Çöpler Remains Well On Track For 2021
Production & Cost Guidance
DENVER, Dec. 24, 2021 /PRNewswire/ - SSR Mining Inc.
(NASDAQ: SSRM) (TSX: SSRM) (ASX: SSR) ("SSR Mining") is pleased to
announce the commencement of commissioning and ramp-up activities
at Çöpler's sulfide plant flotation circuit following the receipt
of all required permits and approvals. A key component of the 2020
Çöpler District Master Plan ("CDMP20"), the Çöpler flotation
circuit was completed on time and on budget in the third quarter of
2021. The flotation circuit utilizes latent capacity in the sulfide
plant, and its commissioning is anticipated to increase the gold
and sulfide sulfur grades processed through the autoclaves, reduce
reagent use, and increase total sulfide plant throughput and gold
production.
About SSR Mining
SSR Mining Inc. is a leading, free cash flow focused
intermediate gold company with four producing assets located in the
USA, Turkey, Canada, and Argentina, combined with a global pipeline of
high-quality development and exploration assets in the USA, Turkey,
Mexico, Peru, and Canada. In 2020, the four operating assets
produced approximately 711,000 gold-equivalent ounces. SSR Mining
is listed under the ticker symbol SSRM on the NASDAQ and the TSX,
and SSR on the ASX.
SSR Mining Contacts
F. Edward Farid, Executive Vice
President, Chief Corporate Development Officer
Alex Hunchak, Director, Corporate
Development and Investor Relations
SSR Mining Inc.
E-Mail: invest@ssrmining.com
Phone: +1 (416) 306-5789
To receive SSR Mining's news releases by e-mail, please
register using the SSR Mining website at
www.ssrmining.com.
Cautionary Note Regarding Forward-Looking
Information
Except for statements of historical fact relating to the
Company, certain statements contained in this press release
constitute forward-looking information, future oriented financial
information, or financial outlooks (collectively "forward-looking
information") within the meaning of Canadian securities laws.
Forward-looking information may be contained in this document and
the Company's other public filings. Forward-looking information
relates to statements concerning the Company's outlook and
anticipated events or results and, in some cases, can be identified
by terminology such as "may", "will", "could", "should", "expect",
"plan", "anticipate", "believe", "intend", "estimate", "projects",
"predict", "potential", "continue" or other similar expressions
concerning matters that are not historical facts.
Forward-looking information in this press release is based on
certain key expectations and assumptions made by the Company.
Although the Company believes that the expectations and assumptions
on which such forward-looking information is based are reasonable,
undue reliance should not be placed on the forward-looking
information because the Company can give no assurance that they
will prove to be correct. Forward-looking information in this press
release include statements concerning, among other things:
forecasts; outlook; production costs and performance of the
Company's processing facilities. Forward-looking information is
only a prediction based on the Company's current expectations and
the Company's projections about future events. Actual results may
vary from such forward-looking information for a variety of reasons
including, but not limited to, risks and uncertainties disclosed in
the Company's filings on the Company's website at
www.ssrmining.com, on SEDAR at www.sedar.com, on EDGAR at
www.sec.gov and on the ASX at www.asx.com.au and other unforeseen
events or circumstances. Other than as required by law, the Company
does not intend, and undertake no obligation to update any
forward-looking information to reflect, among other things, new
information or future events.
View original
content:https://www.prnewswire.com/news-releases/ssr-mining-announces-commissioning-and-ramp-up-of-the-copler-flotation-circuit-301450735.html
SOURCE SSR Mining Inc.