Colonial Coal International Corp. (TSX-V: CAD) (the
“
Company” or “
Colonial
Coal”). David Austin, Colonial Coal’s President and
CEO, is pleased to announce the results of a recent Preliminary
Economic Assessment (the “
PEA”) for a stand-alone
open pit option at the Company’s 100% owned Huguenot coking coal
property (the “
Huguenot Project”)
located approximately 85 kilometres southeast of Tumbler Ridge in
northeast British Columbia.
This PEA for the stand-alone open pit
mine on the Huguenot Project is preliminary in nature and there is
no certainty that the forecast results stated in the PEA will be
realized. In addition, the PEA includes inferred mineral
resources that are considered too speculative geologically to have
the economic considerations applied to them that would enable them
to be categorized as mineral reserves, and there is no certainly
that the preliminary economic assessment will be realized.
Furthermore, mineral resources that are not mineral reserves do not
have demonstrated economic viability.
The PEA report, prepared by Stantec Consulting
Services Inc. (“Stantec”) in accordance with CSA
National Instrument 43-101 (“NI 43-101”)
standards, will be completed and filed on SEDAR (the System for
Electronic Document Analysis and Retrieval) within 45 days.
The results of the PEA show that the Huguenot Project continues to
demonstrate positive economics, has viable development options and
is worthy of advancement.
The current PEA report builds upon an original
PEA report prepared in 2013 by Norwest Corporation that was updated
in 2018 by Norwest, now Stantec, using then current scoping level
cost estimates and economic analyses. The mining studies
previously reported (September 24, 2013 and July 10, 2018 and by
way of corresponding 43-101 Technical Report filings) were based
upon exploiting the coking coal resources by a combination of open
pit and underground mining methods. During the 2018 update,
Stantec recognized an opportunity to significantly expand the open
pit to higher stripping ratios, with correspondingly higher
recoverable tonnages of surface mineable coal, thereby creating the
opportunity to examine a surface stand-alone mining option in a new
PEA.
This PEA does not include any further evaluation
of the underground resources nor any potentially mineable coal
associated with these resources.
For the current study, Stantec used previously
reported surface mineable resources to develop a revised conceptual
mine plan to exploit the coal resources utilizing a stand-alone
open pit, in contrast to the previous approach of a combined open
pit and underground mine. Stantec completed a more detailed
analysis of the open pit design and equipment selection than was
carried out previously, that yielded larger mineable open pit
tonnage, longer mine life and a lower cost mining operation.
In addition, alternative means of product coal transportation
were considered which resulted in a revised plan to transport coal
by conventional haul trucks from the mine to the existing rail line
south of Tumbler Ridge, as opposed to the previous concept of
direct rail transport from the mine. The trucking concept has
the advantage of lower capital costs, lower risk and a shorter
construction schedule than the rail option.
Highlights of the revised PEA report are
summarized below. All costs are in US dollars but, where
Canadian dollar equivalents are provided, they have been converted
using an exchange rate of US$1.00 equals CAD$1.316.
A summary of the financial analyses is presented
in the following tables; the results show the after tax (including
royalty) net present values (NPVs) at various discount rates and
internal rates of return (IRRs) for a range of coal prices.
For the benchmark coal price, Stantec has used US$174 per
tonne. They note that, while a discount may be applied to the
benchmark price for Huguenot product coal, they consider the
potential discount to be within the range of values presented in
the tables below.
The capital expenditures are based on two
scenarios. The first scenario assumes that all major mining
equipment is purchased outright in the year in which it is required
for the mining operation. This includes replacements as they
are required over the life of the mine. The second scenario
assumes that the major mining equipment will be leased in the year
in which it is required for the mining operation and that
replacements will also be leased when the equipment needs to be
replaced.
To view accompanying tables please click on the following
links:
Purchased Equipment Scenario
(US$): https://www.globenewswire.com/NewsRoom/AttachmentNg/0a5e3b07-9a9d-436c-885e-9628e2c81b7c
Purchased Equipment Scenario
(CDN$): https://www.globenewswire.com/NewsRoom/AttachmentNg/a4432bf1-a7bb-4da6-b0de-5ab2ba2e6638
Leased Equipment Scenario
(US$): https://www.globenewswire.com/NewsRoom/AttachmentNg/c31ce66f-6b1c-4c0d-8d1e-9eadab474aa6
Leased Equipment Scenario
(CDN$): https://www.globenewswire.com/NewsRoom/AttachmentNg/e51e3417-b856-406e-aeec-8abf953209d6
- Based on the purchased equipment
scenario the financial analysis suggests that the coal price
required to achieve a zero NPV at discount rates of 5%, 7.5% and
10%, respectively, is about US$113, US$120 and US$125 per tonne.
A coal price of US$137 per tonne is required for an IRR of
15%.
- Based on the leased equipment
option the financial analysis suggests that the coal price required
to achieve a zero NPV at discount rates of 5%, 7.5% and 10%,
respectively, is about US$114, US$119 and US$125 per tonne. A
coal price of US$137 per tonne is required for an IRR of
15%.
- Measured and Indicated surface
mineable coal resources total 132.0 million tonnes, with an
additional Inferred resource of 0.5 million tonnes. Not
included in the current PEA are in-situ underground mineable
resources totaling 145.7 million tonnes (Measured and Indicated)
and 118.7 million tonnes classified as Inferred.
- The current PEA economic analysis
is based on a conceptual open pit mine plan targeting 99 million
run-of-mine (“ROM”) tonnes of resource at an
overall stripping ratio of 10.5:1 (bank cubic metres (bcm):ROM
tonnes), yielding 72 million tonnes of product coal over a mine
life of 27 years. The previous PEA identified a smaller open
pit with ROM tonnage of 56 million tonnes at a stripping ratio of
8.6:1, that yielded 39 million tonnes of product coal over 13
years.
- Projected clean coal production
from open pit mining operations ranges from 0.7 million tonnes per
annum (“Mt/a”) to 3.0 Mt/a, averaging
approximately 2.7 Mt/a.
- Potential coal production is
identified as hard coking coal similar to coking coal currently
exported from northeast British Columbia.
- The stand-alone open pit cash
operating costs for the purchased equipment scenario are estimated
at US$55.08 per tonne of product coal at the mine gate. The
cash operating costs for the leased equipment scenario are
estimated at US$61.47 per tonne.
- Estimated direct operating plus
offsite costs for the purchased equipment scenario (i.e., FOB
cost), total US$91.90 per clean tonne (excluding production taxes
and royalties). The FOB cost for the leased equipment
scenario is estimated at US$98.29 per clean tonne (excluding
production taxes and royalties)
- Pre-production capital cost for the
proposed mine in the purchased equipment scenario is estimated at
US$510 million, with additional sustaining capital of US$215
million over the life-of-mine (LOM). Pre-production capital
cost in the leased equipment scenario is estimated at US$303
million, with additional sustaining capital of US$42 million over
the LOM.
- The Huguenot Project’s proposed
payback of initial capital is estimated within four years from
start-up of operations for both scenarios.
This press release has been reviewed and the
scientific and technical disclosure disclosed herein approved by
Derek Loveday, P.Geo., of Stantec, a Professional Geologist and a
Qualified Person as defined in NI 43-101.
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
About Colonial Coal International
Corp.
Colonial Coal is a publicly traded coal
corporation in British Columbia that focuses primarily on coking
coal projects. The northeast Coal Block of British Columbia,
within which our Corporation’s projects are located, hosts a number
of proven deposits and has been the subject of M&A activities
by Anglo-American and others. Additional information can be
found on the Company's website www.ccoal.ca or by viewing the
Company's filings at www.sedar.com.
Forward-Looking Information
Information set forth in this news release may
involve forward-looking statements. Forward-looking statements are
statements that relate to future, not past, events. In this
context, forward-looking statements often address a company's
expected future business and financial performance, and often
contain words such as "anticipate", "believe", "plan", "estimate",
"expect", and "intend", statements that an action or event "may",
"might", "could", "should", or "will" be taken or occur, or other
similar expressions. By their nature, forward-looking statements
involve known and unknown risks, uncertainties and other factors
which may cause our actual results, performance or achievements, or
other future events, to be materially different from any future
results, performance or achievements expressed or implied by such
forward-looking statements. Such factors include, among others, the
following risks: risks associated with marketing and sale of
securities; the need for additional financing; reliance on key
personnel; the potential for conflicts of interest among certain
officers or directors with certain other projects; and the
volatility of common share price and volume. Forward-looking
statements are made based on management's beliefs, estimates and
opinions on the date that statements are made and except as
required by law, the Company undertakes no obligation to update
forward-looking statements if these beliefs, estimates and opinions
or other circumstances should change. Investors are cautioned
against attributing undue certainty to forward-looking
statements.
THE FORWARD-LOOKING INFORMATION CONTAINED IN
THIS NEWS RELEASE REPRESENTS THE EXPECTATIONS OF THE COMPANY AS OF
THE DATE OF THIS NEWS RELEASE AND, ACCORDINGLY, IS SUBJECT TO
CHANGE AFTER SUCH DATE. READERS SHOULD NOT PLACE UNDUE IMPORTANCE
ON FORWARD-LOOKING INFORMATION AND SHOULD NOT RELY UPON THIS
INFORMATION AS OF ANY OTHER DATE. WHILE THE COMPANY MAY ELECT TO,
IT DOES NOT UNDERTAKE TO UPDATE THIS INFORMATION AT ANY PARTICULAR
TIME EXCEPT AS REQUIRED IN ACCORDANCE WITH APPLICABLE SECURITIES
LEGISLATION.
For further information please contact:
Colonial Coal International Corp. Shane Austin 604.568.4962
saustin@ccoal.ca www.ccoal.ca
Colonial Coal (TSXV:CAD)
Historical Stock Chart
From Nov 2024 to Dec 2024
Colonial Coal (TSXV:CAD)
Historical Stock Chart
From Dec 2023 to Dec 2024