24 April 2024
SOUND ENERGY
PLC
("Sound
Energy", "Sound" or the "Company" and together with subsidiaries
the ''Group'')
FINAL
RESULTS
Sound Energy, the transition energy
company, announces its audited final results for the year ended 31
December 2023.
HIGHLIGHTS
Substantial 2023 Project execution undertaken -
positioned for significant operational and
financial progress through development of pivotal Moroccan Tendrara
Production Concession, with rig activities from June 2024 and plant
commissioning planned by year end
· Phase
1 Micro LNG (''mLNG'') project (''Phase 1''):
o Completed mLNG tank foundations and manufacturing of the main
components of the outer and inner LNG storage tank in
2023
o Advanced construction of the access road, which is scheduled
for completion summer 2024
o Design, planning and procurement of equipment for workover of
wells TE-6 and TE-7. Initial well works setting packers in each
well successfully completed in Q4 2023 with rig activities
scheduled for June 2024
o Processed gas expected at plant by end 2024 with LNG sales
thereafter
· Phase
2 Gas (pipeline) development (''Phase 2'') - financing to be
concluded in 2024
o Receipt of binding conditioned term sheet in June 2023, for
project financing from exclusive lead arranger, Attijariwafa Bank,
Morocco's largest bank
Corporate - strengthening of
financial position
· In
June 2023 the Company entered into a non-binding term sheet with
Calvalley Petroleum (Cyprus) Limited for a partial divestment of a
net 40% working interest in the Tendrara Production Concession and
the Grand Tendrara exploration permit
· In May
2023 the Company entered into a full and final settlement of its
tax disputes with the Moroccan tax authorities and received court
papers in June 2023 confirming the withdrawal of the cases between
the Company and Moroccan tax authority
· In
June 2023 the Company made a drawdown of £2.5 million of up to £4.0
million senior unsecured convertible bond instrument.
· In
December 2023, restructured the Eurobond such that
it will now not be fully redeemed until December 2027 rather than
partially from December 2023
· Phase
2 financing planned to be concluded in 2024 through Project debt
and conclusion of partial asset divestment
Graham Lyon, Executive Chairman said:
''Whilst substantial progress had been made in advancing mLNG
and the financial foundations for Phase 2, execution and closing of
documentation experienced delays. However, timely conclusion of the
proposed partnering arrangement and bank debt financing in 2024
will facilitate progress on the pipeline development at Tendrara,
as well as funding for further exploration on Grand
Tendrara.
The micro-LNG development at Tendrara construction has
suffered from supplier delays and is now expected to be ready to
receive gas into the plant by the end of 2024 with LNG sales
thereafter. The Company continues to uphold strong ESG values and
deliver our work in a manner commensurate with our principles. We
are pleased to have settled our outstanding tax matters such that
we can optimise our resources on field development. We have enjoyed
a supportive working relationship with ONHYM, the Ministry and our
various contractors in Morocco, and, most importantly, we continue
to benefit from the hard work and dedication of our own staff. We
will continue to work diligently to deliver value and progress for
all our stakeholders during 2024 and beyond, as we focus on
delivering material developments in transition
energy.''
For
further information, visit www.soundenergyplc.com
or follow us on
twitter @soundenergyplc
Enquiries:
Flagstaff Strategic and Investor
Communications
Tim Thompson
Mark Edwards
Alison Allfrey
|
Tel: 44
(0)20 129 1474
soundenergy@flagstaffcomms.com
|
Sound Energy
Graham Lyon, Executive
Chairman
|
Chairman@soundenergyplc.com
|
Cavendish Capital Markets - Nominated
Adviser
Ben Jeynes
Peter Lynch
|
Tel: 44
(0)20 7220 0500
|
Zeus - Broker
Simon Johnson
|
Tel:44 (0)20 3829
5000
|
Gneiss Energy Limited - Financial Adviser
Jon Fitzpatrick
Paul Weidman
Doug Rycroft
|
Tel:44 (0)20 3983
9263
|
|
| |
STATEMENT FROM THE EXECUTIVE CHAIRMAN
Introduction
2023 was a year of continued
progress, advancing the Tendrara concession development on all
fronts: the Phase 1 mLNG development, the Phase 2 Pipeline
development and funding, and the announcement of our potential
asset partner, in Eastern Morocco.
Phase 1 of the development, the mLNG
project, progressed with equipment fabrication, site preparation
and construction works undertaken. Materials were purchased,
contracts awarded and the two well recompletion preparation work
commenced.
Fabrication of equipment and site
preparation for the Phase 1 mLNG facility proceeded, delivery and
installation work slowed in the second half of 2023 due to the main
contractor (Italfluid Geoenergy S.r.l ("Italfluid")) experiencing
cost increases and supply chain issues. Italfluid took steps to
mitigate its financing obligations and phase its expenditures. The
updated schedule shows that the LNG storage tank erection work
remains on the critical path and that mechanical completion and
commissioning of the processing equipment should occur in 2024 with
first gas available for delivery to the gas plant in late 2024 and
LNG sales thereafter. Sound Energy is evaluating temporary LNG
storage facilities to facilitate LNG sales.
The Phase 2 pipeline gas project
requires financing to be arranged and finalised prior to taking a
Final Investment Decision (FID). In October 2023, the Company
announced an extension to its approximately $235 million debt
funding term sheet with Attijariwafa bank, Morocco's largest bank,
subject to certain key conditions being concluded. At year end
whilst project debt financing, a gas sales agreement and an equity
partner had been identified and matured, the associated legal
documentation and/or conditions precedent had not been completed or
satisfied. 2024 requires that these key agreements are finalised
and are unconditional such that financing of the pipeline project
can be concluded. During 2024, the Company also plans to refresh
the FEED (front end engineering design) that was completed in 2019
before tendering for Phase 2 engineering, procurement and
construction (EPC) services in readiness for FID. The Company also
announced an extension to the conditional gas sale and purchase
agreement with ONEE (Office National de l'Electricité et de l'Eau
potable).
As part of our wider efforts to
bring funding into our plans for Phase 2, it was announced in June,
that the Company had identified Calvalley as a partner for the
Tendrara Production Concession and the surrounding Grand Tendrara
exploration permits. As at year end, the definitive contractual
documentation with Calvalley had not concluded although the process
was advancing. The transaction would see Calvalley enter the
Concession and Grand Tendrara exploration permits in exchange for
development and exploration financing. Returning to exploration
offers the near-term opportunity to expand the Company's resource
base and unlock its significant basin potential.
It was agreed with ONHYM that all
exploration permits were either extended or advanced into the first
Complementary Period (at year end we are awaiting the various
Authorities final approval of the agreed licences
amendments).
We were pleased that the
long-running dispute with the Moroccan authorities over tax was
settled mid-year, with modest payments phased over a six-year
period. The removal of this tax overhang helped unlock financing
and partnering opportunities at Tendrara, smoothing the pathway
towards Phase 2 FID and, hopefully, further exploration
success.
Corporate
In June, we successfully raised £2.5
million through a convertible equity issue, which was priced at
2.25 pence per share (a premium to the prevailing share price at
the time), with the funds earmarked for pre-FID activities on Phase
2, new ventures activities and corporate G&A. In line
with the terms of debt issue, the Company issued shares following
the conversion of £2.25 million into shares during the second half
of the year. In December, the Company successfully gained
noteholders' support to modify the Euro bond amortisation
obligation (in respect of its Company's Luxembourg listed EUR 28.8m 5.0% senior secured
notes), such that the bond will now not be fully
redeemed until December 2027 rather than partially from December
2023. This, in turn, improved the Company's working capital
position as it moves towards first gas and first revenue, on its
Phase 1 project.
Preparing key elements for Phase 2
documentation for the Final Investment Decision, has taken longer
than expected, but we anticipate the final stages to be completed
in 2024. We have appreciated the ongoing support of our
stakeholders and investors throughout the process.
ESG and keeping our people safe sits
at the heart of our business and, as operations continued, we have
actively monitored and taken timely action on safety or
environmental issues, reports or alerts, as they have arisen. The
Company has a robust health and safety management system in place,
and works hand in hand with our contractors and under the umbrella
of our corporate environmental and safety standards. Thanks to
strong monitoring and constant improvement of working practices, we
have had no serious accidents over the year. Any environmental
issues are also recorded and monitored. Finally, we engage
proactively with our local communities and have taken steps not
only to employ locals where we can, but to keep relevant
stakeholders and communities in Morocco informed about our
activities. Good corporate governance is maintained at all levels
in particular, we note the new amendments to the QCA governance
code and will implement these in due course.
The Company continues to manage its
financial resources prudently whilst making significant capital
investments in pursuing its strategy. The bridge to fund the
company until first revenues from Phase 1 is always under review
and a variety of working capital sources evaluated.
Board
During 2023, the Board continued to
meet regularly and oversee effective implementation of the
Company's strategy. A review of the Board's effectiveness was
conducted in 2022. Scope for improvement was identified with many
resultant initiatives implemented in the Board's 2023 activities.
For example, the Board undertook a focused strategy review session
during 2023 reviewing all aspects of the Company business,
reflecting on its position in the market, risk profile, asset
opportunity, structuring, and scenario planning.
We welcomed Simon Ashby-Rudd as new
independent director as Marco Fumagalli stepped down. Simon brings
a wealth of knowledge, financial skills and deal-making experience
to the Company. We thank Marco for his 9 years of valued service,
advice, and support to the Company.
Conclusion
I am pleased that the Company is on
a stronger footing both operationally and financially for 2024 and
look forward to our delivering upon the compelling investment
opportunity open to us in transition energy this year and
beyond.
Graham Lyon
Chairman (Executive)
PORTFOLIO REVIEW
A
blended portfolio of gas assets
Eastern Morocco
Tendrara Production
Concession
Permit Area
Located proximate to Gazoduc Maghreb
Europe ("GME") pipeline, approximately 120 kilometres to the North.
The 522 kilometre-long Moroccan section is owned by the Moroccan
State and operated by ONHYM. The pipeline connects Morocco to
Spanish/Portuguese gas grids as well as Moroccan gas-fired power
stations.
Geology
The gas is trapped within the
Triassic TAGI 1 reservoir within the structural fault block, termed
the Tendrara TE-5 Horst, and sealed by the overlying salt.
Reservoir characteristics are significantly enhanced by application
of proven hydraulic stimulation techniques to increase gas flow
rates.
Ongoing and Planned Developments
Planned development of our
discovered TE-5 gas to address gas demand in a phased manner is
progressing, with Phase I being the implementation of a micro-LNG
development scheme (currently underway) and a future Phase 2 being
the development of a larger scale central processing facility
("CPF") and gas export pipeline to GME.
Phase 1
Supply of LNG displacing higher
carbon footprint energy (such as heavy fuel, petcoke or imported
LPG).
Phase 1 Micro LNG Development -
Funding arranged to meet Sound Energy's share of sanctioned pre
first gas development costs.
Deployment of field gas treatment,
processing, liquefaction and storage facilities to deliver mobile
LNG to buyer at site. The LNG buyer will distribute and sell on to
its growing Moroccan industrial consumers within the domestic gas
market.
Supplies of LNG are to be an annual
contractual quantity equivalent to approximately 100 million Normal
cubic metres of gas (approximately 3.5 billion standard cubic feet
of gas per year) over a ten-year period.
Binding gas sales agreement and
associated funding are in place with Afriquia Gaz, one of the
largest LPG distributor in Morocco. A ten-year commitment from
first gas to sell annual contractual quantity of 100 million Normal
cubic metres per annum with take or pay agreement priced at
$6-$8.346 per mmBTU ex plant.
Development utilises the existing
wells TE-6 and TE-7, with the drilling of one new well, as
required, to maintain the ten-year period of production at the
plateau.
LNG
Central Processing Facility is under construction by
Italfluid
Micro LNG Plant to be designed,
constructed, commissioned, operated and maintained by Italfluid
with guarantees for plant operability and delivery.
Lease structure (with option to
buy):
• Minimal
LNG tank construction capital payments at and from FID, and
following successful completion of Micro LNG Plant commissioning
(including production build-up)
• Leasing
solution substantially lowers capital investment requirements of
Phase 1 development
• Daily
rental payment paid to Italfluid on guaranteed daily volume
only
•
Performance guarantees on plant availability
Phase 2 - Tendrara TE-5
Development
Concept - Processed gas as a
transition fuel flowing to the GME pipeline:
• 20 inch,
120km Tendrara Gas Export Pipeline ("TGEP"):
• Tie-in to
existing GME pipeline (Station M04), approved by the GME operator
ONHYM
• Pipeline
EIA permit approved and pipeline corridor fully secured. Lease
agreements signed with the landowners and the first lease payments
have been paid.
• CPF EIA
permit approved
• Gas Sales
Agreement ("GSA") with ONEE (Office National de l'Electricité et de
l'Eau potable) signed November 2021 for domestic power plants for
gas-to-power generation (transit via GME line), minimum volume of
0.3 bcm/year (approximately 10.5 billion standard cubic feet of gas
per year) at a fixed sale price over a ten-year term. Extended in
2023.
• Up to six
horizontal wells planned to achieve First Gas (Phase 2)
• Exclusive
partnership with Attijariwafa Bank (which is one of the top banks
in Morocco and in Africa and which is part of the Moroccan King's
holding, MADA) acting as Lead Debt Arranger in order to fund a
substantial part of Phase 2 project. Technical and Legal Due
Diligence completed.
Exploration
Grand Tendrara - two Triassic TAGI1
discoveries
Permit Details
|
|
Area
|
14,411 km2
|
Status
|
Petroleum Agreement:
Exploration
|
Effective date
|
1 October 2018
|
Term
|
8 years
|
Resource Potential
|
Exploration potential in the
Triassic TAGI reservoir of 7.52 Tcf gross/5.64 Tcf net
(arithmetical sum of mid-case un-risked GIIP) identified in
sub-salt concepts, leads and prospects.
|
Permit Area
Surrounds the Tendrara Production
Concession.
Located for access to Gazoduc
Maghreb Europe ("GME") pipeline approximately 120 kilometres to the
north. The 522 kilometres long Moroccan section is owned and
operated by the Moroccan State. The pipeline connects Morocco to
the Spanish/Portuguese gas grids as well as the Moroccan
gas-fired-power stations.
Geology
Only eight wells drilled across the
entire area, all encountered evidence of a petroleum system. The
primary reservoir is the Triassic TAGI1 charged from Palaeozoic
petroleum source rocks and sealed by the overlying Triassic salt,
which is present across much of the basin. This petroleum play is
regionally extensive and extends into Morocco from
Algeria.
Two Triassic TAGI1 gas
discoveries exist within the permit area:
• SBK-1
tested by the previous permit holder at a peak rate of 4.41 mmscf/d
in July 2000
• TE-10
flowed gas at non-commercial rates in May 2019
Exploration potential in the
Triassic TAGI1 reservoir of 7.52 Tcf gross/5.64 Tcf net
(mid-case unrisked GIIP) identified in sub-salt concepts, leads and
prospects.
Future Developments
A number of targets are available
for near-term drilling with two features, the SBK structure and the
TE-4 Horst, high-graded for drilling. Both these structures were
drilled by SBK-1 and TE-4, in 2000 and 2006, respectively, and both
encountered gas shows in the TAGI reservoir. SBK-1 flowed gas to
surface during testing in 2000 at a peak rate of 4.41 mmscf/d post
acidification but was not tested with hydraulic stimulation. TE-4
was tested in 2006 but did not flow gas to the surface. Hydraulic
stimulation has proven to be a key technology to commercially
unlock the potential of the TAGI gas reservoir in the Tendrara TE-5
Horst gas accumulation and, accordingly, the Company believes this
offers potential to develop commercial operations elsewhere in the
basin.
The gross exploration potential of
these high-graded structures, expressed as GIIP2, is as
follows:
Target name
|
Unrisked Volume Potential Gas
Initially in Place (Bcf)
|
Chance of
Success
|
Gross (100%)
basis
|
Low
|
Best
|
High
|
Mean
|
TE-4 Horst Structure
|
153
|
260
|
408
|
273
|
36%
|
SBK-1 Structure
|
71
|
130
|
225
|
140
|
50%
|
A discovery in either structure
would have the potential to be commercialised through the proposed
development infrastructure centred on the TE-5 Horst, with
sufficient capacity in the planned Tendrara Export Pipeline or as
standalone mLNG projects.
Subject to approval by the Ministry
of Energy and Ministry of Finance, the Company has elected to enter
the voluntary first Complementary period, which commenced
mid-October 2022 with one well commitment to be drilled before
October 2024. A well drilled on either the SBK structure or the
TE-4 Horst would satisfy this commitment.
1.
Trias Argilo-Gréseux Inférieur ("TAGI") are sandstones
deposited in a fluvial-alluvial environment and are significant oil
and gas reservoirs
across
Algeria, extending into Morocco
2.
Internal exploration potential estimates, arithmetical sum of
mid-case unrisked Gas Initially In Place ("GIIP")
Anoual
Permit Details
|
|
Area
|
8,873 km2
|
Status
|
Petroleum Agreement:
Exploration
|
Effective date
|
8 September 2017
|
Term
|
10 years
|
Resource
Potential
|
Exploration potential in the
Triassic TAGI reservoir of 11.51 Tcf gross/8.63 Tcf net (mid-case
un-risked GIIP2) identified in sub-salt concepts, leads
and prospects
|
Permit Area
Located for access to Gazoduc
Maghreb Europe ("GME") pipeline approximately 120 kilometres to the
North. The 522 kilometre-long Moroccan section is owned and
operated by the Moroccan State. The pipeline connects Morocco to
the Spanish/Portuguese gas grids as well as the Moroccan gas-fired
power stations.
Geology
Only one well drilled across the
entire area. The primary reservoir is the Triassic TAGI1
charged from Palaeozoic petroleum source rocks and sealed by the
overlying Triassic salt, which is present across much of the basin.
This petroleum play is regionally extensive and extends into
Morocco from Algeria. Committed geophysical surveying completed
with a single well commitment remaining. Exploration potential in
the Triassic TAGI reservoir of 11.51 Tcf gross/8.63 Tcf net
(mid-case un-risked GIIP2) identified in sub-salt
concepts, leads and prospects.
Future Developments
"M5" prospect high graded for
drilling a TAGI1 target, operational planning is
progressing. The Company's estimation of the gross exploration
potential of the M5 exploration prospect, a possible candidate for
the exploration well, expressed in GIIP2, is as
follows:
Target name
|
Unrisked Volume Potential Gas
Initially In Place (Bcf)
|
Chance of
Success
|
Gross (100%)
basis
|
Low
|
Best
|
High
|
Mean
|
M5
Exploration
|
332
|
800
|
1728
|
943
|
21%
|
1.
Trias Argilo-Gréseux Inférieur ("TAGI") are sandstones
deposited in a fluvial-alluvial environment and are significant oil
and gas reservoirs across Algeria, extending into
Morocco
2.
Internal exploration potential estimates, arithmetical sum of
mid-case unrisked Gas Initially In Place ("GIIP")
Sidi Mokhtar
Permit Details
|
|
Area
|
4,712 km2
|
Status
|
Petroleum Agreement:
Exploration
|
Effective date
|
April 2018
|
Term
|
10 years
|
Resource Potential
|
Unrisked exploration potential of
8.9 Tcf mid-case unrisked GIIP2 following interpretation
of the historical 2D seismic
|
Permit Area
The permit in which Sound Energy has
a 75% interest is located onshore on the Atlantic seaboard of
Morocco, approximately 100 kilometres to the west of
Marrakech.
In July 2017, the Company reported
the results of the re-entry, completion, perforation and flow
testing of the existing Koba-1 well, with a focus on previously
producing relatively shallow gas reservoir.
Strategically, the Company has
shifted its focus on the Sidi Mokhtar area towards what it believes
has the potential to be the most significant opportunity amongst
the deeper Triassic TAGI1 and Palaeozoic gas plays in
the region already demonstrated by the gas and condensate producing
adjacent Meskala Field operated by our partner ONHYM. In June 2018,
the Company was awarded a new eight-year Petroleum Agreement and is
now actively seeking a partner to participate in a geophysical
survey programme focused on these deeper objectives.
In December 2020, the Company
announced a further one-year extension to the initial period of the
Sidi Mokhtar permit and that the work programme for the initial
period of the Sidi Mokhtar permit remained unchanged.
Geology
There is initial un-risked
exploration potential of up to 8.9 Tcf gross gas following
interpretation of the historical 2D seismic. The Company believes
the pre-salt plays have been overlooked in the region with limited
drilling to specifically target these deeper
successions.
The sub-salt plays are underexplored
with more than 60 historical exploration wells focused on shallower
objectives in the Jurassic post-salt carbonate successions. The few
historical sub-salt tests were drilled on poor sub-salt seismic
imaging. Recent improvements in seismic acquisition and processing
technologies are expected to provide enhanced imaging of the
sub-salt structure and geology.
Future Developments
Our next step is to mature the
identified leads to drillable prospects with improved seismic
imaging. We aim to acquire new, high-quality 2D seismic data,
focused on improving the sub-salt imaging. This work is hoped to
lead to an exploration well targeting a high-impact gas
prospect.
1.
Trias Argilo-Gréseux Inférieur ("TAGI") are sandstones
deposited in a fluvial-alluvial environment and are significant oil
and gas reservoirs across Algeria, extending into
Morocco
2.
Internal exploration potential estimates, arithmetical sum of
mid-case unrisked Gas Initially In Place ("GIIP")
Financial Review
Income Statement
The pre-tax loss for the year from
continuing operations was £7.2 million (2022: £6.6 million,
profit). Results of an impairment test on the Tendrara Production
Concession carrying amount indicated that no impairment charge was
required (2022: £5.7 million impairment reversal). The discount
rate and forecast gas price are the significant estimates used by
the Company to determine the recoverable amount when undertaking
impairment testing of the Company's Tendrara Production
Concession.
Administrative costs at £2.4 million
were lower than 2022 administration costs (£3.2 million) as no nil
cost options were issued to staff in 2023, as was the case in
2022.
Foreign exchange losses primarily
related to intra-Group loans, which were partially offset by
exchange gains in US dollar and Euro-denominated borrowings.
Foreign exchange gains and losses arising from inter-company loans
that originated on acquisition of Moroccan permits are recognised
in the other comprehensive income section of the statement of
comprehensive income.
Cash Flow/Financing
During 2023, proceeds from
borrowings were approximately £4.4 million (2022: £7.2 million) net
of issue costs. There were no proceeds from equity issues during
the year (2022: £3.7 million).
Financing costs during the year were
£2.0 million (2022: £1.4 million), primarily due to the amortised
costs of the Company's Euro denominated loan notes, the US dollar
Afriquia loan note facility and Convertible Bonds facility
drawdowns, net of interest capitalised to the development and
exploration permits of £0.3 million (2022: £0.1 million). The
increase in finance costs arose due to a further $2.5 million
drawdown from the Afriquia facility and £2.5 million drawdown from
a convertible loan note facility that was entered into during the
year. The convertible loan note facility has a term of five
years with interest of 15% per annum,
payable bi-annually in cash or capitalised to the principal, at the
Company's election. The first tranche of the Convertible Notes comprised £2.5 million
with a fixed conversion price of 2.25 pence per ordinary share, a
premium of approximately 28% to the closing price of 1.76 pence per
ordinary share on 12th June 2023. In connection
with the drawdown of the first tranche, the Company issued
33,333,333 warrants (to the investors) to subscribe for new
ordinary shares in the Company at an exercise price of 2.25 pence
per ordinary share with a term of three years. The Company
successfully restructured its Euro denominated loan notes leading
to removal of 5% semi-annual partial repayment of the principal
amount that was due to commence in December 2023.
The Group spent £2.9 million (2022:
£6.2 million) on investing activities during 2023 primarily related
to the Group's Micro-LNG project with the balance relating to
expenditure on the Group's exploration permits in Morocco and
capitalised general and administrative expenses. As part of the
2018 Italy divestment agreement, the Company was entitled to
receive the proceeds, upon sale, of land associated with the former
Badile onshore Exploration Permit (''Badile land''). The sale of
the remaining area of Badile land completed in Q2 2023 and the
Company received net proceeds of approximately €153,000
(£134,000).
Balance Sheet
As at 31 December 2023, the carrying
amount of property, plant and equipment was £157.9 million (2022:
£163.4 million), primarily related to the development and
production assets in Morocco with a carried value of £157.8 million
(2022: £163.1 million) after taking account of impairment reversal,
additions and foreign exchange movement.
Intangible assets, with a carrying
amount of £35.0 million (2022: £36.0 million), primarily relates to
the Group's investment in its exploration permits in Morocco. The
addition of £0.7 million to intangible assets primarily consisted
of capitalised general and administrative expenses and
£1.8 million foreign exchange movement recognised.
Non-current prepayments of £5.1
million (2022: £4.3 million) relate to the Group's Phase 1 mLNG
project. Other receivables, amounting to £0.9 million (2022:
£2.8 million), primarily related to receivables from our
partners in Morocco permits and recoverable VAT in
Morocco.
Trade and other payables amounting
to £2.5 million (2022: £1.9 million) primarily related to payables
and accruals for the operations in the Group's permits in Morocco,
where the Group, as operator, recognises 100% of the liability and
receives funds from partners to pay the partners' share.
During 2023, the Company issued
114,420,005 ordinary shares which were all non-cash share issues.
The primary non-cash share issues related to 99,9999,994 new shares
issued following the conversion of £2.25 million of Convertible
bonds into shares.
Going Concern
As detailed in note 1 to the
financial statements, the Company's cash flow forecasts, for the
next twelve-month period to April 2025, indicate that additional
funding will be required to enable the Company to continue to meet
its obligations. This condition indicates the existence of a
material uncertainty regarding the Company's ability to continue as
a going concern.
Consolidated Statement of Comprehensive
Income
For the year ended 31 December
2023
|
Notes
|
2023
£'000s
|
2022
£'000s
|
Continuing operations
|
|
|
|
Revenue
|
|
-
|
-
|
Other income
|
|
42
|
43
|
Reversal of impairment on
development assets and exploration costs
|
|
-
|
5,678
|
Gross profit
|
|
42
|
5,721
|
Administrative expenses
|
|
(2,396)
|
(3,175)
|
Group operating (loss)/profit from continuing
operations
|
|
(2,354)
|
2,546
|
Finance revenue
|
|
42
|
13
|
Foreign exchange
(loss)/gain
|
|
(2,846)
|
5,462
|
Finance expense
|
11
|
(1,994)
|
(1,446)
|
(Loss)/profit for the year before taxation
|
|
(7,152)
|
6,575
|
Tax expense
|
4
|
(8)
|
(1,602)
|
(Loss)/profit for the year after taxation
|
|
(7,160)
|
4,973
|
|
|
|
|
Other comprehensive income
|
|
|
|
Items that may subsequently be
reclassified to the profit and loss account
|
|
|
|
Foreign currency translation
(loss)/gain
|
|
(6,555)
|
13,373
|
Total comprehensive (loss)/profit for the
year
|
|
(13,715)
|
18,346
|
(Loss)/profit for the year attributable to:
|
|
|
|
Owners of the Company
|
|
(13,715)
|
18,346
|
|
Notes
|
2023
Pence
|
2022
Pence
|
Basic and diluted (loss)/profit per
share for the year attributable to the equity shareholders of the
parent (pence)
|
5
|
(0.38)
|
0.28
|
Consolidated Balance Sheet as at 31 December
2023
|
Notes
|
2023
£'000s
|
2022
£'000s
|
Non-current assets
|
|
|
|
Property, plant and
equipment
|
6
|
157,927
|
163,362
|
Intangible assets
|
7
|
35,002
|
36,007
|
Prepayments
|
8
|
5,092
|
4,272
|
Interest in Badile land
|
|
-
|
637
|
|
|
198,021
|
204,278
|
Current assets
|
|
|
|
Inventories
|
|
915
|
963
|
Other receivables
|
|
924
|
2,815
|
Prepayments
|
8
|
1,342
|
139
|
Cash and short-term
deposits
|
|
3,016
|
3,861
|
|
|
6,197
|
7,778
|
Total assets
|
|
204,218
|
212,056
|
Current liabilities
|
|
|
|
Trade and other payables
|
|
2,495
|
1,868
|
Tax liabilities
|
4
|
199
|
126
|
Lease liabilities
|
|
121
|
162
|
Loans and borrowings
|
11
|
-
|
1,121
|
|
|
2,815
|
3,277
|
Non-current liabilities
|
|
|
|
Lease liabilities
|
|
-
|
121
|
Tax liabilities
|
4
|
1,410
|
1,505
|
Loans and borrowings
|
11
|
33,285
|
29,068
|
|
|
34,695
|
30,694
|
Total liabilities
|
|
37,510
|
33,971
|
Net
assets
|
|
166,708
|
178,085
|
Capital and reserves
|
|
|
|
Share capital and share
premium
|
|
39,898
|
38,621
|
Shares to be issued
|
|
374
|
404
|
Accumulated surplus
|
|
122,443
|
129,004
|
Warrant reserve
|
|
2,071
|
1,607
|
Convertible bond reserve
|
|
28
|
-
|
Foreign currency reserve
|
|
1,894
|
8,449
|
Total equity
|
|
166,708
|
178,085
|
Consolidated Statement of Changes in Equity
|
Notes
|
Share capital £'000s
|
Share premium £'000s
|
Shares to be issued
£'000s
|
Accumulated surplus
£'000s
|
Warrant reserve £'000s
|
Convertible
Bond
reserve
£'000s
|
Foreign currency reserves
£'000s
|
Total
equity £'000s
|
At 1 January
2023
|
|
18,487
|
20,134
|
404
|
129,004
|
1,607
|
-
|
8,449
|
178,085
|
Total loss for the year
|
|
-
|
-
|
-
|
(7,160)
|
-
|
-
|
-
|
(7,160)
|
Other comprehensive loss
|
|
-
|
-
|
-
|
-
|
-
|
-
|
(6,555)
|
(6,555)
|
Total comprehensive loss
|
|
-
|
-
|
-
|
(7,160)
|
-
|
-
|
(6,555)
|
(13,715)
|
Issue of share capital on conversion of
bond
|
11
|
1,000
|
46
|
-
|
-
|
-
|
-
|
-
|
1,046
|
Other share capital issues
|
|
114
|
87
|
-
|
-
|
-
|
-
|
-
|
201
|
Transfer to share capital on issue of
shares
|
|
30
|
-
|
(30)
|
-
|
-
|
-
|
-
|
-
|
Fair value of warrants issued during the
year
|
|
-
|
-
|
-
|
-
|
464
|
-
|
-
|
464
|
Equity component of convertible bond
|
|
-
|
-
|
-
|
-
|
-
|
562
|
-
|
562
|
Cost of issue allocated to equity
component
|
|
-
|
-
|
-
|
-
|
-
|
(174)
|
-
|
(174)
|
Transfer to accumulated surplus on bond
conversion to shares
|
|
-
|
-
|
-
|
360
|
-
|
(360)
|
-
|
-
|
Share-based payments
|
10
|
-
|
-
|
-
|
239
|
-
|
-
|
-
|
239
|
At 31 December
2023
|
|
19,631
|
20,267
|
374
|
122,443
|
2,071
|
28
|
1,894
|
166,708
|
|
Notes
|
Share
capital
£'000s
|
Share
premium £'000s
|
Shares to
be issued
£'000s
|
Accumulated surplus
£'000s
|
Warrant
reserve
£'000s
|
Foreign
currency reserves
£'000s
|
Total
equity
£'000s
|
At 1 January 2022
|
|
16,292
|
18,281
|
-
|
123,872
|
1,534
|
(4,924)
|
155,055
|
Total profit for the year
|
|
-
|
-
|
-
|
4,973
|
-
|
-
|
4,973
|
Other comprehensive
income
|
|
-
|
-
|
-
|
-
|
-
|
13,373
|
13,373
|
Total comprehensive
income
|
|
-
|
-
|
-
|
4,973
|
-
|
13,373
|
18,346
|
Issue of share capital
|
|
2,195
|
2,246
|
-
|
-
|
-
|
-
|
4,441
|
Share issue costs
|
|
-
|
(393)
|
-
|
-
|
-
|
-
|
(393)
|
Fair value of warrants issued during
the year
|
|
-
|
-
|
-
|
-
|
73
|
-
|
73
|
Vested nil options bonus
awards
|
|
-
|
-
|
404
|
-
|
-
|
-
|
404
|
Share-based payments
|
10
|
-
|
-
|
-
|
159
|
-
|
-
|
159
|
At 31 December 2022
|
|
18,487
|
20,134
|
404
|
129,004
|
1,607
|
8,449
|
178,085
|
Consolidated Statement of Cash Flows
For the year ended 31 December
2023
|
Notes
|
2023
£'000s
|
2022
£'000s
|
Cash flow from operating activities
|
|
|
|
Cash flow from operations
|
|
(1,403)
|
(3,928)
|
Interest received
|
|
42
|
13
|
Tax paid
|
|
(134)
|
(7)
|
Net
cash flow from operating activities
|
|
(1,495)
|
(3,922)
|
Cash flow from investing activities
|
|
|
|
Capital expenditure
|
|
(1,600)
|
(1,519)
|
Exploration expenditure
|
|
(660)
|
(399)
|
Prepayment for Phase 1 the mLNG
project
|
|
(820)
|
(4,272)
|
Receipt from interest in Badile
land
|
|
134
|
-
|
Net
cash flow from investing activities
|
|
(2,946)
|
(6,190)
|
Cash flow from financing activities
|
|
|
|
Net proceeds from equity
issue
|
|
-
|
3,680
|
Net proceeds from
borrowings
|
|
4,442
|
7,233
|
Interest payments
|
11
|
(441)
|
(431)
|
Lease payments
|
|
(180)
|
(58)
|
Net
cash flow from financing activities
|
|
3,821
|
10,424
|
Net (decrease)/increase in cash and
cash equivalents
|
|
(620)
|
312
|
Net foreign exchange
difference
|
|
(225)
|
636
|
Cash and cash equivalents at the
beginning of the year
|
|
3,861
|
2,913
|
Cash and cash equivalents at the end of the
year
|
|
3,016
|
3,861
|
Notes to Statement of Cash Flows
|
|
2023
£'000s
|
2022
£'000s
|
Cash flow from operations reconciliation
|
|
|
|
(Loss)/profit for the year before
tax
|
|
(7,152)
|
6,575
|
Finance revenue
|
|
(42)
|
(13)
|
Decrease/(increase) in drilling
inventories
|
|
48
|
(92)
|
Decrease/(increase) in receivables
and prepayments
|
|
688
|
(2,071)
|
(Decrease)/increase in accruals and
short-term payables
|
|
(343)
|
190
|
Reversal of impairment on
development assets and exploration costs
|
|
-
|
(5,678)
|
Impairment of interest in Badile
land
|
|
125
|
107
|
Depreciation
|
|
194
|
101
|
Share-based payments charge and
remuneration paid in shares
|
|
239
|
969
|
Finance expense and exchange
adjustments
|
|
4,840
|
(4,016)
|
Cash flow from operations
|
|
(1,403)
|
(3,928)
|
Non-cash transactions during the
period included the issue of 99,999,994 ordinary shares, following
partial conversion of the convertible bond. 11,404,221 ordinary
shares were issued to third parties in settlement of approximately
£0.2 million due for services provided and 3,015,790 ordinary
shares were issued following the exercise of nil cost options by a
member of staff. The Group has provided collateral of $1.75 million
(2022: $2.5 million) to the Moroccan Ministry of Petroleum to
guarantee the Group's minimum work programme obligations for the
Anoual, and Sidi Mokhtar permits. The cash is held in a bank
account under the control of the Company and, as the Group expects
the funds to be released as soon as the commitment is fulfilled, on
this basis, the amount remains included within cash and cash
equivalents.
Notes to the Financial Statements for the year ended 31
December 2023
1.
Accounting Policies
Sound Energy plc is a public limited
Company registered and domiciled in England and Wales under the
Companies Act 2006. The Company's registered office is 20 St
Dunstan's Hill, London EC3R 8HL.
The consolidated financial
information contained within this announcement does not constitute
statutory accounts for the year ended 31 December 2023 within the
meaning of Section 434 of the Companies Act 2006 but is derived
from those audited accounts. The auditors reported on those
accounts and their report was unqualified and did not contain any
statement under section 498(2) or section 498(3) of the Companies
Act 2006. The statutory accounts for the year ended 31 December
2023 will be delivered to the Registrar of Companies in due course.
The annual report and statutory accounts will be sent to
shareholders and will be made available to the public on the
Company's website: www.soundenergyplc.com or, upon request, copies
may be obtained from the Company Secretary at the registered office
of Sound Energy plc 20 St Dunstan's Hill,
London, EC3R 8HL.
(a) Basis of preparation
The financial statements of the
Group and its parent Company have been prepared in accordance with
UK-adopted International Accounting Standards.
The consolidated financial
statements have been prepared under the historical cost convention,
except to the extent that the following policies require fair value
adjustments. The Group and its parent Company's financial
statements are presented in sterling (£) and all values are rounded
to the nearest thousand (£'000) except when otherwise
indicated.
The principal accounting policies
set out below have been consistently applied to all financial
reporting periods presented in these consolidated financial
statements and by all Group entities, unless otherwise stated. All
amounts classified as current are expected to be settled/recovered
in less than 12 months unless otherwise stated in the notes to
these financial statements. The Group and its parent Company's
financial statements for the year ended 31 December 2023 were
authorised for issue by the Board of Directors on 23 April
2024.
Going concern
As at 31 March 2024, the Group's
cash balance was £2.5 million (including approximately £0.8 million
held as collateral for a bank guarantee against permit
commitments). The Directors have reviewed the Company's cash flow
forecasts for the next 12-month period to April 2025. The Company's
forecasts and projections indicate that, to fulfil its other
obligations, primarily the Company's exploration permits
commitments, the Company will require additional funding. The
Company commenced its Phase 1 of the Concession upon taking FID on
the micro-LNG project, and has continued to actively monitor the
project schedule, costs and financing. The Company is progressing
towards a final investment decision for Phase 2, pipeline led
development of the Concession and received a conditional offer for
partial financing of the Phase 2 development and continue to work
to satisfy the conditions precedents and other elements necessary
for the taking of Phase 2 FID.
The need for additional financing
indicates the existence of a material uncertainty, which may cast
significant doubt about the Group and Company's ability to continue
as a going concern. These financial statements do not include
adjustments that would be required if the Company was unable to
continue as a going concern. The Company continues to exercise
rigorous cost control to conserve cash resources, and the Directors
believe that there are several corporate funding options available
to the Company, including a farm-down on some of the Company's
permits, and various debt funding options. Furthermore, based upon
the Company's proven track record in raising capital in the London
equity market, and based on feedback from ongoing financing
discussions, the Directors have a reasonable expectation that the
Company and the Group will be able to secure the funding required
to continue in operational existence for the foreseeable future,
and have made a judgement that the Group will continue to realise
its assets and discharge its liabilities in the normal course of
business. Accordingly, the Directors have adopted the going concern
basis in preparing the consolidated financial
statements.
Use
of estimates and key sources of estimation
uncertainty
The preparation of financial
statements in conformity with IFRS requires management to make
estimates and assumptions that affect the reported amounts of
assets and liabilities, as well as the disclosure of contingent
assets and liabilities at the balance sheet date and the reported
amounts of revenues and expenses during the reporting period. The
Group based its assumptions and estimates on parameters available
when the consolidated financial statements were prepared. Existing
circumstances and assumptions about future developments, however,
may change due to market changes or circumstances arising that are
beyond the control of the Group. Such changes are reflected in the
assumptions when they occur.
Estimation and assumptions
The key sources of estimation
uncertainty, that have a significant risk of causing material
adjustment to the carrying amounts of assets and liabilities within
the next financial year, are the impairment of intangible
exploration and evaluation ("E&E") assets, impairment of
development and production assets, investments, warrants, and the
estimation of share-based payment costs.
E&E, development and production assets
When considering whether E&E
assets are impaired, the Group first considers the IFRS 6
indicators set out in note 7. The making of this assessment
involves judgement concerning the Group's future plans and current
technical and legal assessments. In considering whether development
and production assets are impaired, the Group considers various
impairment indicators and whether any of these indicates existence
of an impairment. If those indicators are met, a full impairment
test is performed.
Impairment test
When value in use calculations are
undertaken, management estimates the expected future cash flows
from the asset and chooses a suitable discount rate to calculate
the present value of those cash flows. In undertaking these value
in use calculations, management is required to make use of
estimates and assumptions similar to those described in the
treatment of E&E assets above. Further details are given in
note 7.
At 31 December 2023, the Company's
market capitalisation was £14.0 million, which is below the Group
and Company's net asset value of £166.8 million and £156.8 million,
respectively. Management considers this to be a possible indication
of impairment of the Group and Company's assets. A significant
portion of the Group's net assets is the carrying value of the
development and producing assets and disclosures relating to
management's assessment of impairment for these assets and the
investment in subsidiaries are included in note 6, on the basis
that the recoverability of the investment in subsidiaries in the
Company balance sheet is linked to the value of the development and
producing assets as, ultimately, the cash flows these generate will
determine the subsidiaries' ability to pay returns to
the Company.
Impairment exists when the carrying
value of an asset or cash generating unit exceeds its recoverable
amount, which is the higher of its fair value less costs of
disposal and its value in use. The fair value less costs of
disposal calculation is based on available data from binding sales
transactions, conducted at arm's length, for similar assets or
observable market prices less incremental costs of disposing of the
asset. The fair value is estimated using a discounted cash flow
model ('DCF model''). The cash flows are derived from the latest
budgets, expenditure and price data in signed gas sales agreements
(for contracted gas sales volumes), market based price data (for
uncontracted gas sales volumes), project contract or agreed heads
of terms, and the latest management plans on project phasing. The
recoverable amount is sensitive to the discount rate and gas price
assumption as well as the Brent price assumption that impacts
condensate sales pricing in the DCF model. The impairment test
indicated that there was sufficient headroom and therefore no
impairment charge was recognized as at 31 December 2023. The key
assumptions used to determine the recoverable amount of the
development and production assets are disclosed in note
6.
Share-based payments
The estimation of share-based
payment costs requires the selection of an appropriate valuation
model, consideration as to the inputs necessary for the valuation
model chosen, and the estimation of the number of awards that will
ultimately vest, inputs for which arise from judgements relating to
the continuing participation of key employees (note 10).
Fair value of warrants
Significant judgement and estimation
is also required in the determination of the fair value of
warrants.
Fair value of convertible bonds
The calculation of fair value on
convertible bonds requires estimation of the discount rate to use
when discounting outstanding principal and interest amounts at each
reporting date. The discount rate is a significant input into the
discounted cashflow model used by the Company to estimate the fair
value of the convertible bonds.
Taxation
The Group seeks professional tax and
legal advice to make a judgement on application of tax rules on
underlying transactions within the Group or with third parties. Tax
treatment adopted by the Group may be challenged by tax
authorities. The Group had tax cases where Morocco Tax
Authority had claimed taxes relating to the Group historical
permits transfers and intragroup transactions. During 2023, a
settlement on the tax cases was agreed upon as disclosed in note
4.
Intercompany loans
The Company has funded its
subsidiaries through non-interest bearing loans payable on demand.
Given that the Company has no intention to call in the loans in the
foreseeable future, the loans are classified as non-current
investments. Other sources of estimate concern IFRS 9 on
intercompany loans at parent Company level.
(b) Investment in subsidiaries
Subsidiaries are all entities over
which the Group has the power to govern the financial and operating
policies, is exposed to, or has rights to, variable returns from
its involvement with the entity and has the ability to affect those
returns through its power over the entity. Such power, generally
but not exclusively, accompanies a shareholding of more than
one-half of the voting rights. The Group uses the purchase
method of accounting for the acquisition of subsidiaries. The cost
of an acquisition is measured as the fair value of the assets
given, equity instruments issued and liabilities incurred or
assumed at the date of exchange. Costs of acquisition are expensed
during the period they are incurred.
(c) Foreign currency translation
The functional currency of the
Company is GBP sterling. The Group also has subsidiaries whose
functional currencies are US dollar.
Transactions in foreign currencies
are initially recorded in the functional currency by applying the
spot exchange rate ruling at the date of the transaction. Monetary
assets and liabilities denominated in foreign currencies are
retranslated at the functional currency rate of exchange ruling at
the balance sheet date. All differences are taken to the income
statement.
On consolidation, the assets and
liabilities of foreign operations are translated into sterling at
the rate of exchange ruling at the balance sheet date. Income and
expenses are translated at weighted average exchange rates for the
year unless this is not a reasonable approximation of the rates on
the transaction dates. The resulting exchange differences are
recognised in other comprehensive income and held in a separate
component of equity. On disposal of a foreign entity, the deferred
cumulative amount recognised in equity relating to that foreign
operation is recognised in the income statement.
2.
Segment information
The Group categorises its operations
into three business segments based on corporate, exploration and
appraisal, and development and production.
In the year ended 31 December 2023,
the Group's development, exploration and appraisal activities were
primarily carried out in Morocco.
The Group's reportable segments are
based on internal reports about components of the Group, which are
regularly reviewed and used by the Board of Directors, being the
Chief Operating Decision Maker ("CODM"), for strategic decision
making and resource allocation, in order to allocate resources to
the segment and to assess its performance.
Details regarding each of the
operations of each reportable segments are included in the
following tables.
Segment results for the year ended
31 December 2023:
|
Corporate
£'000s
|
Development and production
£'000s
|
Exploration and appraisal
£'000s
|
Total
£'000s
|
Other income
|
-
|
-
|
42
|
42
|
Impairment of development assets and
exploration costs
|
-
|
-
|
-
|
-
|
Administration expenses
|
(2,396)
|
-
|
-
|
(2,396)
|
Operating (loss)/profit segment result
|
(2,396)
|
-
|
42
|
(2,354)
|
Interest receivable
|
42
|
-
|
-
|
42
|
Finance expense and exchange
adjustments
|
(4,840)
|
-
|
-
|
(4,840)
|
(Loss)/profit for the period before taxation from continuing
operations
|
(7,194)
|
-
|
42
|
(7,152)
|
The segments assets and liabilities
at 31 December 2023 is as follows:
|
Corporate
£'000s
|
Development and production
£'000s
|
Exploration and appraisal
£'000s
|
Total
£'000s
|
Non-current assets
|
137
|
162,908
|
34,976
|
198,021
|
Current assets
|
1,959
|
2,897
|
1,341
|
6,197
|
Liabilities attributable to
continuing operations
|
(23,551)
|
(11,368)
|
(2,591)
|
(37,510)
|
The geographical split of
non-current assets is as follows:
|
UK
£'000s
|
Morocco
£'000s
|
Development and production
assets
|
-
|
157,816
|
Fixtures, fittings and office
equipment
|
4
|
6
|
Right of use assets
|
101
|
-
|
Software
|
18
|
8
|
Prepayments
|
-
|
5,092
|
Exploration and evaluation
assets
|
-
|
34,976
|
Total
|
123
|
197,898
|
Segment results for the year ended
31 December 2022 were as follows:
|
Corporate
£'000s
|
Development and production £'000s
|
Exploration and appraisal £'000s
|
Total
£'000s
|
Other income
|
-
|
-
|
43
|
43
|
Reversal of impairment of
development assets and exploration costs
|
-
|
5,678
|
-
|
5,678
|
Administration expenses
|
(3,175)
|
-
|
-
|
(3,175)
|
Operating profit/(loss) segment
result
|
(3,175)
|
5,678
|
43
|
2,546
|
Interest receivable
|
13
|
-
|
-
|
13
|
Finance costs and exchange
adjustments
|
4,016
|
-
|
-
|
4,016
|
Profit/(loss) for the period before
taxation from continuing operations
|
854
|
5,678
|
43
|
6,575
|
The segments assets and liabilities
at 31 December 2022 were as follows:
|
Corporate
£'000s
|
Development and production £'000s
|
Exploration and appraisal £'000s
|
Total
£'000s
|
Non-current assets
|
944
|
167,346
|
35,988
|
204,278
|
Current assets
|
4,224
|
2,141
|
1,413
|
7,778
|
Liabilities attributable to
continuing operations
|
(23,024)
|
(8,301)
|
(2,646)
|
(33,971)
|
The geographical split of
non-current assets were as follows:
|
Europe
£'000s
|
Morocco
£'000s
|
Development and production
assets
|
-
|
163,074
|
Interest in Badile land
|
637
|
-
|
Fixtures, fittings and office
equipment
|
5
|
9
|
Right of use assets
|
274
|
-
|
Software
|
-
|
19
|
Prepayments
|
-
|
4,272
|
Exploration and evaluation
assets
|
-
|
35,988
|
Total
|
916
|
203,362
|
4.
Taxation
(a)
Analysis of the tax charge for the year:
|
2023
£'000s
|
2022
£'000s
|
Current tax
|
|
|
UK corporation tax
|
-
|
-
|
Adjustment to tax expense in respect
of prior years
|
(8)
|
(7)
|
Tax cases settlement (overseas
tax)
|
-
|
(1,595)
|
Total current tax (charge)/credit
|
(8)
|
(1,602)
|
Deferred tax credit arising in the
current year
|
-
|
-
|
Total tax (charge)/credit
|
(8)
|
(1,602)
|
(b)
Reconciliation of tax charge
|
2023
£'000s
|
2022
£'000s
|
(Loss)/profit before tax
|
(7,152)
|
6,575
|
Tax (charge)/credit charged at UK
corporation tax rate of 23.5% (2022: 19%)
|
1,681
|
(1,249)
|
Tax effect of:
|
|
|
Expenses not deductible for tax
purposes
|
(82)
|
(49)
|
Settlement of tax cases
|
-
|
(1,595)
|
Tax losses not recognised
|
(1,264)
|
1,276
|
Change in UK tax rate
|
(322)
|
-
|
Differences in overseas tax
rates
|
(21)
|
15
|
Total tax (charge)/credit
|
(8)
|
(1,602)
|
Deferred tax assets have not been
recognised in respect of tax losses available due to the
uncertainty of the utilisation of those assets. Unrecognised tax
losses as at 31 December 2023 were estimated to be approximately
£14.8 million (2022: £8.8 million).
The Group had tax cases where
Morocco Tax Authority had claimed taxes relating to the Group
historical permits transfers and intragroup transactions. In May
2023, the Company entered into a settlement agreement with Morocco
Tax Authority on a phased payment schedule back ended over 6 years.
The amount paid on entry into the settlement agreement was
approximately £126k (after taking account of exchange rate
movements). The discounted non-current liability amounted to
approximately £1.6 million as at 31 December 2023.
The table below sets out the current
and non-current tax liability and the movement during the
year.
|
2023
£'000s
|
2022
£'000s
|
Amounts due within one
year
|
199
|
126
|
Amounts due after more than one
year
|
1,410
|
1,505
|
|
1,609
|
1,631
|
The movement during the year is as
below:
|
|
|
As at 1 January
|
1,631
|
-
|
Tax settlement
|
-
|
1,631
|
Unwinding of discount
|
101
|
-
|
Tax payment
|
(126)
|
-
|
Exchange adjustment
|
3
|
-
|
As
at 31 December
|
1,609
|
1,631
|
5.
(Loss)/profit per share
The calculation of basic
profit/(loss) per ordinary share is based on the profit/(loss)
after tax and on the weighted average number of ordinary shares in
issue during the year. The calculation of diluted profit/(loss) per
share is based on profit/(loss) after tax on the weighted average
number of ordinary shares in issue, plus the weighted average
number of shares that would be issued if dilutive options and
warrants were converted into shares. Basic and diluted
profit/(loss) per share is calculated as follows:
|
2023
£'000s
|
2022
£'000s
|
Loss for the year after taxation
|
(7,160)
|
4,973
|
|
2023
Million
|
2022
Million
|
Basic weighted average shares in issue
|
1,882
|
1,752
|
Dilutive potential ordinary
shares
|
-
|
7
|
Diluted weighted average number of shares
|
1,882
|
1,759
|
|
2023
Pence
|
2022
Pence
|
Basic (loss)/profit per share
|
(0.38)
|
0.28
|
Diluted (loss)/profit per share
|
(0.38)
|
0.28
|
Due to loss during the year, the
effect of the potential dilutive shares on the earnings per share
would have been anti-dilutive and therefore were not included in
the calculation of the dilutive earnings per share. In 2022, LTIP
options awards and warrants totalling 138.8 million were all
anti-dilutive and were not included in the calculation of diluted
weighted average number of shares.
6.
Property, Plant and Equipment
|
Development and production assets
£'000s
|
Fixtures,
fittings and office equipment
£'000s
|
Right-of-use assets
£'000s
|
2023
£'000s
|
Cost
|
|
|
|
|
At 1 January 2023
|
163,074
|
656
|
331
|
164,061
|
Additions
|
2,737
|
2
|
-
|
2,739
|
Exchange adjustments
|
(7,995)
|
(14)
|
-
|
(8,009)
|
At 31 December 2023
|
157,816
|
644
|
331
|
158,791
|
Impairment and depreciation
|
|
|
|
|
At 1 January 2023
|
-
|
642
|
57
|
699
|
(Reversal)/charge for
period
|
-
|
4
|
173
|
177
|
Exchange adjustments
|
-
|
(12)
|
-
|
(12)
|
At 31 December 2023
|
-
|
634
|
230
|
864
|
Net book amount
|
157,816
|
10
|
101
|
157,927
|
|
Development and production assets
£'000s
|
Fixtures,
fittings and office equipment
£'000s
|
Right-of-use assets
£'000s
|
2022
£'000s
|
Cost
|
|
|
|
|
At 1 January 2022
|
144,735
|
626
|
-
|
145,361
|
Additions
|
1,597
|
4
|
331
|
1,932
|
Disposal
|
-
|
(3)
|
-
|
(3)
|
Exchange adjustments
|
16,742
|
29
|
-
|
16,771
|
At 31 December 2022
|
163,074
|
656
|
331
|
164,061
|
Impairment and
depreciation
|
|
|
|
|
At 1 January 2022
|
5,107
|
588
|
-
|
5,695
|
(Reversal)/charge for
period
|
(5,678)
|
30
|
57
|
(5,591)
|
Disposal
|
-
|
(2)
|
-
|
(2)
|
Exchange adjustments
|
571
|
26
|
-
|
597
|
At 31 December 2022
|
-
|
642
|
57
|
699
|
Net book amount
|
163,074
|
14
|
274
|
163,362
|
Change in estimate
The discount rate and forecast gas
price are significant estimates used by the Company to determine
the recoverable amount when undertaking impairment testing of the
Company's Tendrara Production Concession. The Company has taken
account of changes in market conditions and certain corporate
parameters during the period and accordingly revised the discount
rate to 11.25% as at 31 December 2023 from 12.5% at 31 December
2022. The Company at 31 December 2022 used an average of forecast
gas price referenced to the Title Transfer Facility (''TTF'') in
the Netherlands and the UK National Balancing Point (''NBP'') for
pricing the forecasted uncontracted gas sales volumes for
impairment testing. At 31 December 2023 the Company has used
average TTF prices only since future gas sales contracts the
Company is likely to enter into are expected to be priced in
reference to TTF and in addition, the Company received an
indicative non-binding gas pricing term sheet referenced to TTF.
For the impairment testing, the average TTF gas price projections,
from leading independent industry consultants, used for the period
to 2032 (and increasing at 2% inflationary rate thereafter) was
14.39 US$/MMBtu. The average TTF and NBP gas price projections for
the period to 2032 was 14.45 US$/MMBtu.
The Company's market capitalisation
was £14.0 million as at 31 December 2023, which is below the
Group's net assets of £166.8 million and the Company's net assets
of £156.8 million. An impairment indicator therefore exists. The
Company is pursuing a micro-LNG development (phase 1) followed by
full field development (phase 2) of its TE-5 Horst concession at
the Group's Tendrara permit and an impairment test was undertaken
on the carrying amount of the Tendrara Production Concession. The
Company used a DCF model ('Model'') to calculate the recoverable
amount for the Company's share of the Tendrara Production
Concession. The Model has an NPV of $214.3 million (£168.3 million)
which when compared to the carrying amount of the development
expenditure of £157.8 million indicated that no impairment was
required.
The Model covers the period 2024 to
2049. The input to the Model included a discount rate of 11.25% and
phase 1 gas price of $8.0 per mmbtu rising to the phase 1 gas price
ceiling of $8.346 per mmbtu, indexed using a combination of the TTF
and United States Henry Hub benchmark indexes. Phase 2 gas price
used is a fixed price for the first 10 years for annual volume of
0.3 bcm and the price for uncontracted volumes referenced to an
average forecast price of TTF and NBP with price range of US$12.10
per mmBTU in 2024 and $14.68 per mmBTU in 2033, increasing at 2%
per annum thereafter, consistent with published sources. The base
gas prices used are consistent with LNG GSA for the Phase 1
development and Phase 2 gas price is based on GSA signed with ONEE
for the first ten years. The production volumes data was based on
the 2018 CPR for Tendrara TE-5 Horst.
The well cost assumptions used were
based on management's past experience; mLNG plant leasing costs
were based on contract with the micro-LNG plant contractor; and
pipeline related costs were based on Head of Terms entered into
with a consortium of partners that had offered to provide a build,
own, operate and transfer (''BOOT'') solution for the Phase 2 of
the development. The Company's latest forecast covered the period
to 2027, but the model extends to 2049, as that is the period
required to produce the gas resources at Tendrara Production
Concession and the economic cut-off. A change in the discount rate
by 1% has a $23.2 million (£18.3 million) impact on the NPV and
change in average TTF and NBP forecast gas price by $1/bbl has a
$11.4 million (£9.0 million) impact on the NPV.
7.
Intangibles
|
Software
£'000s
|
Exploration &
Evaluation Assets
£'000s
|
2023
£'000s
|
Cost
|
|
|
|
At 1 January 2023
|
375
|
46,594
|
46,969
|
Additions
|
22
|
729
|
751
|
Exchange adjustments
|
(15)
|
(1,741)
|
(1,756)
|
At 31 December 2023
|
382
|
45,582
|
45,964
|
Impairment and depreciation
|
|
|
|
At the start of the year
|
356
|
10,606
|
10,962
|
Charge for the year
|
17
|
-
|
17
|
Exchange adjustments
|
(17)
|
-
|
(17)
|
At 31 December 2023
|
356
|
10,606
|
10,962
|
Net
book amount
|
26
|
34,976
|
35,002
|
|
Software
£'000s
|
Exploration & Evaluation Assets
£'000s
|
2022
£'000s
|
|
Cost
|
|
|
|
|
At 1 January 2022
|
352
|
42,204
|
42,556
|
|
Additions
|
23
|
813
|
836
|
|
Exchange adjustments
|
-
|
3,577
|
3,577
|
|
At 31 December 2022
|
375
|
46,594
|
46,969
|
|
Impairment and
depreciation
|
|
|
|
|
At the start of the year
|
352
|
10,606
|
10,958
|
|
Charge for the year
|
14
|
-
|
14
|
|
Exchange adjustments
|
(10)
|
-
|
(10)
|
|
At 31 December 2022
|
356
|
10,606
|
10,962
|
|
Net book amount
|
19
|
35,988
|
36,007
|
|
|
|
|
|
|
|
| |
Exploration and evaluation assets
Details regarding the geography of
the Group's E&E assets is contained in note 2. The Directors
assess for impairment when facts and circumstances suggest that the
carrying amount of an E&E asset may exceed its recoverable
amount. In making this assessment, the Directors have regard to the
facts and circumstances noted in IFRS 6 paragraph 20. In performing
their assessment of each of these factors, at 31 December 2023, the
Directors have:
a. reviewed the
time period that the Group has the right to explore the area and
noted no instances of expiration, or permits that are expected to
expire in the near future and not be renewed;
b. determined that
further E&E expenditure is either budgeted or planned for all
permits;
c. not decided to
discontinue exploration activity due to there being a lack of
quantifiable mineral resource; and
d. not identified any
instances where sufficient data exists to indicate that there are
permits where the E&E spend is unlikely to be recovered from
successful development or sale.
On the basis of the above
assessment, the Directors are not aware of any facts or
circumstances that would suggest the carrying amount of the E&E
asset may exceed its recoverable amount. During the year, the Group
had capitalised interest costs of approximately £0.3 million (2022:
£0.1 million).
8.
Prepayments
Non-current prepayment of £5.1 million (2022: £4.3 million)
and current prepayment of £1.3 million (2022; nil) relates to
activities of the Company's Phase 1 mLNG Project in the Concession.
Non-current prepayment of £5.1 million (2022: £4.3 million) and
current prepayment of £1.3 million (2022; nil) relates to
activities of the Company's Phase 1 mLNG Project in the
Concession.
9.
Capital and Reserves
|
2023
Number
of shares
|
£'000s
|
2022
Number
of
shares
|
£'000s
|
Ordinary shares - 1p
|
1,963,122,679
|
19,631
|
1,848,702,674
|
18,487
|
|
2023
Number
of shares
|
2022
Number
of
shares
|
At 1 January
|
1,848,702,674
|
1,629,183,907
|
Issued during the year for
cash
|
-
|
200,000,000
|
Non-cash share issue
|
114,420,005
|
19,518,767
|
At
31 December
|
1,963,122,679
|
1,848,702,674
|
The share
issues described below were all non-cash
transactions.
Share issues
In June 2023, the Company issued
11,404,221 shares to third parties in
settlement of services provided to the
Company amounting to approximately £0.2 million.
In July 2023, the Company issued 3,015,790
shares following the exercise of nil cost options
by a member of
staff.
In August 2023, the Company issued
22,222,221 shares following a partial conversion amounting to
£500,000 by the holders of the Company's £2.5 million convertible
bonds (''the convertible bonds'').
In September 2023, the Company
issued 22,222,221 shares following a partial conversion amounting
to £500,000 by the holders of the convertible bonds.
In October 2023, the Company issued
22,222,221 shares following a partial conversion amounting to
£500,000 by the holders of the convertible bonds.
In November 2023, the Company issued
22,222,221 shares following a partial conversion amounting to
£500,000 by the holders of the convertible bonds.
In December 2023, the Company issued
11,111,110 shares following a partial conversion amounting to
£250,000 by the holders of the convertible bonds.
Reserves
In 2018, the Company sought, and was
granted, a court order approving a capital reduction following the
cancellation of the share premium account. This resulted in the
transfer of £277.7 million to distributable reserves.
10.
Share based payments
|
2023
£'000s
|
2022
£'000s
|
Expense arising from equity settled
LTIP
|
239
|
159
|
Bonuses paid in shares and nil cost
options
|
-
|
810
|
|
239
|
969
|
LTIP Awards
In 2022, the
Company adopted a new long term incentive plan (the ''LTIP''),
designed to reward, incentivise and retain the Company's Executives
and senior management to deliver sustainable growth for
shareholders.
The maximum number of awards that
may be issued under the LTIP from time to time will be limited to
3% of the Company's issued share capital on the date of grant of
awards, and, together, with all other options issued by the Company
under any employee share scheme from time to time, will not exceed
an aggregate of 15% of the Company's issued ordinary share capital
in a rolling ten year period. Awards granted under the LTIP will,
generally, be subject to a three-year vesting period from the date
of grant, the number of awards, ultimately, vesting dependent on
the grantee's continued service and on additional performance
conditions set by the Remuneration Committee.
The Company issued 48,875,515
options to subscribe for new ordinary shares under the LTIP, out of
which 31,769,085 options were allocated to qualifying Executives
and senior management and the balance of 17,106,430 was retained
for future allocations. The LTIP awards are exercisable at 2.4
pence per share and expire ten years after the grant.
The fair
value of LTIP awards granted was estimated at the date of grant
using a Black-Scholes model, taking account of the terms and
conditions upon which, the awards were granted.
The expected
life of the LTIP award is based on the maximum award period and is
not necessarily indicative of exercise patterns that may occur.
Expected volatility was determined by reference to the historical
volatility of the Company's share price over a five-year period.
The expected volatility reflects the assumption that the historical
volatility is indicative of future trends, which may not
necessarily be the actual outcome. The valuation assumed an
expected life of ten years and used the following additional
assumptions for the LTIP awards granted during the year:
(i) Share price on grant
date: n/a (2022: 2.53 pence)
(ii) Average risk free interest
rate: n/a (2022: 1.79%)
(iii) Expected volatility:
n/a (2022: 99.11%)
(iv) Assumed forfeitures:
n/a (2022: 0%)
(v) Expected dividends:
n/a (2022: nil)
No other features of the LTIP awards
were incorporated into the measurement of fair value. The fair
value of the LTIP award granted was n/a
(2022: 2.26 pence). The remaining contractual life of
the LTIP awards outstanding at 31 December 2023 is 8.3 years. If all the 31,769,085 LTIP
awards were exercisable immediately, new ordinary shares equal to
approximately 1.6% (2022: 1.7%)
of the shares currently in issue, would be
created.
Share options
All previously outstanding share
options expired in 2022.
|
2023
Number
|
Weighted average exercise
price
Pence
|
2022
Number
|
Weighted
average exercise
price
Pence
|
Share options outstanding at the
start of the year
|
-
|
-
|
5,450,000
|
66.47
|
Share options granted
|
-
|
-
|
-
|
-
|
Share options expired
|
-
|
-
|
(5,450,000)
|
22.29
|
Share options exercised
|
-
|
-
|
-
|
-
|
Share options outstanding at the end
of the year
|
-
|
-
|
-
|
-
|
All RSU awards vested or
expired in 2022.
|
2023
Number
|
2022
Number
|
RSU awards outstanding at the start
of the year
|
-
|
1,165,400
|
Granted during the year
|
-
|
-
|
Expired during the year
|
-
|
(108,189)
|
Vested during the year
|
-
|
(1,057,211)
|
RSU awards outstanding at the end of
the year
|
-
|
-
|
The weighted average share price at
the date of vesting of the RSU awards was n/a (2022: 2.5 pence).
Warrants
As at 31
December 2023, the
Company had the following outstanding warrants to subscribe to the
Company's ordinary shares.
2023
|
Exercise
price
Pence
|
Expiry date
|
Number at
1 January
|
Granted
/(exercised)
|
Expired
|
Number at
31 December
|
2023 Warrants
|
2.25
|
13 June
2026
|
-
|
40,476,190
|
-
|
40,476,190
|
2022 Warrants
|
2.75
|
13 June
2025
|
7,056,875
|
-
|
-
|
7,056,875
|
2021 Warrants
|
2.75
|
21 December
2027
|
99,999,936
|
-
|
-
|
99,999,936
|
|
|
|
107,056,811
|
40,476,190
|
-
|
147,533,001
|
2022
|
Exercise
price
Pence
|
Expiry
date
|
Number
at
1
January
|
Granted
/(exercised)
|
Expired
|
Number
at
31
December
|
2022 Warrants
|
2.75
|
13 June
2025
|
-
|
7,056,875
|
-
|
7,056,875
|
2021 Warrants
|
2.75
|
21
December 2027
|
99,999,936
|
-
|
-
|
99,999,936
|
|
|
|
99,999,936
|
7,056,875
|
-
|
107,056,811
|
11.
Loans and borrowings
|
Secured
Bonds
£'000s
|
Loan note-
Afriquia
£'000s
|
Convertible
Bonds
£'000s
|
2023
Total
£'000s
|
Current liabilities
|
|
|
|
|
At
1 January
|
1,121
|
-
|
-
|
1,121
|
Reclassification to non-current liability
|
(1,121)
|
-
|
-
|
(1,121)
|
At
31 December
|
-
|
-
|
-
|
-
|
Non-current liabilities
|
|
|
|
|
At
1 January
|
20,855
|
8,213
|
-
|
29,068
|
Gross amount of loan drawdown during the
year
|
-
|
2,017
|
2,500
|
4,517
|
Amortised finance charges
|
890
|
532
|
-
|
1,422
|
Unwinding of discount
|
-
|
-
|
137
|
137
|
Interest payments
|
(441)
|
-
|
-
|
(441)
|
Gross equity component at date of issue
|
-
|
-
|
(562)
|
(562)
|
Debt conversion to equity
|
-
|
-
|
(1,046)
|
(1,046)
|
Exchange adjustments
|
(445)
|
(486)
|
-
|
(931)
|
Reclassification from current liabilities
|
1,121
|
-
|
-
|
1,121
|
At
31 December
|
21,980
|
10,276
|
1,029
|
33,285
|
|
Secured
bonds
£'000s
|
Loan note-
Afriquia
£'000s
|
Total
2022
£'000s
|
Current liabilities
|
|
|
|
At 1 January
|
-
|
-
|
-
|
Amount converted into ordinary
shares of the Company
|
-
|
-
|
-
|
Fair value of warrants
issued
|
-
|
-
|
-
|
Amortised finance charges
|
-
|
-
|
-
|
Interest payments
|
-
|
-
|
-
|
Exchange adjustments
|
-
|
-
|
-
|
Reclassification from/(to)
non-current liability
|
1,121
|
-
|
1,121
|
At 31 December
|
1,121
|
-
|
1,121
|
|
|
|
|
Non-current liabilities
|
|
|
|
At 1 January
|
20,039
|
-
|
20,039
|
Drawdown during the year
|
-
|
7,233
|
7,233
|
Amortised finance charges
|
1,245
|
324
|
1,569
|
Interest payments
|
(431)
|
-
|
(431)
|
Exchange adjustments
|
1,123
|
656
|
1,779
|
Reclassification (to)/from current
liabilities
|
(1,121)
|
-
|
(1,121)
|
At 31 December
|
20,855
|
8,213
|
29,068
|
The Company has €25.32 million
secured bonds (the "Bonds"). The Bonds mature on 21 December 2027.
The outstanding principal amount of the Bonds was initially
expected to partially repaid at a rate of 5% every six months,
commencing on 21 December 2023, but this requirement was removed in
early December 2023. Until maturity, the Bonds bear 2% cash
interest paid per annum and a 3% deferred interest per annum to be
paid at redemption. The Company has the right, at any time until 21
December 2024, to redeem the Bonds in full for 70% of the principal
value then outstanding together with any unpaid interest at the date of
redemption. The Company issued to the Bondholders 99,999,936
warrants to subscribe for new ordinary shares in the Company at an
exercise price of 2.75 pence per share. The warrants expire on 21
December 2027. The Bonds are secured on the issued share capital of
Sound Energy Morocco South Limited. After taking account of the
terms of the Bonds, the effective interest is approximately
6.5%.
The Company has drawn down $12.0
million from the Company's $18.0 million 6% secured loan note
facility with Afriquia Gaz maturing in December 2033 (the
''Loan''). The drawn down principal bears 6% interest per annum
payable quarterly, but deferred and capitalised semi-annually,
until the second anniversary of the issue of Notice to Proceed.
Thereafter, principal and deferred interest will be repayable,
annually, in equal installments commencing December 2028. The Loan
is secured on the issued share capital of Sound Energy Meridja
Limited. The weighted effective interest on the drawdowns made is
approximately 6.2%.
In June 2023, the Company issued
£2.5 million convertible bonds from a senior unsecured convertible
bond facility of up to £4.0 million. The £2.5 million Convertible
bonds have a fixed conversion price of 2.25 pence per ordinary
share. The term of the Convertible bonds is 5 years from drawdown
date, with interest of 15% per annum payable bi-annually in cash or
capitalised to the principal, at the Company's election.
Other key
terms of the Convertible bonds (''Bonds'') are:
1) Issue
price and redemption price on maturity is 100% of par
value;
2) Early
redemption/change of control: callable in cash by the Company at
any time after drawdown or in the event of a change of control of
the Company at 110% of par value together with all unpaid interest.
If the Bonds are redeemed by the Company, the maximum amount of
future interest payable by the Company in respect of any early
redemption occurring on or prior to the second anniversary will be
15% of the Bonds and after second anniversary, 10% of the
Bonds;
3) Convertible into the
Company's ordinary shares at the fixed conversion price. Upon
conversion, interest shall be rolled up and paid as if the Bonds
were held to the redemption date, with such interest convertible at
the lower of the applicable fixed conversion price and the average
of the 5 daily value weighted average price calculations selected
by the holder out of the 15 trading days prior to the conversion
date;
4) The Company issued to
Bonds holders 33,333,333 warrants to subscribe for new ordinary
shares in the Company at an exercise price of 2.25 pence per
ordinary share with a term of 3 years.
During the year, the Company issued
99,999,994 new shares following the conversion of £2,250,000 of the
Bonds. The carrying amount of the Bonds is stated at fair
value and is measured using the discounted cashflow method. A
discount rate of 17.7% was used to discount the outstanding
principal and capitalised interest over the outstanding term of the
bonds.
Reconciliation of liabilities arising from financing
activities
|
|
|
Non-cash
changes
|
|
2023
|
1 January
2023
£'000s
|
Cash flows
£'000s
|
Finance charges
£'000s
|
Exchange adjustments
£'000s
|
Convertible Bonds non-cash
movements
£'000s
|
31 December
2023
£'000s
|
Long-term borrowings
|
30,189
|
4,001
|
1,559
|
(931)
|
(1,533)
|
33,285
|
Leases
|
283
|
(180)
|
18
|
-
|
-
|
121
|
Total liabilities from financing activities
|
30,472
|
3,821
|
1,577
|
(931)
|
(1,533)
|
33,406
|
|
|
|
Non-cash
changes
|
|
2022
|
1
January 2022
£'000s
|
Cash flows
£'000s
|
Amortised
finance charges £'000s
|
Exchange
adjustments £'000s
|
Office
lease entry
£'000s
|
31
December 2022
£'000s
|
Long-term borrowings
|
20,039
|
6,802
|
1,569
|
1,779
|
-
|
30,189
|
Leases
|
-
|
(58)
|
10
|
-
|
331
|
283
|
Total liabilities from financing
activities
|
20,039
|
6,744
|
1,579
|
1,779
|
331
|
30,472
|
Reconciliation of finance expense
|
2023
£'000s
|
2022
£'000s
|
Amortised finance charges
|
1,422
|
1,569
|
Unwinding of discount
|
256
|
10
|
Bond issue costs expensed
|
601
|
-
|
Less capitalised interest
|
(285)
|
(133)
|
Total finance expense for the year
|
1,994
|
1,446
|
12.
Post Balance Sheet events
In March 2014, the Company announced
that receipt of conversion notices to issue 30 million new ordinary
shares (''Conversion Shares'') at a conversion price of 1 pence per
share under the terms of an existing Convertible Loan Note
Agreement (the ''Convertible Loan Note''). The Convertible Loan
Note has a remaining principal outstanding of £250,000 and the
issue of the Conversion Shares reduces the interest owing on the
converted portion of the Convertible Loan Notes by £300,000 to
£1,387,500. The Conversion Shares were admitted to trading on AIM
in April 2024.