Marula Mining
PLC
("Marula'' or the "Company")
26 September
2024
Revised Development Plan for
Kinusi Copper Mine
Copper Cathode Production
Proposed to Commence in 2025
Marula Mining (AQSE: MARU A2X: MARU)
an African focused mining and development company, is pleased to
provide an update on its planned development and production plans
for the Kinusi Copper Mine ("Kinusi") located in the Mpwapwa
District in the Dodoma Region of central Tanzania.
The updated mine development plan
involves a large conventional open pit mine development and a
two-phase processing operation comprising initially of a gravity
concentrate, coarse jigging and fines dewatering circuit to produce
a 24,000 tonnes per annum ("tpa") of high-grade copper concentrate
("Phase 1"). The estimated capital costs
for the Phase 1
gravity concentrate, coarse jigging and fines
dewatering circuit based on the quotes received is approx. ZAR 27.4
million (approximately £1.4 million), which will be funded
from available, but undrawn amounts due, from the subscription
agreement entered into with AUO Commercial Brokerage LLC in 2024.
Phase 2 will then incorporate a hydrometallurgy fines optimised
heap leaching circuit, a copper solvent extraction as well as
electrowinning refining process ("Phase 2") to produce an initial
10,200 tpa of copper cathode.
The Company's Board of Directors has
now approved the updated development plan for Kinusi and the
recommendations made by the Company's technical management and
independent geological and processing consultants who undertook a
series of site visits to Kinusi in H1 2024 and most recently in
August 2024.
Final test work for the Phase 1
gravity concentrate, jigging and fines dewatering circuit has been
approved by the Board and will be completed in South Africa in Q4
2024. The associated Phase 2 test work has also been approved
by the Board. This will comprise hydrometallurgy test work, copper
leach kinetic tests, and fines optimised heap leaching polymer
screening as well as column tests. In addition, detailed quotes
have now been received from a number of mineral processing groups
for the initial gravity concentrate coarse jigging and fines
dewatering circuit which are being reviewed by the Company's
Executive Management, ahead of awarding the contract for the
commencement of its installation and commissioning in late Q4 2024
and early Q1 2025.
Open pit mine planning and initial
mining activities will commence in Q4 2024, with high-grade copper
ore to be stockpiled ahead of the commissioning of the Phase 1
gravity concentrate coarse jigging and fines dewatering
circuit. High grade copper concentrate
production is now planned to commence in Q1 2025 with first export
sales to be completed late in the quarter.
Highlights:
• Updated and
'high-value' mine development and copper
processing plan for Kinusi approved by the Company's Board
of Directors
• The updated
mine development and processing plan follows numerous site visits
by the Company's Executive Management team. Accompanying reports
and recommendations from independent geological and mineral
processing consultants in 2024 have been received which confirms
the following key parameters:
• the
presence of a significant high-grade copper that extends for over 1
kilometre ("km") in length and over 300 metres ("m") in width at
the main Sasimo Prospect (announced on 18 August
2023).
•
estimates of an initial Exploration Target at Kinusi of a
10-15 Metric tonnes ("Mt") deposit of high-grade copper, gold, and
other base metals (announced on 18 August 2023)
•
the copper mineralogy is highly
oxidized, with malachite and azurite being the predominant
mineralogy
• the
road access, existing on-site power and water availability is
sufficient to support the planned open pit mining operations and
two-phase copper processing operation through to production of an
LME grade copper cathode
•
recommendation to begin developing the more
apparent and accessible surface open pits, in order to feed a
gravity concentrate circuit consisting of a crushing, screening and
coarse size fraction jigging circuit
• the gravity
concentrates and jigging circuit is a relatively simple, fast
implementation, processing installation which requires low power
and relatively low water consumption infrastructure
•
the copper mineralogy is
considered sufficiently oxidised, to be amenable to processing by
way of a sulphuric acid hydrometallurgy processing flowsheet route,
to produce LME grade copper cathode
• the
assessed copper cathode design production capacity of 10,200 tpa
has been chosen, based upon preliminary assumed available power of
5 kVA and an estimated installed power demand by the processing
plant of 3.5kVA
•
further test work is now required to commence the finalisation of
the Phase 1 gravity concentrate and jigging circuit and will
includes materials hardness, bond work index and particle size
distribution testing
•
additional test work is also required for the Phase 2
hydrometallurgy fines optimised heap leaching
circuit, and copper solvent extraction and electrowinning refining
process and includes hyrometallurgy chemistry test work, copper
leach kinetic tests, and heap leaching polymer screening and column
tests
• Based
on the recommendations received from the various independent
consultants and the Company's technical management team, Takela
Mining Tanzania Limited ("Takela Mining") is commencing open pit
mining in early October 2024 in line with the new development plan
and using new mining equipment recently purchased by the Company's
Tanzanian subsidiary
•
High-grade copper ore from this open pit mining is to be stockpiled
over Q4 2024 whilst sampled material from Pit 4 is
sent to South Africa for final test work to optimise the
design of the Phase 1 gravity concentrate, coarse
jigging and fines dewatering circuit that is intended to produce
24,000 tpa of high-grade saleable copper
concentrate
•
Detailed quotes, power requirements and
installation and commissioning schedules for the Phase 1
gravity concentrate, coarse jigging and fines
dewatering circuit have already been received from a number of
mineral processing groups in South Africa
•
The estimated capital costs for
the Phase 1 gravity concentrate, coarse jigging and fines dewatering
circuit based on the quotes received is approximately ZAR 27.4
million (approximately £1.4 million)
•
The Phase 1 processing circuit has been designed
to produce 24,000 tpa of a saleable
high-grade copper concentrate and to be
relatively simple, allowing for both flexible operations and the
planned successful production of a high-quality copper concentrate
given the expected coarse particle size performance in the gravity
concentrate circuit
•
The award of the Phase 1 contract is to be made in
Q4 2024, and installation and commissioning will then commence and
continue into Q1 2025
•
During Q4 2024 and throughout the initial
commissioning and operation of the Phase 1 processing plant in Q1
2025, further test work is to be completed
to allow for the detailed design of the Phase 2 fines optimised
heap leaching option, and the back-end refining solvent extraction
and electrowinning refining processes to be completed
•
The Phase 2 processing flowsheet is to then be
fully integrated into the Phase 1 processing flowsheet and includes
the crushing of the coarse jig concentrate and incorporates this
copper-enriched stream into the fines optimised heap leach
feed
•
The planned heap leach operation is proposed to be
optimised with more copper per cubic metre of deposited solids,
which is proposed to increase recoverable copper units by way of
leaching. The resulting enrichment of the leach feed also improves
acid utilisation. The resultant pregnant leach solution is
collected as run-off from the fines optimised heap leach deposition
solids and serves as feed solution for the copper solvent
extraction and electrowinning refining circuit
•
The copper is to be extracted from the pregnant
leach solution in solvent extraction plant and from there the
resultant enriched copper solution is then transferred to the
copper electrowinning circuit where the copper cathode is produced
and is to be then stockpiled ahead of transportation through to Dar
es Salaam for export
•
The initial design of the Phase 2 fines optimised
heap leaching option, and the back-end refining solvent extraction
and electrowinning refining processes and mine economics have been
based on a run-of-mine ore grade of 2.6% copper (which is line with
the assay results received from Kinusi in Q4 2023), and copper
recoveries of 85% to produce an
initial 10,200 tpa of copper cathode
•
In parallel with the implementation of the updated
mine and processing plan, plus the work that has already been
carried out, the Company will commence its Phase 2 Exploration
Program including the resource drilling program that is aimed at
increasing confidence in the 10-15Mt Exploration Target that has
already been defined at Kinusi
•
The Company's CEO, Executive Chairman and
Non-Executive Director, Ms Hannah Wang'Ombe will be in London
during the London Metals Exchange Week, which commences 30
September 2024, to finalise its ongoing sales and offtake
negotiations on copper concentrate and copper cathode production
from Kinusi
Jason Brewer, Marula Mining PLC CEO said:
"There has been a tremendous amount of work completed at the
Kinusi Copper Mine over 2024, following the results of the Phase 1
Exploration Programme. This work has been completed by numerous
independent consultants, both from a geological, mining and mineral
processing perspective.
The results of this work have caused us to re-assess the
previously proposed development plans, which were solely based on
production of high-grade copper concentrates. The independent
mineral processing work completed most recently in August 2024 has
demonstrated the real opportunity that exists at the Kinusi Copper
Mine. We already believed from our earlier work that the potential
of the Kinusi Copper Mine was quite significant, not only in terms
of the high-grade and significant copper mineralisation that had
been identified, but also from the existing infrastructure that was
already in place to support our development
plans.
The potential now is to establish the Kinusi Copper Mine as a
producer and exporter of LME grade copper cathode, which presents
the Company with the opportunity to add significant value to a
strategically important mining operation in the Dodoma Region of
Tanzania that will provide far reaching economic and employment
benefits to the communities and stakeholders we work alongside
with.
I
look forward to see the mining activities accelerate over the
coming quarter and updating shareholders and our stakeholders on
these activities as well as the results from the test work that is
to now due to commence in support of the expanded two-phase mineral
processing operation that is to proceed."
The
Directors of Marula are responsible for the contents of this
announcement. This announcement contains
inside information for the purposes of UK Market Abuse
Regulation.
About Marula Mining
Marula Mining (AQSE: MARU A2X: MARU)
is an African focused battery metals investment and exploration
company and has interests in several high value mining operations
and mine development projects in Africa: the Blesberg Lithium and
Tantalum Mine, Northern Cape Lithium and Tungsten Project, Korridor
Lithium Project and Kruisrivier Cobalt Mine, all in South Africa;
the Larisoro Manganese Mine and Kilifi Manganese Processing
Operation both in Kenya; the Kinusi Copper Mine, the Nyorinyori
Graphite Project, the NyoriGreen Graphite Project and the Bagamoyo
Graphite Project all in Tanzania and the Nkombwa Hill Project in
Zambia. As we advance operations at these battery metals focused
projects, Marula will continue to build and expand its interests in
other high-quality projects in Africa.
Marula's strategy is to identify and
invest in advanced and high-value mining projects throughout East,
Central and Southern Africa that the Directors believe would
deliver returns for its shareholders. The Board and Management team
aims to establish Marula as a socially and environmentally
responsible, sustainable, and profitable producer of critical
metals and commodities that are of increasingly strategic
importance to modern technologies and the global economy. Marula's
shares are traded on AQUIS Stock Exchange ("AQSE") in London and
A2X Markets in South Africa. Marula is exploring opportunities to
admit its shares to trading on Kenya's Nairobi Securities Exchange
and South Africa's Johannesburg Stock Exchange.
For
enquiries contact:
Marula Mining PLC
Jason Brewer,
Chief Executive Officer
Faith Kinyanjui Mumbi
Investor Relations
|
Email :
jason@marulamining.com
Email : info@marulamining.com
|
AQSE Corporate Adviser
Cairn Financial Advisers LLP,
Liam Murray / Ludovico Lazzaretti
|
+44 (0)20
7213 0880
|
Broker
Peterhouse Capital Limited,
Charles Goodfellow / Duncan Vasey
|
+44
(0)20 7469 0930
|
Financial PR and IR
BlytheRay
Tim
Blythe / Megan Ray / Said Izagaren
|
+44 (0)20 7138 3204
|
A2X
Advisor
AcaciaCap Advisors Proprietary Limited
Michelle Krastanov
|
+27 (11)
480 8500
|
Caution:
Certain statements in this
announcement, are, or may be deemed to be, forward looking
statements. Forward looking statements are identified by their use
of terms and phrases such as ''believe'', ''could'', "should"
''envisage'', ''estimate'', ''intend'', ''may'', ''plan'',
''potentially'', "expect", ''will'' or the negative of those,
variations or comparable expressions, including references to
assumptions. These forward-looking statements are not based on
historical facts but rather on the Directors' current expectations
and assumptions regarding the Company's future growth, results of
operations, performance, future capital and other expenditures
(including the amount, nature and sources of funding thereof),
competitive advantages, business prospects and opportunities. Such
forward looking statements reflect the Directors' current beliefs
and assumptions and are based on information currently available to
the Directors.