount, but only to the extent
that the increased carrying amount does not exceed the carrying
amount that would have been determined had no impairment loss been
recognised for the cash generating unit in prior years.
A reversal of an impairment loss
is recognised immediately in profit or loss, unless the relevant
asset is carried at a revalued amount, in which case the reversal
of an impairment loss is treated as a revaluation
increase.
2.11 Exploration and evaluation
asset
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Balance at the beginning of the
year
|
24,809
|
25,261
|
Expenditure for the
year
|
12,172
|
12,175
|
Transfer to property, plant, and
equipment
|
(12,172)
|
(12,627)
|
Balance at the end of the
year
|
24,809
|
24,809
|
The exploration and evaluation
asset relates to the drilling, geological exploration and sampling
of potential ore reserves and can all be attributed to Egypt,
within the brownfield site at Sukari (US$24.8 million (2022:
US$24.8 million)).
In accordance with the
requirements of IAS 36 Impairment of
assets ("IAS 36") and IFRS 6 Exploration
for and evaluation of mineral resources ("IFRS 6")
exploration and evaluation assets are assessed for impairment when
facts and circumstances (as defined in IFRS 6) suggest that the
carrying amount of exploration and evaluation assets may exceed its
recoverable amount.
An impairment trigger assessment
was performed on the SGM's exploration and evaluation assets, and
no impairment triggers were noted and therefore no formal
impairment test has been
performed.
ACCOUNTING POLICY: EXPLORATION,
EVALUATION AND DEVELOPMENT EXPENDITURE
Exploration and evaluation
expenditures in relation to each separate area of interest are
differentiated between greenfield and brownfield exploration
activities in the year in which they are incurred.
The greenfield and brownfield
terms are generally used in the minerals sector and have been
adopted to differentiate high risk remote exploration activity from
near-mine exploration activity:
(a)
|
greenfield exploration refers to
territory, where mineral deposits are not already developed and has
the goal of establishing a new mine requiring new
infrastructure, regardless of it being in an established mining
field or in a remote location. Greenfield exploration projects can
be subdivided into grassroots and advanced projects embracing
prospecting, geoscientific surveys, drilling, sample collection and
testing, but excludes work of brownfields nature, pit and shaft
sinking and bulk sampling; and
|
(b)
|
brownfield exploration, also known
as near-mine exploration, refers to areas where mineral deposits
were previously developed. In brownfield exploration,
geologists look for deposits near or adjacent to an already
operating mine with the objective of extending its operating life
and taking advantage of the established infrastructure.
|
Greenfield exploration costs are
expensed as incurred and are not capitalised to the balance sheet
until definitive feasibility studies have been completed for the
project that would allow for the application and successful receipt
of a mining license. Brownfield exploration costs continue to be
capitalised to the statement of financial position. Brownfield
exploration and evaluation expenditures in relation to each
separate area of interest are recognised as an exploration
and evaluation asset in the year in which they are incurred
where the following conditions are satisfied:
●
|
The rights to tenure of the area
of interest are current; and
|
●
|
At least one of the following
conditions is also met:
|
|
−
|
the exploration and evaluation
expenditures are expected to be recouped through successful
development and exploration of the area of interest, or
alternatively, by its sale; or
|
|
−
|
exploration and evaluation
activities in the area of interest have not at the reporting date
reached a stage which permits a reasonable assessment of the
existence or otherwise of economically recoverable reserves, and
active and significant operations in, or in relation to, the area
of interest are continuing.
|
Exploration and evaluation assets
are initially measured at cost and include acquisition of rights to
explore, studies, exploration drilling, trenching, and sampling and
associated activities. General and administrative costs are only
included in the measurement of exploration and evaluation
costs where they are related directly to operational activities in
a particular area of interest.
Exploration and evaluation assets
are assessed for impairment when facts and circumstances (as
defined in IFRS 6) suggest that the carrying amount of exploration
and evaluation assets may exceed its recoverable amount. The
recoverable amount of the exploration and evaluation assets (or the
cash generating unit(s) to which it has been allocated, being no
larger than the relevant area of interest) is estimated to
determine the extent of the impairment loss (if any). Where an
impairment loss subsequently reverses, the carrying amount of the
asset is increased to the revised estimate of its recoverable
amount, but only to the extent that the increased carrying amount
does not exceed the carrying amount that would have been
determined had no impairment loss been recognised for the asset in
previous years. The E&E asset's recoverable amount which is the
higher of the amount to be recovered through use of the asset and
the amount to be recovered through sale of the asset is determined
based on the provisions of IAS
36.
In accordance with IFRS 6, the
full balance of the Group's E&E assets which do not currently
generate cash inflows is allocated to a producing mine's
cash-generating unit (CGU) for the purpose of assessing and testing
the assets for impairment as this is considered the most
appropriate level of reporting reflecting the way the Groups'
operations are managed. Management considers an operation actively
mining precious metals as a distinct CGU and only E&E
expenditure on such active mining operations is capitalised. Any
E&E expenditure on operations exploring for precious metals is
expensed.
The application of the Group's
accounting policy for E&E expenditure requires judgement to
determine whether future economic benefits are likely from either
future exploitation or sale, or whether activities have not reached
a stage that permits a reasonable assessment of the existence of
reserves.
In addition to applying judgement
to determine whether future economic benefits are likely to arise
from the Group's E&E assets or whether activities have not
reached a stage that permits a reasonable assessment of the
existence of reserves, the Group has to apply a number of estimates
and assumptions. The determination of the Group's ore reserves and
mineral resource estimates is itself an estimation process that
involves varying degrees of uncertainty depending on how the
resources are classified (i.e., measured, indicated or inferred),
refer to note 1.2.3. The estimates directly impact when the Group
reclassifies E&E expenditure to mine development properties.
The reclassification process requires management to make certain
estimates and assumptions about future events and circumstances,
particularly, when a decision is made to proceed with development
in respect of a particular exploration area to start the economic
extraction operation of the ore. Any such estimates and assumptions
may change as new information becomes available. If, after
expenditure is capitalised, information becomes available
suggesting that the recovery of expenditure is unlikely, the
relevant capitalised amount is written off to the statement of
profit or loss and other comprehensive income in the period when
the new information becomes available.
Where a decision is made to
proceed with development in respect of a particular area of
interest based on the commercial and technical feasibility, the
relevant exploration and evaluation asset is tested for impairment,
reclassified to mine development properties, and then amortised
over the life of the reserves associated with the area of interest
once mining operations have commenced.
Mine development expenditure is
recognised at cost less accumulated amortisation and any impairment
losses. When commercial production has commenced, the associated
costs are amortised over the estimated economic life of the mine
on a units of production basis. Changes in factors such as
estimates of proved and probable reserves that affect the unit of
production calculations are dealt with on a prospective
basis.
All revenues recognised after the
commencement of commercial production are recognised in accordance
with the Revenue Policy stated in note 2.2.
The commencement date of
commercial production is determined when stable and sustained
production capacity has been achieved.
2.12 INVENTORIES
The treatment and classification
of mining stockpiles within inventory is split between current and
non-current assets. Priority is placed on the higher-grade ore,
accordingly, stockpiles which will not be consumed within the next
twelve months based on mining and processing forecasts have been
classified to non-current assets. The volume of ore extracted from
the open pit in the year exceeded the volume that could be
processed, which has caused an increase in the volume and value of
the mining stockpiles.
The carrying value of the
non-current asset portion is assessed at the lower of cost or net
realisable value. The long-term gold price would have to reduce to
approximately US$1,475 per ounce for the net realisable value to
fall below carrying value.
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Non-current
|
|
|
Mining stockpiles
|
103,121
|
94,773
|
|
|
|
Current
|
|
|
Mining stockpiles, ore in circuit,
doré supplies
|
45,807
|
40,836
|
Stores inventory
|
106,150
|
99,733
|
Provision for obsolete stores
inventory
|
(2,500)
|
(6,504)
|
|
149,457
|
134,065
|
The calculation of weighted
average costs of mining stockpiles is applied at a detailed level
of ore grade categories. The open pit ore on the run-of-mine
("ROM") is split into seven different grade categories and the
underground ore is treated as a single high-grade category. Each
grade category is costed individually on a weighted average basis
applying costs specifically related to extracting and moving that
grade of ore to and from the ROM pad. The grade categories range
from high-grade underground and open pit ore to low-grade open pit
ore. Costs per contained ounce differ between the various cost
categories.
Currently at Sukari, low-grade
(0.4 to 0.5g/t) open pit stockpile material above the cut-off grade
of 0.4g/t has been classified as follows on the statement of
financial position:
●
|
Current assets (ore tonnes
scheduled to be processed within the next twelve months):
None
|
●
|
Non-current assets (ore tonnes not
scheduled to be processed within the next twelve months): 15.2Mt at
an average grade of 0.45g/t
|
ACCOUNTING POLICY:
INVENTORIES
Inventories include mining
stockpiles, gold in circuit, doré supplies and stores and
materials. All inventories are stated at the lower of cost and net
realisable value ("NRV"). The cost of mining stockpiles and gold
produced is determined principally by the weighted average cost
method using related production costs.
The cost of mining stockpiles
includes costs incurred up to the point of stockpiling, such as
mining and grade control costs, but excludes future costs of
production. Ore extracted is allocated to stockpiles based on
estimated grade, with grades below defined cut-off levels treated
as waste and expensed. Material piled on the ROM pad is accounted
for in their separate grade categories. While held in physically
separate stockpiles, the Group blends the ore from selected
stockpiles when feeding the processing plant to achieve the
resultant gold content. In such circumstances, lower and
higher-grade ore stockpiles each represent a raw material, used in
conjunction with each other, to deliver overall gold production, as
supported by the relevant feed plan.
The processing of ore in
stockpiles occurs in accordance with the LOM processing plan and is
constantly being optimised based on the known Mineral Reserves,
current plant capacity and mine design. Ore tonnes contained in the
stockpiles which exceed the annual tonnes to be milled as per the
mine plan in the following year, are classified as non-current in
the statement of financial position.
Costs of gold inventories include
all costs incurred up until production of an ounce of gold such as
milling costs, mining costs and directly attributable mine general
and administration costs but excludes transport costs, refining
costs and royalties. NRV is determined with reference to estimated
contained gold and market gold prices, less estimated refining and
transport costs.
Stores and materials consist of
consumable stores and are valued at weighted average cost after
appropriate impairment of redundant and slow-moving items.
Consumable stock for which the Group has substantially all the
risks and rewards of ownership are brought onto the statement
of financial position as current assets.
2.13 TRADE AND OTHER PAYABLES
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Non-current
|
|
|
Other creditors (1)(2)
|
8,264
|
11,801
|
|
|
|
Current
|
|
|
Trade payables
|
27,637
|
43,493
|
Other creditors and accruals
(2)(3)
|
66,611
|
55,902
|
|
94,248
|
99,395
|
(1) Included
within non-current other creditors is US$4.8m (2022: US$7.3m) in
relation to the remaining instalments of a US$17.6m settlement
agreement signed with EMRA in 2021. By its nature, elements of the
cost recovery mechanism within the Concession Agreement are subject
to interpretation and ongoing audits by EMRA. It is possible that
future settlement agreements may be agreed with EMRA in relation to
historic items. The Directors have assessed that it is not probable
that any additional settlements with EMRA will be required as at 31
December 2023, and therefore no additional provisions have been
recognised within these financial statements, therefore, this has
been disclosed under contingent liabilities, refer to note
5.1.
(2) Lease
liabilities - finance lease liabilities relating to some of the
Group's property, plant and equipment of US$1.7m (2022: US$1.9m)
are included in the current portion of other creditors and accruals
balance and US$3.4m (2022: US$4.5m) is included in the non-current
other creditors balance.
(3) The current
portion of the EMRA settlement agreement referred to in (1) above
of US$4.9m (2022: US$4.9m) is included in the current other
creditors and accruals balance above. Also included within the
current other creditors and accruals are stock accruals of US$35m
(2022: US$17m) and non-stock items accruals of US$25m (2022:
US$32m).
Trade payables principally
comprise the amounts outstanding for trade purchases and ongoing
costs. The average credit period taken for trade purchases is 17
days (2022: 29 days). Trade payables are interest free for periods
ranging from 30 to 180 days. Thereafter interest is charged at
commercial rates.
The Group has financial risk
management policies in place to ensure that all payables are paid
within the credit timeframe. Other creditors and accruals relate to
various accruals that have been recognised due to amounts known to
be outstanding for which the related invoices have not yet been
received.
The Directors consider that the
carrying amount of trade payables approximate their fair
value.
Accounting policy: Trade and other
payables
These amounts represent
liabilities for goods and services provided to the Group prior to
the end of the financial year which are unpaid. The amounts are
unsecured and are usually paid within 30 days of recognition. Trade
and other payables are presented as current liabilities unless
payment is not due within twelve months after the reporting period.
They are recognised initially at their fair value and subsequently
measured at amortised cost using the effective interest
method.
2.14 Provisions
|
For the year ended
31
December 2023
US$'000
|
For the year ended
31
December 2022
US$'000
|
Current
|
|
|
Employee benefits (1)
|
1,054
|
2,276
|
Other current provisions
(2)
|
930
|
980
|
|
1,984
|
3,256
|
Non-current
|
|
|
Restoration and rehabilitation
(3)
|
40,039
|
37,396
|
Other non-current
provisions
|
−
|
29
|
|
40,039
|
37,425
|
Movement in restoration and
rehabilitation provision
|
|
|
Balance at beginning of the
year
|
37,396
|
42,647
|
Increase/(Decrease) in
provision
|
1,310
|
(5,839)
|
Interest expense - unwinding of
discount
|
1,333
|
588
|
Balance at end of the
year
|
40,039
|
37,396
|
(1) Employee benefits relate
to annual, sick, and long service leave entitlements and
bonuses.
(2) Provision for customs,
rebates and withholding taxes.
(3) The provision for
restoration and rehabilitation has been discounted by 4.01% (2022:
3.63%) using a US$ applicable rate and inflation applied at 2.40%
(2022: 2.37%). The annual review undertaken as at 31 December 2023
has resulted in a US$1.3 million increase in the provision (2022:
US$5.8 million decrease). The key assumptions used to determine the
provision are disclosed in note 1.2.4.
The Group recognises the Global
Industry Standard on Tailings Management (GISTM) and is committed
to full implementation of the GISTM at all its tailings storage
facilities (TSFs). The standard sets a high bar and contains 77
requirements integrating social, environmental, local economic and
technical considerations; with the aim to eliminate harm to people
and the environment.
The Group manages two TSFs at
Sukari, both of which are active. The TSFs are designed,
constructed and operated to a rigorous set of standards and are
carefully managed and monitored through a layered assurance system
by internal specialists and independent external third-party
reviews, with mechanisms in place for reporting risk and tracking
mitigation measures. The GISTM guides and supports the Group's
tailings management framework.
In 2023, the Group made
significant progress to align its tailings management framework to
the GISTM and is able to report its level of conformance against
each principle of the standard. This did not have a material impact
on the provision recognised during the year. Overall, the Group's
tailings management and governance system was assessed to be in
conformance with approximately 80 to 85% of the GISTM requirements.
The Group has put in place a clear action plan and roadmap to fully
conform with the GISTM by end-2025. We will monitor and report on
our progress towards full conformance.
The Group publishes an annual
disclosure report on its tailings facilities on its website. In
2024, the content of this disclosure will be updated to align with
Principle 15 of the GISTM.
ACCOUNTING POLICY: RESTORATION AND
REHABILITATION
A provision for restoration and
rehabilitation is recognised when there is a present legal or
constructive obligation as a result of exploration, development and
production activities undertaken, it is probable that an outflow of
economic benefits will be required to settle the obligation, and
the amount of the provision can be measured reliably. The estimated
future obligations include the costs of dismantling and removal of
facilities, restoration, and monitoring of the affected areas. The
provision for future restoration costs is the best estimate of the
present value of the expenditure required to settle the restoration
obligation at the reporting date in accordance with the
requirements of the Concession Agreement. Future restoration costs
are reviewed annually and any changes in the estimate are reflected
in the present value of the restoration provision at each reporting
date.
The provision for restoration and
rehabilitation represents the present value of the Directors' best
estimate of the future outflow of economic benefits that will be
required to decommission infrastructure, restore affected areas by
ripping and grading of compacted surfaces to blend with the
surroundings, closure of project components to ensure stability and
safety at the Group's sites at the end of the life of mine. This
restoration and rehabilitation estimate has been made based on
benchmark assessments of restoration works required following mine
closure and after considering the projected area disturbed to
date.
Discount rates to present value
the future obligations are determined by reference to risk free
rates for periods which approximate the period of the associated
obligation.
The initial estimate of the
restoration and rehabilitation provision relating to exploration,
development and mining production activities is capitalised into
the cost of the related asset and amortised on the same basis as
the related asset, unless the present obligation arises from the
production of the inventory in the period, in which case the amount
is included in the cost of production for the period. Changes in
the estimate of the provision of restoration and rehabilitation are
treated in the same manner, except that the unwinding of the effect
of discounting on the provision is recognised as a finance cost
within the income statement rather than capitalised to the related
asset.
2.15 Issued capital
|
31
December 2023
|
31
December 2022
|
|
Number
|
US$'000
|
Number
|
US$'000
|
Fully paid ordinary
shares
|
|
|
|
|
Balance at beginning of the
year
|
1,156,450,695
|
670,994
|
1,156,450,695
|
669,531
|
Own shares acquired during the
year (1)
|
−
|
(245)
|
−
|
−
|
Employee share option scheme -
newly issued shares
|
1,982,000
|
−
|
−
|
−
|
Transfer from share option
reserve
|
−
|
2,683
|
−
|
1,463
|
Balance at end of the
year
|
1,158,432,695
|
673,432
|
1,156,450,695
|
670,994
|
(1) The US$ 0.2 million (2022: US$
Nil ) represents the cost of shares in Centamin plc purchased on
the market and held by the Centamin plc Employee Benefit Trust to
satisfy share awards under the Group's share options
plans.
The authorised share capital is an
unlimited number of no-par value shares.
Pursuant to the plan rules, at 31
December 2023, the trustee of the deferred bonus share plan and
Centamin incentive plan held 656,764 ordinary shares (2022:
1,187,779 ordinary shares).
Fully paid ordinary shares carry
one vote per share and carry the right to dividends. See note 6.3
for more details of the share awards.
ACCOUNTING POLICY: ISSUED
CAPITAL
Ordinary shares are classified as
equity. Incremental costs directly attributable to the issue of new
shares or options are shown in equity as a deduction, net of tax,
from the proceeds.
Where the Company or other members
of the consolidated Group purchase the Company's equity share
capital, the consideration paid is deducted from the total
shareholders' equity of the Group and/or of the Company as treasury
shares until they are cancelled. Where such shares are subsequently
sold or reissued, any consideration received is included in
shareholders' equity of the Group and/or
the Company.
2.16 Share option
reserve
|
For the year ended
31
December 2023
US$'000
|
For the year ended
31
December 2022
US$'000
|
Share option reserve
|
|
|
Balance at beginning of the
year
|
6,082
|
4,975
|
Share-based payments
expense
|
6,725
|
2,570
|
Transfer to issued
capital
|
(2,683)
|
(1,463)
|
Balance at the end of the
year
|
10,124
|
6,082
|
The share option reserve arises on
the grant of share options to employees under the employee share
option plan. Amounts are transferred out of the reserve and into
issued capital when the options and warrants are exercised/vested.
Amounts are transferred out of the reserve into accumulated
profits when the options and warrants are forfeited.
2.17 Cash flow
information
(A) RECONCILIATION OF CASH AND
CASH EQUIVALENTS
For the purpose of the statement
of cash flows, cash and cash equivalents includes cash on hand and
at bank and deposits.
|
For the year ended
31
December 2023
US$'000
|
For the year ended
31
December 2022
US$'000
|
Cash and cash equivalents
|
93,322
|
102,373
|
Most funds have been invested in
international rolling short-term fixed interest money market
deposits.
The Company secured an RCF on 22
December 2022 and the facility is secured by certain financial
covenants on the Company (see note 2.7). The covenant specific to
the Company's cash assets states that:
• Liquidity
shall at all times exceed US$50 million and as 31 December 2023,
the Company was in compliance with this financial covenant
requirement.
The carrying amounts of financial
assets pledged as security for the facility, being the cash is
included in 2.17 above.
ACCOUNTING POLICY: CASH AND CASH
EQUIVALENTS
Cash comprises cash on hand and
demand deposits. Cash equivalents are short-term, highly liquid
investments that are readily convertible to known amounts of cash
and which are subject to an insignificant risk of changes in value.
Investments normally only qualify as cash equivalent if they have a
short maturity of three months or less from the date of
acquisition.
(B) RECONCILIATION OF PROFIT
BEFORE TAX FOR THE YEAR TO CASH FLOWS FROM OPERATING
ACTIVITIES
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022(1)
US$'000 (restated)
|
Profit for the year before
tax
|
195,140
|
171,001
|
Adjusted for:
|
|
|
Depreciation/amortisation of
property, plant, and equipment
|
198,127
|
146,769
|
Inventory written off
|
3,721
|
2
|
Inventory obsolescence
provision
|
(4,004)
|
579
|
Net fair value movements on
derivative financial instruments
|
5,509
|
-
|
Foreign exchange gains,
net
|
(5,682)
|
(6,559)
|
Share-based payments
expense
|
7,306
|
2,570#
|
Finance income
|
(4,127)
|
(1,214)
|
Finance costs
|
3,526
|
2,459
|
Loss on disposal of property,
plant, and equipment
|
9,415
|
899
|
Changes in working capital during
the year:
|
|
|
Increase in trade and other
receivables
|
(13,815)
|
(3,049)
|
Increase in inventories
|
(19,737)
|
(35,940)
|
Increase in prepayments
|
(3,181)
|
(7,172)
|
Purchase of derivative financial
instruments
|
(6,163)
|
-
|
(Decrease)/Increase in trade and
other payables
|
(9,901)
|
25,053
|
Increase/(decrease) in
provisions
|
61
|
(773)
|
Cash flows generated from
operating activities
|
356,195
|
294,625
|
(1) The
comparatives as at 31 December 2022 have been restated to reflect
finance costs of US$2.5m, now added back to cash flows from
operating activities.
(C) NON-CASH FINANCING AND
INVESTING ACTIVITIES
During the year there have been no
non-cash financing and investing activities other than in relation
to leases accounted for under IFRS 16 Leases.
3. Group financial risk and
capital management
3.1 Group financial risk
management
3.1.1 Financial
instruments
(a) Group risk
management
The Group manages its capital to
ensure that entities within the Group will be able to continue as a
going concern while maximising the return to stakeholders through
the optimisation of the cash and equity balances. The Group's
overall strategy remains unchanged from the previous financial
year.
The Group has no debt and thus is
not geared at the year end or in the prior year. However, on 22
December 2022, the Company entered into an agreement for a US$150
million revolving credit facility ("RCF") with four banks. The
facility will introduce debt and gearing to the Company when drawn
down. As at 31 December 2023, there were no draw downs on the
facility and there were also no drawdowns during the
year.
The capital structure currently
consists of cash and cash equivalents and equity attributable to
equity holders of the parent, comprising issued capital and
reserves as disclosed in notes 2.15 and 2.16. The Group operates in
Australia, Jersey, United Kingdom, Egypt and Côte d'Ivoire and is
currently winding down its project in Burkina Faso. None of the
Group's entities are subject to externally imposed capital
requirements.
The Group utilises inflows of
funds towards the ongoing exploration and development of SGM in
Egypt and the exploration projects in both Côte d'Ivoire and
Egypt.
Categories of financial assets and
liabilities
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Financial assets
|
|
|
Non-current
|
|
|
Other receivables -
deposits
|
1,014
|
1,372
|
Current
|
|
|
Cash and cash
equivalents
|
93,322
|
102,373
|
Trade and other receivables
(1)
|
45,214
|
33,848
|
Derivative financial
instruments
|
654
|
−
|
|
140,204
|
137,593
|
Financial liabilities
|
|
|
Non-current
|
|
|
Other payables
|
8,264
|
11,801
|
Current
|
|
|
Trade and other
payables
|
94,248
|
99,395
|
|
102,512
|
111,196
|
1. The prior
year amount for Trade and other receivables has been restated to
exclude an amount relating to taxes receivable.
(b) Financial risk management and
objectives
The Group's overall risk
management programme focuses on the unpredictability of financial
markets and seeks to minimise potential risk adverse effects and
ensure that net cash flows are sufficient to support the delivery
of the Group's financial targets whilst protecting future financial
security. The Group continually monitors and tests its forecast
financial position against these objectives.
The Group's activities expose it
to a variety of financial risks: market, commodity, credit,
liquidity, foreign exchange, and interest rate. These risks are
managed under Board approved directives through the Audit and Risk
Committee. The Group's principal financial instruments comprise
interest bearing cash and cash equivalents. Other financial
instruments include trade receivables and trade payables, which
arise directly from operations.
It is, and has been throughout the
period under review, Group policy that no speculative trading in
financial instruments be undertaken.
(c) Market risk
The Group operates internationally
and is exposed to foreign exchange risk arising from various
currency exposures, primarily with respect to the Australian
dollar, Great British pound, and Egyptian pound. Foreign exchange
risk arises from future commercial transactions and recognised
assets and liabilities that are denominated in a currency that is
not the entity's functional currency. The risk is
measured by regularly monitoring, forecasting and performing
sensitivity analyses on the Group's financial position.
Financial instruments denominated
in Great British pounds, Australian dollars and Egyptian pounds are
as follows:
|
Great British pound
|
Australian dollar
|
Egyptian pound
|
31 December 2023
US$'000
|
31 December 2022
US$'000
|
31 December 2023
US$'000
|
31 December 2022
US$'000
|
31 December 2023
US$'000
|
31 December 2022
US$'000
|
Financial assets
|
|
|
|
|
|
|
Cash and cash
equivalents
|
728
|
622
|
261
|
343
|
1,486
|
837
|
|
728
|
622
|
261
|
343
|
1,486
|
837
|
Financial liabilities
|
|
|
|
|
|
|
Trade and other
payables
|
3,464
|
2,084
|
13,139
|
11,751
|
15,383
|
37,218
|
|
3,464
|
2,084
|
13,139
|
11,751
|
15,383
|
37,218
|
Net exposure
|
(2,736)
|
(1,462)
|
(12,878)
|
(11,408)
|
(13,897)
|
(36,381)
|
The following table summarises the
sensitivity of financial instruments held at the reporting date to
movements in the exchange rate of the Great British pound, Egyptian
pound, and Australian dollar to the US dollar, with all other
variables held constant. The sensitivities are based on reasonably
possible changes over a financial year, using the observed range of
actual historical rates.
|
Impact on profit
|
Impact on equity
|
31 December 2023
US$'000
|
31 December 2022
US$'000
|
31 December 2023
US$'000
|
31 December 2022
US$'000
|
US$/GBP increase by 10%
|
389
|
482
|
−
|
−
|
US$/GBP decrease by 10%
|
(476)
|
(590)
|
−
|
−
|
US$/AUD increase by 10%
|
(342)
|
98
|
−
|
−
|
US$/AUD decrease by 10%
|
417
|
(119)
|
−
|
−
|
US$/EGP increase by 20%
(2022:10%)
|
833
|
(2,816)
|
−
|
−
|
US$/EGP decrease by 20%
(2022:10%)
|
(1,249)
|
3,443
|
−
|
−
|
The amounts shown above are the
main currencies to which the Group is exposed. The Group also has
small deposits in Euro US$443,522 (2022: US$335,586) and West
African Franc US$1,496,766 (2022: US$1,422,704), and net payables
in Euro US$4,285,177 (2022: US$5,277,783) and in West African
Franc US$3,024,139 (2022: US$3,064,019). A movement of
10% up or down in these currencies would have a negligible effect
on the assets/liabilities.
The Group has not entered into
forward foreign exchange contracts. Natural hedges are utilised
wherever possible to offset foreign currency liabilities. The
Company maintains a policy of not hedging its currency positions
and maintains currency holdings in line with underlying
requirements and commitments.
The 20% used for the EGP in the
current year is in line with the average devaluation of the EGP
against the USD during the year.
(d) Commodity price risk
The Group's future revenue
forecasts are exposed to commodity price fluctuations, in
particular gold that it produces and sells into the global market
and fuel prices. The market prices of gold is the key driver of the
Group's capacity to generate cash flow. The Group has not entered
into any forward gold or fuel hedging contracts, it has however,
entered into a series of gold put option contracts during the year,
refer to note 2.4 for further details.
Gold price
The table below summarises the
impact of increases/decreases of the average realised gold price on
the Group's profit after tax for the year. The analysis
assumes that the average realised gold price per ounce of
US$1,948/oz (2022: US$1,794/oz) had increased/decreased by 10% with
other variables held constant.
|
Impact on after tax profit
|
31
December 2023
US$'000
|
31
December 2022
US$'000
|
After tax profit
|
194,885
|
170,775
|
After tax profit with impact of
increase by 10% US$/oz
|
281,155
|
247,106
|
After tax profit with impact of
decrease by 10% US$/oz
|
108,615
|
94,444
|
The table above is considered
before factoring in the impact of the Group's gold price protection
programme. Should the gold price per ounce drop to below
US$1,900/oz, the gold put option contracts will pay out to the
Group the difference between the realised average price per ounce
and US$1,900/oz. Therefore, a 10% decrease on the average realised
gold price during the year would result in all the six contracts
for the 2023 financial year with a total of 120,000 ounces paying
out approximately US$18 million. Refer to note 2.4 for further
details on the gold price protection programme.
Fuel price
Any variation in the fuel price
has an impact on the mine production costs and the table below
summarises the impact of increases/decreases of the average fuel
price on the Group's mine production costs. The analysis assumes
that the average fuel price of US$ 0.80 per litre (2022: US$ 0.88
per litre) had increased/decreased by 10% per litre with all other
variables held constant.
|
Impact on mine production costs
|
31 December 2023
US$'000
|
31 December 2022
US$'000
|
Mine production costs
|
(412,827)
|
(408,543)
|
Mine production costs with impact
of increase by 10% US$/litre
|
14,910
|
16,943
|
Mine production costs with impact
of decrease by 10% US$/litre
|
(14,910)
|
(16,943)
|
(e) Interest rate risk and
liquidity risk
The Group's main interest rate
risk arises from cash and short-term deposits. Given the size of
these balances and that the Group does not have any debt
instruments, interest rate risk is not considered to be material.
Cash deposits are placed on a term period of no more than 30 days
at a time.
The financial instruments exposed
to interest rate risk and the Group's exposure to interest rate
risk as at the balance sheet date were as per the table below. The
table analyses the Group's financial liabilities into relevant
maturity groupings based on their expected settlement profiles for
all non-derivative financial liabilities. The amounts disclosed in
the table are the undiscounted expected cash flows. A separate line
for lease liabilities has been presented in the maturity analysis
of the Group's financial liabilities in the table below.
The Group's liquidity position is
managed to ensure that sufficient funds are available to meet its
financial commitments in a timely and cost-effective manner. The
RCF requires a minimum liquidity level at all times of US$50
million.
Ultimate responsibility for
liquidity risk management rests with the Board, which has
established an appropriate management framework for the management
of the Group's funding requirements. The Group manages liquidity
risk by maintaining adequate cash reserves and management monitors
rolling forecasts of the Group's liquidity based on expected cash
flows. The tables in section (a) to (c) of this note above reflect
a balanced view of cash inflows and outflows and show the implied
risk based on those values. Trade payables and other financial
liabilities originate from the financing of assets used in the
Group's ongoing operations. These assets are considered in the
Group's overall liquidity risk. Management continually reviews the
Group's liquidity position including cash flow forecasts to
determine the forecast liquidity position and maintain appropriate
liquidity levels.
|
Weighted average
effective interest rate %
|
Less than one month
US$'000
|
Between
1 and 12 months
US$'000
|
Between
1 and 2 years
US$'000
|
Between
2 and 5 years
US$'000
|
Over 5 years
US$'000
|
Total
US$'000
|
31 December 2023
|
|
|
|
|
|
|
|
Financial assets
|
|
|
|
|
|
|
|
Fixed interest rate
instruments
|
3.99%
|
31,868
|
33,775
|
−
|
−
|
−
|
65,643
|
Non-interest bearing
|
|
77,775
|
−
|
−
|
−
|
−
|
77,775
|
|
|
109,643
|
33,775
|
−
|
−
|
−
|
143,418
|
Financial liabilities
|
|
|
|
|
|
|
|
Non-interest bearing
|
0%
|
95,112
|
2,500
|
2,500
|
2,500
|
−
|
102,612
|
Lease liabilities
|
|
165
|
1,629
|
1,662
|
1,962
|
378
|
5,795
|
|
|
95,277
|
4,129
|
4,162
|
4,462
|
378
|
108,407
|
|
Weighted average
effective interest rate
%
|
Less than one month
US$'000
|
Between
1 and 12 months
US$'000
|
Between
1 and 2 years
US$'000
|
Between
2 and 5 years
US$'000
|
Over 5 years
US$'000
|
Total
US$'000
|
31 December 2022
|
|
|
|
|
|
|
|
Financial assets
|
|
|
|
|
|
|
|
Fixed interest rate
instruments
|
1.04%
|
21,394
|
54,998
|
−
|
−
|
−
|
76,392
|
Non-interest bearing
|
−
|
61,610
|
−
|
−
|
−
|
−
|
61,610
|
|
|
83,004
|
54,998
|
−
|
−
|
−
|
138,002
|
Financial liabilities
|
|
|
|
|
|
|
|
Non-interest bearing
|
0%
|
97,716
|
2,500
|
2,500
|
5,000
|
−
|
107,716
|
Lease liabilities
|
|
234
|
1,929
|
1,750
|
2,587
|
549
|
7,049
|
|
|
97,950
|
4,429
|
4,250
|
7,587
|
549
|
114,765
|
(f) Credit risk
Credit risk refers to the risk
that a counterparty will default on its contractual obligations
resulting in financial loss to the Group. The Group has
adopted a policy of only dealing with creditworthy counterparties
and obtaining sufficient collateral or other security where
appropriate, as a means of mitigating the risk of financial loss
from defaults. The Group measures credit risk on a fair value
basis. The Group's credit risk is concentrated in one entity, the
refiner Asahi Refining Canada Ltd, up to 30 June 2023 and
thereafter MKS PAMP SA, but the Group has good credit control on
its customer and none of the trade receivables from the customer
have been past due. Also, the cash balances held in all currencies
are held with financial institutions with a high credit
rating.
The gross carrying amount of
financial assets recorded in the financial statements represents
the Group's maximum exposure to credit risk without taking account
of the value of collateral or other security obtained.
(g) Fair value
The carrying amount of financial
assets and financial liabilities recorded in the financial
statements represents their respective fair values, other than in
relation to lease liabilities, principally as a consequence of the
short-term maturity thereof.
(h) Mineral reserve and resource
statement impact on ore reserves
The following disclosure provides
information to help users of the financial statements understand
the judgements made about the future and other sources of
estimation uncertainty. The key sources of estimation uncertainty
described in note 1.2.3 above and the range of possible outcomes
are described more fully below.
Depreciation of capitalised
underground mine development costs
Depreciation of capitalised
underground mine development costs at SGM is based on reserve
estimates. Management believe that these estimates are both
realistic and conservative, based on current information. The
sensitivity analysis assumes that the reserve estimate has
increased/decreased by 25% with all other variables held
constant.
|
Decrease by 25%
US$'000
|
31
December 2023
US$'000
|
Increase by 25%
US$'000
|
Amortisation of rehabilitation
asset (within mine development properties)
|
(3,452)
|
(2,589)
|
(1,942)
|
Amortisation of mine development
properties (remainder)
|
(111,537)
|
(83,653)
|
(62,740)
|
Mine development properties - net
book value
|
587,950
|
616,697
|
638,258
|
Property, plant, and equipment -
net book value*
|
1,055,272
|
1,084,019
|
1,105,580
|
* Reflects
the impact on the overall property, plant and equipment carrying
amount at the reporting date from the movements in mine development
amortisation above.
|
Decrease by 25%
US$'000
|
31
December 2022
US$'000
|
Increase by 25%
US$'000
|
Amortisation of rehabilitation
asset (within mine development properties)
|
(3,978)
|
(2,984)
|
(2,238)
|
Amortisation of mine development
properties (remainder)
|
(83,766)
|
(62,824)
|
(47,118)
|
Mine development properties - net
book value
|
549,761
|
571,697
|
588,149
|
Property, plant, and equipment -
net book value*
|
1,070,553
|
1,092,489
|
1,108,941
|
* Reflects
the impact on the overall property, plant and equipment carrying
amount at the reporting date from the movements in mine development
amortisation above.
The sensitivity analysis presented
above includes the impact on the amortisation amounts of the
capitalised deferred stripping asset. The deferred stripping asset
and the rehabilitation asset are included within the Mine
Development Properties category in the Group's property, plant and
equipment.
(i) Loan covenants
On 22 December 2022, the Company
entered into an agreement for a US$150 million RCF with four banks:
Bank of Montreal (London Branch), HSBC Bank plc, ING Bank N.V.
(Amsterdam Branch) and Nedbank Limited (London Branch) (see note
2.7).
The terms of the facility impose
certain financial covenants on the Company in respect of each
Relevant Period that has an outstanding borrowing, refer to note
2.7 for further information on the covenant requirements. As at 31
December 2023, the Company was in compliance with all the RCF's
financial covenants requirements however, there were no drawdowns
on the facility yet.
3.2 Capital management
3.2.1 RISK MANAGEMENT
The Group's objectives when
managing capital are to:
●
|
safeguard their ability to
continue as a going concern, so that they can continue to provide
returns for shareholders and benefits for other stakeholders;
and
|
●
|
maintain an optimal capital
structure to reduce the cost of capital.
|
To maintain or adjust the capital
structure, the Group may adjust the amount of dividends paid to
owners of the parent, return capital to owners of the parent
or issue new shares.
3.2.2
DIVIDENDS TO OWNERS OF THE PARENT
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Ordinary shares
|
|
|
Final dividend for the year ended
31 December 2022 of 2.5 US cents per share
|
29,100
|
57,740
|
(2022: Q1 Final dividend for the
year ended 31 December 2021 of 5.0 US cents per share)
|
|
|
Q2 Interim dividend for the year
ended 31 December 2023 of 2.0 US cents per share
|
23,065
|
28,464
|
(2022: Q2 Interim dividend for the
year ended 31 December 2022 of 2.5 US cents per share)
|
|
|
Total dividends provided for or
paid
|
52,166
|
86,204
|
Dividends to owners of the
parent:
|
|
|
Paid in cash
|
52,166
|
86,204
|
4. Group structure
4.1 Subsidiaries and controlled
entities
The parent entity of the Group is
Centamin plc, incorporated in Jersey, and details of its
subsidiaries and controlled entities are
as follows:
|
Nature
of
activity
|
Country
of incorporation
|
Ownership interest
|
31 December 2023
%
|
31 December 2022
%
|
Centamin Egypt Limited
|
Holding
company
|
Australia(1)
|
100
|
100
|
Pharaoh Gold Mines NL (holder of
an Egyptian branch)
|
Holding
company
|
Australia(1)
|
100
|
100
|
Sukari Gold Mining Company
(*)
|
Mining
company
|
Egypt(2)
|
50
|
50
|
Centamin Group Services UK
Limited
|
Services company
|
UK(3)
|
100
|
100
|
Centamin West Africa Holdings
Limited
|
Holding
company
|
UK(3)
|
100
|
100
|
Centamin Group Services
Limited
|
Services company
|
Jersey(4)
|
100
|
100
|
Centamin Holdings
Limited
|
Holding
company
|
Jersey(4)
|
100
|
100
|
MHA Limited
|
Holding
company
|
Jersey(4)
|
100
|
100
|
Ampella Mining Limited
(in
Liquidation)
|
Holding
company
|
Australia(1)
|
100
|
100
|
Ampella Mining Gold SARL
(in
Liquidation)
|
Exploration company
|
Burkina
Faso(5)
|
100
|
100
|
Ampella Mining SARL (in Liquidation)
|
Exploration company
|
Burkina
Faso(5)
|
100
|
100
|
Ampella Resources Burkina Faso
(in
Liquidation)
|
Exploration company
|
Burkina
Faso(5)
|
100
|
100
|
Konkera SA (in Liquidation)
|
Mining
company
|
Burkina
Faso(5)
|
100
|
100
|
Ampella Mining Côte
d'Ivoire
|
Exploration company
|
Côte
d'Ivoire(6)
|
100
|
100
|
Centamin Côte d'Ivoire
|
Exploration company
|
Côte
d'Ivoire(6)
|
100
|
100
|
Ampella Mining Exploration
CDI
|
Exploration company
|
Côte
d'Ivoire(6)
|
100
|
100
|
Centamin Exploration CI
|
Exploration company
|
Côte
d'Ivoire(6)
|
100
|
100
|
Centamin Egypt Investments 1 (UK)
Limited
|
Holding
company
|
UK(7)
|
100
|
100
|
Centamin Egypt Investments 2 (UK)
Limited
|
Holding
company
|
UK(7)
|
100
|
100
|
Centamin Egypt Investments 3 (UK)
Limited
|
Holding
company
|
UK(7)
|
100
|
100
|
Centamin Mining Services Egypt
LLC
|
Services company
|
Egypt(8)
|
100
|
100
|
Centamin Central Mining
SAE
|
Exploration
|
Egypt(8)
|
100
|
100
|
Centamin North Mining
SAE
|
Exploration
|
Egypt(8)
|
100
|
100
|
Centamin South Mining
SAE
|
Exploration
|
Egypt(8)
|
100
|
100
|
(*) Sukari Gold Mining
Company is fully consolidated within the Group under IFRS 10
Consolidated financial statements as if it
were a subsidiary due to it being a controlled entity, reflecting
the substance and economic reality of the Concession Agreement
("CA") (see note 1.2.1).
(1) Address of all
Australian entities: Suite 8, 7 The Esplanade, Mount Pleasant, WA
6153.
(2) Address of all
Egypt entities (except the new exploration entities in (11) and
(12): 361 El-Horreya Road, Sedi Gaber, Alexandria,
Egypt.
(3) Address of all UK
entities: Hill House, 1 Little New Street, London, EC4A
3TR.
(4) Address of all
Jersey entities: 2 Mulcaster Street, St Helier, Jersey, JE2
3NJ.
(5) Address of all
Burkina Faso entities: Ampella Resources Burkina Faso: 11 BP 1974
Ouaga 11. Ampella Mining SARL: 01 BP 1621 Ouaga 01.
Ampella Mining Gold SARL: 11 BP 1974 CMS 11 Ouaga 11.
Konkera SA: 11 BP 1974 Ouaga CM11.
(6) Address of all
Côte d'Ivoire entities: Cocody II Plateaux Les Vallons, En face de
la Résidence Bertille Lot 1557, Ilot 149
(7) Address of all the
UK holding companies of the new Egypt exploration companies; Hill
House, 1 Little New Street, London, EC4A 3TR.
(8) Address of the new
Egypt exploration companies: F-1-5 ,Agora Mall, EL Nasr St. , 5th
settlement, Cairo..
Through its wholly owned
subsidiary, PGM, the Company entered into the Concession Agreement
("CA") with EMRA and the ARE granting PGM and EMRA the right -
through SGM as Operating Company - to explore, develop, mine and
sell gold and associated minerals in specific concession areas
located in the Eastern Desert of Egypt. The CA came into effect
under Egyptian law on 13 June 1995.
In 2005 PGM, together with EMRA,
were granted an exploitation lease over 160 km2 surrounding the Sukari Gold Mine site.
The exploitation lease was signed by PGM, EMRA and the
Egyptian Minister of Petroleum and gives tenure for a period of
30 years, commencing 24 May 2005 and extendable by PGM for an
additional 30 years upon PGM providing reasonable commercial
justification.
In 2006 SGM was incorporated under
the laws of Egypt. SGM was formed to conduct exploration,
development, exploitation, and marketing operations in accordance
with the CA. Responsibility for the day-to-day management of the
project rests with the general manager, who is appointed by
PGM.
The fiscal terms of the CA require
that PGM solely funds SGM. PGM is however entitled to recover from
sales revenue recoverable costs, as defined in the CA. EMRA is
entitled to a share of SGM's net production surplus or profit share
(defined as revenue less payment of the fixed royalty to ARE and
recoverable costs). During 2016, payments to EMRA commenced as
advance profit share distributions. Any payment made to EMRA
pursuant to these provisions of the CA are recognised as dividend
paid to the non-controlling interest in SGM.
5. Unrecognised items
5.1 Contingent liabilities and
contingent assets
CONTINGENT LIABILITIES
Refer to note 2.13 for additional
information on the EMRA position with respect to
provisions.
Other than as highlighted above,
there were no contingent liabilities at year end.
Contingent assets
There were no contingent assets at
year-end, and none in 2022.
5.2 Dividends per share
The dividends paid in 2023 were
US$52 million and are reflected in the consolidated statement of
changes in equity for the year (2022: US$86 million).
A final dividend in respect of the
year ended 31 December 2023 of 2.0 US cents per share, totalling
approximately US$23 million has been proposed by the Board of
Directors and is subject to shareholder approval at the Annual
General Meeting on 21 May 2024. These financial statements do not
reflect the dividend payable.
As announced on 9 January 2017,
the update to the Company's dividend policy sets a minimum payout
level relative to cash flow while considering the financial
condition of, and outlook for, the Company. When determining the
amount to be paid, the Board will take into consideration the
underlying profitability of the Company and significant known or
expected funding commitments. Specifically, the Board will aim to
approve an annual dividend of at least 30% of the Company's net
cash flow after sustaining capital costs and following the payment
of profit share due to the government of Egypt.
5.3 Subsequent events
As referred to in note 5.2,
subsequent to the year end, the Board proposed a final dividend for
2023 of 2.0 US cents per share. Subject to shareholder approval at
the Annual General Meeting on 21 May 2024, the final dividend will
be paid on 19 June 2024 to shareholders on record date of 31 May
2024.
Other than as noted above, there
were no other significant events occurring after the reporting date
requiring disclosure in the financial statements.
6. Other information
6.1 Related party
transactions
(A) EQUITY INTERESTS IN RELATED
PARTIES
Equity interests in
subsidiaries
Details of the percentage of
ordinary shares held in subsidiaries are disclosed in note
4.1.
(B) KEY MANAGEMENT PERSONNEL AND
NON-EXECUTIVE DIRECTOR COMPENSATION
Key management personnel are
persons having authority and responsibility for planning,
directing, and controlling the activities of the Group, directly or
indirectly, including any Director (executive or otherwise) of the
Group.
The aggregate compensation made to
key management personnel of the consolidated entity is set out
below:
|
For the year ended
31 December 2023
US$
|
For the year ended
31 December 2022
US$
|
Short-term employee
benefits
|
9,212,369
|
10,261,960
|
Post-employment
benefits
|
−
|
1,320
|
Share-based payments
|
3,352,786
|
1,949,569
|
|
12,565,155
|
12,212,849
|
(C) KEY MANAGEMENT PERSONNEL AND
NON-EXECUTIVE DIRECTOR EQUITY HOLDINGS
The details of the movement in key
management personnel equity holdings of fully paid ordinary shares
in Centamin plc during the financial year ended 31 December 2023
are as follows:
For the year ended
31 December 2023
|
Balance at
1 January 2023
|
Granted as remuneration
("DBSP")
|
Granted as remuneration
("PSP")
|
Net other change - share plan
lapse(1)
|
Net other change(2)
|
Balance at
31 December 2023(3)
|
M Horgan
|
2,326,193
|
−
|
835,800
|
(217,710)
|
(76,013)
|
2,868,270
|
R Jerrard
|
2,348,000
|
−
|
667,300
|
(143,910)
|
53,000
|
2,924,390
|
J Rutherford
|
250,000
|
−
|
−
|
−
|
−
|
250,000
|
S Eyre
|
15,000
|
−
|
−
|
−
|
−
|
15,000
|
M Bankes
|
319,000
|
−
|
−
|
−
|
−
|
319,000
|
M Cloete
|
15,000
|
−
|
−
|
−
|
−
|
15,000
|
C Farrow
|
30,000
|
−
|
−
|
−
|
−
|
30,000
|
I Fawzy
|
140,000
|
−
|
−
|
−
|
−
|
140,000
|
H Faul
|
−
|
−
|
−
|
−
|
−
|
−
|
G Du Toit
|
1,442,000
|
−
|
400,000
|
−
|
−
|
1,842,000
|
A Hassouna
|
697,931
|
−
|
400,000
|
−
|
−
|
1,097,931
|
C Barker
|
771,000
|
−
|
375,000
|
−
|
−
|
1,146,000
|
M Stoner
|
314,000
|
−
|
295,000
|
−
|
−
|
609,000
|
H Bills
|
980,000
|
−
|
375,000
|
(73,800)
|
(59,433)
|
1,221,767
|
P Cannon
|
627,000
|
−
|
295,000
|
−
|
−
|
922,000
|
C Murray
|
911,000
|
−
|
295,000
|
(73,800)
|
−
|
1,132,200
|
A Carse
|
856,688
|
−
|
295,000
|
(29,520)
|
(36,332)
|
1,085,836
|
D Le Masurier
|
677,300
|
−
|
250,000
|
(24,908)
|
(42,593)
|
859,799
|
R Nel
|
607,306
|
−
|
295,000
|
(18,450)
|
(48,216)
|
835,640
|
(1) 'Net other change
- share plan lapse' relates to awards that have lapsed following
partial vesting of the 2020 grant.
(2) 'Net other change'
relates to the on-market acquisition or disposal of fully paid
ordinary shares.
(3) Balance includes
unvested grants under the Company's performance share
plan.
Since 31 December 2023 to the date
of this report there have been no transactions notified by the
Company in accordance with the requirements of Article 19 of the UK
Market Abuse Regulation (Regulation (EU) 596/2014.
The details of the movement in key
management personnel and non-executive director's equity holdings
of fully paid ordinary shares in Centamin plc during the financial
year ended 31 December 2022 are as follows:
For the year ended
31 December 2022
|
Balance at
1 January 2022
|
Granted as remuneration
("DBSP")
|
Granted as remuneration
("PSP")
|
Net other change - share plan
lapse(1)
|
Net other change(2)
|
Balance at
31 December 2022(3)
|
M Horgan
|
1,281,405
|
−
|
979,000
|
−
|
65,788
|
2,326,193
|
R Jerrard
|
2,077,000
|
−
|
821,000
|
(617,000)
|
67,000
|
2,348,000
|
J Rutherford
|
250,000
|
−
|
−
|
−
|
−
|
250,000
|
S Eyre
|
15,000
|
−
|
−
|
−
|
−
|
15,000
|
M Bankes
|
289,000
|
−
|
−
|
−
|
30,000
|
319,000
|
M Cloete
|
15,000
|
−
|
−
|
−
|
−
|
15,000
|
C Farrow
|
30,000
|
−
|
−
|
−
|
−
|
30,000
|
I Fawzy
|
140,000
|
−
|
−
|
−
|
−
|
140,000
|
H Faul
|
−
|
−
|
−
|
−
|
−
|
−
|
G Du Toit
|
950,000
|
−
|
492,000
|
−
|
−
|
1,442,000
|
A Hassouna
|
236,931
|
−
|
492,000
|
(31,000)
|
−
|
697,931
|
C Barker
|
300,000
|
−
|
471,000
|
−
|
−
|
771,000
|
M Stoner
|
−
|
−
|
314,000
|
−
|
−
|
314,000
|
H Bills
|
500,000
|
−
|
480,000
|
−
|
−
|
980,000
|
P Cannon
|
250,000
|
−
|
377,000
|
−
|
−
|
627,000
|
C Murray
|
474,000
|
−
|
461,000
|
−
|
(24,000)
|
911,000
|
A Carse
|
648,688
|
−
|
377,000
|
(169,000)
|
−
|
856,688
|
D Le Masurier
|
517,300
|
−
|
287,000
|
(127,000)
|
−
|
677,300
|
R Nel
|
401,973
|
−
|
332,000
|
(110,000)
|
(16,667)
|
607,306
|
(1) 'Net other change
- share plan lapse' relates to awards that have lapsed due to the
full performance conditions not being met on the 2019
grant.
(2) 'Net other change'
relates to the on-market acquisition or disposal of fully paid
ordinary shares.
(3) Balance includes
unvested grants under the Company's performance share
plan.
(D) KEY MANAGEMENT PERSONNEL AND
NON-EXECUTIVE DIRECTOR SHARE OPTION HOLDINGS
There were no options held,
granted, or exercised during the year by Directors or senior
management in respect of ordinary shares in Centamin
plc.
(E) OTHER TRANSACTIONS WITH KEY
MANAGEMENT PERSONNEL AND NON-EXECUTIVE DIRECTOR
The related party transactions for
the year ended 31 December 2023 are summarised below:
• salaries,
superannuation contributions, bonuses, LTIs, consulting and
Directors' fees paid to Directors during the year ended
31 December 2023 amounted to US$4,439,649 (31 December 2022:
US$3,918,404), with pension contributions amounting to US$51,753
(2022: US$16,670).
(F) TRANSACTIONS WITH THE
GOVERNMENT OF EGYPT
Royalty costs attributable to the
government of Egypt of US$26,681,717 (2022: US$23,842,287) were
incurred in 2023. Profit share to EMRA of US$112,000,000 (2022: US$
35,492,459) was incurred in 2023.
(G) TRANSACTIONS WITH OTHER
RELATED PARTIES
Other related parties include the
parent entity, subsidiaries, and other related parties as disclosed
in 4.1 above.
All amounts advanced to related
parties are unsecured. No expense has been recognised in the year
for bad or doubtful debts in respect of amounts owed by related
parties.
Transactions and balances between
the Company and its subsidiaries were eliminated in the preparation
of the consolidated financial statements of the Group.
6.2 Contributions to
Egypt
(a) Gold sales
agreement
On 27 March 2023, SGM and the
Central Bank of Egypt ("CBE") amended their 20 December 2016
agreement with respect to SGM's facilitation of the purchase of
refined gold bullion for the CBE from its refiner. The amended
agreement provides that the parties may elect, on a monthly basis,
for the CBE to supply SGM with its local Egyptian currency
requirements for that month to a maximum value of EGP130 million
(2022: EGP80 million). In return, SGM facilitates the purchase of
refined gold bullion for the CBE from SGM's refiner, Asahi Refining
Canada Ltd up to 30 June 2023 and thereafter, MKS PAMP SA. This
transaction has been entered into as SGM requires local currency
for its operations in Egypt (it receives its revenue for gold sales
in US dollars). The values related to these transactions are as
follows:
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Gold purchased
|
34,124
|
50,497
|
Refining costs
|
17
|
28
|
Freight costs
|
43
|
56
|
|
34,184
|
50,581
|
|
|
|
|
For the year ended
31 December 2023
Oz
|
For the year ended
31 December 2022
Oz
|
Gold purchased
|
17,520
|
27,907
|
At 31 December 2023 the amount
receivable from CBE is approximately US$25,045 (2022:
US$23,681 net receivable).
(B) UNIVERSITY GRANT
During 2018, the Group together
with Sami El-Raghy and the University of Alexandria Faculty of
Science initiated a sponsored scholarship agreement, the Michael
Kriewaldt Scholarships, to outstanding geology major students to
enrol at the postgraduate research programme of the geology
department of the University for their MSc and/or PhD in mining and
mineral resources. An amount of EGP10,000,000 was deposited with an
Egyptian bank as a nucleus of the scholarship fund in a fixed
deposit account, with contributions of EGP7,330,000 from PGM and
EGP2,670,000 from Sami El-Raghy. The interest earned on the account
will be put towards the cost of the scholarships and will be
administered by the University on the conditions set out in the
agreement. This amount was accounted for under donations expense in
profit and loss and any interest earned on the deposit is also
accounted for under donations expense.
6.3 SHARE-BASED
PAYMENTS
PERFORMANCE SHARE PLAN
The Company's shareholder approved
Performance Share Plan ("PSP") allows the Company the right to
grant awards (as defined below) to employees of the Group. Awards
may take the form of either conditional share awards, where shares
are transferred conditionally upon the satisfaction of performance
conditions; or share options, which may take the form of nil cost
options or have a nominal exercise price, the exercise of which is
again subject to satisfaction of applicable performance
conditions.
The awards granted in April 2023
will vest following the passing of three years. Vesting will be
subject to the satisfaction of the performance conditions (and for
Executive Directors a full two-year post-vesting holding period).
Awards will vest based upon a blend of three-year relative TSR,
cash flow and production targets, full details of which are set out
in the Directors' Remuneration Report. These measures are assessed
by reference to current market practice and the Remuneration
Committee will have regard to current market practice when
establishing the precise performance conditions for
awards.
To date, the Company has granted
the following conditional awards to employees of the
Group:
June 2020 awards
Of the 2,582,500 awards granted on
5 June 2020 under the PSP, 1,153,153 vested to eligible
participants (nine in total)
April 2021 awards
Of the 5,945,000 awards granted on
30 April 2021 under the PSP, 5,330,000 awards remain granted to
eligible participants (28 in total) applying the
following performance criteria:
●
|
50% of the award shall be assessed
by reference to a target total shareholder return;
|
●
|
25% of the award shall be assessed
by reference to compound growth in adjusted free cash flow;
and
|
●
|
25% of the award shall be assessed
by reference to compound growth in gold production.
|
May 2022 awards
Of the 9,042,000 contingent share
awards granted on 20 May 2022 under the Incentive Share Plan
("ISP"), 8,982,000 awards remain granted to eligible participants
(33 in total) applying the following performance
criteria:
●
|
50% of the award shall be assessed
by reference to a target total shareholder return;
|
●
|
25% of the award shall be assessed
by reference to compound growth in adjusted free cash flow;
and
|
●
|
25% of the award shall be assessed
by reference to compound growth in gold production.
|
Conditional share awards and
options together constitute 'awards' under the plan and those in
receipt of awards are 'award holders'.
A detailed summary of the scheme
rules is set out in the 2022 AGM Notice which are available at
www.centamin.com. In brief, awards will vest following the passing
of three years from the date of the award and vesting will be
subject to satisfaction of performance conditions. The above
measures are assessed by reference to current market practice and
the Remuneration Committee will have regard to market practice when
establishing the precise performance conditions for future
awards.
Where the performance conditions
have been met, in the case of conditional awards awarded to certain
participants, 50% of the total shares under the award will be
issued or transferred to the award holders on or as soon as
possible following the specified vesting date, with the remaining
50% being issued with a two year restriction on trading.
April 2023 awards
Performance share plan awards
granted during the year:
Grant date
|
ISP 2023
25
April 2023
|
Number of instruments
|
1,903,100
|
TSR: fair value at grant date
GBP(1)
|
0.59
|
TSR: fair value at grant date
US$(1)
|
0.74
|
Adjusted free cash flow, gold
production and decarbonisation targets: fair value at grant date
GBP(1)
|
1.04
|
Adjusted free cash flow, gold
production and decarbonisation targets: fair value at grant date
US$(1)
|
1.29
|
Vesting period (years)
|
3
|
Holding period applicable to the
award (years)
|
2
|
Expected volatility (%)
|
41.52%
|
Expected dividend yield
(%)
|
4.89%
|
Number of instruments
|
4,537,500
|
TSR: fair value at grant date
GBP(1)
|
0.59
|
TSR: fair value at grant date
US$(1)
|
0.74
|
Adjusted free cash flow, gold
production and decarbonisation targets: fair value at grant date
GBP(1)
|
1.04
|
Adjusted free cash flow, gold
production and decarbonisation targets: fair value at grant date
US$(1)
|
1.29
|
Vesting period (years)
|
3
|
Holding period applicable to the
award (years)
|
0
|
Expected volatility (%)
|
41.52%
|
Expected dividend yield
(%)
|
4.89%
|
(1) The vesting of 50% of
the awards granted under this plan are dependent on a TSR
performance condition. As relative TSR is defined as a market
condition under IFRS 2 Share-based
payments, this requires that the valuation model used
considers the anticipated performance outcome. We have therefore
applied a Monte-Carlo simulation model. The simulation model
considers the probability of performance based on the expected
volatility of Centamin and the peer group companies and the
expected correlation of returns between the companies in the
comparator group. The remaining 50% of the awards are subject to
adjusted free cash flow , decarbonisation targets and gold
production performance conditions. As these are classified as
non-market conditions under IFRS 2 they do not need to be
considered when determining the fair value. The fair value
calculated was then converted at the closing GBP:US$ foreign
exchange rate on grant date.
RESTRICTED SHARE AWARDS
("RSA")
Under the Company's Incentive
Share Plan ("ISP"), the Company has restricted share awards, which
are a long-term share incentive arrangement for senior management
(but not Executive Directors) and other employees
(participants).
The RSA awards shall be subject to
the terms and conditions of the ISP and shall ordinarily vest in
three equal tranches on the anniversary of the grant date,
conditional upon the continued employment with the
Group.
RSA awards granted during the
year:
Grant date
|
RSA 2023
25
April 2023
|
Number of instruments
|
3,069,000
|
Fair value at grant date -
tranches 1 to 3 £(1)
|
1.04
|
Fair value at grant date -
tranches 1 to 3 US$(1)
|
1.29
|
Vesting period Tranche 1
(years)(2)
|
1
|
Vesting period Tranche 2
(years)(2)
|
2
|
Vesting period Tranche 3
(years)(2)
|
3
|
Expected dividend yield Tranche 1
(%)
|
4.87%
|
Expected dividend yield Tranche 2
(%)
|
4.88%
|
Expected dividend yield Tranche 3
(%)
|
4.89%
|
(1) The fair value of
the shares awarded under the RSA were calculated by using the
closing share price on grant date, converted at the closing GBP:US$
foreign exchange rate on that day. No other factors were considered
in determining the fair value of the shares awarded under the
RSA.
(2) Variable vesting
dependent on one to three years of continuous
employment.
ACCOUNTING POLICY: SHARE-BASED
PAYMENTS
Equity settled share-based
payments with employees and others providing similar services are
measured at the fair value of the equity instrument at grant date.
Fair value is measured using the Black-Scholes model. Where
share-based payments are subject to market conditions, fair value
is measured using a Monte-Carlo simulation. The fair value
determined at the grant date of the equity settled share-based
payments is expensed over the vesting period, based on the
consolidated entity's estimate of shares that will eventually
vest.
SHARE-BASED PAYMENTS
Equity settled share-based
transactions with other parties are measured at the fair value of
the goods or services received, except where the fair value cannot
be estimated reliably, in which case they are measured at the fair
value of the equity instruments granted, measured at the date the
entity obtains the goods or the counterparty renders the service.
The fair value of the employee services received in exchange for
the grant of the options is recognised as an expense. The total
amount to be expensed is determined by reference to the fair value
of the options granted:
●
|
including any market performance
conditions (for example, an entity's share price);
|
●
|
excluding the impact of any
service and non-market performance vesting conditions (for example,
profitability and remaining an employee of the entity over a
specified period); and
|
●
|
including the impact of any
non-vesting conditions (for example, the requirement for employees
to save or holding shares for a specific period).
|
When the options are exercised,
the Company issues new shares. The proceeds received net of any
directly attributable transaction costs are credited to share
capital (nominal value) and share premium. The expected life used
in the model has been adjusted, based on management's best
estimate, for the effects of non-transferability, exercise
restrictions, and behavioural considerations. Further details on
how the fair value of equity settled share-based transactions has
been determined can be found above. At each reporting date, the
Group revises its estimate of the number of equity instruments
expected to vest. The impact of the revision of the original
estimates, if any, is recognised in profit or loss over the
remaining vesting period, with corresponding adjustment to the
equity settled employee benefits reserve.
6.4 EARNINGS PER SHARE ("EPS") ATTRIBUTABLE TO OWNERS OF THE
PARENT
|
For the year ended
31 December 2023
US cents per share
|
For the year ended
31 December 2022
US cents per share
|
Basic earnings per
share
|
7.970
|
6.287
|
Diluted earnings per
share
|
7.817
|
6.203
|
BASIC EARNINGS PER SHARE
ATTRIBUTABLE TO OWNERS OF THE PARENT
The earnings and weighted average
number of ordinary shares used in the calculation of basic earnings
per share are as follows:
|
For the year ended
31
December 2023
US$'000
|
For the year ended
31
December 2022
US$'000
|
Earnings used in the calculation
of basic EPS
|
92,284
|
72,490
|
|
|
|
|
For the year ended
31 December 2023
Number of shares
|
For the year ended
31 December 2022
Number of Shares
|
Weighted average number of
ordinary shares for the purpose of basic EPS
|
1,157,933,122
|
1,152,960,534
|
DILUTED EARNINGS PER SHARE
ATTRIBUTED TO OWNERS OF THE PARENT
The earnings and weighted average
number of ordinary shares used in the calculation of diluted
earnings per share are as follows:
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Earnings used in the calculation
of diluted EPS
|
92,284
|
72,490
|
|
For the year ended
31 December 2023
Number of shares
|
For the year ended
31 December 2022
Number of shares
|
Weighted average number of
ordinary shares for the purpose of basic EPS
|
1,157,933,122
|
1,152,960,534
|
Shares deemed to be issued for no
consideration in respect of employee options
|
22,654,848
|
15,597,563
|
Weighted average number of
ordinary shares used in the calculation of diluted EPS
|
1,180,587,971
|
1,168,558,097
|
No potential ordinary shares were
excluded from the calculation of weighted average number of
ordinary shares for the purpose of diluted earnings per
share.
6.5 AUDITORS'
REMUNERATION
The analysis of the auditors'
remuneration is as follows:
|
For the year ended
31 December 2023
US$'000
|
For the year ended
31 December 2022
US$'000
|
Fees payable to the Company's
auditors and their associates for the audit of the Company's annual
financial statements
|
|
|
Audit fee for the current year
audit(1)
|
790
|
630
|
Fees payable to the Company's
auditors and their associates for other services to the
Group
|
|
|
Audit fee of the Company's
subsidiaries
|
225
|
126
|
Total audit fees
|
1,015
|
756
|
Non-audit fees:
|
|
|
Audit related assurance services -
interim review
|
151
|
139
|
Total non-audit fees
|
151
|
139
|
(1) The audit fee amount
disclosed in note 2.3 is for the Jersey, UK and Australian
companies only, the note above is for all the Group
entities.
The audit fees for the corporate
entities are billed in GBP and were translated at an average
foreign exchange rate for the year ended 31 December 2023 of
US$1.25:GB£1 (rate on 31 December 2022: US$1.23:GB£1). Not
included within the above amounts are auditors' expenses (recharged
to the Company) of US$31k (2022: US$19k).
6.6 General information
Centamin plc (the "Company") is a
listed public company, incorporated and domiciled in Jersey and
operating through subsidiaries and jointly controlled entities
operating in Egypt, Burkina Faso, Côte d'Ivoire, United Kingdom,
Jersey and Australia. It is the Parent Company of the Group,
comprising the Company and its subsidiaries and joint
arrangements.
Registered office and principal
place of business:
Centamin plc
2 Mulcaster Street
St Helier
Jersey
JE2 3NJ
The nature of the Group's
operations and its principal activities are set out in the
Governance Report and the Strategic Report of the 2023 Annual
Report.