MUMBAI, India, October 10, 2014 /PRNewswire/ --
Q2 Highlights
- Zinc-India: Production volumes
improving in line with mine-plan; higher mined metal expected in
H2
- Oil & Gas: Rajasthan production normalised after successful
completion of planned maintenance shut down at Mangala Processing
Terminal
- Aluminium: First phase of 50 pots of 1.25 mtpa Jharsuguda-II
pot-lines commenced start up
- Copper India: Operating at
high efficiency following planned maintenance shutdown in Q1
(Logo:
http://photos.prnewswire.com/prnh/20140117/663814 )
Oil and Gas
Q2 Q1 H1
% change % change
Particulars FY2015 FY2014 YoY FY2015 FY2015 FY2014 YoY
OIL AND GAS (boepd)
Average Daily Total Gross
Operated Production
(boepd) - including
internal gas consumption 204,128 221,190 (8%) 226,597 215,301 220,884 (3%)
Average Daily Gross
Operated Production
(boepd) 194,508 213,299 (9%) 217,869 206,125 212,873 (3%)
Rajasthan 163,262 175,478 (7%) 183,164 173,158 174,503 (1%)
Ravva 20,596 29,151 (29%) 23,940 22,259 28,704 (22%)
Cambay 10,651 8,671 23% 10,765 10,708 9,666 11%
Average Daily Working
Interest Production
(boepd) 123,178 132,862 (7%) 137,907 130,502 132,477 (1%)
Rajasthan 114,283 122,835 (7%) 128,215 121,211 122,152 (1%)
Ravva 4,634 6,559 (29%) 5,386 5,008 6,458 (22%)
Cambay 4,260 3,468 23% 4,306 4,283 3,866 11%
Total Oil and Gas
Production (million boe)
Oil & Gas- Gross 17.89 19.62 (9%) 19.83 37.72 38.96 (3%)
Oil & Gas-Working
Interest 11.33 12.22 (7%) 12.55 23.88 24.24 (1%)
Average gross production for H1 FY2015 was 206,125 barrels of
oil equivalent per day (boepd), 3% lower than the previous year due
to the planned maintenance shutdown at the Rajasthan facilities and
a suspension of gas sales at the Ravva block, partially offset by
higher production at the Cambay block.
In Q2 FY2015, average gross operated production and working
interest production were 9% and 7% lower year on year (yoy) at
194,508 boepd and 123,178 boepd, respectively. At Rajasthan, we
successfully completed the planned shutdown announced in Q1, for
routine operational and statutory maintenance activity at the
Mangala Processing Terminal, which resulted in lower production of
163,262 boepd, with Development Area (DA)-1 and DA-2 producing
gross averages of 134,539 boepd and 28,723 boepd respectively. We
are back to normal production levels at Rajasthan after the
shutdown; excluding the shutdown period, Q2 production was
comparable to Q1. We also utilized this opportunity to tie-in new
facility enhancements related to development projects.
At Ravva, gas sales have been suspended since 4 July 2014 on account of one of the customers
undertaking a major unplanned maintenance activity within their
Andhra Pradesh pipeline network. Hence, production at Ravva was
lower at 20,596 boepd during the quarter despite a positive oil
contribution from the 4D infill well campaign.
At Cambay, production increased by 23% yoy at 10,651 boepd
during Q2 on account of successful well intervention measures
undertaken in the previous quarter.
Zinc India
Q2 Q1 H1
Particulars (in'000 tonnes, or % change % change
as stated) FY2015 FY2014 YoY FY2015 FY2015 FY2014 YoY
Mined metal content 213 222 (4%) 163 376 459 (18%)
Refined Zinc - Total 181 196 (8%) 141 321 370 (13%)
Refined Zinc - Integrated 174 195 (11%) 139 312 368 (15%)
Refined Zinc - Custom 7 1 - 2 9 2 -
Refined Lead - Total [1] 30 30 - 31 61 61 -
Refined Lead - Integrated 26 29 (12%) 22 47 56 (16%)
Refined Lead - Custom 5 1 - 9 14 5 -
Saleable Silver - Total (in
tonnes) [2] 80 90 (11%) 82 162 186 (13%)
Saleable Silver - Integrated (in
tonnes) 67 83 (19%) 56 123 160 (23%)
Saleable Silver - Custom (in
tonnes) 13 6 27 39 26
During Q2, mined metal production was 30% higher than Q1, but 4%
lower than the corresponding prior quarter. This is in line with
our mine plan at Rampura Agucha mine (RAM), of lower mined metal
production in the first half of the year as we excavated more waste
than ore and exposed the ore body by end September, which will
contribute to higher volumes in the second half of the year.
Integrated production of refined zinc, lead and silver was lower
than the corresponding prior period due to lower mined metal
production and smelter shutdown.
Zinc International
Q2 Q1 H1
%
Particulars (in'000 tonnes, or as % change change
stated) FY2015 FY2014 YoY FY2015 FY2015 FY2014 YoY
Zinc International 79 106 (26%) 84 163 196 (17%)
Refined Zinc - Skorpion 27 35 (22%) 33 60 69 (13%)
Mined metal content - BMM and
Lisheen 52 71 (27%) 51 103 127 (19%)
Refined zinc metal production at Skorpion was lower than the
corresponding prior quarter due to unplanned maintenance activities
at the mill. Zinc-lead mined metal production was lower mainly at
Lisheen due to lower grades as per mine plan sequencing.
Iron Ore
Q2 Q1 H1
Particulars (in million dry % change % change
metric tonnes, or as stated) FY2015 FY2014 YoY FY2015 FY2015 FY2014 YoY
IRON ORE
Sales 0.6 - - 0.5 1.1 - -
Goa - - - - - - -
Karnataka 0.6 - - 0.5 1.1 - -
Production of Saleable Ore 0.3 - - - 0.3 - -
Goa - - - - - - -
Karnataka 0.3 - - - 0.3 - -
Production ('000 tonnes)
Pig Iron 154 129 19% 146 300 238 26%
At Karnataka, we had resumed production in December 2013 and since then we have produced 1.8
mt and sold 1.08 mt through e-auctions till 30 September 2014, of which 0.3mt production and
0.6mt sales were in Q2 FY2015. The mine is currently not producing
or selling ore since August 2014 and
is awaiting forest clearance and mining lease renewal, which is
expected to be received in Q3. Overall, we expect to produce at our
provisional annual capacity of 2.29 million tonnes during the year.
At Goa, the State Cabinet has
approved a new policy for grant of mining leases in October. The
policy states that the leases will be categorized and renewed and
will not be auctioned. Earlier, the High Court of
Bombay at Goa had directed the State Government to renew
mining leases for the mines that have paid the stamp duty, and we
expect the mining in Goa to resume
in Q4 FY2015.
Production of pig iron was 19% higher as compared to
corresponding prior quarter as production ramped up.
At Liberia, most of our
leadership team has been temporarily moved out of the country and
we continue to monitor the Ebola epidemic. The local government is
focused on containing the situation and we expect to resume working
with the government on infrastructure solutions for an early phase
mining operation once the situation is normalised.
Copper ― India and
Australia
Q2 Q1 H1
Particulars (in'000 tonnes, % change % change
or as stated) FY2015 FY2014 YoY FY2015 FY2015 FY2014 YoY
Copper - Mined metal content - 6 - - - 12 -
Copper - Cathodes 100 82 22% 66 166 98 70%
Tuticorin Power Plant Sales
(MU) 183 158 16% 136 319 295 8%
Copper cathode production was 22% higher than the corresponding
prior period with the Tuticorin smelter delivering record
production since its planned shutdown in Q1. In Q2, we delivered
strong operational efficiency and we expect to produce at over 90%
utilizations going forward.
The 160MW power plant at Tuticorin continued to operate
efficiently at a Plant Load Factor (PLF) of 94% in Q2 and 82% in
H1.
As previously announced, our Australian mine was put on care and
maintenance in July. We continue to progress on reviewing the
technical and economic feasibility of a program for additional
exploration to enable re-opening after FY 2016.
Aluminium
Q2 Q1 H1
Particulars (in'000 tonnes, % change % change
or as stated) FY2015 FY2014 YoY FY2015 FY2015 FY2014 YoY
Alumina - Lanjigarh 226 116 96% 233 460 116 -
Total Aluminum Production 222 200 11% 203 424 395 7%
Jharsuguda-I 138 137 1% 132 270 271 -
245kt Korba-I 65 63 3% 60 125 124 1%
325kt Korba- II [3] 19 - - 11 29 - -
The Lanjigarh alumina refinery operated above 90% of its rated
capacity and produced 226,000 tonnes in Q2. The numbers for the
corresponding prior period are not comparable as the plant
restarted in July last year and ramped up thereafter.
In Q2, production at the 500kt Jharsuguda-I & 245kt Korba-I
smelters remained stable and above rated capacities despite
incidences of grid failures. We have realised healthy premiums
during the quarter. The continued challenges to coal
availability in the country due to lower volumes of e-auction coal,
rail logistics constraints and increased reliance on imports
continue to adversely impact costs. Due to low coal
availability, we resorted to some temporary power purchases at
Korba-I during the quarter. We expect this challenging environment
for coal availability to continue in the short term till it is
alleviated by government policy interventions.
The 84 pots at the 325kt Korba-II smelter ramped up and were
capitalized from beginning of September. During the quarter, it
produced 19,000 tonnes, of which 13,000 tonnes were under trial
runs. We will further ramp up the smelter to full capacity
subsequent to the commissioning of the 1,200 MW power plant, for
which we are working on the final stages of regulatory
approvals.
We have commenced the start up of the first phase of 50 pots of
the 1.25 mtpa Jharsuguda II pot-lines and will ramp-up using
surplus power from the 1,215 MW power plant.
In September 2014, the Supreme
Court of India passed a judgment
cancelling 214 coal block allocations since 1993, which included
our coal block at BALCO. This block was at advanced stages of
approvals but not commenced mining. We await further government
action to deal with this matter.
Power
Q2 Q1 H1
% %
change change
Particulars (in million units) FY2015 FY2014 YoY FY2015 FY2015 FY2014 YoY
Total Power Sales 2,028 1,910 6% 2,599 4,627 5,087 (9%)
Jharsuguda 2400 MW 1,653 1,494 11% 2,154 3,807 4,098 (7%)
MALCO 204 221 (8%) 229 433 445 (3%)
HZL Wind Power 170 151 13% 146 316 313 1%
BALCO 270MW Power 1 44 (98%) 70 71 231 (69%)
The Jharsuguda 2,400MW power plant operated at a PLF of 38% in
Q2, which was higher than Q2 FY2014 but lower than Q1 FY2015,
largely due to operational issues with one of the four 600MW units,
which has now been rectified. Power from the BALCO 270MW power
plant was primarily used to ramp up 84 pots of the 325kt Korba-II
smelter.
The first 660MW unit of the Talwandi Sabo power plant is
currently under commissioning and its reliability run is expected
to take place in Q3. During the quarter, unprecedented rainfall
resulted in breach of an irrigation canal nearby and flooding of
the plant premises, and we are implementing a durable solution to
prevent future incidences.
Production Summary (Unaudited)
(in '000 tonnes, except as stated)
Q2 Q1 H1
% change % change
Particulars FY2015 FY2014 YoY FY2015 FY2015 FY2014 YoY
OIL AND GAS (boepd)
Average Daily Total Gross
Operated Production
(boepd) - including
internal gas consumption 204,128 221,190 (8%) 226,597 215,301 220,884 (3%)
Average Daily Gross
Operated Production
(boepd) 194,508 213,299 (9%) 217,869 206,125 212,873 (3%)
Rajasthan 163,262 175,478 (7%) 183,164 173,158 174,503 (1%)
Ravva 20,596 29,151 (29%) 23,940 22,259 28,704 (22%)
Cambay 10,651 8,671 23% 10,765 10,708 9,666 11%
Average Daily Working
Interest Production
(boepd) 123,178 132,862 (7%) 137,907 130,502 132,477 (1%)
Rajasthan 114,283 122,835 (7%) 128,215 121,211 122,152 (1%)
Ravva 4,634 6,559 (29%) 5,386 5,008 6,458 (22%)
Cambay 4,260 3,468 23% 4,306 4,283 3,866 11%
Total Oil and Gas
Production (million boe)
Oil & Gas- Gross 17.89 19.62 (9%) 19.83 37.72 38.96 (3%)
Oil & Gas-Working
Interest 11.33 12.22 (7%) 12.55 23.88 24.24 (1%)
ZINC INDIA
Mined metal content 213 222 (4%) 163 376 459 (18%)
Refined Zinc - Total 181 196 (8%) 141 321 370 (13%)
Refined Zinc - Integrated 174 195 (11%) 139 312 368 (15%)
Refined Zinc - Custom 7 1 - 2 9 2 -
Refined Lead - Total [1] 30 30 - 31 61 61 -
Refined Lead - Integrated 26 29 (12%) 22 47 56 (16%)
Refined Lead - Custom 5 1 - 9 14 5 -
Saleable Silver - Total
(in tonnes) [2] 80 90 (11%) 82 162 186 (13%)
Saleable Silver -
Integrated (in MT) 67 83 (19%) 56 123 160 (23%)
Saleable Silver - Custom
(in MT) 13 6 - 27 39 26 -
ZINC INTERNATIONAL 79 106 (26%) 84 163 196 (17%)
Refined Zinc - Skorpion 27 35 (22%) 33 60 69 (13%)
Mined metal content - BMM
and Lisheen 52 71 (27%) 51 103 127 (19%)
IRON ORE
Sales 0.6 - - 0.5 1.1 - -
Goa - - - - - - -
Karnataka 0.6 - - 0.5 1.1 - -
Production of Saleable
Ore 0.3 - - - 0.3 - -
Goa - - - - - - -
Karnataka 0.3 - - - 0.3 - -
Production ('000 tonnes)
Pig Iron 154 129 19% 146 300 238 26%
COPPER INDIA & AUSTRALIA
Copper - Mined metal
content - 6 - - - 12 -
Copper - Cathodes 100 82 22% 66 166 98 70%
Tuticorin Power Plant
Sales (MU) 222 158 40% 136 358 295 21%
(in '000 tonnes, except as stated)
Q2 Q1 H1
% change % change
Particulars FY2015 FY2014 YoY FY2015 FY2015 FY2014 YoY
ALUMINIUM
Alumina - Lanjigarh 226 116 96% 233 460 116 -
Total Aluminum Production 222 200 11% 203 424 395 7%
Jharsuguda-I 138 137 1% 132 270 271 -
245kt Korba-I 65 63 3% 60 125 124 1%
325kt Korba- II [3] 19 - - 11 29 - -
POWER
Total Power Sales 2,028 1,910 6% 2,599 4,627 5,087 (9%)
Jharsuguda 2400 MW 1,653 1,494 11% 2,154 3,807 4,098 (7%)
MALCO 204 221 (8%) 229 433 445 (3%)
HZL Wind Power 170 151 13% 146 316 313 1%
BALCO 270MW Power 1 44 (98%) 70 71 231 (69%)
Ports - VGCB (in million
tonnes) [4]
Cargo Discharge 1.7 0.9 98% 1.8 3.5 2.0 77%
Cargo Dispatches 1.8 0.9 105% 1.7 3.5 1.9 87%
- Excluding captive consumption of 1,762 tonnes in Q2 FY2015
vs. vs. 1,700 tonnes in Q2 FY2014 and 3,451 tonnes in H1 FY 2015
vs. 3,344 tonnes in H1 FY2014
- Excluding captive consumption of 9.1 tonnes in Q2 FY2015 vs.
9.0 tonnes in Q1 FY2014 and 17.8 tonnes in H1 FY2015
vs. 17.8 tonnes in H1 FY2014
- Trial run production of 13 kt in Q2 FY2015 and 23 kt in H1
FY2015 from Korba II 325 kt smelter
- VGCB refers to Vizag General Cargo Berth
About Sesa Sterlite Limited
Sesa Sterlite Limited ("Sesa Sterlite") is one of the world's
largest diversified natural resources companies. Our business
primarily involves exploring, extracting and processing minerals
and oil & gas. We produce oil & gas, zinc, lead, silver,
copper, iron ore, aluminium and commercial power and have a
presence across India,
South Africa, Namibia, Ireland, Australia, Liberia and Sri
Lanka. Sesa Sterlite has a strong position in emerging
markets with over 80% of its revenues from India, China,
East Asia, Africa and the Middle East.
Sustainability is at the core of Sesa Sterlite's strategy, with
a strong focus on health, safety and environment and on enhancing
the lives of local communities.
Sesa Sterlite is a subsidiary of Vedanta Resources plc, a
London-listed company. Sesa
Sterlite is listed on the Bombay Stock Exchange and the National
Stock Exchange in India and has
ADRs listed on the New York Stock Exchange.
Disclaimer
This press release contains "forward-looking statements" - that
is, statements related to future, not past, events. In this
context, forward-looking statements often address our expected
future business and financial performance, and often contain words
such as "expects," "anticipates," "intends," "plans," "believes,"
"seeks," "should" or "will." Forward-looking statements by their
nature address matters that are, to different degrees, uncertain.
For us, uncertainties arise from the behaviour of financial and
metals markets including the London Metal Exchange, fluctuations in
interest and or exchange rates and metal prices; from future
integration of acquired businesses; and from numerous other matters
of national, regional and global scale, including those of a
political, economic, business, competitive or regulatory nature.
These uncertainties may cause our actual future results to be
materially different that those expressed in our forward-looking
statements. We do not undertake to update our forward-looking
statements.
For further information, please
contact:
Communications
Roma
Balwani
Executive Vice President -
Group Communications & CSR
Tel: +91-22-6646-1330
gc@vedanta.co.in
Investor Relations
Ashwin
Bajaj
Senior Vice President - Investor Relations
Sheetal
Khanduja
Associate General Manager - Investor Relations
Tel: +91-22-6646-1531
sesasterlite.ir@vedanta.co.in
SOURCE Sesa Sterlite Limited