RNS Number : 3369H
  China Goldmines PLC
  04 November 2008
   

    China Goldmines plc
    ("China Goldmines" (CGM) or the "Company")
    (AIM:CGM)

    CHINA GOLDMINES GUANZHUANG GOLD PROJECT QUARTERLY UPDATE
    SEPTEMBER 2008 (3Q08)
    Highlights 

 1  Three processing plants are now in operation. They have a total capacity
    of 350 tonnes per day (tpd). By March 2009, the three plants will be
    upgraded to 570 tpd.

 2  Production for the 3Q08 was 7,552 tonnes at 4 g/t (average). CGM is
    estimated to produce a total of 5,000 - 6,000 ounces of gold by 31
    December 2008. Although average grades for the quarter have been running
    below budget, we are continuing to observe evidence of high grades from
    drilling and underground sampling results (up to 91 grams Au per tonne).

 3  Drilling during the 3Q08 was on target with 5,000 metres.

 4  CGM's production target has been set at 20,000 - 25,000 oz of gold to be
    produced during the year ending 31 December 2009.  

 5  A consolidated mining licence (incorporating all eight mining licences)
    has been issued to our Chinese JV Company Hunan Westralian Mining Co. Ltd.

 6  Our cash position remains strong with USD 17.3m in the bank as of 30
    September 2008. The Board will review all capital and operating costs in
    light of the current economic and currency climate in order to monitor and
    maintain our strong cash position.

 7  The Board has decided not to bring forward and fast track the "Central
    Decline Project", but rather to remain on course with the original
    development plan scheduled to start in mid-2009.

 8  Our emphasis on safety has resulted in an excellent safety record for the
    3Q08.

    COMMENTARY


    1. Processing Plants

    CGM has successfully commissioned three gold processing plants:-

 1.1  The Bao Mu Yuan (BMY) Processing Plant was upgraded during 3Q08 from 50
      tpd to 200 tpd. It was commissioned on the 4th August 2008, meeting our
      objective stated in the 2Q08 project update.

      Designs for the new Bao Mu Yuan tailing dam have been approved by the
      Chinese authorities and construction will start in 4Q08.

 1.2  The De Sheng Processing Plant (DS) was refurbished to 50 tpd and is now
      in operation following the commissioning of the 2.5 km tailings line to
      the Bao Mu Yuan tailing dam.

      CGM has begun upgrading the processing plant to increase from 50 tpd to
      100 tpd and it is expected to be in full operation by 31 December 2008.

 1.3  The Xiao Chong Zi (XCZ) Processing Plant.  CGM has installed a 100 tpd
      mill, which will be upgraded to 350 tpd by the end of 1Q09.

      Summary of Processing Plants: "Maximum Operating Capacity"

 Mine  T/day   Key Date
 BMY    180   Operational
 DS     80       4Q08
 XCZ    310      1Q09
        570


  
    The three processing plants have a total 650 tpd mill capability; they have all been scheduled to run continuously using three shifts
per day to provide a maximum 570 tpd operating capacity.



    2. Production and Drilling Results

    Summary of production to date:-

                                     CONCENTRATE
                HEAD   CONCENTRATE      GRADE      GRAVITY  TAILS  Recovery
        TONNES  GRADE    TONNES     (grams/tonne)  GOLD(g)   g/t      %
 2Q 08  5,172   2.82       110           100        2,216   0.27     90%
 3Q 08  7,552     4        290           85         3,715   0.27     93%
 Total  12,724   3.5       400           90         5,841   0.27     92%
    Based on production results to date for the three quarters ending September 2008, CGM will produce 5,000 to 6,000 ounces for the year
ending 31 December 2008.  
    We revised our 2008 gold production figures for a number of reasons, including: 
 *  a Board decision to add stringent underground mining safety procedures;
 *  the slower-than-expected ramp-up due to delays in underground mine
    refurbishment;
 *  the lower than expected grades in the upper remnant zones;
 *  the harshest winter in living memory;
 *  frequent power cut-offs and outages; and
 *  the suspension of visas and explosives during the Olympics.
    As a result, we will produce 5,000 to 6,000 ounces of gold for the year ending 31 December 2008. CGM expect that once refurbishment is
completed and the plants have been upgraded to 570 tpd (with higher grades indicated in deeper zones of mines), there will be a higher
output of 20,000 to 25,000 ounces for the year ending 31 December 2009.  

    The Company remains confident that productivity levels will increase in the coming quarters and the set target levels will be achieved.
    During the year, the Company's health and safety policy was a major priority, both in implementing Western procedures and in the ongoing
audit and training. This has resulted in an excellent health and safety record to date.

    Drilling Results

    The company drilled 5,000m in the 3Q08, using six surface diamond-drill rigs.

    Our subcontractor, Ausino Drilling Services, commenced a 9,000m underground drilling programme in September for grade control and we
gained further confidence in our gold resources.

    Drilling and underground sampling results:

    Sampling results > 6 g/t
 Sample-ID  App. Length   True Length   Au Grade   Mine
                (M)           (M)         (g/t)


 1750  Rock-chip Sampling  24.44  BMY
 1734     1         1      19.02  BMY
 1736    0.7       0.7     18.48  BMY
 1721  Rock-chip Sampling  15.59  BMY
 1395  Rock-chip Sampling  12.77  BMY
 2958    1.2       0.9     12.47  BMY
 1895    1.7       1.3     11.51  BMY
 3116  Rock-chip Sampling  9.85   BMY
 1397  Rock-chip Sampling  9.41   BMY
 1798    1.2       0.9     9.33   BMY
 1374     1        0.4     7.49   BMY
 1729     1         1      7.07   BMY
 1816    1.5       0.6     6.85   BMY
 1335     1        0.83    6.72   BMY
 3071    1.3       1.15    6.35   BMY
 3116     1        0.9     9.85   BMY
 3091    0.5       0.4     91.05  BMY
 3154     1         1      10.7   BMY
 3202     1         1      30.76  BMY
 3200    1.2       1.14     6.8   BMY
 3208    1.1       0.9      8.7   BMY
 3213    0.9       0.7     10.2   BMY
 3215    1.6       1.4     6.98   BMY
 3232     1        0.93    7.55   BMY
 3236     1        0.9     8.92   BMY
 3237    1.6       0.7      8.1   BMY
 3295    0.8       0.8      18    BMY
 3296    1.15      1.15    41.48  BMY
 5020    0.8       0.8     19.01  BMY
 5025    0.6       0.6     13.06  BMY
 5267    0.8       0.8     25.35  BMY
 5400    0.6       0.4     21.5   BMY
 5446     1        0.55    7.03   BMY
 5449    0.85      0.85    14.51  BMY
 5453    0.25      0.25    6.59   BMY
 5455     1        0.95    14.38  BMY
 5458    1.1        1      9.82   BMY
 5462  Rock-chip Sampling  8.47   BMY
 1863     1         1       8.3   XCZ
 1840  Rock-chip Sampling   7.9   XCZ
 1853              0.8     7.56   XCZ
 1862     1         1      6.28   XCZ
 1857     1         1      6.02   XCZ
 3163    1.5       1.5     6.23   XCZ
 3335    0.2       0.2     37.35  XCZ
 3415     1        0.9     31.12  XCZ
 3424    0.8       0.75    7.81   XCZ
 3425    0.9       0.85    7.88   XCZ
 3434    0.4       0.4     8.41   XCZ
 5469  Rock-chip Sampling  13.29  XCZ
 5005  Rock-chip Sampling  8.02   SJY
 5014    0.75      0.7     12.21  SJY
 5015    1.8       1.8     11.62  SJY
 5282                      7.68   SJY
 5297     1        0.85     8.6   SJY
 5079    1.4       1.3     6.35   SJY
 5304    1.35      1.3     10.78  SJY
 5305  Rock-chip Sampling  11.97  SJY
 5327    1.8       1.7     11.18  SJY
 5328    1.7       1.45    17.94  SJY
 5350    0.7       0.6     26.26  SJY
 5357    0.5       0.5     6.85   SJY
 5361    0.47      0.47    17.49  SJY
 5366    0.5       0.5     6.88   SJY
 5367     1         1      7.12   SJY
 5468    0.4       0.4     71.63  SJY
 5471    0.5       0.4     16.23  SJY
 5476    0.48      0.41    23.17  SJY
 1802    1015      1.02    24.09  DS
 3072    0.9       0.9     12.5   DS
 3080    1.1       0.9     12.1   DS
 1803    0.8       0.58    9.02   DS
 3082     1        0.85    5.62   DS
 3072    0.9       0.9     12.5   DS
 3080    1.1       0.9     12.1   DS
 5037  Rock-chip Sampling  6.95   DS
 5048    1.2       1.1     6.37   DS
 5049    0.95      0.95    6.98   DS
 5318    1.2       1.1     22.57  DS
 5378    1.5       1.5     6.55   DS
 5380    0.8       0.8     7.66   DS
 5381    0.5       0.5     11.66  DS
 U005    1.5       1.5      7.7   DS
 U013    0.8       0.8     8.22   DS
 3210  Rock-chip Sampling  12.43  ZJS
 3282    0.35      0.35    13.73  ZJS
 3284  Rock-chip Sampling  7.22   ZJS
 3336  Rock-chip Sampling  30.06  ZJS
 3338  Rock-chip Sampling  18.38  ZJS
 3344     1         1      6.21   ZJS
 3397    0.85      0.8     6.94   ZJS
 5201    0.8       0.75    11.43  ZJS
 5204    0.8       0.7     10.85  ZJS
 5207    0.9       0.9     13.5   ZJS
 5228     1         1      7.01   ZJS
 5031  Rock-chip Sampling  32.99  ZJS
 5040     1        0.8     7.09   ZJS
 3488    0.7       0.7     8.18   ZJS
 3490    1.3       1.3     36.22  ZJS
 3491     1         1      7.58   ZJS
 5419    0.7       0.7     6.31   ZJS
 5432    1.1       1.1     6.12   ZJS
 3150     1        0.7     9.01   XL

    Drill Results

 Drill hole   Beijing Grid East     Beijing Grid North   Beijing Grid RL (m)  From (m)  To (m)  Grade (g/t)
                     (m)                   (m)

  SJDD0002       37501333.21           3160298.113             224.01          149.65   151.62     2.48
  SJDD0002       37501333.21           3160298.113             224.01          182.59   183.09     19.5
  SJDD0002       37501333.21           3160298.113             224.01          196.99   197.69     2.93
  SJDD0003       37501333.21           3160298.113             224.01          210.75   211.58     10.5
  SJDD0004       37501333.21           3160298.113             224.01           250      251       3.86
  SJDD0004       37501333.21           3160298.113             224.01          293.6     295       3.09
  SJDD0004       37501333.21           3160298.113             224.01          298.35    299        2.9
  SJDD0004       37501333.21           3160298.113             224.01          306.75   307.15     7.97
  SJDD0004       37501333.21           3160298.113             224.01          309.5     310       2.42
  SJDD0004       37501333.21           3160298.113             224.01           310      311       2.95
  SJDD0004       37501333.21           3160298.113             224.01          324.8     326       11.4
  SJDD0012       37501554.91           3160289.262             357.881          115      116       7.33
  SJDD0015       37500722.12           3160042.842             222.463          290     291.1      1.73
  SJDD0016       37500816.04           3160127.248             226.927         227.6    228.3      7.57
  SJDD0022       37501519.38            3160340.12             353.581         267.46   268.16     2.83
  SJDD0022       37501519.38            3160340.12             353.581          492      493       2.95
  SJDD0022       37501519.38            3160340.12             353.581          493      494       2.59
  SJDD0026       37498084.88           3159178.284             257.42           290     291.1      1.73
  SJDD0037       37501178.96           3160304.125             265.745         430.05    431       7.11
  SJDD0037       37501178.96           3160304.125             265.745          431      432       5.75
  SJDD0037       37501178.96           3160304.125             265.745          432      433       5.64
 SJUG00001         37497853              3159018              -110.744          71.5     72.3      2.88
 SJUG00001         37497853              3159018              -110.744          72.3     73.5      2.88
    3. Mine Updates
    The Company is confident of reaching the target set of 20,000 to 25,000 ounces for the year ending 31 December 2009 year.

    A summary of the progress 3Q08 of all mines is as follows:-

 *  Shen Jia Ya Mine (SJY)

    The connection with Bao Mu Yuan (BMY) mine was achieved in 3Q08. This will
    enable the haulage of gold ore and waste between the two mines and the
    establishment of a ventilation circuit.

    Active stopes:    No. 070 (500t @ 6 g/t) 
       No. 050 (2,000t @ 4 g/t). 

    Indentified stopes for development total 19,000t @ 4.5 g/t.

 *  Bao Mu Yuan Mine (BMY)

    The connection with Shen Jia Ya (SJY) mine was achieved in 3Q08.

    Active stopes:    No. 100 (2,200t @ 3 g/t) 
       No. 075 (1,500t @ 4.5 g/t)
       No. 905 (1,000t @ 3.5 g/t)
       No. 850 (5,000t @ 4.5 g/t)

    Identified stopes for development total 5,000t @ 4.5 g/t

 *  De Sheng Mine (DS)

    CGM finished a new 150m decline from the surface winch at the processing
    plant to level 1 of the De Sheng Mine.

    Active stopes :    No. 600 (800t @ 3.5 g/t)
       No. 700 (800t @ 7.9 g/t)
       No. 605 (1,000t @ 4 g/t)
       No. 650 (2,000t @ 6 g/t)
       No. 660 (5,800t @ 3 g/t)

    Identified stopes for development total 13,000t @ 7 g/t and 52,000t @ 4.5
    g/t.

 *  Zheng Jia Shan Mine (ZJS)

    Connection with Jiu Fa mine was achieved in 3Q08. Refurbishment of the
    ventilation and communication systems is in progress.

    Active stopes:    No. 925 (500t @ 5 g/t)
       No. 950 (500t @ 5 g/t)

    Identified stopes for development total 29,000t @ 4 g/t.

 *  Jiu Fa Mine (JF)

    Connection to Zheng Jia Shan mine was achieved. Refurbishment is ongoing
    with the replacement of several winches to increase haulage capacity and
    to establish ventilation to the lower portion of the mine.

    During 3Q08, no active or identified stopes.

 *  Jin Zhu Wan Mine (JZW)

    Work continues to connect Jiu Fa (JF) mine. We estimate that the task will
    be completed by the end of August 2009, including the refurbishment
    associated with haulage, ventilation and ground services.  

    Identified stopes 40,000t @ 4 g/t and 45,000t @ 5 g/t.

 *  Xiang Lu Mine (XL)

    The Company finished the haulage tunnel from XL through an adjacent hill
    to a road with more favourable access for large road trucks. This will
    facilitate the transport of ore to our processing plants.

    Refurbishment XL is ongoing and ore mining is anticipated in 4Q08.

    Identified stopes for development are estimated at a total of 25,000t @ 3
    g/t and 40,000t @ 6 g/t. 

 *  Xiao Chong Zi (XCZ)

    Refurbishment was completed at the end of 3Q08 when the Company achieved
    the breakthrough to Shen Jia Ya mine (SJY). This will improve haulage
    productivity in the coming quarter.

    Note: Identified stopes are based on geological interpretation from underground sampling and drilling and are classified as inferred
resources.
    4. Single Consolidated Mining Licence in CGM's Name 
    On 18 August 2008, CGM received Mining Licence No. 4300000820405. The licence incorporates all eight operating gold mines into one
licence that is now registered in the name of our China JV Company "Hunan Westralian Mining Co. Ltd". This mining licence covers one
registered mining area of 6.24 km2 with a depth of -230 metres (approximately 550m vertical depth from surface). In November 2007, the
purchase of the mining licence was concluded and CGM now has 100% control of all eight individual producing gold mines in the Shen Jia Ya
Prospect, together with all mining permits and licences.  The new licence gives us production rights not just on the original eight ML's but
also for the territory surrounding the mines.

    5. CGM Cash Position

    CGM actively monitors and reviews all aspects of planned capital expenditure and operating costs associated with our Chinese operations
in view of external macro conditions.  

    CGM's cash position on 30 September 2008 was USD17.3m. We have an additional USD1.7m in cash equivalent assets such as gold stock and
security bonds, taking our cash reserves to USD19m at the end of 3Q08.

    As a result of prudent cash management of expenditure, CGM remains on track with its budgeted cash position.

    In light of the unstable financial climate associated with capital markets, currency movements (GBP to USD) and the gold price, the
Board will continue to adopt a prudent approach to expenditure for the foreseeable future.

    6. Central Decline Project

    As announced on 31 July 2008, the Company has entered into a contract with Hunan Tunnel Engineering General Corporation to construct a
central decline and a 4km underground haulage system.

    Update on the project:-
 *  Land and Acquisition

    The Company has successfully acquired its central site location in Zheng
    Jia Shan for RMB 1,156,231 (USD170,000) from the local villagers for the
    land right usage.

 *  Contractor

    In view of the current economic climate and the projected ramp-up of gold
    production for the 2009 year, the Board has decided to revert to the
    original date of mid-2009 for the commencement of the central decline
    project.

    7. Human Resources and Safety

 *  The Company has 476 full-time staff and 600 contractors working on the
    Guanzhuang Gold Project.

 *  CGM has an excellent safety record and the Company is proud that no time
    has been lost through injury in 3Q08. This has been achieved through
    extensive training and safety development programs.


 China Goldmines plc
 Frank Vanspeybroeck (CEO)                  +86 731 518 8200
 Alex Worrall (Director/Company Secretary)  +44 207 788 7621
 Marinko Vidovich (CFO)                     +61 8 6216 5200
 Guanzhuang Site Office                     +86 745 463 9900

 Brewin Dolphin Ltd (Nomad)
 Alex Dewar / Sandy Fraser                  +44 131 529 0276
 (Nominated Adviser)

    Notes to Editors

    China Goldmines plc is a UK mining company listed on AIM on 7 February 2006 as a gold resources company focussed on the discovery and
development of gold projects in Hunan Province, China.

    CGM's Gold Project is known as the Guanzhuang Gold Project. Based on an Independent Geological Report, the project has an estimated
inferred resource of 1.8m ounces within the top 325m from the surface and over a strike distance of 1.5km. The resources have been
identified from CGM's 100% owned/controlled Shen Jia Ya Prospect, which is within the Guanzhuang Gold Project. 

    The Shen Jia Ya Prospect consists of eight gold mines that have now been converted into a single mining licence. The Company plans to
consolidate all eight individual mines. That consolidation will result in a mining operation with a long life producing 150,000 oz Au/pa,
beginning in the near future. At the same time as mining the existing eight mines, China Goldmines will continue to investigate the
potential of the project area that remains under-explored.

    The information in this report was derived from data compiled by Hunan Westralian Mining Co., Ltd, China and reported by John Warner B.
App. Sc. (App. Geol), MAIG, MGAA. John Warner is the Group Geology Manager to the Company. He has the required experience of the style of
mineralisation and types of deposit under consideration and of the activity he is undertaking so that he is qualified as a Competent Person
as defined by the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves.' John
Warner consents to the inclusion in the report of matters based on his information in the form and context in which it appears and has
reviewed the contents of this announcement.




This information is provided by RNS
The company news service from the London Stock Exchange
 
  END 
 
TSTBLBDBUSGGGIX

China Goldmines (LSE:CGM)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more China Goldmines Charts.
China Goldmines (LSE:CGM)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more China Goldmines Charts.