TIDMTLOU
RNS Number : 0452H
Tlou Energy Ltd
25 July 2023
25 July 2023
Tlou Energy Limited
("Tlou" or "the Company")
Quarterly Activities Report for the quarter ended 30 June
2023
Highlights
Ø Lesedi 6 production pod drilling completed
Ø The 66kV overhead transmission line is approximately 79%
complete
Ø At the quarter end the Company had A$6.85m cash on hand
(unaudited)
Activities
Tlou Energy continues to have three key project areas referred
to as the:
-- Lesedi Project - focused on gas-to-power development as well
as exploration and evaluation.
-- Mamba Project - focused on exploration and evaluation.
-- Boomslang Project - focused on exploration and
evaluation.
Lesedi Project
The Lesedi project is Tlou's most advanced. At Lesedi the
Company is developing a proposed 10MW gas-to-power project. The
Lesedi project area has four Prospecting Licenses (PL) and a
Production Licence which is the key focus area for the development
of Tlou's independently certified gas reserves and contingent
resources. The table below summarises the status of the Lesedi
licences:
Licence Expiry Status
Production Licence Aug-42 Current
2017/18L
------- --------
PL001/2004 Sep-23 Current
------- --------
PL003/2004 Sep-23 Current
------- --------
PL035/2000 Mar-25 Current
------- --------
PL037/2000 Mar-25 Current
------- --------
PL renewal applications are submitted three months prior to
expiration. Renewal applications were submitted for PL001/2004 and
PL003/2004 during the quarter.
Gas to Power Project
The first electricity to be generated at Lesedi is planned to go
towards satisfying the 10MW Power Purchase Agreement (PPA) with
Botswana Power Corporation (BPC) the national power utility. The
Lesedi project currently has several components of the development
process underway including the construction of transmission lines,
substations, a field operations facility and generation site as
well as production well drilling.
Transmission Line Construction
The Lesedi project is approximately 100km from the nearest BPC
substation connection in Serowe. To connect to the national grid,
the Company is undertaking the construction and installation of a
100km 66kV transmission line. This, together with the ongoing
drilling program should enable the Company to connect and provide
electricity into Botswana's power network.
The construction of the 66kV transmission line is being carried
out by Zismo Engineering Pty Ltd with progress at the end of June
2023 estimated at approximately 79%. The expected July 2023
completion date has been pushed back due to a delay in availability
of line conductors as well as hard rock excavation and the
discovery of previously unknown sub-surface services with has
slowed progress. However, the transmission line construction
remains on target to be completed well in advance of proposed first
power generation.
Substation Construction
Substations are required at either end of the transmission line,
one to tie Tlou's generators to the transmission line at Lesedi and
another to integrate the line with the existing BPC substation at
Serowe. The planned substation at Lesedi is currently designed for
an initial 5MW of power which can be upgraded to 10MW at a later
stage with the project anticipated to be completed in early 2024.
The Company is now assessing options that may allow the current
substation design to be adapted to facilitate expansion beyond
10MW.
Drilling Operations
During the quarter the Company began drilling the latest
production pod, Lesedi 6, the first of a series of new pods (funds
permitting) that the Company plans to drill as part of the 10MW gas
to power project. Lesedi 6 comprises one vertical production well
(Lesedi 6P) intersected by two lateral wells (Lesedi 6A and 6B)
drilled horizontally through the target reservoir section for
several hundred metres.
Lesedi 6P - Vertical Production Well
This well was drilled to a depth of 589m and intersected 6m of
the target lower Morupule coal. Well casing was cemented in place,
with fiberglass casing over the target coal seam underreamed to
expose the coal to the well bore to facilitate dewatering and gas
flow.
Lesedi 6A and Lesedi 6B - Lateral Wells
The top hole (or vertical) sections of Lesedi 6A and Lesedi 6B
were drilled during the quarter. Both were drilled to a depth of
150m and cased with steel casing and cemented. Following cementing,
the wells were deepened in preparation for running the directional
tools which are required to complete the lateral section of the
well. Drilling of the lateral sections commenced thereafter with
both lateral sections successfully intersecting Lesedi 6P post
quarter end.
Core-hole drilling
In addition to the Lesedi 6 production pod, a core-hole was
drilled close to the vertical sections of Lesedi 6A and 6B. The
objective of the core-hole was to provide further geological
control. In addition to providing coal and gas content data, the
core-hole accurately determined the top and bottom of the target
coal seam. The core-hole was completed and logged after reaching a
total depth of 535m and intersecting 6m of coal. A total of 18 coal
samples were taken and placed in desorption canisters for further
analysis.
A further core-hole was commenced prior to quarter end which was
located close to where another new production pod (Lesedi 7) is
proposed to be drilled at a later date.
****
Mamba Project
The Mamba project is in the exploration and evaluation phase
with further operations required on the operating licences. It
consists of five Prospecting Licences covering an area of
approximately 4,500 Km(2) . The Mamba area is situated adjacent to
Lesedi. In the event of successful drilling results at Mamba, it is
envisioned that this area would be developed as a separate project
from Lesedi. The Mamba area provides the Company with flexibility
and optionality. The status of the Mamba licences is as
follows:
Licence Expiry Status
PL 237/2014 September 2023 Current
--------------- --------
PL 238/2014 September 2023 Current
--------------- --------
PL 239/2014 September 2023 Current
--------------- --------
PL 240/2014 September 2023 Current
--------------- --------
PL 241/2014 September 2023 Current
--------------- --------
PL renewal applications are submitted three months prior to
expiration. Renewal applications for all Mamba project licences
were submitted during the quarter.
****
Boomslang Project
Prospecting Licence, PL011/2019 designated "Boomslang", is
approximately 1,000 Km(2) and is situated adjacent to the Company's
existing licences. To date, the Company has not carried out ground
operations in the Boomslang area. The status of the Boomslang
licence is as follows:
Licence Expiry Status
PL 011/2019 June 2024 Current
---------- --------
PL renewal applications are submitted three months prior to
expiration.
****
Cash Position
At the end of the quarter the Company had A$6.85m cash on hand
(unaudited). The aggregate value of payments to related parties and
their associates of A$235k for the quarter (shown in item 6.1 of
the attached Quarterly Cashflow Report) relates to directors'
salaries and fees (including tax and superannuation payments made
on their behalf) and office rent.
The information contained within this announcement is deemed to
constitute inside information as stipulated under the retained EU
law version of the Market Abuse Regulation (EU) No. 596/2014 (the
"UK MAR") which is part of UK law by virtue of the European Union
(withdrawal) Act 2018. The information is disclosed in accordance
with the Company's obligations under Article 17 of the UK MAR. Upon
the publication of this announcement, this inside information is
now considered to be in the public domain.
By Authority of the Board of Directors
Mr. Anthony Gilby
Managing Director
****
For further information regarding this announcement please
contact:
Tlou Energy Limited +61 7 3040 9084
Tony Gilby, Managing Director
---------------------
Solomon Rowland, General Manager
---------------------
Grant Thornton (Nominated Adviser) +44 (0)20 7383 5100
---------------------
Harrison Clarke, Colin Aaronson, Ciara Donnelly
---------------------
Zeus Capital (UK Broker) +44 (0)20 3829 5000
---------------------
Simon Johnson
---------------------
Public Relations
---------------------
Ashley Seller +61 418 556 875
---------------------
About Tlou
Tlou is developing energy solutions in Sub-Saharan Africa
through gas-fired power and ancillary projects. The Company is
listed on the ASX (Australia), AIM (UK) and the BSE (Botswana). The
Lesedi Gas-to-Power Project ("Lesedi") is 100% owned and is the
Company's most advanced project. Tlou's competitive advantages
include the ability to drill cost effectively for gas, operational
experience and Lesedi's strategic location in relation to energy
customers. All major government approvals have been achieved.
Forward-Looking Statements
This announcement may contain certain forward-looking
statements. Actual results may differ materially from those
projected or implied in any forward-looking statements. Such
forward-looking information involves risks and uncertainties that
could significantly affect expected results. No representation is
made that any of those statements or forecasts will come to pass or
that any forecast results will be achieved. You are cautioned not
to place any reliance on such statements or forecasts. Those
forward-looking and other statements speak only as at the date of
this announcement. Save as required by any applicable law or
regulation, Tlou Energy Limited undertakes no obligation to update
any forward-looking statements.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
------------------------------------------------------
Tlou Energy Limited
ABN Quarter ended ("current quarter")
--------------- -----------------------------------
79 136 739 967 30 June 2023
-----------------------------------
Consolidated statement of cash Current quarter Year to date
flows (12 months)
$A'000 $A'000
1. Cash flows from operating
activities
1.1 Receipts from customers
1.2 Payments for
(a) exploration & evaluation
(b) development (81) (329)
(c) production
(d) staff costs (321) (1,216)
(e) administration and corporate
costs (366) (1,900)
1.3 Dividends received (see note
3)
1.4 Interest received 6 22
Interest and other costs of
1.5 finance paid (16) (16)
1.6 Income taxes paid
1.7 Government grants and tax
incentives
Other (provide details if
1.8 material) 75 422
---------------- -------------
Net cash from / (used in)
1.9 operating activities (703) (3,018)
----------------- ----------------------------------- ---------------- -------------
2. Cash flows from investing
activities
2.1 Payments to acquire or for:
(a) entities
(b) tenements
(c) property, plant and equipment (667) (1,884)
(d) exploration & evaluation (2,441) (5,969)
(e) investments
(f) other non-current assets (1,103) (5,622)
2.2 Proceeds from the disposal
of:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) investments
(e) other non-current assets
2.3 Cash flows from loans to other
entities
2.4 Dividends received (see note
3)
2.5 Other (provide details if
material)
---------------- -------------
Net cash from / (used in)
2.6 investing activities (4,211) (13,474)
----------------- ----------------------------------- ---------------- -------------
3. Cash flows from financing
activities
Proceeds from issues of equity
securities (excluding convertible
3.1 debt securities) 6,585 14,854
3.2 Proceeds from issue of convertible
debt securities
3.3 Proceeds from exercise of
options
Transaction costs related
to issues of equity securities
3.4 or convertible debt securities (108) (108)
3.5 Proceeds from borrowings 2,000 2,000
3.6 Repayment of borrowings
3.7 Transaction costs related
to loans and borrowings
3.8 Dividends paid
Other (provide details if
3.9 material) (15)
---------------- -------------
Net cash from / (used in)
3.10 financing activities 8,477 16,730
----------------- ----------------------------------- ---------------- -------------
4. Net increase / (decrease)
in cash and cash equivalents
for the period
Cash and cash equivalents
4.1 at beginning of period 3,540 7,875
Net cash from / (used in)
operating activities (item
4.2 1.9 above) (703) (3,018)
Net cash from / (used in)
investing activities (item
4.3 2.6 above) (4,211) (13,474)
Net cash from / (used in)
financing activities (item
4.4 3.10 above) 8,477 16,730
Effect of movement in exchange
4.5 rates on cash held (253) (1,262)
---------------- -------------
Cash and cash equivalents
4.6 at end of period 6,851 6,851
----------------- ----------------------------------- ---------------- -------------
5. Reconciliation of cash and Current quarter Previous quarter
cash equivalents $A'000 $A'000
at the end of the quarter
(as shown in the consolidated
statement of cash flows) to
the related items in the accounts
5.1 Bank balances 6,851 3,540
5.2 Call deposits
5.3 Bank overdrafts
5.4 Other (provide details)
---------------- -----------------
Cash and cash equivalents
at end of quarter (should
5.5 equal item 4.6 above) 6,851 3,540
----------------- ------------------------------------ ---------------- -----------------
6. Payments to related parties of the entity Current quarter
and their associates $A'000
Aggregate amount of payments to related
parties and their associates included in
6.1 item 1 235
----------------
6.2 Aggregate amount of payments to related
parties and their associates included in
item 2
----------------
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly
activity report must include a description of, and an explanation
for, such payments.
7. Financing facilities Total facility Amount drawn
Note: the term "facility' amount at quarter at quarter end
includes all forms of financing end $A'000
arrangements available to $A'000
the entity. Add notes as necessary
for an understanding of the
sources of finance available
to the entity.
7.1 Loan facilities
------------------- ----------------
7.2 Credit standby arrangements
------------------- ----------------
7.3 Other (please specify)
------------------- ----------------
7.4 Total financing facilities
------------------- ----------------
7.5 Unused financing facilities available at
quarter end
----------------
7.6 Include in the box below a description of each facility
above, including the lender, interest rate, maturity date
and whether it is secured or unsecured. If any additional
financing facilities have been entered into or are proposed
to be entered into after quarter end, include a note providing
details of those facilities as well.
----------------- ----------------------------------------------------------------------------
8. Estimated cash available for future operating $A'000
activities
Net cash from / (used in) operating activities
8.1 (item 1.9) 703
8.2 (Payments for exploration & evaluation classified 2,441
as investing activities) (item 2.1(d))
8.3 Total relevant outgoings (item 8.1 + item 3,144
8.2)
8.4 Cash and cash equivalents at quarter end 6,851
(item 4.6)
8.5 Unused finance facilities available at quarter -
end (item 7.5)
-------
8.6 Total available funding (item 8.4 + item 6,851
8.5)
-------
Estimated quarters of funding available
8.7 (item 8.6 divided by item 8.3) 2.2
-------
Note: if the entity has reported positive relevant outgoings
(ie a net cash inflow) in item 8.3, answer item 8.7 as
"N/A". Otherwise, a figure for the estimated quarters
of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers
to the following questions:
8.8.1 Does the entity expect that it will continue to
have the current level of net operating cash flows for
the time being and, if not, why not?
-------------------------------------------------------------------
Answer:
-------------------------------------------------------------------
8.8.2 Has the entity taken any steps, or does it propose
to take any steps, to raise further cash to fund its operations
and, if so, what are those steps and how likely does it
believe that they will be successful?
-------------------------------------------------------------------
Answer:
-------------------------------------------------------------------
8.8.3 Does the entity expect to be able to continue its
operations and to meet its business objectives and, if
so, on what basis?
-------------------------------------------------------------------
Answer:
-------------------------------------------------------------------
Note: where item 8.7 is less than 2 quarters, all of
questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
----------------- -------------------------------------------------------------------
Compliance statement
1 This statement has been prepared in accordance with accounting
standards and policies which comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date: .....25/07/2023...............................................................
Authorised by: ....By the
Board.............................................................
(Name of body or officer authorising release - see note 4)
Notes
1. This quarterly cash flow report and the accompanying activity
report provide a basis for informing the market about the entity's
activities for the past quarter, how they have been financed and
the effect this has had on its cash position. An entity that wishes
to disclose additional information over and above the minimum
required under the Listing Rules is encouraged to do so.
2. If this quarterly cash flow report has been prepared in
accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of
Mineral Resources and AASB 107: Statement of Cash Flows apply to
this report. If this quarterly cash flow report has been prepared
in accordance with other accounting standards agreed by ASX
pursuant to Listing Rule 19.11A, the corresponding equivalent
standards apply to this report.
3. Dividends received may be classified either as cash flows
from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market
by your board of directors, you can insert here: "By the board". If
it has been authorised for release to the market by a committee of
your board of directors, you can insert here: "By the [name of
board committee - eg Audit and Risk Committee]". If it has been
authorised for release to the market by a disclosure committee, you
can insert here: "By the Disclosure Committee".
5. If this report has been authorised for release to the market
by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance
Council's Corporate Governance Principles and Recommendations, the
board should have received a declaration from its CEO and CFO that,
in their opinion, the financial records of the entity have been
properly maintained, that this report complies with the appropriate
accounting standards and gives a true and fair view of the cash
flows of the entity, and that their opinion has been formed on the
basis of a sound system of risk management and internal control
which is operating effectively.
This information is provided by RNS, the news service of the
London Stock Exchange. RNS is approved by the Financial Conduct
Authority to act as a Primary Information Provider in the United
Kingdom. Terms and conditions relating to the use and distribution
of this information may apply. For further information, please
contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms
and conditions, to analyse how you engage with the information
contained in this communication, and to share such analysis on an
anonymised basis with others as part of our commercial services.
For further information about how RNS and the London Stock Exchange
use the personal data you provide us, please see our Privacy
Policy.
END
UPDRAMBTMTITMIJ
(END) Dow Jones Newswires
July 25, 2023 02:00 ET (06:00 GMT)
Tlou Energy (LSE:TLOU)
Historical Stock Chart
From Apr 2024 to May 2024
Tlou Energy (LSE:TLOU)
Historical Stock Chart
From May 2023 to May 2024