THEMAC Resources Group Limited (TSX VENTURE:MAC)
("THEMAC" or the "Company"), through its wholly-owned subsidiary
New Mexico Copper Corporation (NMCC), is currently engaged in
securing two important state operating permits: a Groundwater
Discharge Permit (focused on groundwater protection) from the New
Mexico Environment Department (NMED); and a New Mine Permit to
regulate mine operation and reclamation from the New Mexico Mining
and Minerals Division (NMMMD).
The Company submitted an application for a
Groundwater Discharge Permit to NMED in October 2015. After two
years of review, NMED published a proposed Discharge Permit for the
Copper Flat Mine in February 2018. NMED has invited public review
and comment on the draft Discharge Permit and the Agency has
scheduled a hearing on the proposed Discharge Permit for the week
of September 24 in Truth or Consequences, NM.
The Company has also applied to NMMMD for a
mining permit under the State New Mine Regulations. This process,
which started in 2012, includes an agency approved sampling and
analysis plan, collecting and reporting base line data, and a
detailed description of the mine operation and reclamation plan.
NMMMD has reviewed Company submittals, and the Agency has prepared
a Draft Environmental Evaluation of the mine and reclamation
plan. In a letter dated July 13, 2018, NMMMD gave notice to
the Company that the Copper Flat Mine Permit Application Package is
technically approvable. The Agency is now collecting public
comments on the plan and has scheduled a public hearing on the Mine
in Sierra County during the dates of October 23 - 26, 2018.
The Copper Flat Mine Plan is also being
evaluated by the Bureau of Land Management (BLM) through the
development of a National Environmental Policy Act (NEPA) compliant
Environmental Impact Statement (EIS). The BLM released the Draft
EIS on the Copper Flat Copper Mine Project in November 2015, hosted
two public meetings, and allowed 120 days for public comment on the
Draft EIS. In early 2018, following receipt of comments and follow
up by the BLM, the Agency indicated its intention to move forward
to a Final EIS with the following statement posted on the Agency
webpage for the Copper Flat EIS: “The timeline for the Final EIS is
tentatively scheduled for the summer of 2018, but is subject to the
review and approval of the Biological Assessment by the U.S. Fish
and Wildlife Service.” BLM is consulting with the US Fish and
Wildlife Service in the development of the Biological Assessment as
noted on their website.
THEMAC CEO Andrew Maloney notes, “Our progress
with permitting is noteworthy. We have passed several
important milestones on the way to bringing the Copper Flat Mine to
production and we are gaining momentum. We have developed
responsible plans for mining and reclamation at Copper Flat and we
are confident that we are on the right path to permitting the
Mine.”
About THEMAC Resources Group Limited
THEMAC is a copper development company with a
strong management team and as of May 18, 2011, a 100% ownership
interest in the Copper Flat copper-molybdenum-gold-silver project
in New Mexico, USA. We are continuing to advance the closed copper
mine, Copper Flat, in Sierra County, New Mexico, toward production
with innovation and a sustainable approach to mining development
and production, local economic opportunities, and the best
reclamation practices for our unique environment. The Company is
listed on the TSX Venture Exchange (ticker: MAC) and has issued
share capital of 79,400,122 common shares (fully diluted share
capital 93,425,316).
For more information please visit
www.themacresourcesgroup.com or review the Company’s filings on
SEDAR (www.sedar.com).
For further information
contact:
THEMAC Resources Group Limited
Andrew MaloneyChief Executive OfficerPhone: +1
505.382.5770www.themacresourcesgroup.com
Themac Resources (TSXV:MAC)
Historical Stock Chart
From Nov 2024 to Dec 2024
Themac Resources (TSXV:MAC)
Historical Stock Chart
From Dec 2023 to Dec 2024