Hana Mining Ltd. ("Hana" or the "Company") (TSX VENTURE:HMG)(FRANKFURT:4LH) is
pleased to announce the positive results of its initial independent National
Instrument 43-101 compliant Preliminary Economic Assessment ("PEA") for the
Banana Zone and Zone 5 at its 70-percent owned Ghanzi Copper-Silver Project
("Project") in northwestern Botswana. The PEA was prepared by independent
consultants and DRA Mineral Projects ("DRA") of Johannesburg, South Africa and
will be filed on SEDAR within 45 days of this news release. The results of the
PEA describe the technical and economic viability of establishing a new
copper-silver mine and mill complex for the Project. The base-case scenario
utilizes a long-term copper price of US$3.40/lb. This copper price represents
the current three-year trailing average LME price for reference purposes. As a
result of the positive outcome of the PEA, Hana will now commence with a
feasibility study on the Project.


The PEA is based on the mineral resources at the Banana Zone and Zone 5 that are
detailed later in this press release. Drilling is continuing through 2012 to
explore the potential to extend and upgrade the current planned in-pit and
global resources. The results from these holes will be included in the
feasibility study.


Key highlights of the PEA study are as follows: 



--  Initial development capital expenditure of US$285.5 million and a total
    capital expenditure of US$399.0 million 
--  Pre-tax NPV(8%) of US$363.3 million and an IRR of 22.1% for the base
    case, using prices of US$3.40/lb for copper, US$30/oz for silver and a
    discount rate of 8% 
--  After-tax NPV(8%) of US$262.5 million for the base case 
--  After-tax IRR of 19.3% for the base case 
--  Payback of capital in 5 years 
--  Minimum 13-year mine life supporting a 10,000 tonne-per-day conventional
    grinding mill and flotation circuit to produce a clean high-grade
    (approximately 46% copper) copper-silver concentrate 
--  Life-of-mine strip ratio of 6.8 to 1 to an average pit depth of 183m
    from four pits with no more than two pits operating at any given time.
    Mining operations will be carried out utilizing contract mining 
--  Average production of 66.4 million pounds of copper and 878,000 ounces
    of silver for life of mine 
--  Cash costs utilizing heavy fuel oil ("HFO") generator power of
    US$1.96/lb of payable copper (net of silver byproduct credits) for the
    first five years and US$1.75/lb (power supplied by Botswana Power
    Corporation ("BPC") from the national power grid for the remaining life
    of mine (C1 costs include on-site mining and processing costs, transport
    and TC/RC charges and is net of by-product credits) 
--  Strongly leveraged for potential upside: 
    --  Adding an additional two years to the mine life increases the
        NPV(8%) by 19% to US$313.7 million 
    --  Increasing the life-of-mine copper grade by 0.10% increases the
        NPV(8%) by 44% 
    --  A 10% increase in copper prices or grades increases the NPV(8%) by
        48% 
--  Robust economic indicators justify immediate commencement of the
    feasibility study 



A PEA should not be considered to be a pre-feasibility or feasibility study, as
the economics and technical viability of the Project has not been demonstrated
at this time. A PEA is preliminary in nature and includes Inferred Mineral
Resources that are considered too geologically speculative at this time to have
the economic considerations applied to them to be categorized as Mineral
Reserves. Furthermore, there is no certainty that the details outlined in the
PEA will be realized. 


Hana Mining's CEO and Chairman, Marek Kreczmer, commented as follows:

"The PEA is the culmination of many months of hard work by our
highly-experienced technical team. This document represents a current snap shot
and firmly demonstrates that the Project has robust economics and will be a
long-lived copper-silver operation. Therefore, we have commenced activities for
a feasibility study, 


The initial capital cost of US$285.5 million will support a 31,000 tonne per
year copper-silver mining operation, meaning that this project will have one of
the lowest capital intensities among global copper development projects. While
the PEA assumes contract mining, where a third party contract-mining firm would
carry out the in-pit mining operations, lower cost owner-operated mining needs
to be considered, and this will be done in the feasibility study. In addition,
none of the holes drilled in 2012, including those with high copper and silver
values from the Northeast Fold area were included in the PEA. However, the
results from these holes and holes from other parts of the Banana Zone and Zone
5 will be included in the feasibility study. With the additional drilling
planned for the next few months we also expect to get a better handle on pit
optimization in order to potentially reduce the payback period and increase the
NPV of the project. 


There are many aspects of the PEA which I believe can be optimized during the
feasibility study such as:




--  Upside potential at Zone 5, Zone 6, and the Banana Zone, specifically in
    the Northeast Fold area where the high-grade copper-silver drilling
    results from 2012 were not included in the PEA, 
--  There is excellent potential for identification of additional
    mineralization through infill and expansion drilling at the Project
    which could support estimation of additional mineral resources, and be
    incorporated into an updated mine plan, 
--  A reduction in our projected mining and milling costs through further
    optimization of our processes and the possible utilization of
    alternative energy resources such as solar and wind power. Owner versus
    contract mining will also be investigated, 
--  A reduction in the estimated capital costs of the project through
    further optimization in the costs of the plant and other equipment
    needed to operate the mine and mill, 
--  The economics of the project may also be significantly optimized with
    more timely access to Botswana's national power grid, 
--  Investigating the economics of establishing an underground mining
    operation. 



Our primary corporate focus is to work with the Botswana government to
accelerate the extension of their national grid to the project site. As well, we
will also investigate the use of alternative energy sources such as coal, solar
and wind power to offset the higher cost HFO generated power that was used in
the study. 


The Project is uniquely positioned to secure low-cost financing given that it
has a low capital cost, will produce a high-quality highly sought after
concentrate and is located in one of the most stable mining jurisdictions in the
world.


Given the positive outcome of the PEA we will now move forward with a
feasibility study. We remain well financed with Cdn$20 million in cash in the
treasury."


Preliminary Economic Assessment - Mining and Processing:

The PEA is based on a conventional truck and shovel, open-pit mine design at
four pits with milling and sulphide concentration of both near-surface
secondary/transition copper material and underlying primary sulphide
mineralization. 


Preliminary metallurgical work on the oxide/transitional material and sulphides
show an average blended recovery of 87% for copper and 80% for silver. The two
mineralization types will be processed simultaneously through conventional
milling and flotation for a minimum mine life of 13 years. Total production is
projected to be 10,000 tonnes per day. 


Production will come from two pits, at any given time, at the Northeast Fold,
New Discovery and South Limb areas of the Banana Zone and from Zone 5. Pit
depths in the Banana Zone will have a maximum vertical extent up to 200 m,
whereas the pit depth in Zone 5 is currently 150 m. Key parameters and
assumptions used for the PEA study are discussed below and summarized in a
series of tables on the following pages.




----------------------------------------------------------------------------
                                             Avg t/yr                 Total 
Type of Mining                  Total Years    (000's)  Avg t/day    (000's)
----------------------------------------------------------------------------
Open pit mineralized material                                               
 (Years 0 - 13)                          13     3,600      10,000    45,700 
----------------------------------------------------------------------------
Open pit waste (Years 0 - 13)            13    23,880      66,000   310,000 
----------------------------------------------------------------------------
                                                                            
                                --------------------------------------------
                                Total material mined                355,700 
                                --------------------------------------------
                                Average strip ratio for the life            
                                of mine                               6.8:1 
----------------------------------------------------------------------------
                                                                            
Table 1 - Mining rates and volumes of mined material                        
                                                                            
----------------------------------------------------------------------------
                                                                     Average
                                                           Annual Production
Metal                              Total Production             Life of Mine
----------------------------------------------------------------------------
                            lbs (000's)      tonnes  lbs (000's)      Tonnes
----------------------------------------------------------------------------
Copper in concentrate          863,000      392,000      68,000       31,000
----------------------------------------------------------------------------
                                             ounces                   Ounces
----------------------------------------------------------------------------
Silver in concentrate                    11,408,000                  899,000
----------------------------------------------------------------------------
                                                                            
Table 2 - Projected metal production                                        
                                                                            
----------------------------------------------------------------------------
Head Grades                                                                 
----------------------------------------------------------------------------
Copper                                                           %      1.02
----------------------------------------------------------------------------
Silver                                                         g/t     12.13
----------------------------------------------------------------------------
Metal Recoveries                                                            
----------------------------------------------------------------------------
Copper - sulphides                                               %        91
----------------------------------------------------------------------------
Copper - oxides                                                  %        50
----------------------------------------------------------------------------
Average copper recovery - sulphides and oxides                   %        87
----------------------------------------------------------------------------
Smelter losses                                                   %         3
----------------------------------------------------------------------------
Total payable copper                                             %        84
----------------------------------------------------------------------------
Average silver recovery - sulphides and oxides                   %        80
----------------------------------------------------------------------------
Total payable silver                                             %        64
----------------------------------------------------------------------------
Copper concentrate grade                                         %        46
----------------------------------------------------------------------------
Silver concentrate grade                                       g/t       414
----------------------------------------------------------------------------
Metal Prices                                                                
----------------------------------------------------------------------------
Copper                                                      US$/lb      3.40
----------------------------------------------------------------------------
Silver                                                      US$/oz     30.00
----------------------------------------------------------------------------
Other Parameters                                                            
----------------------------------------------------------------------------
Life of mine                                                 Years        13
----------------------------------------------------------------------------
Heavy fuel oil price                                         US$/l      1.06
----------------------------------------------------------------------------
Electrical power - HFO                                    US$/kWhr      0.22
----------------------------------------------------------------------------
Electrical power - national grid                          US$/kWhr      0.12
----------------------------------------------------------------------------
                                                                            
Table 3 - The Base case head grades, recoveries, metal prices, and other    
data used.                                                                  



Preliminary Economic Assessment - Project Economics:

The results of a discounted cash flow analysis for the Project are presented in
Table 4 below. Net Present Value (NPV), Internal Rate of Return (IRR) and
Payback values are presented for both pre-tax and after-tax scenarios. The
base-case scenario utilizes a long-term copper price of US$3.40/lb and a
discount rate of 8%. IRR and NPV values are calculated for a range of copper
prices from US$3.00 to US$4.00. The copper price of US$3.40/lb represents the
current three-year trailing average LME price for reference purposes. The
discount rate of 8% is indicative for a stable country like Botswana. Table 5
summarizes the key financial results for the project.


A Botswana net smelter return royalty of 3% for base metals and 5% for precious
metals, and a corporate tax rate of 22.5%, have been used in the cash flow
analysis.


Please note that as Mineral Resources (of the Indicated and Inferred categories)
do not have economic viability and are geologically considered to be too
speculative to have economic considerations applied to them, this PEA is
entirely preliminary in nature. 




----------------------------------------------------------------------------
                                                      Copper Price         
                                                         (US$/lb)           
                                              ------------------------------
                                                            Base            
Pre-tax NPV                                                 Case            
(US$ million)                                   3.00  3.25  3.40  3.50  4.00
----------------------------------------------------------------------------
Discount Rates         5%                        289   431   516   573   857
                       -----------------------------------------------------
                       Base Case 8%              173   291   363   410   646
                       -----------------------------------------------------
                       10%                       113   218   281   324   535
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
IRR                    %                        15.0  19.5  22.0  23.7  31.8
----------------------------------------------------------------------------
Payback                Years                       7     6     5     5     4
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
                                                       Copper Price         
                                                         (US$/lb)           
                                              ------------------------------
                                                            Base            
After-tax NPV                                               Case            
(US$ million)                                   3.00  3.25  3.40  3.50  4.00
----------------------------------------------------------------------------
Discount Rates         5%                        209   320   387   431   652
                       -----------------------------------------------------
                       Base Case 8%              112   206   262   299   484
                       -----------------------------------------------------
                       10%                        61   145   196   229   394
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
IRR                    %                        13.0  17.0  19.3  20.7  27.9
----------------------------------------------------------------------------
Payback                Years                       7     6     5     5     4
----------------------------------------------------------------------------
                                                                            
Table 4 - Pre-tax and after-tax discounted cash flow results for varying    
copper prices                                                               
                                                                            
----------------------------------------------------------------------------
                                      Total     Annual                      
Cash costs                          Life of    Life of     Annual     Annual
(US$ million)                          Mine       Mine  Years 1-5 Years 6-10
----------------------------------------------------------------------------
Royalties (Cu at 3%, Ag at 5%)           88        6.8        6.8        6.8
----------------------------------------------------------------------------
Net pre-tax income                      932       71.7       68.9       79.8
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
                                               Life of                      
Cash Costs (US$/lb Cu produced)                   Mine  Years 1-5 Years 6-13
----------------------------------------------------------------------------
Mine site (net of by-product credits)             1.48       1.62       1.40
----------------------------------------------------------------------------
C1 (delivered metal - net of by-product                                     
 credits)                                         1.82       1.96       1.75
----------------------------------------------------------------------------
                                                                            
Table 5 - Summary of cash costs                                             



Capital Costs

The PEA estimates the initial development capital expenditure at US$285.5
million during the proposed 1.5-year construction period and the first year of
partial production. With sustaining (deferred and working) capital over the life
of the mine, the expected investment is US$399.0 million. All estimates are
based on the consultant's experience with similar projects and are not
definitive estimates based on vendor quotations.




----------------------------------------------------------------------------
Capital Estimate                                                            
(US$ million)                                                               
----------------------------------------------------------------------------
Mining infrastructure                                                   31.1
----------------------------------------------------------------------------
Concentrator plant                                                     125.1
----------------------------------------------------------------------------
Surface general infrastructure                                          17.6
----------------------------------------------------------------------------
Power generation                                                        19.3
----------------------------------------------------------------------------
Tailings dam and piping                                                  9.9
----------------------------------------------------------------------------
Wellfield and piping                                                    13.1
----------------------------------------------------------------------------
Accommodation                                                           15.3
----------------------------------------------------------------------------
Indirect (managing contractor, owner's costs, spare, etc.)              54.0
----------------------------------------------------------------------------
Initial development capital                                            285.5
----------------------------------------------------------------------------
Pre-production costs                                                    15.0
----------------------------------------------------------------------------
Sustaining capital                                                      82.1
----------------------------------------------------------------------------
Deferred capital (tailing dam extensions)                               16.4
----------------------------------------------------------------------------
Total capital expenditure for the life of mine                         399.0
----------------------------------------------------------------------------
                                                                            
Table 6 - Capital estimate summary                                          



Infrastructure

Power will be supplied by 20MW onsite heavy fuel oil ("HFO") generators, at a
capital cost of US$19.3 million, for the first five years of commercial
production. In year six of operations, which is projected to be the year 2021,
BPC is expected to have connected the Project to the national power grid. Onsite
power costs using HFO are estimated to be US$0.22/kWh, assuming a HFO of
US$1.06/l. Power from the grid is expected to cost US$0.08/kWh. Water will be
supplied from an aquifer located approximately 50 kilometers from the
concentrator facility. Water will be transported to the processing plant by
pipeline. 


Operating Costs

The project produces approximately 863 million pounds of copper at an average C1
cash operating cost of US$1.82/lb Cu over the 13-year mine life. For the first
five full years of production, utilizing HFO generators, C1 cash costs are
estimated to be US$1.96/lb Cu. For the remaining eight years, with power sourced
from the national grid, C1 cash costs are expected to decrease to US$1.75/lb Cu.
These cash costs are net of silver byproducts and include transport and refining
charges. Cash operating costs are based on prevailing wage rates, commodity
prices, and power rates in southern Africa. Maintenance parts and repairs are
estimated based on industry standard factors for these costs. Details of the
operating costs are presented in Table 7 below.




----------------------------------------------------------------------------
Operating Cost                                                              
(as indicated)                                                              
----------------------------------------------------------------------------
Mining                                           $/tonne processed     20.80
----------------------------------------------------------------------------
Processing - HFO generated                       $/tonne processed     13.92
----------------------------------------------------------------------------
Processing - Grid power                          $/tonne processed      9.92
----------------------------------------------------------------------------
Overheads - Administration                       $/tonne processed      2.90
----------------------------------------------------------------------------
Overheads - Marketing commission                      % of revenue      1.50
----------------------------------------------------------------------------
Overheads - Transportation concentrate    US$/tonne of concentrate    180.00
----------------------------------------------------------------------------
Overheads - Toll treatment                            % of revenue      3.00
----------------------------------------------------------------------------
                                                                            
Table 7 - Operating costs, freight, treatment and refinement charges        



Mineral Resource Estimate

The mineral resource estimate upon which the PEA was based was completed by or
under the direction of Ms. Susan N. Meister, SME, and an independent Qualified
Person as set forth by NI 43-101. Drill results used in the mineral resource
estimates include core and RC drilling from the 2011 drilling program, 2006-2011
drilling by Hana and drilling completed by previous owners that could be
verified in the field. The drilling cutoff date for Banana Zone and Zone 5 was
December 13, 2011 with assay results available on February 15, 2012. The
drilling cutoff date for one sub-zone, NLN, was 28 August 2011 with assays
finalized on October 18, 2011. The overall effective date of this resource is
February 15, 2012. The mineral resource for Banana Zone is supported by 559 core
holes (approximately 75,800 m) and 431 RC holes (approximately 51,400m) drilled
by Hana and 21 core holes (approximately 4,250m) and 31 RC holes (approximately
(3,600m) drilled by predecessors on the property. Zone 5 is supported by 69 RC
drill holes (approximately 7,400m) and 2 core holes (approximately 370m) drilled
by Hana. The geological and assay database have been reviewed and audited by
Grant Geological Services. Included in this review was the analysis of assaying
QA/QC measures implemented by Hana, a study of core to RC drill results and a
review of pre-Hana drilling. 


Mineral Resources are reported from six block models covering the Banana Zone
and a separate one covering Zone 5. Three dimensional solids models were created
of continuous mineralized zones at 0.1% Cu and 0.5% Cu grade thresholds that are
tied to lithology. The block size (5x1.5x4m, 5x3x4m, 10x3x4m and 40x6x4m) in
combination with partial block coding maintained control on mineralized zone
volumes and boundary limits. Cu and Ag assays were variably capped by sub-zone
prior to compositing and block grade estimation. Nearest neighbor (NN) and
inverse distance to a power of 3 (ID3) estimates were run, with ID3 used for
resource reporting and NN used for checking. Cu and Ag grades were interpolated
for the different grade zones then combined into an overall grade for the
mineralized portion of the block. Search distances ranged from 450x350x250m to
150x105x20m, depending upon the estimation pass number and drill spacing within
the subzone. In general, blocks were categorized as Indicated within areas of
100 x 50m drill spacing, and Inferred in areas with approximate 200m spacing
along strike.


Differences between the previously reported mineral resource estimate (as
reported in the Technical Report dated February 3, 2011) are primarily related
to additional drilling (292 drill holes, approximately 39,700m in Banana Zone
and 33 drill holes, 3800m in Zone 5), a different resource modeling approach and
a reduction in the projection distance for categorizing Inferred Mineral
Resources.


An updated resource model is planned for Zone 6 following completion of
additional drilling, assaying and geological interpretations.  


Additional information about the resource modeling methodology and differences
between previously issued resource statements will be documented in the upcoming
43-101 technical report.




----------------------------------------------------------------------------
                 Banana Zone - Indicated Mineral Resource                   
 New Discovery, North Limb North, Northeast Fold and South Limb Definition  
                                  Subzones                                  
----------------------------------------------------------------------------
                           Contained CU Metal             Contained Ag Metal
Cutoff                  Cu -------------------       Ag  -------------------
    Cu     Tonnes    Grade                        Grade  
    (%) (M tonnes)      (%) (K tonnes)  (M lbs)    (g/t)  (tonnes) (M oz Ag)
----------------------------------------------------------------------------
   0.3       53.1     0.75        396      873     10.7       569      18.3 
----------------------------------------------------------------------------
   0.4       40.9     0.87        354      780     12.5       510      16.4 
----------------------------------------------------------------------------
   0.5       31.7     0.99        313      690     14.3       453      14.6 
----------------------------------------------------------------------------
   0.6       24.7     1.11        275      605     16.3       402      13.0 
----------------------------------------------------------------------------
   0.7       19.6     1.23        242      533     18.2       358      11.5 
----------------------------------------------------------------------------
   0.8       15.9     1.35        214      472     20.2       320      10.3 
----------------------------------------------------------------------------
   0.9       12.9     1.47        189      417     22.2       287       9.2 
----------------------------------------------------------------------------
   1.0       10.5     1.58        166      366     24.3       254       8.2 
----------------------------------------------------------------------------
                  Banana Zone - Inferred Mineral Resource                   
                           (includes Chalcocite)                            
----------------------------------------------------------------------------
                           Contained CU Metal             Contained Ag Metal
Cutoff                  Cu -------------------       Ag  -------------------
    Cu     Tonnes    Grade                        Grade  
    (%) (M tonnes)      (%) (K tonnes)  (M lbs)    (g/t)  (tonnes) (M oz Ag)
----------------------------------------------------------------------------
   0.3      299.5     0.51      1,575    3,472      6.0     1,771      57.0 
----------------------------------------------------------------------------
   0.4      191.6     0.60      1,207    2,662      7.1     1,392      44.7 
----------------------------------------------------------------------------
   0.5      120.3     0.70        892    1,966      8.4     1,060      34.1 
----------------------------------------------------------------------------
   0.6       76.0     0.80        652    1,438      9.8       797      25.6 
----------------------------------------------------------------------------
   0.7       49.1     0.90        480    1,057     11.1       602      19.4 
----------------------------------------------------------------------------
   0.8       31.8     1.00        351      775     12.5       453      14.6 
----------------------------------------------------------------------------
   0.9       21.6     1.10        266      586     13.7       348      11.2 
----------------------------------------------------------------------------
   1.0       14.3     1.22        197      435     14.9       263       8.5 
----------------------------------------------------------------------------
                     Zone 5 - Inferred Mineral Resource                     
----------------------------------------------------------------------------
                           Contained CU Metal             Contained Ag Metal
Cutoff                  Cu -------------------       Ag  -------------------
    Cu     Tonnes    Grade                        Grade  
    (%) (M tonnes)      (%) (K tonnes)  (M lbs)    (g/t)  (tonnes) (M oz Ag)
----------------------------------------------------------------------------
   0.3       16.9     1.41        239      526     12.6       213       6.8 
----------------------------------------------------------------------------
   0.4       16.0     1.47        236      520     13.2       211       6.8 
----------------------------------------------------------------------------
   0.5       16.0     1.47        236      520     13.2       211       6.8 
----------------------------------------------------------------------------
   0.6       16.0     1.47        236      519     13.2       211       6.8 
----------------------------------------------------------------------------
   0.7       15.5     1.50        232      512     13.2       205       6.6 
----------------------------------------------------------------------------
   0.8       14.9     1.53        228      502     13.5       201       6.5 
----------------------------------------------------------------------------
   0.9       14.1     1.57        221      488     13.8       195       6.3 
----------------------------------------------------------------------------
   1.0       13.3     1.61        213      470     14.2       189       6.1 
----------------------------------------------------------------------------
                                                                            
Notes:                                                                      

1.  Mineral Resources are not Mineral Reserves and do not have demonstrated
    economic viability.  
2.  Indicated Mineral Resources are supported by an approximate drill hole
    spacing of 100 x 50m.  
3.  Inferred Mineral Resources are supported by an approximate drill hole
    spacing of 200m along strike. 
4.  The Base Case Mineral Resources are reported above a 0.3% Cu cutoff,
    based on commodity pricing of US$3.40/lb Cu and US$30.00/oz Ag,
    additional cutoffs are shown as sensitivity cases. 

Table 8 - Indicated and Inferred Resources at the Banana Zone and Zone 5    



DRA carried out pit optimization using the Whittle Four-X software. The optimal
shells for Indicated and Inferred Mineral Resources were selected through a
combination of maximum NPV and optimum strip ratios. 




----------------------------------------------------------------------------
               Copper Grade    Silver Grade   In-pit Material  
                    (%)            (g/t)        (M tonnes)     
             ------------------------------------------------         Waste 
               Indi-           Indi-           Indi-          Strip      (M 
               cated Inferred  cated Inferred  cated Inferred Ratio  tonnes)
----------------------------------------------------------------------------
New Discovery   0.88     0.87  14.26    13.30 10.131    0.025  5.74  53.340 
----------------------------------------------------------------------------
North East                                                                  
 Fold           0.84     1.16  11.16    12.18 12.168    1.624  7.15  98.586 
----------------------------------------------------------------------------
South Limb                                                                  
 Definition     0.79     0.98  10.95    15.14  3.262    1.066 10.07  43.562 
----------------------------------------------------------------------------
South Limb                                                                  
 South             -     0.90      -    10.94      -    2.981  8.14  24.270 
----------------------------------------------------------------------------
Zone 5             -     1.33      -    11.75      -   14.437  5.93  85.624 
----------------------------------------------------------------------------
Total           0.85     1.23  12.36    11.85 25.560   20.132  6.79 310.382
                                                                (i) 
----------------------------------------------------------------------------
                                                                            
(i) Average                                                                 
                                                                            
----------------------------------------------------------------------------
                     Contained Copper   Contained Copper   Contained Silver 
                        (k tonnes)          (M lbs)           (M ounces)    
                   ---------------------------------------------------------
                    Indicated Inferred Indicated Inferred Indicated Inferred
----------------------------------------------------------------------------
New Discovery          89.397    0.216   197.087    0.476     4.644    0.011
----------------------------------------------------------------------------
North East Fold       102.342   18.854   225.625   41.567     4.364    0.636
----------------------------------------------------------------------------
South Limb                                                                  
 Definition            25.777   10.419    56.829   22.970     1.149    0.519
----------------------------------------------------------------------------
South Limb South            -   26.859         -   59.214         -    1.048
----------------------------------------------------------------------------
Zone 5                      -  191.708         -  422.644         -    5.456
----------------------------------------------------------------------------
Total                 217.516  248.056   479.541  546.871    10.157    7.670
----------------------------------------------------------------------------
                                                                            
Note: No reserves can be declared in the PEA                                
Table 9 - Results of the pit optimization                                   



Project Sensitivities

Project cash flow is highly sensitive to changes in the price of copper as
indicated in Table 10. The project is also sensitive to variations in capital
and operating costs as indicated in Table 11 below. These tables show the effect
of increasing or decreasing the capital expenditure and operating expenditure
estimates for the project by +/-10% and +/-20%.




----------------------------------------------------------------------------
                            Capex Estimate Variance  Opex Estimate Variance 
NPV                        -------------------------------------------------
After-Tax                            Base                      Base         
(US$ million)                  +10%  Case      -10%      +10%  Case     -10%
----------------------------------------------------------------------------
Discount Rates 5%               361   388       414       282   388      494
               -------------------------------------------------------------
               Base Case 8%     236   263       289       174   263      351
               -------------------------------------------------------------
               10%              169   196       196       116   196      276
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
               IRR%            17.5  19.3      19.3      10.0  19.3     22.8
----------------------------------------------------------------------------
                                                                            
Table 10 - Project sensitivity to variations in capital and operating       
expenditure                                                                 
                                                                            
----------------------------------------------------------------------------
                                   Variance in Cu Head Grades               
                    --------------------------------------------------------
                                      1.02%                                 
After-tax NPV                         (Base                                 
(US$ Million)          0.90%   0.95%   Case)   1.10%   1.20%   1.30%   1.40%
----------------------------------------------------------------------------
Discount                                                                    
 Rates            5%                    388      499     638     776     915
        --------------------------------------------------------------------
        Base Case 8%                    263      355     472     587     702
        --------------------------------------------------------------------
                 10%                    196      $79     383     487     590
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
IRR                %                   19.3     23.0    27.4    31.7    35.9
----------------------------------------------------------------------------

Table 11 - Project sensitivity to variations in copper head grades




Project Information

All drilling for the Project, up to December 13, 2011 was incorporated into the
PEA. In the preparation of the PEA, the Independent Consultants and DRA received
written or verbal data from Hana's staff, metallurgical reports from G&T
Metallurgical Services Ltd. of Kamloops, British Columbia and Mintek of
Johannesburg, South Africa. The parties listed in Table 12 above independently
confirmed the data utilized in the preparation of this PEA. The capital and
operating data developed in the PEA came from review of the metallurgical test
work, in-house DRA data and discussions with other consultants and copper mining
operations in southern Africa and elsewhere. Hana provided the tax, royalty and
legal information.


Qualified Persons and NI 43-101 Technical Report

The PEA summarized here for the Project was completed by the independent
consultants and DRA (listed in Table 12); and will be incorporated in a NI
43-101 compliant, independent Technical Report which will be available on SEDAR
and the Hana website within 45 days from the date of this news release. 




----------------------------------------------------------------------------
Area of             Contributing                          Professional      
 Responsibility     Company            Qualified Person   Qualification     
----------------------------------------------------------------------------
Geology             Farscape           David Catterall    Pr.Sci.Nat        
                    Exploration                                             
----------------------------------------------------------------------------
Database Validation Grant Geology      Jerry Grant        P.Geo             
----------------------------------------------------------------------------
Resource Estimate   Independent        Susan Meister      SME               
----------------------------------------------------------------------------
Mining and          DRA                Thomas Obiri-      Pr.Eng            
 Infrastructure                        Yeboah                               
----------------------------------------------------------------------------
Metallurgy and      DRA                Mark Cresswell     Pr.Eng            
 Infrastructure                                                             
----------------------------------------------------------------------------
                                                                            
Table 12 - PEA Contributors                                                 



All of Hana's exploration programs and pertinent disclosure of a technical or
scientific nature are prepared by, or prepared under the direct supervision of
Mr. Marek Kreczmer, Hana's CEO and Chairman, who serves as the Qualified Person
(QP) under the definitions of National Instrument 43-101. Hana's security, chain
of custody and quality control procedures are described on their website and are
filed on the website and on SEDAR under the section on best practices - sampling
methodologies. Mr. Kreczmer has reviewed and approved the information contained
in this release. 


The PEA is preliminary in nature and includes the use of Inferred Resources,
which are considered too speculative to apply economic considerations that would
enable them to be categorized as Mineral Reserves. Mineral Resources do not have
demonstrated economic viability and future in-fill drilling and scoping,
pre-feasibility and feasibility studies will determine what percentage of the
inferred resource can be placed into the mineable category. Thus, there is no
certainty that the production profile concluded in the PEA will be realized.
Actual results may vary, perhaps materially. The Company is not aware of any
environmental, permitting, legal, title, taxation, socio-political, marketing or
other issue which may materially affect this estimate of mineral resources. The
projections, forecasts and estimates presented in the scoping study and PEA
constitute forward-looking statements and readers are urged not to place undue
reliance on such forward-looking statements. Additional cautionary and
forward-looking statement information is detailed at the end of this press
release.


Statements in this press release, other than purely historical information,
including statements relating to the Company's future plans and objectives or
expected results, may include forward-looking statements. Forward-looking
statements are based on numerous assumptions and are subject to all of the risks
and uncertainties inherent in resource exploration and development. As a result,
actual results may vary materially from those described in the forward-looking
statements.


Hana Mining Ltd. (TSXV:HMG)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Hana Mining Ltd. Charts.
Hana Mining Ltd. (TSXV:HMG)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Hana Mining Ltd. Charts.