Red Rock Energy Inc. (TSX VENTURE:RRK) announced today that it has recently
received assay test results which confirm an extension of the recently
discovered Fusion uranium zone. These results suggest that both the length and
breadth of the Fusion Zone continues to be significant with grades up to 0.612%
U3O8 (12.24 lbs /ton) over 5 metres of core length.


Generated as part of its continuing 2008 Diamond Drilling Campaign, Red Rock has
received additional analytical results testing the Fusion Zone up to and
including hole 08RB2-13 (with the exception of hole 08RB2-12 which results are
expected shortly). Of prime interest are the Fusion Zone intersections of the
Lake Cinch Main Ore Fault structure (MOF) in hole 08RB2-13. These grade 0.373%
U3O8 (7.46 lbs/ton) across 8.50 m core length from 311.00 m to 319.50 m,
including 0.612% (12.24 lbs/ton) U3O8 across a 5.0 m core length from 313.00 m
to 318.00 m. A second intercept has grades of 0.475% (9.5 lbs/ton) across 2.0 m
of core length from 335.0 m to 337.0 m


These intersections are from the Fusion zone that was initially discovered in
hole 08RB2-03 which assays 0.082% U3O8 across 14.50 m core length including
0.123% U3O8 across 7.00 m core length (Red Rock Press Release of April 7, 2008).
Prior drilling in hole 08RB2-07 extended the Fusion uranium zone up-dip on the
Lake Cinch MOF structure, with this hole having assayed 0.051% U3O8 across 11.50
m core length including 0.131% U3O8 across 1.5 m core length (Red Rock Press
Release May 20 2008).


The current intercepts in hole 08RB2-13 are about mid-way between the intercepts
in hole 08RB2-03 and hole 08RB2-07; as a result the Fusion uranium zone has now
been extended for at least 85 m, with the uranium zone raking steeply down dip
in the plane of the Lake Cinch MOF structure at a depth of about 270 m below
ground surface. The Lake Cinch MOF structure is known to continue up dip,
therefore there is the potential to extend the Fusion uranium zone upwards and
possibly link to one or more radioactive intercepts previously drilled by former
operators.


In reviewing the latest assay results, Sandy L. Loutitt, President of Red Rock,
commented: "The drilling being done to define and expand the Fusion uranium zone
is compatible with Red Rock's corporate vision to identify new uranium zones,
and then build uranium resources and reserves pound-by-pound until sufficient
resources have been identified to initiate a preliminary feasibility study. With
an economic significance cutoff grade of .05% (1 lbs/ton), the current drill
program continues to produce significant intersections in every hole drilled. As
historic production was centered around 2 - 6 ft (0.6m - 1.8m) zones typically
grading 0.200% U308 (4 lbs /ton), we are extremely pleased with the higher
grades - up to 0.612% (12lbs/ton) and the wider widths , 2 m -8.5 m (6.6 ft-
27.9 ft) - found thus far in the new Fusion Zone."


The result highlights for holes 08RB2-08 to 08RB2-11 and 08RB2-13 are tabulated
in Table 1. As of early July Red Rock has now completed a total of 5,707.0 m in
16 holes to test the Lake Cinch MOF structure at depth northeast of the former
Lake Cinch mine underground workings. Assay results are still pending for holes
08RB2-12, and 08RB2-14 to 08RB2-16. Red Rock has now started a program of 10 to
12 holes to test the upper portion of the Lake Cinch MOF structure up-dip from
the Fusion uranium zone. Once this drilling is completed in late July or early
August, a decision will be made as to whether added infill or step out drilling
are required in order to have sufficient drill pierce points to perform a
preliminary uranium resource estimate on the Fusion uranium zone.




Table 1: Drilling Highlights from Red Rock Energy Inc. 2008 Drill Campaign
for holes 0RB2-08 to 08RB2-11, and 08RB2-13

----------------------------------------------------------------------------
Hole                  UTM             UTM        Collar              Collar
                Easting(1)     Northing(1)      Azimuth         Inclination
----------------------------------------------------------------------------
08RB2-08           632411         6603151   310 degrees         -70 degrees
----------------------------------------------------------------------------
Including
08RB2-08
----------------------------------------------------------------------------
08RB2-09           632462         6603179   310 degrees         -50 degrees
----------------------------------------------------------------------------
Including
08RB2-09
----------------------------------------------------------------------------
08RB2-10           432462         6603179   310 degrees         -70 degrees
----------------------------------------------------------------------------
Including
08RB2-10
----------------------------------------------------------------------------
08RB2-10
----------------------------------------------------------------------------
08RB2-11           632522         6603196   310 degrees         -50 degrees
----------------------------------------------------------------------------
08RB2-11
----------------------------------------------------------------------------
Including
08RB2-11
----------------------------------------------------------------------------
08RB2-11
----------------------------------------------------------------------------
08RB2-13           632440         6603167   310 degrees         -60 degrees
----------------------------------------------------------------------------
Including
08RB2-13
----------------------------------------------------------------------------
08RB2-13
----------------------------------------------------------------------------
08RB2-13
----------------------------------------------------------------------------
Including
08RB2-13
----------------------------------------------------------------------------
08RB2-13
----------------------------------------------------------------------------


----------------------------------------------------------------------------
Hole               From        To       Core      Average      Intersection
                     (m)       (m) Length (m)  Grade U3O8              Type
----------------------------------------------------------------------------
08RB2-08         198.50    201.00       2.50        0.054% Cross-fracture(2)
----------------------------------------------------------------------------
Including
08RB2-08         199.50    201.00       1.50        0.075%   Cross-fracture
----------------------------------------------------------------------------
08RB2-09         290.70    293.20       2.50        0.081%      Cinch MOF(3)
----------------------------------------------------------------------------
Including
08RB2-09         291.20    292.20       1.00        0.178%        Cinch MOF
----------------------------------------------------------------------------
08RB2-10         326.00    335.50       9.50        0.023%        Cinch MOF
----------------------------------------------------------------------------
Including
08RB2-10         332.00    335.50       3.50        0.081%        Cinch MOF
----------------------------------------------------------------------------
08RB2-10         340.50    341.50       1.00        0.110%        Cinch MOF
----------------------------------------------------------------------------
08RB2-11         287.30    287.70       0.40        0.192%   Cross-fracture
----------------------------------------------------------------------------
08RB2-11         316.00    322.00       6.50        0.024%        Cinch MOF
----------------------------------------------------------------------------
Including
08RB2-11         321.50    322.00       0.50        0.062%        Cinch MOF
----------------------------------------------------------------------------
08RB2-11         330.50    336.00       5.50        0.024%        Cinch MOF
----------------------------------------------------------------------------
08RB2-13         311.00    319.50       8.50        0.373         Cinch MOF
----------------------------------------------------------------------------
Including
08RB2-13         313.00    318.00       5.00        0.612         Cinch MOF
----------------------------------------------------------------------------
08RB2-13         335.00    337.00       2.00        0.475         Cinch MOF
----------------------------------------------------------------------------
08RB2-13         351.00    355.50       4.50        0.035%        Cinch MOF?
----------------------------------------------------------------------------
Including
08RB2-13         354.50    355.50       1.00        0.089%        Cinch MOF?
----------------------------------------------------------------------------
08RB2-13         358.50    360.00       1.50        0.127%        Cinch MOF?
----------------------------------------------------------------------------

(1)Note: UTM Eastings and Northings are given for a datum of NAD83, Zone
   12N.
(2)Note: Cross-fracture refers to a uranium-bearing structure that exists
   in the hangingwall of the Cinch Main Ore Fault.
(3)Note: Cinch MOF means Lake Cinch Main Ore Fault.



Reg A. Olson, Ph.D., P. Geol., a Qualified Person under NI 43-101 and supervisor
of the 2007 and 2008 field exploration and drill programs, has reviewed and is
in agreement with the contents of this release.


READER ADVISORY

Statements in this press release may contain forward-looking information
including expectations of future production, operating costs, commodity prices,
administrative costs, commodity price risk management activity, acquisitions and
dispositions, capital spending, access to credit facilities, income taxes,
regulatory changes, and other components of cash flow and earnings. The reader
is cautioned that assumptions used in the preparation of such information may
prove to be incorrect. Events or circumstances may cause actual results to
differ materially from those predicted, a result of numerous known and unknown
risks, uncertainties, and other factors, many of which are beyond the control of
the company. These risks include, but are not limited to, the risks associated
with the mining industry, commodity prices and exchange rate changes. Industry
related risks could include, but are not limited to, operational risks in
exploration, development and production, delays or changes in plans, risks
associated to the uncertainty of reserve estimates, health and safety risks and
the uncertainty of estimates and projections of production, costs and expenses.
The reader is cautioned not to place undue reliance on this forward-looking
information.


The reader is further cautioned that the preparation of financial statements in
accordance with generally accepted accounting principles requires management to
make certain judgements and estimates that affect the reported amounts of
assets, liabilities, revenues and expenses. Estimating reserves is also critical
to several accounting estimates and requires judgments and decisions based upon
available geological, geophysical, engineering and economic data. These
estimates may change, having either a negative or positive effect on net
earnings as further information becomes available, and as the economic
environment changes.


Red Rock Energy Inc. (TSXV:RRK)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Red Rock Energy Inc. Charts.
Red Rock Energy Inc. (TSXV:RRK)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Red Rock Energy Inc. Charts.