QUARTERLY UPDATE TO 30 September 2023

Metals Exploration plc (AIM: MTL) ("Metals Exploration", the "Company" or the "Group"), a gold producer in the Philippines, is pleased to announce its quarterly results for Q3 2023.

Finance and corporate

Ø Gold revenue of US$42.4 million (Q2 2023: US$49.1 million).

Ø Gold sales of 22,043 ounces sold at an average realised gold price of US$1,926 per ounce (Q2 2023: 24,744 ounces at an average US$1,984 per ounce).

Ø Positive free cash flow of US$19.0 million (Q2 2023: US$24.1 million).

Ø Elevation of mezzanine debt to secured status is progressing to execution stage, however uncertainty remains over the interest rate, as well as the date of its application, which will be applied to the outstanding loan in the period prior to completion of the elevation.

Ø Mezzanine debt repayments of US$18.5 million (Q2 2023: US$20.7 million).

Ø Net debt as at 30 September 2023 was US$30.6 million (30 June 2023: US$48.3 million).

Mining Operations

Ø No lost time injuries occurred during the period - over 20 million hours worked without a reportable injury .

Ø Mining production of ore and waste was above forecast at 3.30Mt (Q2 2023: 3.49Mt), with a total of 568Kt of ore mined in Q3 2023 (Q2 2023: 566Kt).

Processing Operations

Ø Gold production of 22,034 ounces (Q2 2023: 24,235 ounces) recovered from 483Kt at a head grade of 1.60g/t (Q2 2023: 522Kt at a head grade of 1.66g/t).

Ø Gold recovery of 88.7% (Q2 2023: 86.9%).

Darren Bowden, CEO of Metals Exploration, commented :

"This has been another very strong operational quarter at Runruno with mining production above forecast with excellent gold recovery in our processing operations. Although a lower head grade is expected in the remaining quarter of the year we look forward to a strong finish to the year; whilst maintaining focus on our exceptional health and safety standards. I would also like to congratulate the team for being nominated as the Philippines national representative in the Association of Southeast Asian Nations ("ASEAN") mining industry awards in both the mining and processing categories; and further being shortlisted in the final three candidates in both categories."

Production and Finance Summary

 
 Runruno Project 
  Report                                     Quarter              Quarter             FY 2023              FY 2022 
                                          ----------  -------------------  ------------------  ------------------- 
 FY 2023                                      Actual               Actual              Actual               Actual 
                                          ----------  -------------------  ------------------  ------------------- 
 PHYSICALS                    Units          Q3 2023              Q3 2022            9 Months             9 Months 
                          -------------               -------------------                      ------------------- 
 Mining 
                          -------------               -------------------                      ------------------- 
   Ore Mined                  Tonnes         567,816              380,071           1,415,839            1,669,194 
                          --------------              -------------------                      ------------------- 
   Waste Mined                Tonnes       2,731,344            3,264,442           8,117,273            7,212,607 
                          --------------              -------------------                      ------------------- 
   Total Mined                Tonnes       3,299,160            3,644,513           9,533,112            8,881,802 
                          --------------              -------------------                      ------------------- 
   Au Grade Mined             g/tonne           1.49                 1.49                1.55                 1.19 
                          --------------              -------------------                      ------------------- 
   Strip Ratio                                  4.48                 8.57                5.43                45.24 
                                                      -------------------                      ------------------- 
 Processing 
                          -------------               -------------------                      ------------------- 
   Ore Milled                 Tonnes         482,743              455,907           1,551,133            1,473,165 
                          --------------              -------------------                      ------------------- 
   Au Grade                   g/tonne           1.60                 1.26                1.51                 1.15 
                          --------------              -------------------                      ------------------- 
   S(2) Grade                    %              1.46                 1.80                1.43                 1.23 
                          --------------              -------------------                      ------------------- 
   Au Milled (contained)      Ounces          24,850               18,541              75,551               54,283 
                          --------------              -------------------                      ------------------- 
   Recovery                      %              88.7                 84.8                89.4                 86.7 
                          --------------              -------------------                      ------------------- 
   Au Recovered/Poured        Ounces          22,034               15,715              67,568               47,063 
                          --------------              -------------------                      ------------------- 
 Sales 
                          -------------               -------------------                      ------------------- 
   Au Sold                    Ounces          22,043               14,980              68,230               45,641 
                          --------------              -------------------                      ------------------- 
   Au Price                   US$/oz           1,926                1,714               1,935                1,825 
                          --------------              -------------------                      ------------------- 
 FINANCIALS (Unaudited) 
------------------------  -------------               -------------------                      ------------------- 
 Revenue 
                          -------------               -------------------                      ------------------- 
   Gold Sales               (US$000's)        42,448               25,676             131,999               83,298 
                          --------------              -------------------                      ------------------- 
 Operating Costs 
  - Summary 
                          -------------               -------------------                      ------------------- 
   Mining                   (US$000's)         5,280                5,907              15,747               19,214 
                          --------------              -------------------                      ------------------- 
   Processing               (US$000's)         8,322                7,675              26,135               21,971 
                          --------------              -------------------                      ------------------- 
   G&A                      (US$000's)         2,816                2,557               8,718                7,873 
                          --------------              ------------------- 
 Total Operating 
  Costs                     (US$000's)        16,419               16,139              50,599               49,059 
                          --------------              ------------------- 
   Excise Duty              (US$000's)         1,708                1,045               5,318                3,362 
                          --------------              -------------------                      ------------------- 
   UK/Philippine G&A        (US$000's)         2,180                1,684               6,841                6,467 
                          --------------              -------------------                      ------------------- 
 Total Direct Production 
  Costs                     (US$000's)        20,307               18,869              62,658               58,888 
                          --------------              -------------------                      ------------------- 
 Net Cash Income            (US$000's)        22,141                6,807              69,241               24,410 
                          --------------              -------------------                      ------------------- 
 Total Capital Costs        (US$000's)         3,150                2,634               8,357                6,672 
                          --------------              -------------------                      ------------------- 
 Total non-cash 
  costs                     (US$000's)         6,340                4,030              21,704               11,712 
                          --------------              -------------------                      ------------------- 
 Free Cashflow              ( US$000's)       18,991                4,173              60,885               17,737 
                          --------------              -------------------                      ------------------- 
 Cash Cost / oz 
  Sold - C1                   US$/oz             736                  989                 792                  970 
                          --------------              -------------------                      ------------------- 
 Cash Cost / oz 
  Sold - AISC                 US$/oz           1,055                1,347               1,092                1,332 
                          --------------              -------------------                      ------------------- 
 

Note: AISC includes all UK Corporate costs.

Review of Operations

Q3 2023 operations produced another strong quarter result for the Company. Gold sales for Q3 2023 were US$42.4 million (Q2 2023: US$49.1 million), at an average realised gold price of US$1,926 per ounce (Q2 2023: average realised gold price of US$1,984 per ounce); producing a positive free cash flow of US$19.0 million (Q2 2023: US$24.1 million).

Finance

The process of elevating the status of the mezzanine loans to that of secured debt continues and the process of executing the relevant documents is expected to be completed during Q4 2023.

As previously advised, the October 2020 debt restructuring agreements envisage the interest rate applicable to the mezzanine debt being reduced from 15% to 7% once the senior debt is repaid and the elevation of the mezzanine debt to "new" senior debt is complete.

The majority mezzanine lender, MTL Luxemburg (Nick Candy's investment vehicle holding 70.7% of the mezzanine debt), has confirmed in writing that, subject to completion of the elevation documents within a reasonable period, the interest rate on its portion of the mezzanine debt will reduce to 7% per annum from 15% per annum as from 3 November 2022 (being the date that the Company could have fully repaid the Senior Facility, but for the requirements of the elevation).

The minority 29.3% mezzanine lender, the RHL Group, has not confirmed the same in writing. However, the Company is hopeful the RHL Group will apply the 7% interest rate from 3 November 2022 and that this will be formalised once the elevation documents are completed.

Total mezzanine debt payments of US$18.5 million were made during Q3 2023 (Q2 2023: US$20.7 million).

The net debt position of the Group as at 30 September 2023 was US$30.6 million (30 June 2023: US$48.3 million). Cash holdings as at 30 September 2023 were US$0.9 million (30 June 2023: US$1.0 million).

Mining Operations

Mining production of ore and waste for Q3 2023 was above forecast at 3.30Mt (Q2 2023: 3.49Mt), with a total of 568Kt of ore mined in Q3 2023 (Q2 2023: 566kt).

An additional six drill holes are planned to complete the exploration programme in Stages 4 and 5, undertaken with the objective of identifying new gold resources both in and near-to the current pit-shell design. To date, this drilling has not produced any material gold discoveries significantly reducing the potential for life of mine extensions.

Process Plant

During Q3 2023, most aspects of the process plant performed adequately, although BIOX continues to under-perform, however ongoing engineering improvements to the cooling circuits within the BIOX process are expected to deliver a sustained increase in performance.

Gold produced during Q3 2023 was 22,034 ounces for the quarter (Q2 2023: 24,235 ounces). Throughput for Q3 2023 was 483Kt at a head grade of 1.60g/t (Q2 2023: 522Kt at a head grade of 1.66g/t) and had a recovery rate of 88.7% (Q2 2023: 86.9%). The expectation is that, in Q4 2023, the trend of decreasing head grade is set to continue.

Planned downtime included scheduled maintenance on the SAG mill, while unplanned downtime consisted mainly of repairs to tails lines, tails line pump change overs and temporary BIOX failure due to power outages.

Residual Storage Impoundment ("RSI")

The RSI dam-wall is at its final height and the d am water freeboard remains well above design minimum levels. Earthworks for the construction of the RSI final in-rock spillway are well advanced and continuing.

Occupational Health & Safety

Runruno continues to record an exceptional safety record with over 20 million hours worked without a lost-time reportable injury as at the date of this announcement.

Environment and Compliance

Compliance matters continue to be successfully monitored, and the mine remains compliant, with no outstanding material issues.

Community & Government Relations

The Company continues to receive strong support from local communities and government agencies. The operations have been nominated for several government industry awards which will be awarded before the end of the year.

This announcement contains inside information for the purposes of Article 7 of EU Regulation 596/2014, which forms part of United Kingdom domestic law by virtue of the European Union (Withdrawal) Act 2018 (as amended). Upon the publication of this announcement, this inside information is now considered to be in the public domain.

   -       END    - 

-

For further information please visit or contact:

 
 Metals Exploration PLC 
 Via Tavistock Communications 
  Limited                        +44 (0) 207 920 3150 
                                ------------------------- 
 Nominated & Financial           STRAND HANSON LIMITED 
  Adviser: 
                                ------------------------- 
 James Spinney, James 
  Dance, Rob Patrick             +44 (0) 207 409 3494 
                                ------------------------- 
 Financial Adviser &             HANNAM & PARTNERS 
  Broker: 
                                ------------------------- 
 Matt Hasson, Franck Nganou      +44 (0) 207 907 8500 
                                ------------------------- 
 Public Relations:               TAVISTOCK COMMUNICATIONS 
                                  LIMITED 
                                ------------------------- 
 Jos Simson, Nick Elwes          +44 (0) 207 920 3150 
                                ------------------------- 
 
   Web:                      www.metalsexploration.com 
   Twitter:                  @MTLexploration 
   LinkedIn:               Metals Exploration 

Competent Person's Statement

Mr Darren Bowden, a director of the Company, a Member of the Australasian Institute of Mining and Metallurgy and who has been involved in the mining industry for more than 25 years, has compiled, read and approved the technical disclosure in this regulatory announcement in accordance with the AIM Rules - Note for Mining and Oil & Gas Companies.

Forward Looking Statements

Certain statements relating to the estimated or expected future production, operating results, cash flows and costs and financial condition of Metals Explorations, planned work at the Company's projects and the expected results of such work contained herein are forward-looking statements which are based on current expectations, estimates and projections about the potential returns of the Group, industry and markets in which the Group operates in, the Directors' beliefs and assumptions made by the Directors . Forward-looking statements are statements that are not historical facts and are generally, but not always, identified by words such as the following: "expects", "plans", "anticipates", "forecasts", "believes", "intends", "estimates", "projects", "assumes", "potential" or variations of such words and similar expressions. Forward-looking statements also include reference to events or conditions that will, would, may, could or should occur. Information concerning exploration results and mineral reserve and resource estimates may also be deemed to be forward-looking statements, as it constitutes a prediction of what might be found to be present when and if a project is actually developed.

These statements are not guarantees of future performance or the ability to identify and consummate investments and involve certain risks, uncertainties and assumptions that are difficult to predict, qualify or quantify. Among the factors that could cause actual results or projections to differ materially include, without limitation: uncertainties related to raising sufficient financing to fund the planned work in a timely manner and on acceptable terms; changes in planned work resulting from logistical, technical or other factors; the possibility that results of work will not fulfil projections/expectations and realize the perceived potential of the Company's projects; uncertainties involved in the interpretation of drilling results and other tests and the estimation of gold reserves and resources; risk of accidents, equipment breakdowns and labour disputes or other unanticipated difficulties or interruptions; the possibility of environmental issues at the Company's projects; the possibility of cost overruns or unanticipated expenses in work programs; the need to obtain permits and comply with environmental laws and regulations and other government requirements; fluctuations in the price of gold and other risks and uncertainties.

The Company expressly disclaims any obligation or undertaking to disseminate any updates or revisions to any forward looking statements contained herein to reflect any change in the Group's expectations with regard thereto or any change in events, conditions or circumstances on which any such statements are based unless required to do so by applicable law or the AIM Rules.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

QRTEQLFFXBLBFBK

(END) Dow Jones Newswires

October 17, 2023 02:00 ET (06:00 GMT)

Metals Exploration (LSE:MTL)
Historical Stock Chart
From Apr 2024 to May 2024 Click Here for more Metals Exploration Charts.
Metals Exploration (LSE:MTL)
Historical Stock Chart
From May 2023 to May 2024 Click Here for more Metals Exploration Charts.