For immediate release
22
March 2023
Serabi Gold
Plc (“Serabi” or the
“Company”)Coringa
Project Update
Serabi Gold plc (AIM:SRB, TSX:SBI), the
Brazilian-focused gold mining and development company,
is pleased to provide an update on progress at its Coringa
project(“the Project”) located in
the Tapajos region of Para, Brazil.
Highlights
- Imminent
completion and submission of the Indigenous Impact Study (“ECI”) to
FUNAI, a key outstanding component for the award of the
Installation Licence (“LI”) by SEMAS
- Serabi plans
to install a crusher and ore-sorter at Coringa (a “classification
plant”) as an interim step ahead of a full processing plant at a
later date
- The Coringa
ore is highly amenable to ore-sorting, and the classification plant
will significantly reduce the amount of initial capital expenditure
required to achieve consolidated group production of approximately
60,000 ounces per annum without the requirement for plant expansion
at Palito and with gold production and tailings consolidated at a
single site
Michael Hodgson, CEO of Serabi
commented,
“We have been continuing to make steady progress
at Coringa both with our production activities and the advancement
of the licencing process and this update provides a summary of the
activities over the past six months and our plans going forward. I
am pleased to advise the imminent completion of the Indigenous
Impact Study that we initially commissioned at the beginning of
2022. Whilst progress has been slower than we were originally led
to believe, the final report is expected to be available to be
presented to the authorities for their review in the next few
weeks. This report should allow the authorities to move forward
with the final analysis culminating in approval of our application
for an Installation Licence (“LI”), which in turn allows us to
install a full process plant at Coringa in due course.
“As previously advised, we produced 1,103 ounces
from Coringa during the period July 2022 to December 2022 by
trucking high grade ore from Coringa to our Palito operation for
processing. We are continuing this activity during 2023. Ore
sorting test work on the Coringa ore has produced excellent results
with between 45% and 50% reduction in the mass needing to be
processed. Whilst we remain in the early stages of the development
of Coringa it is therefore our intention to install a crushing and
ore-sorting plant at Coringa as a Stage 1 of a plant installation
and continue to truck the upgraded ore to Palito for processing. We
view this as an attractive option for shareholders as it will
minimise the initial capital requirements for the on-going
development and allow a future installation of a full processing
plant to be supported by the cash flow from a larger production
operation. Our internal assessment, based on the ore-sorting
results obtained to date, is that gold production from a combined
Palito Complex and Coringa operation could reach approximately
60,000 ounces per annum without the need for significant expansion
of the existing plant at Palito.”
Indigenous Impact Study
(“ECI”)
Brandt Meio Ambiente (“Brandt”) were engaged by
the Company, in January 2022, to undertake the Indigenous Impact
Study (“ECI”) on behalf of Serabi. The scope of work was
established in co-operation with FUNAI, (‘Fundação Nacional dos
Povos Indígenas’ or ‘National Indigenous People Foundation’) the
government agency for Indigenous Communities. who are, by law,
responsible for, and required to be involved in, any consultation
process with an indigenous community. Upon agreement FUNAI then
co-ordinated meetings with the various tribes of the BAU Indigenous
Territories (“Bau TI”) to confirm the programme and the approach.
FUNAI approved the programme in May 2022 with the communities
confirming their approval and granting access for interviews in
September 2022. Researchers undertook the necessary interviews and
other field work in November and December 2022.
The researchers are now in the final stages of
preparing their report, which will be presented to the indigenous
communities, for their review and approval. It is expected that
these meetings can be arranged to take place in late April, early
May. Following approval by the indigenous communities, the ECI will
be shared with FUNAI for final approval, which we believe should
take place within a further period of one month.
Operational Update
As previously notified on 17 January 2023,
during 2022 the Company recovered 1,103 ounces of gold from ore
mined at Coringa having commenced processing of ore in July 2022.
The highest grade ore is being transported from Coringa to the
Palito Complex for processing. This initial mining activity has
provided bulk samples for ore-sorting test work which has been very
successful in the elimination of waste material from the ore being
mined from development. Following elimination of low grade waste
the mass is being reduced by up to 50% with a corresponding uplift
in the grade of the resulting ore stockpile. As a result, the
Company intends to install, as Stage 1 of the process plant
construction, a crushing and ore sorting plant at Coringa and will
continue to truck the upgraded ore to Palito for processing.
Internal studies indicate that gold production from a combined
Palito Complex and Coringa operation could reach approximately
60,000 ounces per annum without the need for significant expansion
of the existing plant at Palito. This option allows for a faster
and cheaper ramp up of production at Coringa compared with the
construction of the full process plant from the outset and reduces
the initial capital cost required to build production from Coringa
to an annual rate of 30,000 to 35,000 ounces. A full-scale process
plant can be installed subsequently but its cost should also be
supported by the cash flow generated from a larger production
base.
Licencing
Coringa is currently operating under the
authorisation of a trial mining licence or Guia de Utilização
(“GUIA”) issued by the national mining agency (“ANM”) and an GUIA
Operating Licence (“LOG”) issued by the state environmental agency
(“SEMAS”). The court decision issued in December 2021 (see news
release of 9 December 2021) which was upheld in August 2022
following appeals lodged by each of the ANM, SEMAS and the Company
(see news release 23 August 2022) did not affect the validity of
the GUIA and the LOG and the Company has therefore been able to
continue its operations under these licenses. The court’s decision
only suspended the issuing of new licences i) until a consultation
as per ILO Convention 169, has been made with the indigenous people
or ii) where the issuing authority can demonstrate unequivocally
the absence of impact to the Bau TI in respect of the activity
being authorised under that specific licence. With the ECI now
reaching completion and to be passed to FUNAI and in turn the other
interested parties for their review, the Company expects the
Installation Licence to be issued in the coming months. The Company
anticipates that the issuing of the LI will be the trigger for
being able to start the next stage of expanding the mining
operations at Coringa.
Brazilian law also provides for automatic
extension of the GUIA and LOG if a formal renewal has not been
issued at the date of their initial expiry, provided that renewal
applications have been submitted prior to the expiry date within
the stipulated time frame or until the issuing authority provides a
notification that it does not intend to grant the renewal. The
Company confirms that renewal applications have been submitted
within the stipulated time frames and that no notifications have
been received from the issuing authorities that renewal will not be
approved. Accordingly, these licences, which had an initial expiry
date of 8 August 2022, remain valid.
Environmental and
Social
As previously reported, in connection with the
licencing process for the Project, in February 2020, the Company
held a public hearing attended by approximately 600 people
including more than 100 members of the indigenous tribes. The
hearing was held in the town of Novo Progresso, the nearest major
town to the Project. The location was selected by SEMAS who had
responsibility for arranging this to ensure that the widest
possible consultation could occur. In the plans for the Project
presented at this meeting the Company had replaced the use of
conventional “wet mine tailings dams” with a procedure that
involves drying the processed tailings prior to these being safely
stored as dry tailings. The Project is located close to a tributary
that feeds into the Curuá River and the use of dry tailings was
expected to minimise any concerns of the communities that are
dependent on the Curuá River regarding the potential for pollution.
With the decision to introduce an ore sorter, no processed tailings
will be produced during Stage 1 of the Project when material is
being transported to Palito for processing. The ore sorter works by
separating ore from waste based on colour. It is therefore a
physical process with no chemicals involved, and therefore
completely eliminates the possibility for unnatural or contaminated
materials to enter any water course of the Curuá River.
The Coringa mine is located more than 11 kilometres from the
boundaries of the Bau indigenous territories and over 20 kilometres
a from the Curuá River itself. The nearest villages are located
over 30 kilometres from the Coringa mine.
From the beginning of its activities in the
region, the Company has held meetings with the indigenous
communities, along with the Institute Kabu and the Mantinó
Association, which both represent the tribes within the Baú TI.
Land Rights
Land Rights are governed by INCRA, the national
agency for land ownership. The Brazilian Mining Code provides
protection for mining companies and land access rights by providing
a legal process to enforce land access for mining activity where
the company has been granted a permit by the ANM and also holds the
proper environmental permit. Despite this, land possession in the
area where the Coringa Project is located has been subject to
various challenges over the years. The Company has been in regular
contact with INCRA since acquiring the Project in 2017. Pending
completion of the proper legal administrative process overseen by
INCRA to determine the legitimate title holder, all royalties due
to the relevant landowner are currently being provided for by the
Company and payment will be made to the appropriate title holder as
and when title is formally confirmed.
The information contained within this
announcement is deemed by the Company to constitute inside
information as stipulated under the Market Abuse Regulations (EU)
No. 596/2014 as it forms part of UK Domestic Law by virtue of the
European Union (Withdrawal) Act 2018.
The person who arranged for the release of this
announcement on behalf of the Company was Clive Line, Director.
Enquiries:
Serabi Gold plc |
|
Michael Hodgson |
Tel: +44 (0)20 7246 6830 |
Chief Executive |
Mobile: +44 (0)7799 473621 |
|
|
Clive Line |
Tel: +44 (0)20 7246 6830 |
Finance Director |
Mobile: +44 (0)7710 151692 |
|
|
Email: contact@serabigold.com |
|
Website: www.serabigold.com |
|
|
|
Beaumont Cornish LimitedNominated Adviser and
Financial Adviser |
|
Roland Cornish / Michael Cornish |
Tel: +44 (0)20 7628 3396 |
|
|
Peel Hunt LLPJoint UK Broker |
|
Ross Allister |
Tel: +44 (0)20 7418 9000 |
|
|
Tamesis Partners LLPJoint UK Broker |
|
Charlie Bendon / Richard Greenfield |
Tel: +44 (0)20 3882 2868 |
|
|
Camarco Financial
PR |
|
Gordon Poole / Emily Hall |
Tel: +44(0) 20 3757 4980 |
A copy of this announcement is available from the Company’s
website at www.serabigold.com
Neither the Toronto Stock Exchange, nor any
other securities regulatory authority, has approved or disapproved
of the contents of this announcement.
See
www.serabigold.com for more information
and follow us on twitter @Serabi_Gold
ENDS
Serabi Gold (TSX:SBI)
Historical Stock Chart
From Dec 2024 to Jan 2025
Serabi Gold (TSX:SBI)
Historical Stock Chart
From Jan 2024 to Jan 2025